Location
Submitted
SN NO. Trade RFI NO. (Building Date
/ Zone)
1 S KAIG3-RFI-CO-S-8415-00 2R 1-Aug-22
2 S KAIG3-RFI-EC-S-8422-00 5A 2-Aug-22
3 S KAIG3-RFI-CO-S-8475-00 2D 2-Aug-22
4 S KAIG3-RFI-PC-S-8462-00 4 4-Aug-22
5 S KAIG3-RFI-EC-S-8487-00 5A 6-Aug-22
6 A KAIG3-RFI-PA-A-0390-00 K 8-Aug-22
7 A KAIG3-RFI-CO-A-0990-00 1B 8-Aug-22
8 C KAIG3-RFI-SW-C-5075-01 6B 9-Aug-22
9 C KAIG3-RFI-SW-C-5073-01 6B 9-Aug-22
10 S KAIG3-RFI-PG-S-8525-00 4D 9-Aug-22
11 C KAIG3-RFI-SW-C-3010-01 6A 11-Aug-22
12 S KAIG3-RFI-EC-S-8568-00 5A 11-Aug-22
13 S KAIG3-RFI-WG-S-8542-00 4 13-Aug-22
14 A KAIG3-RFI-CO-A-1000-00 1C 14-Aug-22
15 E KAIG3-RFI-TG-E-0404-01 1N 14-Aug-22
16 LC KAIG3-RFI-SM-LC-0752-00 1G 14-Aug-22
17 LC KAIG3-RFI-SM-LC-0753-00 1G 14-Aug-22
18 C KAIG3-RFI-SW-C-6834-00 6B 15-Aug-22
19 C KAIG3-RFI-SW-C-6848-00 DE2 8-Aug-22
20 C KAIG3-RFI-SW-C-6940-00 6 15-Aug-22
21 C KAIG3-RFI-DG-C-6949-00 6A 16-Aug-22
22 C KAIG3-RFI-DG-C-6948-00 DE2 16-Aug-22
23 C KAIG3-RFI-DG-C-6947-00 H6 16-Aug-22
24 LC KAIG3-RFI-MB-LC-0677-00 4B 16-Aug-22
25 E KAIG3-RFI-SW-E-0542-00 2B 17-Aug-22
26 C KAIG3-RFI-PG-C-7003-00 4D 18-Aug-22
27 C KAIG3-RFI-PG-C-7004-00 4D 18-Aug-22
28 E KAIG3-RFI-SW-E-0543-00 2B 18-Aug-22
29 A KAIG3-RFI-AG-A-1004-00 2B 20-Aug-22
30 A KAIG3-RFI-AG-A-1005-00 2Q 20-Aug-22
31 S KAIG3-RFI-CO-S-8689-00 2E 20-Aug-22
32 S KAIG3-RFI-EC-S-8667-00 5A 20-Aug-22
33 S KAIG3-RFI-EC-S-8746-00 5A 20-Aug-22
34 S KAIG3-RFI-EC-S-8747-00 5A 20-Aug-22
35 E KAIG3-RFI-SW-E-0551-00 2B 21-Aug-22
36 C KAIG3-RFI-SW-C-6982-00 G 22-Aug-22
37 E KAIG3-RFI-SW-E-0554-00 3A 22-Aug-22
38 LC KAIG3-RFI-SW-LC-0769-00 4C 22-Aug-22
39 LC KAIG3-RFI-SW-LC-0770-00 4C 22-Aug-22
40 S KAIG3-RFI-CO-S-8754-00 2M 22-Aug-22
41 C KAIG3-RFI-SW-C-7080-00 G 23-Aug-22
42 C KAIG3-RFI-SW-C-7120-00 G&K 23-Aug-22
43 C KAIG3-RFI-SW-C-7130-00 G 23-Aug-22
44 C KAIG3-RFI-SW-C-7133-00 B 23-Aug-22
45 P KAIG3-RFI-PC-P-0284-00 2C 23-Aug-22
46 C KAIG3-RFI-SW-C-7077-00 L5 24-Aug-22
47 S KAIG3-RFI-CO-S-8757-00 2H 24-Aug-22
48 E KAIG3-RFI-MB-E-0555-00 4B 25-Aug-22
49 SU KAIG3-RFI-CO-SU-2906-00 1A 25-Aug-22
50 S KAIG3-RFI-CO-S-8561-00 2M 27-Aug-22
51 S KAIG3-RFI-CO-S-8856-00 2E 28-Aug-22
52 S KAIG3-RFI-CO-S-8865-00 2R 28-Aug-22
53 A KAIG3-RFI-CO-A-1021-00 2M 31-Aug-22
54 A KAIG3-RFI-CO-A-1020-00 2M 31-Aug-22
55 C KAIG3-RFI-RD-C-7290-00 F&K 30-Aug-22
56 C KAIG3-RFI-SW-C-7287-00 F&G 30-Aug-22
57 C KAIG3-RFI-SW-C-7270-00 G4 30-Aug-22
58 C KAIG3-RFI-SW-C-7260-00 F 30-Aug-22
59 M KAIG3-RFI-SW-M-0291-00 G 31-Aug-22
60 M KAIG3-RFI-SW-M-0290-00 G 31-Aug-22
61 S KAIG3-RFI-CO-S-8880-00 2N 29-Aug-22
62 SU KAIG3-RFI-CO-SU-2910-00 2N 29-Aug-22
63 C KAIG3-RFI-SW-C-7228-00 E 30-Aug-22
64 C KAIG3-RFI-SW-C-7227-00 E 30-Aug-22
65 C KAIG3-RFI-SW-C-6980-00 E&D 30-Aug-22
66 C KAIG3-RFI-SW-C-6980-01 E&D 30-Aug-22
67 S KAIG3-RFI-CO-S-8843-00 2H 29-Aug-22
68 S KAIG3-RFI-CO-S-8844-00 2H 29-Aug-22
69 C KAIG3-RFI-RG-C-7229-00 2D & 2E 30-Aug-22
70 S KAIG3-RFI-CO-S-8813-00 6 29-Aug-22
Action Taken
