Jinka Hospital Payment Certificate
Jinka Hospital Payment Certificate
የገንዘቡ ልክ ብር
አባሪ በሆነው የክፍያ ሰነድ ጥያቄ መሰረት እስከ ዛሬ ድረስ ተቋራጩ የሠራው ሥራና ያቀረበው ዕቃ ዋጋ Total Amount
As per the attached statement the value of work executed and for material supplied to date is 11,953,162.46
Privious Payment/አስቀድሞ የተከፈለ 11,953,162.46
ቁጥር ቀን የገንዘቡ ልክ ብር ተ.እ.ታ
No. Date Amount /Birr/ Vat
1 Advance Pay 17,514,963.87 2,627,244.58 ተቀናሽ የገንዘቡ ልክ ብር
2 1st pay 5,065,314.37 810,450.30 Deductions Amount/Birr
3 2nd pay - - 1.አስቀድሞ የተከፈለ
4 - - Previous paymen 5,065,314.37
5 2.ቅናሽ
6 Rebate 2% 239,063.25
7 3.መያዣ
ድምር Retention (5%) 585,704.96
Total 5,065,314.37 810,450.30 4.መቀጫ
Penalty -
5. የቅድምያ ክፍያ
20% Advance Payment Chek Advance Payment (20%) 2,342,819.84
Amount of advance taken 17,514,963.87 6. ድምር
Amount of advance repaied 2,342,819.84 Total 8,232,902.42 8,232,902.42
Out standing advance payment 15,172,144.03 7. የተጣራ ክፍያ
Net Sum Before 15% VAT 3,720,260.04
8. 15% ተ.ዕ.ታ
VAT 15% 595,241.61
9. ጠቅላላ ድምር+15%ተ.ዕ.ታ
Total with 15% VAT 4,315,501.65
We certify that the contractor is now entitled to the sum of birr 4,315,501.65//Four Million Three hundred fifteenThousand
five hundred one & 65/100 // including 15% VAT.
ÃzUjW ፊርማ ቀን
Prepared By:- ____________________________ Signature Date __________________________
ÃidqW ፊርማ ቀን
Approved By:- _____________________________ Signature ______________________ Date __________________________
Y^¨< ዋናው ውል
Project:- JINKA GENERAL HOSPITAL EXPANSION PROJECT WORK Main Contract 87,574,819.35
x¨< Supplementry Contract
Location:- S/OMO ZONE JINKA TOWN 1 -
›W]¨< S/u?ƒ -
[Link]
Employer:- SNN Peoples Regional State Health Bureau
¾Y^¨< }s^ß 87,574,819.35
Contractor:- DAMAT CONSTRUCTION 15% VAT 13,136,222.90
›T"] SG”Ç=e ድምር
Consultant:- SOUTH OMO ZONE URBAN & CONSTRUCTION DEPARTMENT Total sum 100,711,042.25
Previous VAT
የተከናወነው ሥራ መጠን
አስቀድሞ የተከፈለ ተ.ዕ.ታ
Amount // Birr//
ተ.ቁ
ቀን የገንዘቡ ልክ የተ.እ.ታ. Excuted Amount (Birr)
DATE Amount (Birr) Amount (Birr)
11,953,162.46
No.
