Project Safety
Action Plan
Project Number: Project Name: Project Superintendent: Date:
1908-026 JCLDS URDANETA TEMPLE PROJECT
Project Location: Description of Work: Regional Safety Supervisor:
Philippines Erection of steel structure for Temple, Ancillary and
Utility Building
Project Address: Project Manager:
McArthur HighwayUrdaneta, Pangasinan, Philippines EDWINT. TRINOS
SR. PMES MANAGER
1. INTRODUCTION / SCOPE OF WORK:
Erection of bolted Steel Structure with heavy tack weld. Use and rectification of Scaffolding.
2. PROJECTED WORKFORCE AND DURATION:
Peak Number of Employees Peak Work Hours (Day): Peak Number of Employees Peak Work Hours Duration of Peak Period
(Day): (Night): (Night): (Weeks):
50 0700-2000 h N/A N/A
Projected Start Date: Projected End Date:
3. SAFETY COVERAGE / PROCEDURES:
Safety Meetings with Contract Partners Startup Kit received
Contract Partners Program Evaluation in place Emergency Action Plan completed
Underground or overhead hazards identified Current First Aid & CPR training held
SAFETY PROGRAM, PROCEDURES (Welding, Compress Gas Cylinders, Lifting, Rainy
Season)
4. PRE-PLACEMENT EVALUATION & DRUG SCREENING:
Lab identified for drug screening Modified Duty Letter sent to project medical facility
5. TRAINING REQUIREMENTS:
Mobile equipment training Excavation training Respiratory training
FIREWATCH MAN, BANKS MAN
Page 1 of Revised July
Project Safety Action
6. SPECIAL REQUIREMENTS:
Hot work permits required? Lockout/Tagout procedures required?
Client orientation required? Confined space entry procedures required?
7. HAZARD ASSESSMENT (Including Environmental)
Hazard Hazard Control Measures
1 .ELECTRICAL = Ensure competent electrician to do the task.
= License Electrical engineer to calculate, design and give
specification for all electrical materials to be use.
2. MECHANICAL = Certified operators and competent persons to do activity on
equipment.
= Pre-use and after inspection checklist to be done by certified
persons.
3. FALL = Use of lanyard to all materials on heights.
= Proper use of Full Body Harness with lifeline.
= Scaffold are installed with toe boards.
4. PHYSICAL = Conduct tool box/safety meeting before work.
= Hazards are mitigated to all workers.
= Use of proper Personal Protective Equipment is mandatory.
5. MEDICAL = All workers to under go employment medical examination with
PHYSICALLY FIT (Class A and B) declaration by medical
doctors.
= Certified First Aider to do monitoring on site.
6. ENVIRONMENTAL = All chemical to have proper disposal and storage area.
= Spill kit to be on work site all the time.
= Rainy season protocol to be implemented.
7.
8.
9.
10.
Page 2 of Revised July
Project Safety Action
8. EMERGENCY ACTION PLAN & MEDICAL SERVICES
Emergency Service Phone Number Address
Emergency Notification NA
Ambulance/Paramedics NA
Primary Physician
Secondary Physician
Hospital
Fire Department
Sheriff/Police
Insurance Carrier
Key Contacts Name Phone Number
Emergency Notification
Ambulance/Paramedics
Primary Physician
Secondary Physician
Hospital
Fire Department
Sheriff/Police
Insurance Carrier
9. APPROVALS
Signatures below indicate agreement to follow the requirements stated in the PSAP for the named
project. Signature also indicates the understanding that during the course of work conditions may
change. In such circumstances not all potential hazards and their control measures may have
been addressed in this PSAP.
EDWIN T. TRINOS
Client Representative Project Manager
EGBERT CUDAL
Director of Construction Project Superintendent
FERDINAND H. PERALTA
Project Safety Coordinator Regional Safety Supervisor
Page 3 of Revised July