Steel Reinforcements for internal columns and
wall of NORTH ADMINSTRATION axis 02/BC,
02/1-02/2 to 02/AZ, 02/1-02/2 (as highlighted)
Zone 2R (LEVEL as highlighted)
Concrete Pouring & Shuttering for Columns
(above the level +872.35) of Boundary Wall @
Grid (R/18-22), at Energy Center 2, as highlighted
area in attached drawing's.
Steel Reeinforcements for RC concrete ETFE
PUMP ROOM S.O.G.. zone 2D axis 02-J inner line
(as highlighted) at CRESCENT ,KAIG3-SCR-CO-S-
0193-00
Concreting for central bridge abutment grid
01/M zone 4 (as highlighted)
Concrete Pouring & Shuttering for Columns of
Boundary Wall @ Grid (A/6-12B), at Energy
Center 2, as highlighted area in attached
drawing's.
Inspection for application of Cementitious water
Proofing (3rd Coat) at Prayer Area Zone-K
(outside) - as Highlighted
Base Seal and Extrusion Aluminum Installation
between Axis 01/D - 01/E.
Base Seal and Extrusion Aluminum Installation
between Axis 01/D - 01/E.
"INSPECTION FOR INSTALLATION OF ALL RINGS
(RISER) AND SLAB FOR FW-A-3-7.1 (As
Highlighted) "
Concrete Pouring for Blinding under Fountain 1,
At Inner Side of Plant room, Inside Physic
Garden, as highlighted in attached drawing's.
INSPECTION OF INSTALLATION OF ALL RINGS
(RAISER) AND SLAB FOR FW-A-07 (AS ATTACHED)
Surface Preparation prior to Waterpoofing for
Footings & Garde Beams @ Grid (1-3/C-I), Inside
Energy Center 2, as highlighted area in attached
drawing's.
Surface Preparation prior to Waterpoofing for
Beams of Jetty 1 & Jetty 2 at Boat Garden inside
Water Garden , as highlighted area in the
attached drawings
Base Seal and Extrusion Aluminum Installation
between Axis 01/I-01/J.
Installation of PVC Conduit Sleeves Passing the
Concrete (3x75mm) for Low Voltage (Power
System) at Butterfly Garden and as highlighted in
the drawing.
Installation of straight PVC conduit (dia.25mm)
and Box for Voice and DATA (WIFI & CAM) at
Crescent - 01 Infill Wall (axis in between 01/1P &
01/1Q) as per attached highlighted drawing.
Installation of straight PVC conduit (dia.25mm)
and Box for Security (CAM) at Crescent - 01 Infill
Wall (axis in between 01/1P & 01/1Q) as per
attached highlighted drawing.
"INSPECTION FOR INSTALLATION OF ALL RINGS
(RISER) AND SLAB FOR FW-A-3-14 (As
Highlighted) "
Inspection of Excavation for MV Line from
D/MV/18 to E/MV/09 and D/MV/19 to E/MV/08
including all Pit - at Zone-D&E - as highlighted
Inspection of Excavation for Heating and Chilled
Water Line at Zone-G&K including Pit K/DC/02,
K/DC/01, G/DC/16, G/DC/08, G/DC/15 - As
highlighted ,
Inspection & Compaction tests of Single Layer
(Sub-Base) Backfilling on Irrigation Sub-Main Line
Distribution Network (50,90 mm line) at
Discovery Garden, as highlighted in attached
drawings.(SP 140)
Inspection & Compaction tests of Single Layer
(Sub-Base) Backfilling on Low Current Lines of
Telecom and Fire Alarm & Security Lines, Inside
Discovery Garden at highlighted area in attached
Drawing's.