ÃzUjW ፊርማ ቀን
Prepared By:- __________________________ Signature Date __________________________
ÃidqW ፊርማ ቀን
Approved By:- _____________________________ Signature ______________________ Date ______________________
Project Name: Jinka General Hospita Expansion
Client : Southern Nations Nationalities Peoples Regional State Health Bureau
Contractor: Damat Construction
3
Project Name: Jinka General Hospita Expansion
Client : Southern Nations Nationalities Peoples Regional State Health Bureau
Contractor: Damat Construction
4
[Link] IPD BLOCK
1.03 Clear off site to remove top soil to an average depth of 20cm m2 946.00 979.63 17.75 17,388.34
Bulk excavation in ordinary soil to a depth not exceeding 2.5 m
1.04 starting from reduced level m3 1,050.00 2,449.06 120.75 295,724.30
1.07 Cart away surplus excavated material to ana ppropriate tip m3 1,960.06 2,644.99 53.40 141,242.33
25cm thick basaltic or equivalent stone hard core well rolled
1.08 consolidated and blinded with crushed stones. m2 640.58 666.05 144.05 95,943.78
Total Carried to Summary [Link] 1,397,615.36
2. CONCRETE WORK -
2.10 5cm thick lean concrete class C-7, with -
minimum cement content of 150kg /m3 -
[Link] massonary foundation ,retaining wall and grade beam m2 331.83 161.02 123.23 19,842.49
2.20 10cm thick reinforced concrete floor slab class -
C-20,with minimum cement content of 320 kg /m3 -
well spread and leveled steel bar m. separately) m2 640.58 666.05 315.94 210,430.26
2.30 Reinforced concrete class C -25, with minimum -
cement content of 360 kg / m3 filled into form -
work and vibrated around rod reinforcement. -
steel bar and form work measured separately -
[Link] grade beam ,strip beam ,ramp & Steps m3 59.89 36.22 3,159.41 114,448.05
2.40 Provide, cut and fix in position sawn structural -
wood or steel formwork which ever is appropriate. -
[Link] Grade beam ,strip beam and ramp m2 322.70 310.45 264.92 82,244.41
b. To Steps m2 25.00 - 264.92 -
2.50 Reinforcement steel bar according to [Link] -
price shall includes cutting, bending, placing in -
position and tying wires. -
Dia 8 mm deformed bar kg 3,999.53 3,602.68 78.50 282,810.11
Dia 12 mm deformed bar kg 344.97 392.58 78.50 30,817.72
Dia 14 mm deformed bar kg 3,157.89 2,599.95 78.50 204,096.17
10X2 cm chip wood expansion joint between [Link] and slab
2.60 painted with two coats of asphalt ml 467.50 567.70 75.00 42,577.50
Total Carried to Summary [Link] 987,266.71
3. MASONRY WORK
3.10 Trychitic or equivalent stone masonry foundation -
wall BNGL bedded in cement mortar 1:3 m3 83.05 76.80 2,500.00 192,000.00
3.20 Ditto but above natural ground level externally -
(price includes poiting). m3 124.58 38.15 2,500.00 95,375.00
5/39
[Link] IPD BLOCK
Quantity
ITEM DESCRIPTION Unit RATE Amount Excuted
Construct Trychitic or equivalent stone masonry Retaining wall
bedded in cement mortar of 1:3, Price shall include pointing
exposed faces,5cm thick concrete copping and back fill with
3.30 selected material. m3 345.00 - 1,500.00 -
Total Carried to Summary [Link] 287,375.00
B. SUPER - STRUCTURE -
[Link] WORK -
1.10 Reinforced concrete class C -25, with minimum -
cement content of 360 kg / m3 filled into form -
work and vibrated around rod reinforcement. -
steel bar and form work measured separately -
[Link] elevation column m3 6.32 4.40 3,159.41 13,901.40
[Link] beams and lintel m3 44.21 20.69 3,159.41 65,380.83
1.20 Provide, cut and fix in position sawn structural -
wood or steel formwork which ever is appropriate. -
a. To Elevation column m2 139.04 88.00 264.92 23,312.96
[Link] Beam and lintel m2 576.24 275.92 264.92 73,096.73
1.30 Reinforcement steel bar according to [Link] -
price includes cutting, bending, placing in -
position and tying wires. -
Dia 8 mm deformed bar kg 1,508.93 779.14 78.50 61,162.29