Inspection & (SPCompaction
140) tests of Single Layer
(Sub-Base) Backfilling on Electrical Lines of Low
voltage Lines & Emergency Lines, Inside
Discovery Garden at highlighted area in attached
Drawing's.
Installation(SP
of 140)
EMT Conduit (Dia. 3/4) and Box
for Voice Data (CAM, WIFI & Telephone) at
Management and Maintenance Bldg. (GF 5000D
Passage, GF 5000 Reception) as per attached
Installation
highlighted of straight UPVC Conduit (Dia.
drawing.
160mm) Medium Voltage Ductbank no. DD/D-
MV/29 (from Manhole no. D/MV/17 to
D/MV/33) and (from Manhole no. D/MV/33 to
D/MV/03) at the Site Work as per attached
highlighted drawings.
Excavation & Bed Preparation for Electrical Lines
of Low Voltage (MH/PG/LV/09-12) and
Emergency (MH/PG/EM/10-13), Inside Physic
Garden as highlighted in attached drawing's.
Excavation & Bed Preparation for Low Current
Lines (MH/PG/LC/13-17) and Fire Alarm &
Security lines (MH/PG/FA/09-12), Inside Physic
Garden as highlighted
Installation of straight in attached
UPVC drawing's.
Conduit (Dia.
160mm) Medium Voltage Ductbank no. DD/D-
MV/12 (from Manhole no. D/MV/08 to
D/MV/31) and (from Manhole no. D/MV/31 to
D/MV/19) at the Site Work as per attached
highlighted
Mockup for drawings.
Stone Cladding on Boundary wall
(Outer Side) of Aviary Garden, Installed Location
at Grid (12-14/Left Side) at Aviary Garden, as
Highlighted area in Attached Drawings & Photos.
Mockup for Stone Cladding for Crescent
between Axis 02AY-02AZ & 02AW-02AX as
highligted (Zone 2Q).
Concreting for Infill wall inner at Crescent at axis
02O & 02P buttress BII BIV 77 & 78 (As
highlighted) ZONE 2E
Concrete Pouring & Shuttering for Columns (2nd
lift, above the level +872.35) of Boundary Wall @
Grid (M/17-22), at Energy Center 2, as
highlighted area in attached drawing's.
Surface preparation prior to waterproofing for
footings (inner Side) of Boundary wall @ grid
(01-C1), inside energy center 2, as highlighted
area in attached drawing's
Base Primer Coating prior to damp proofing for
Footings (Inner Side) of Boundary Wall @ Grid
(0-1/C-I), Inside Energy Center 2, as highlighted
area in attached
Installation drawing's.
of straight UPVC Conduit (Dia.
160mm) Medium Voltage Ductbank no. DD/D-
MV/15 (from Manhole no. D/MV/17 to
D/MV/02) & DD/D-MV/08 (from Manhole no.
D/MV/02 to D/MV/01) at the Site Work as per
attached
Inspectionhighlighted drawings.
and Compaction Test for backfilling
Sub-grade 5th Layer (5 of 6) around MV Line Pit
G/MV/28 at Zone-G - As Highlighted (Stock Pile#
133 A-1-B)
Installation of straight UPVC Conduit (Dia.
160mm) Medium Voltage Ductbank no. CC/D-
MV/03 (from Manhole no. C/MV/03 to
C/MV/30) at the Site Work as per attached
highlighted
Installation ofdrawings.
UPVC conduit (2x110mm dia.) Low
Current (Fire and Security) Ductbank [Link]/D-
FS/01 in between Hanhole (G/RC-FS/02 to G/RC-
FS/45) at the South Side Nursery (SW) as per
attached highlighted drawing.
Installation of UPVC conduit (4x110mm dia.) Low
Current (TELECOM) Ductbank [Link]/D-TL/01 in
between Handhole (G/TL/03 to G/TL/01) at the
South Side Nursery (SW) as per attached
highlighted drawing.
Antitermite for ETFE PUMP ROOM under mass
concrete zone 2M (as highlighted) at CRESCENT
Inspection of Blinding Concrete under Heating &
Chilled Water Line Isolation Pit for G/DH/04,
G/DH/05 and G/DC/06 at Zone-G - as highlighted
Inspection of Blinding Concrete under Heating &
Chilled Water Line Isolation Pit for G/DC/15,
G/DC/08, G/DC/16, K/DC/01, K/DC/02 at Zone-
G&K - as highlighted
Inspection of Excavation for Heating and Chilled
Water Line at Zone-G including Pit F/DH/04,
F/DC/05, G/DC/01, G/DH/02 - As highlighted
Inspection of Excavation for Heating and Chilled
Water Line at Zone-B including Pit G/DC/20,
G/DH/21, G/DC/22 - As highlighted
Pipe Sleeves Installation of Outer infill Wall
Mechanical CHW (S&R) From Axis (02/2G to
02/H ) At Crescent 2; (UPVC Pipe Class 4 dia 400
mm); As per High lighted Attached Approved
Shop Drawing.
"Inspection of Excavation for MV Line Pulling Pit
- L/MV/16, L/MV/05, L/MV/01 - as highlighted "
Steel Reinforcements for Tunnel 1 wall & slab
part-C (as Highlighted) Zone 2H 875.00
Installation of EMT Conduit (Dia. 3/4, 1 inch.)
and Box (Ceiling Mounted) for Lighting (E1,E1/CE
& Presence Detector ) at Management and
Maintenance Bldg. (GF 5000 C Passage & GF
5000 Lobby ) as per attached highlighted
drawing.
Level and Location for Strip Footing blinding
between PC 5-7 Zone 1A (as highlighted)
Concreting for plain concrete at DEVONIAN
GARDEN zone 2M BETWEEN axis 02-AN & 02-AL
(as highlighted)
Concreting for Infill wall Beam at axis 02P - 02Q
Zone 2E (as highlighted)
Surface preparation & Base primer coating for
Infill wall bw BOI 126_127 BII 128_127_126 zone
2R up S. O. G level 870.40 at CRESCENT (as
highlighted)
CHB laying for Pump Room upto lintel beam at
Zone 2M axis 02AN (as highlighted) using 20cm
CHB
1st Layer of CHB laying for Pump Room at Zone
2M axis 02AN (as highlighted) using 20cm CHB
Excavation and Soil Preparation prior to start
backfilling Layers for Roads, Starting from
ST.0+000 to 0+300 at Zone F&K - as highlighted
Inspection of Blinding Concrete under Heating &
Chilled Water Line Isolation Pit for F/DH/04,
F/DC/01, F/DC/05 at Zone-F&G - as highlighted
Inspection of Blinding Concrete under Heating &
Chilled Water Line Isolation Pit for G/DH/02,
G/DH/21, G/DC/01, G/DC/03, G/DC/20, G/DC/22
at Zone-B&G - as highlighted
Inspection of Excavation for Heating and Chilled
Water Line at Zone-F including Pit F/DC/01 &
F/DC/02 - As Chiled
Pre insulated highlighted
Water Pipes (S&R)
200mmØ( laying ,Aligment ,Leveling and fit up)
From point (E:647483.48 N:2713871.373) to
(E:647576.326 N:2713932.524). Pre insulated
Heat Water Pipes (S&R)
150mmØ( laying
Pre insulated ,Aligment
Heat ,Leveling
Water Pipes (S&R)and fit up)
From point (E
150mmØ( laying ,Aligment ,Leveling and fit up)
From point (E:647473.054 N:2713846.088) to
(E:647499.164 N:2713788.554). At zone G. As
per highlighted Area in the attached Dwg.
Concreting for Diaphragm Wall axis 02AQ (1st
stage toc 874.00) (2nd part) (as highlighted)
Zone 2N
Level and Location for Diaphragm Wall axis 02AQ
(1st stage toc 874.00) (2nd part) (as highlighted)
Zone 2N
Inspection of Concrete Pouring for Wall of MV
Line Pit - E/MV/02, E/MV/05, E/MV/01 and
E/MV/03 at Zone-E (As Highlighted)
Inspection of Formwork for Wall of MV Line Pit -
E/MV/02, E/MV/05, E/MV/01 and E/MV/03 at
Zone-E (As Highlighted)
Inspection of Formwork for footing of MV Line
Pit - E/MV/02, E/MV/05, D/MV/04, D/MV/32
and D/MV/03 at Zone-E&D (As Highlighted)
Inspection of Formwork for footing of MV Line
Pit - E/MV/02, E/MV/05, D/MV/04, D/MV/32
and D/MV/03 at Zone-E&D (As Highlighted)
Two layer of 4mm thick modified bituminous
waterproofing membrane for TUNNEL 1 wall
(outer) Zone 2H PART C (as highlihgted)
Protection layer of 4mm thick bituminous
protection board for TUNNEL 1 wall (outer) Zone
2H PART C (as highlihgted)
"Inspection and compaction test for 1st layer
under lower EPDM for cretaceous garden zone
2D,2E (as highlighted), KAIG3-SCR-GN-C-0027-
00 "
Concreting for Retaining wall (FOUNDATION)