Dia 12mm deformed bar kg 3,423.12 1,910.21 78.50 149,951.65
Dia 14mm deformed bar kg 1,500.13 716.32 78.50 56,231.12
Total Carried to Summary [Link] 443,036.98
2. BLOCK WORK -
2.10 200mm thick class C- HCB wall with the designed -
compressive strength capacity, bedded in cement -
mortar ratio (1:3) and both sides left for plastering. m2 600.84 - 363.83 -
2.20 Ditto as Item 2.01 but 150mm thick HCB wall. m2 501.72 - 311.60 -
2.30 Ditto as Item 2.01 but 100mm thick HCB wall. m2 51.56 - 272.54 -
Total Carried to Summary [Link] -
6/39
Employer: Southern Nations Nationalities Peoples Regional State Health Bureau Takeoff sheet
Consultant: S/N/N/P/R State Construction Authority IPD block
Contractor: Daemat Construction Location Jinka
Project: Jinka General Hospital Expantion Project
page 1
No L*W*H Description No L*W*H Description
11
[Link] OPD BLOCK
1.40 Excavation for isolated footing foundation to a depth not exceeding 99.00 - 166.18
2500mm in ordinary soil with 0.25m working space on both way. m3 -
Trench excavation in ordinary soil for masonry foundation to a
1.5 depth not exceeding 1100 mm from reduced level. m3 149.93 - 135.40 -
1.6 Selected borrowed fill brought from out side -
under hard core well ram in layers not -
exceeding 20cm thick. m3 895.72 2,286.78 238.35 545,052.82
1.7 Cart away surplus excavated material to an -
appropriate tip m3 1,449.95 1,815.80 53.44 97,036.57
1.8 25cm thick basaltic or equivalent stone hard -
core well rolled consolidated and blinded with -
crushed stones. m2 410.44 410.38 144.05 59,114.52
Total Carried to Summary [Link] 1,066,326.24
2. CONCRETE WORK
2.1 5cm thick lean concrete class C-7, with
minimum cement content of 150kg /m3
[Link] footing foundation m2 48.40 48.60 123.23 5,988.98
[Link] massonary foundation m 2
79.08 66.15 123.23 8,151.66
[Link] grade beam m2 44.84 37.80 123.23 4,658.09
2.2 10cm thick reinforced concrete floor slab class -
C-25,with minimum cement content of 360 kg /m3 -
well spread and leveled steel bar m. separately) m2 410.44 410.38 315.94 129,653.88
2.3 Reinforced concrete class C -25, with minimum -
cement content of 360 kg / m3 filled into form -
work and vibrated around rod reinforcement. -
steel bar and form work measured separately -
[Link] footing pads m3 11.00 7.25 3,159.41 22,913.62
[Link] foundation columns m3 4.40 - 3,159.41 -
[Link] grade beam ,ramps & Steps m3 32.32 22.52 3,159.41 71,149.91
2.4 Provide, cut and fix in position sawn structural -
wood or steel formwork which ever is appropriate. -
[Link] footing pads m2 48.40 29.01 264.92 7,685.33
[Link] foundation columns m2 88.00 - 264.92 -
[Link] Grade beam m2 225.20 253.89 264.92 67,260.54
[Link] Steps and ramps m2 25.00 - 264.92 -
2.5 Reinforcement steel bar according to [Link] -
price shall includes cutting, bending, placing in -
position and tying wires. -
a) Dia 8 mm deformed bar kg 2,308.62 2,442.82 78.50 191,761.23
b) Dia 12 mm deformed bar kg 468.86 330.71 78.50 25,960.58
c) Dia 14 mm deformed bar kg 3,196.22 2,230.45 78.50 175,090.60
12/39
[Link] OPD BLOCK
Quantity
ITEM DESCRIPTION Unit RATE Amount Excuted
2.60 10X2 cm chip wood expansion joint between -
[Link] and slab painted with two coats of asphalt ml 436.86 466.30 75.00 34,972.50
Total Carried to Summary [Link] 745,246.93
3. MASONRY WORK
3.1 50cm thick Trychitic or equivalent stone masonry
foundation wall BNGL bedded in cement mortar 1:3. m3 65.90 65.90 2,500.00 164,750.00
3.2 Ditto but above natural ground level externally -
(price includes pointing). m3 72.49 32.95 2,500.00 82,375.00
Total Carried to Summary [Link] 247,125.00
B. SUPER - STRUCTURE
[Link] WORK
1.10 Reinforced concrete class C -25, with minimum
cement content of 360 kg / m3 filled into form
work and vibrated around rod reinforcement.