Between Axis 02M-02L (as highlighted) Zone 6
Location
Submitted
SN NO. Trade RFI NO. (Building Date
/ Zone)
1 s KAIG3-RFI-CO-S-8331-01 2D 9/10/22
2 s KAIG3-RFI-CO-S-8582-00 2Q 9/11/22
3 s KAIG3-RFI-CO-S-8928-00 1A 9/5/22
4 s KAIG3-RFI-CO-S-9027-00 2F 9/20/22
5 s KAIG3-RFI-CO-S-9028-00 2R 9/1/22
6 s KAIG3-RFI-LM-S-9042-00 1G 9/1/22
7 s KAIG3-RFI-LM-S-9043-00 1G 9/1/22
8 s KAIG3-RFI-CO-S-9083-00 1P 9/6/22
9 s KAIG3-RFI-CO-S-9093-00 2R 9/4/22
10 s KAIG3-RFI-CO-S-9094-00 2R 9/4/22
11 s KAIG3-RFI-CO-S-9095-00 2R 9/4/22
12 s KAIG3-RFI-CO-S-9162-00 2R 9/7/22
13 s KAIG3-RFI-CO-S-9171-00 2E 9/7/22
14 s KAIG3-RFI-CO-S-9172-00 2E 9/7/22
15 s KAIG3-RFI-CO-S-9173-00 2E 9/8/22
16 s KAIG3-RFI-LM-S-9178-00 1G 9/7/22
17 s KAIG3-RFI-LM-S-9180-00 1G 9/7/22
18 s KAIG3-RFI-CO-S-9228-00 2Q 9/11/22
19 s KAIG3-RFI-WG-S-9272-00 4A 9/13/22
20 s KAIG3-RFI-WG-S-9273-00 4A 9/13/22
21 s KAIG3-RFI-WG-S-9273-01 4A 9/20/22
22 s KAIG3-RFI-CO-S-9318-00 2H 9/17/22
23 s KAIG3-RFI-LM-S-9330-00 1G 9/18/22
24 s KAIG3-RFI-LM-S-9331-00 1G 9/20/22
25 s KAIG3-RFI-VG-S-9381-00 2M 9/21/22
26 s KAIG3-RFI-LM-S-9400-00 1G 9/25/22
27 A KAIG3-RFI-CO-A-1025-00 2N 9/4/22
28 A KAIG3-RFI-CO-A-1034-00 1C 9/8/22
29 A KAIG3-RFI-CO-A-1061-00 2M 9/19/22
30 A KAIG3-RFI-CO-A-1062-00 2M 9/19/22
31 A KAIG3-RFI-CO-A-1063-00 2M 9/19/22
32 A KAIG3-RFI-CO-A-1064-00 2M 9/19/22
33 A KAIG3-RFI-CO-A-1069-00 2J 9/20/22
34 A KAIG3-RFI-EC-A-1070-00 5A 9/20/22
35 C KAIG3-RFI-RD-C-7290-01 FK45 9/18/22
36 C KAIG3-RFI-SW-C-7373-00 BG35 9/1/22
37 C KAIG3-RFI-SW-C-7420-00 G5 9/3/22
38 C KAIG3-RFI-SW-C-7441-00 B4 9/4/22
39 C KAIG3-RFI-SW-C-7443-00 G4 9/4/22
40 C KAIG3-RFI-SW-C-7458-00 G4 9/5/22
41 C KAIG3-RFI-JG-C-7491-00 2G 2H 9/6/22
42 C KAIG3-RFI-NA-C-7546-00 2R 9/8/22
43 C KAIG3-RFI-WG-C-7643-00 7 9/12/22
44 C KAIG3-RFI-WG-C-7644-00 4A 9/12/22
45 C KAIG3-RFI-SW-C-7645-00 4A 9/12/22
46 C KAIG3-RFI-WG-C-7702-00 4A 9/14/22
47 C KAIG3-RFI-WG-C-7703-00 4A 9/14/22
48 C KAIG3-RFI-SW-C-7721-00 6A 9/15/22
49 C KAIG3-RFI-SW-C-7734-00 H6 9/17/22
50 C KAIG3-RFI-SW-C-7740-00 C3 9/17/22
51 C KAIG3-RFI-SW-C-7769-00 H6 9/19/22
52 C KAIG3-RFI-SW-C-7789-00 DE2 9/19/22
53 C KAIG3-RFI-SW-C-7824-00 L5 9/21/22
54 SU KAIG3-RFI-CO-SU-2944-00 2R 9/1/22
55 SU KAIG3-RFI-LM-SU-2945-00 1G 9/1/22
56 SU KAIG3-RFI-CO-SU-2962-00 1A 9/5/22
57 SU KAIG3-RFI-LM-SU-3059-00 1G 9/27/22
58 E KAIG3-RFI-TT-E-0559-00 4D 9/25/22
59 E KAIG3-RFI-TT-E-0560-00 4D 9/25/22
60 E KAIG3-RFI-PC-E-0573-00 2D 9/1/22
61 E KAIG3-RFI-TT-E-0575-00 4D 9/7/22
62 E KAIG3-RFI-PC-E-0577-00 2A 9/8/22
63 E KAIG3-RFI-TG-E-0599-00 4C 9/27/22
64 P KAIG3-RFI-SW-M-0290-01 G 9/18/22
65 P KAIG3-RFI-SW-M-0291-01 G 9/18/22
66 P KAIG3-RFI-CC-M-0304-00 H5 9/14/22
67 P KAIG3-RFI-SW-M-0309-00 B 9/20/22
68 SS KAIG3-RFI-AG-SS-0426 4B 9/1/22
Action Taken
Concreting for Infill wall for 2 infill walls
Buttress 71 axis ( 02/J ) & Butterss 72 axis
( 02/K ) (as highlighted) Zone 2D
Concreting for Infill inner wall at Crescent
between (02-AY & 02-AX) (As highlighted)
ZONE 2Q
Concreting for Kicker of Infill wall for Zone 1A
between Axis 01A-01B-01C-01D (PC 1-3-5, 2-4-
6-8) (as highlighted)
Concreting for outer infill wall with counter fort
at Axis 02S-02T (as highlighted) Zone 2F
(KAIG3-SCR-CO-A-0204-00 with attachments)
Shuttering for internal buliding foundation for
stair between axis (02-BB & 02-BA) (as
highlighted) Zone 2R (as highlighted)
Steel Reinforcements for STAIR at Large
Mosque, Axis E-F, 1-1.1 zone 1G (as
highlighted)
Shuttering for STAIR at Large Mosque, Axis E-
F, 1-1.1 zone 1G (as highlighted)
Concreting for Buttress Head at BOI, BOV, BII,
BIV 57, 58 (as highlighted) at Zone 1P (KAIG3-
SCR-CO-S-198-00)
Surface preparation & Base primer coating for
Stair for Internal Building Foundation ZONE 2R
at AXIS 02BA TO 02BB up to level 870.40 at
CRESCENT (as highlighted)
Two coat of bituminous damp proofing coating
for Stair for Internal Building Foundation ZONE
2R at AXIS 02BA TO 02BB up to level 870.40
at CRESCENT (as highlighted)
Protection layer of 4mm thick bituminous
protection board for Stair for Internal Building
Foundation ZONE 2R at AXIS 02BA TO 02BB
up to level 870.40 at CRESCENT (as
highlighted)
Concreting for internal buliding foundation for
stair between axis (02-BB & 02-BA) (as
highlighted) Zone 2R (as highlighted)
Antitermite for ETFE PUMP ROOM for Mass
Concrete under SOG at Zone 2E axis 02Q (as
highlighted) (KAIG3-SCR-CO-S-0193-00)
Shuttering for ETFE PUMP ROOM for Mass
Concrete under SOG at Zone 2E axis 02Q (as
highlighted) (KAIG3-SCR-CO-S-0193-00)
Concreting for ETFE PUMP ROOM for Mass
Concrete under SOG at Zone 2E axis 02Q (as
highlighted) (KAIG3-SCR-CO-S-0193-00)
Steel reinforcements for Large Mosque Lower
1st floor suspended slab and Beams at Axis 5-6,
C-F (as highlighted) Zone 1G
Concreting for Large Mosque Lower 1st floor
suspended slab and Beams at Axis 5-6, C-F (as
highlighted) Zone 1G
Concreting Infill wall on BOI 122 Axis 02AX (as
highlighted) Zone 2Q
Surface Preparation prior to Repair by
Nitomortar TC2000 Epoxy, for All Inner Surface
of tank Wet Well E, Inside Water Garden as
highlighted area in attached drawing's.
Inspection for Repair by Nitomortar TC2000
Epoxy, for Inner Surfaces of tank of Wet Well F,
Inside Water Garden as highlighted area in
attached drawing's.
Inspection for Repair by Nitomortar TC2000
Epoxy, for Inner Surfaces of tank of Wet Well F,
Inside Water Garden as highlighted area in
attached drawing's.
Steel Reinforcement for Infill wall (inner) at
Zone 2H Axis 02AA-02AB TOC 876.00 (as
highlighted)
Shuttering for Large Mosque for Upper First
Floor for columns (C3A,C4,C5 ) Walls (W1),
Axis C-F, 1-2 Zone 1G (as highlighted)
Concreting for Large Mosque for Upper First
Floor for columns (C3A,C4,C5 ) Walls (W1),
Axis C-F, 1-2 Zone 1G (as highlighted)
Shuttering for Devonian Garden Wall (1st) at
zone 2M axis 02M (as highlighted) TOC 874.80
Concreting for Stairs at Large Mosque Zone 1G
Axis 5.1-6, E-F from 871.10 to 874.60 (as
highlihgted)
Aluminum Cap Installation between Axis 02/AR
- 02/AS.
CHB laying and Stifiner (ST-02) for Pump Room
at Zone 1C axis 01I (as highlighted) using 20cm
CHB upto 876.00
Aluminum Cap Installation between Axis 02/AO
- 02/AP.
Aluminum Cap Installation between Axis 02/AN
- 02/AO.
Aluminum Cap Installation between Axis 02/AM
- 02/AN.
Aluminum Cap Installation between Axis 02/AL
- 02/AN.
Installed Base Extrusion and Base Seal between
Axis 02/AB - 02/AC.