steel bar and form work measured separately
[Link] elevation column m3 5.28 4.40 3,159.41 13,901.40
[Link] beams and lintel m3 19.09 16.89 3,159.41 53,362.43
1.2 Provide, cut and fix in position sawn structural -
wood or steel formwork which ever is appropriate. -
a. To Elevation column m2 116.16 88.00 264.92 23,312.96
[Link] toptie Beam and lintel m2 247.72 225.20 264.92 59,659.98
1.3 Reinforcement steel bar according to [Link] -
price includes cutting, bending, placing in -
position and tying wires. -
a) Dia 8 mm deformed bar kg 775.37 669.29 78.50 52,539.11
b) Dia 12mm deformed bar kg 1,800.58 1,631.14 78.50 128,044.27
c) Dia 14mm deformed bar kg 872.41 716.32 78.50 56,231.12
Total Carried to Summary [Link] 387,051.28
13/39
Employer: Southern Nations Nationalities Peoples Regional State Health Bureau Takeoff sheet
Consultant: S/N/N/P/R State Construction Authority OPD block
Contractor: Daemat Construction Location Jinka
Project: Jinka General Hospital Expantion Project
page 1
No L*W*H Description No L*W*H Description
A. SUB- STRUCTURE 2. CONCRETE WORK
1. EXCAVATION & EARTH WORK 2.10 Lean concrete
1.01 Demolish existing stracture a,under strip beam
2 35.10 at axia X01',X01&X04
1 1.00 1.00 pcs 0.50
1.00 pcs total 35.10 m2
1.02 Trees Removing 2 13.50 at axia Y01&Y08
20 1.00 20.00 pcs 0.50
20.00 pcs total 13.50 m2
1.03 Site clearance 48.60 m2 total
1 39.10 L=35.10+(2*2)=39.10 under masonry
17.20 W=13.20+(2*2)=17.20 3 35.10 at axia X01',X01&X04
672.52 m2 0.50
672.52 m2 total 52.65 m2
1.04 Bulk excavation 2 13.50 at axia Y01&Y08
1 39.10 L=35.10+(2*2)=39.10 0.50
17.20 W=13.20+(2*2)=17.20 13.50 m2
2.50 D=2.50 66.15 m2 total
1,681.30 m2 under grade beam
1,681.30 m2 total 2 35.10 at axis X01'-X04
1.06 Back fill 0.25
1 39.10 L=35.10+(2*2)=39.10 17.55 m2
17.20 W=13.20+(2*2)=17.20 6 13.50 at axis Y01-Y08
3.25 D=2.50+0.60+0.15=3.25 0.25
2,185.69 m3 20.25 m2
Deduction 37.80 m2 total
2 35.10 L=35.10m 2.20 Floor slab
0.50 W=0.50m 410.38 referb area of hard core
1.15 D=1.150m 410.38 m2 total
40.37 m2 ------ deduct beam+masonry 2.30 RC concrete c-25
2 13.20 L=13.20m 2 35.10 a, strip beam
2.00 W=0.50m 0.50 at axia X01',X01&X04
1.15 D=1.150m 0.15
60.72 m2 ------ deduct beam+masonry 5.27 m3
2,286.78 m3 total 2 13.25 at axis Y01 & Y08
1.07 Cart away 0.50
672.52 0.15
0.20 1.9875 m3
134.50 m3 for site clearance 7.25 m3 total
1,681.30 m for bulk excavation
3
b, grade beam
1,815.80 m3 total 5 35.10 at axis X01 - X05
1.08 Hard core 0.20 m2
1.0 33.50 L=35.10-(8*0.20)=33.50 0.40
12.25 W=13.20-(5*0.20)=12.20 14.04 m3
410.38 m2 2 13.25 at axis Y01 & Y08
410.38 m2 total 0.20
0.40
2.12 m3
Employer: Southern Nations Nationalities Peoples Regional State Health Bureau Takeoff sheet
Consultant: S/N/N/P/R State Construction Authority OPD block
Contractor: Daemat Construction Location Jinka
Project: Jinka General Hospital Expantion Project
page 2
No L*W*H Description No L*W*H Description
6.00 13.25 at axis Y02-Y07 3.2 Masonry ANGL
0.20 3 35.10 at axis X01',X01&X04
0.40 0.50
6.36 m3 0.50
22.52 m3 total 26.33 m3
2.40 Formwork 2 13.25 at axis Y01 & Y08
strip beam 0.50
2 35.10 at axia X01',X01&X04 0.50
0.30 W=2*0.15=0.30 6.63 m3
21.06 m2 32.95 m3 total
2 13.25 at axis Y01 & Y08
0.30 W=2*0.15=0.30 B. SUPER- STRUCTURE
7.95 m2 [Link] WORK
b,grade beam 1.1 reiforsd concrete class C-25
5 35.10 40 2.75 [Link] elevation column
0.80 W=2*0.40=0.80 0.20
140.40 m2 0.20
8 13.20 at axis Y02-Y07 4.40 m3
0.80 W=2*0.40=0.80 4.40 m3 total
84.48 m2 b. in top tie beam
253.89 m2 total 5 35.10
2.50 Reinforcement steel bar 0.20
refer bar schedule tabel 0.30
2,442.82 kg total Dia 8 mm deformed bar 10.53 m3
330.71 kg total Dia 12 mm deformed bar 8 13.25
2,230.45 kg total Dia 14 mm deformed bar 0.20
2.60 10X2 cm chip wood expansion 0.30
4.00 6.36 m3
2.00 35.10 16.89 m3 total
280.80 ml 1.20 formwork
7.00 [Link] elevation column
2.00 13.25 40 2.75 L=2.75
185.50 ml 0.80 W=(4*0.20)=0.80
466.30 ml total 88.00 m2
3. MASONRY WORK 88.00 m2
3.1 Masonry BNGL b. in top tie beam
3.00 35.10 at axis X01',X01&X04 5 35.10
0.50 0.80 W=(2*0.30)+0.2=0.80
1.00 140.40 m2
52.65 m3 8 13.25 L=13.25
2.00 13.25 at axis Y01 & Y08 0.80 W=(2*0.30)+0.2=0.80
0.50 84.8 m2
1.00 225.20 m2
13.25 m3 1.30 Reinforcement steel bar
65.90 m3 total //refer bar schedule tabel
669.29 kg total Dia 8 mm deformed bar
1,631.14 kg total Dia 12 mm deformed bar
716.32 kg total Dia 14 mm deformed bar
SUB-STRUCTURE-OPD
Total Length of bar (m)
Bar Location Bar dia (mm) Bar Length (M) Bar per membr No Of member Total no of bar ɸ8 ɸ10 ɸ12 ɸ14 ɸ16 ɸ20
STRIP BEAM
sb1 ɸ12 12.00 9.00 2.00 18.00 216.00
ɸ8 0.50 176.00 2.00 352.00 176.00
sb2 ɸ12 12.00 6.00 2.00 12.00 144.00
ɸ12 2.00 3.00 2.00 6.00 12.00
STRRUP ɸ8 0.50 96.00 2.00 192.00 96.00
GRADE BEAM
GB1 & GB2 on axis X01 to X05
TOP ɸ14 11.88 3.00 5.00 15.00 178.20
ɸ14 10.60 3.00 5.00 15.00 159.00
ɸ14 5.92 3.00 5.00 15.00 88.80
ɸ14 9.25 3.00 5.00 15.00 138.75
BOTTOM ɸ14 9.30 3.00 5.00 15.00 139.50
ɸ14 10.45 6.00 5.00 30.00 313.50
ɸ14 6.40 3.00 5.00 15.00 96.00
STRRUP ɸ8 1.10 176.00 5.00 880.00 968.00
GB3 & GB4 on axis Y01 to Y08
TOP ɸ14 9.75 3.00 8.00 24.00 234.00
ɸ14 6.95 3.00 8.00 24.00 166.80
BOTTOM ɸ14 7.10 3.00 8.00 24.00 170.40
ɸ14 6.60 3.00 8.00 24.00 158.40
STRRUP ɸ8 1.10 67.00 8.00 536.00 589.60
FLOOR SLAB ɸ8 3.70 66.00 1.00 66.00 244.20
ɸ8 4.80 66.00 5.00 330.00 1584.00
ɸ8 5.80 66.00 1.00 66.00 382.80
L=4*2+2.4+1.85=12.25 ɸ8 12.25 20.00 1.00 20.00 245.00