1st Layer of Block Work layout for Energy
Center outer Wall axis 17-29, R (as highlighted)
Excavation and Soil Preparation prior to start
backfilling Layers for Roads, Starting from
ST.0+000 to 0+300 at Zone F&K - as highlighted
Inspection of Blinding Concrete under Heating &
Chilled Water Line Isolation Pit for B/DC/02,
B/DC/06, G/DC/13 at Zone-B&G - as
highlighted
Inspection of Excavation for Heating and Chilled
Water Line Pit G/DH/19, G/DC/18 at Zone-G -
As highlighted
Inspection and Compaction test for backfilling
Sub-grade 1st Layer (1 of 6) for Non potable
water line pit POC-6 at zone B - As Highlighted
(Stock Pile# 131 A-1-B)
Inspection of Excavation for Heating and Chilled
Water Line at Zone-G - As highlighted
Inspection of Sand bediing under pipe for
Heating and Chilled Water Line at Zone-G - As
highlighted (Stock Pile# 132)
Level and Location for Foundation of strip
footing between PC 23 & PC 25 zone 1D at
CRESCENT AXIS 01-M TO 01-L (as
highlighted) TOC 866.00 - 867.00
Installation of Soak Away Base (SA-03) at north
administration building Zone 2R
Inspection for Installed Electrical Handholes of
Low Voltage (MH/WG/LV/22, 27 & 28) and
Emergency (MH/WG/EM/14), inside water play
Garden, at Water Garden, as highlighted in
attached drawing's.
Inspection for Installed Low Current Handholes
(MH/WG/LC/05, 06, 07 & 09) and Fire Alarm &
Security (MH/WG/FA/07, 08, 09, 10, 11, 12, 13,
16 & 32), Inside water play Garden, at Water
Garden, as highlighted in attached drawing's.
'Bedding of Gravel 3/8" and Geotextile
Surrounding Foul Water Line for (160&110mmØ
- UPVC- Class 4) from (FW-A-13-6). At
CRECENT Zone 7 ( Cenozoic Garden). As per
highlighted Area in the attached Dwg.
Inspection for Installed Electrical Handholes of
Low Voltage (MH/WG/LV/01, 02, 03, 04, 05,
06, 07, 08, 09 & 10), Inside Mist Garden, at
water Garden, as highlighted area in attached
drawing's.
Inspection for Installed Low Current Handholes
of Fire Alarm & Security (MH/WG/FA/01,02 &
03), Inside Mist Garden, at water Garden, as
highlighted area in attached drawing's.
Inspection and Compaction test for backfilling
Sub-grade 1st Layer (1 of 6) above gravel For
Manhole FW-A-9 - As Highlighted (SP#136 A-
1-B)
Inspection for Installation of Heating and Chilled
Water Line Pit for H/DH/26, H/DH/25,
H/DH/29, H/DH/30, H/DH/35, H/DH/36,
H/DC/24, H/DC/23, H/DC/27, H/DC/17,
H/DC/33, H/DC/34 at Zone-H - As highlighted
Surface Preparation prior to start backfilling for
the Duct Bank of MV Line from C/MV/12 to
C/MV/20 at Zone- C (As Highlighted)
Inspection for Blinding Concrete under MV Line
Pulling Pit H/MV/30 - as highlighted
Inspection of Sand Covering Layer for Protection
of MV Line from D/MV/35 to E/MV/05 &
D/MV/34 to E-MV/02 at Zone-D&E as
highlighted in the attached drawing (Stock Pile #
132)
Inspection of Excavation for Heating and Chilled
Water Line at Zone-L - As highlighted
Level and Location for internal buliding
foundation for stair between axis (02-BB & 02-
BA) (as highlighted) Zone 2R (as highlighted)
Level and location for STAIR at Large Mosque,
Axis E-F, 1-1.1 zone 1G (as highlighted)
Level and Location for Kicker of outer Infill wall
for Zone 1A between Axis 01A-01B-01C (PC 1-
3-5) (as highlighted)
Level and Location for Large Mosque for Upper
First Floor for Columns & Walls
(C5,C4,C3A,C2A,C2C,W5) , Axis C-E, 5-6
Zone 1G (as highlighted)
Installation of straight PVC Conduit (Dia. 25mm)
& Boxes for Power System (Socket Outlet) at
First Floor Site Tower No. 2 as per attached
highlighted drawing.
Installation of straight PVC Conduit (Dia. 25mm)
& Boxes for Lighting System (LED W5, LED
W5/E) at First Floor Site Tower No. 2 as per
attached highlighted drawing.
Installation of PVC Conduit (Dia. 25mm) for
Lighting (EXIT Sign) at the Crescent-02 at the
Infill Wall (between Axis 02/1AD & 02/1AE) as
per attached highlighted drawing.
Installation of straight PVC Conduit (Dia. 25mm)
& Boxes for Power System (Socket Outlet, Fused
Connection &Three Phase Isolator) at Site Tower
No. 2 as per attached highlighted drawing.