ɸ8 12.25 25.00 5.00 125.00 1531.25
ɸ8 12.25 30.00 1.00 30.00 367.50
Total Length (M) 6,184.35 - 372.00 1,843.35 - -
Weight per Kg 0.395 0.617 0.889 1.210 1.580 2.469
Total Kg 2,442.82 - 330.71 2,230.45 - -
SUPER-STRUCTURE-OPD
19
[Link] DIAGNOSTIC BLOCK
20/39
[Link] DIAGNOSTIC BLOCK
21/39
Employer: Southern Nations Nationalities Peoples Regional State Health Bureau Takeoff sheet
Consultant: S/N/N/P/R State Construction Authority DIAGNOSTIC block
Contractor: Daemat Construction Location Jinka
Project: Jinka General Hospital Expantion Project
page 1
No L*W*H Description No L*W*H Description
Employer: Southern Nations Nationalities Peoples Regional State Health Bureau Takeoff sheet
Consultant: S/N/N/P/R State Construction Authority DIAGNOSTIC block
Contractor: Daemat Construction Location Jinka
Project: Jinka General Hospital Expantion Project
page 2
No L*W*H Description No L*W*H Description
grade beam B. SUPER- STRUCTURE
at axis X01,X02 & X03 [Link] WORK
3 21.95 W=2*0.40=0.80 a. in elevation column
0.80 18 2.75
52.68 m2 0.20
6 12.35 at axis Y01-Y06 0.20
0.80 W=2*0.40=0.80 1.98 m3
59.28 m 2
1.98 m3 total
132.54 m2 total b. in top tie beam
2.50 Reinforcement steel bar 3 21.95
refer bar schedule tabel 0.20 m2
1,396.25 kg total Dia 8 mm deformed bar 0.30
253.10 kg total Dia 12 mm deformed bar 3.95 m3
1,054.26 kg total Dia 14 mm deformed bar 6 12.35 m2
2.60 10X2 cm chip wood expansion 0.20
3 21.95 65.85 0.30
65.85 ml 4.45 m3
6 12.35 74.10 8.40 m3 total
74.10 ml 1.2. formwork
139.95 ml total 18 2.75 a. in elevation column
3. MASONRY WORK 4 0.20
3.1 Masonry BNGL 39.60 m2
3 21.95 at axis X01,X02 & X03 39.60 m2 total
0.50 b. in top tie beam
1.00 0
32.93 m3 3 21.95
2 12.35 at axis Y01 & Y06 0.80
0.50 52.68 m2
1.00 6 12.35
12.35 m3 0.80
45.28 m3 total 59.28 m2
3.2 Masonry ANGL 111.96 m2 total
3 21.95 at axis X01,X02 & X03 1.30 Reinforcement steel bar
0.50 refer bar schedule tabel
0.50 Davge=0.5(0.3+.7)=0.50m 322.08 kg total Dia 8 mm deformed bar
16.46 m3 769.78 kg total Dia 12 mm deformed bar
2 12.35 at axis Y01 & Y06 322.34 kg total Dia 14 mm deformed bar
0.50
0.50 Davge=0.5(0.3+.7)=0.50m
6.18 m3
22.64 m3 total
Employer: Southern Nations Nationalities Peoples Regional State Health Bureau Takeoff sheet
Consultant: S/N/N/P/R State Construction Authority DIAGNOSTIC block
Contractor: Daemat Construction Location Jinka
Project: Jinka General Hospital Expantion Project
page 2
No L*W*H Description No L*W*H Description
2.0 .Block Work deductions
2.1 .20 cm thick 8 0.80 W=0.9
2 18.25 L=21.95-(6*.20)=20.75-2.50=18.25 2.73 H=2.73
2.73 H=2.73 -17.47 m2 D7
99.65 m2 13 0.70 W=0.7
2 11.75 L=12.35-(3*.20)=11.75 2.73 H=2.10
2.73 H=2.73 -24.84 m2 D8
64.16 m2 1 1.40 W=1.20
163.80 m2 2.73 H=2.
deductions -3.82 m2 D15
7 1.50 W=1.50 1 0.80 W=1.20
1.63 H=1.63 2.73 H=2.
-17.12 m2 W2 -2.18 m2 D16
1 1.05 W=1.03 4 1.20 W=1.20
1.63 H=1.63 1.5 H=0.6
-1.71 m2 W13 -7.20 m2 W19
4 1.20 W=1.20 1 0.80 W=0.8
0.6 H=0.6 1 H=0.6
-2.88 m2 W20 -0.80 m2 W3
1 4.15 W=4.15 1 1.20 W=1.20
0.6 H=0.6 0.6 H=0.6
-2.49 m2 W26 -0.72 m2 W20
-24.20 442.84 m2 total
139.60 m total
2
27
[Link] MCH BLOCK
A B C D E F G
1
2 Block ID :- MCH BLOCK
3 Quantity
ITEM DESCRIPTION Unit RATE Amount Excuted
4 Contract Excuted
5 A. SUB STRUCTURE
6 [Link] & Earth work
Demolish any stracture exist on the construction site and relocate existing
7 1.1 utilities to an approprate place. Price shall include excavation,demolishing,
cartaway transported soil and other related works to clear and prepare the
site for the new building to be constructed. Ls 1.00 1.00 50,000.00 50,000.00
28/39
[Link] MCH BLOCK
A B C D E F G
49 [Link] and slab painted with two coats of ml 216.00 393.20 75.00 29,490.00
50 Total Carried to Summary [Link] 1,894,049.02
51
52 3. Masonary Work
53 Trychitic or equivalent stone masonry foundation
Supply and Construct 50cm thick basaltic or equivalent stone masonry
54 3.1 foundation below NGL, bedded and jointed in cement and sand mortar,
1:[Link] to the drawing. m3 143.80 93.78 2,500.00 234,451.88
Ditto item 3.1,but roughly dressed Trachytic stone masonry foundation
55 3.2 above NGL , bedded , jointed and one side pointed in cement and sand
mortar,1:3. m3 32.25 44.66 2,500.00 111,643.75
56 3.3 Ditto as Itm 3.2, but for steps and ramps m3 15.76 - 2,500.00 -
57 Total Carried to Summary [Link] 346,095.63
58
59 B) SUPER STRUCTURE
60 1 . Concrete Work
Reinforced Concrete class C-25, a minimum cement content of 360kg /m3 of
concrete, filled in to formwork and vibrated around reinforcements,
61 1.1 formwork and reinforcements shall be measured separately.
29/39
Employer: Southern Nations Nationalities Peoples Regional State Health Bureau Takeoff sheet
Consultant: S/N/N/P/R State Construction Authority MCH block
Contractor: Daemat Construction Location Jinka
Project: Jinka General Hospital Expantion Project
page 1
No L*W*H Description No L*W*H Description
Floor Slab
L=5-0.2=4.80 ɸ8 4.80 30.00 1.00 30.00 144.00
ɸ8 4.80 12.00 1.00 12.00 57.60
ɸ8 4.80 22.00 1.00 22.00 105.60
ɸ8 4.80 14.00 1.00 14.00 67.20
L=4.2-0.2=4 ɸ8 4.00 30.00 1.00 30.00 120.00
ɸ8 4.00 12.00 1.00 12.00 48.00
ɸ8 4.00 22.00 1.00 22.00 88.00
ɸ8 4.00 14.00 1.00 14.00 56.00
L=5.65-0.2=5.45 ɸ8 5.45 30.00 1.00 30.00 163.50
ɸ8 5.45 12.00 1.00 12.00 65.40
ɸ8 5.45 22.00 1.00 22.00 119.90
ɸ8 5.45 14.00 1.00 14.00 76.30