Installation of straight UPVC Conduit (Dia.
160mm) Low Voltage Ducts (Submain Cables) at
Crescent-02 beside the Cafeteria (between Axis
02/2A & 02/2B) as per attached highlighted
drawings.
Installation of UPVC conduit (dia. 50mm
&75mm) passing through the Wall for Low
Voltage Ductbank (Power & Lighting) at the
Butterfly Garden as per attached highlighted
drawing.
Pre insulated Heat Water Pipes (S&R) 150mmØ(
laying ,Aligment ,Leveling and fit up) From
point (E:647473.054 N:2713846.088) to
(E:647499.164 N:2713788.554). At zone G. As
per highlighted Area in the attached Dwg.
Pre insulated Chiled Water Pipes (S&R)
200mmØ( laying ,Aligment ,Leveling and fit up)
From point (E:647483.48 N:2713871.373) to
(E:647576.326 N:2713932.524). Pre insulated
Heat Water Pipes (S&R)
150mmØ( laying ,Aligment ,Leveling and fit up)
From point (E
Pre insulated Chiled Water Pipes (S&R)
150mmØ &
100mmØ( laying ,Aligment ,Leveling and fit up)
From point (E:648100.9898 N:2714189.5670) to
(E:648080.8758 N:2714226.973). At zone H. As
per highlighted Area in the attached Dwg.
Pre insulated chilled Water Pipes (S&R)
65mmØ( laying ,Aligment ,Leveling and fit up)
From point (E:647552.974 N:2714089.840) to
(E:647553.171 N:2714061.144) &
200mmØ( laying ,Aligment ,Leveling and fit up)
From point (E:647553.171 N:2714061.144) to
(E:64
Final Inspection for the Ivory Garden from Grid
lines 01 to 23
Location
SN NO. Trade RFI NO. (Building / Submitted Date
Zone)
1 S KAIG3-RFI-CO-S-8340-01 2R 17-Oct-22
2 S KAIG3-RFI-CF-S-9527-00 2A 2-Oct-22
3 S KAIG3-RFI-WG-S-9565-00 4A 4-Oct-22
4 S KAIG3-RFI-WG-S-9566-00 4A 4-Oct-22
5 S KAIG3-RFI-CO-S-9762-00 2A 25-Oct-22
6 S KAIG3-RFI-WG-S-9764-00 4A 18-Oct-22
7 S KAIG3-RFI-CO-S-9796-00 1A 20-Oct-22
8 S KAIG3-RFI-CO-S-9811-00 1M 24-Oct-22
9 S KAIG3-RFI-CO-S-9869-00 1M 25-Oct-22
10 S KAIG3-RFI-WG-S-9884-00 4A 25-Oct-22
11 S KAIG3-RFI-CO-S-9950-00 1M 29-Oct-22
12 A KAIG3-RFI-CO-A-1084-00 2B 1-Oct-22
13 A KAIG3-RFI-CO-A-1088-00 2C 1-Oct-22
14 A KAIG3-RFI-CO-A-1106-00 1C 2-Oct-22
15 A KAIG3-RFI-CO-A-1136-00 1C 9-Oct-22
16 LS KAIG3-RFI-PA-LS-1618-00 G 2-Oct-22
17 LS KAIG3-RFI-TG-LS-1629-00 4C 5-Oct-22
18 LS KAIG3-RFI-PG-LS-1649-00 4D 11-Oct-22
19 LS KAIG3-RFI-PG-LS-1650-00 4D 11-Oct-22
20 C KAIG3-RFI-SW-C-5491-01 4 11-Oct-22
21 C KAIG3-RFI-SW-C-8005-00 C3 2-Oct-22
22 C KAIG3-RFI-WG-C-8025-00 4A 2-Oct-22
23 C KAIG3-RFI-SW-C-8036-00 C3 3-Oct-22
24 C KAIG3-RFI-SW-C-8077-00 C3 5-Oct-22
25 C KAIG3-RFI-VG-C-8172-00 2M 10-Oct-22
26 C KAIG3-RFI-SW-C-8182-00 G4 12-Oct-22
27 C KAIG3-RFI-TG-C-8211-00 4C 11-Oct-22
28 C KAIG3-RFI-TG-C-8212-00 4C 11-Oct-22
29 C KAIG3-RFI-EC-C-8226-00 5A 12-Oct-22
30 C KAIG3-RFI-SW-C-8285-00 3 17-Oct-22
31 C KAIG3-RFI-SW-C-8300-00 G3 17-Oct-22
32 C KAIG3-RFI-TT-C-8311-00 4 17-Oct-22
33 C KAIG3-RFI-VG-C-8330-00 2M 18-Oct-22
34 C KAIG3-RFI-SW-C-8346-00 F5 19-Oct-22
35 C KAIG3-RFI-SW-C-8396-00 D2 23-Oct-22
36 M KAIG3-RFI-SW-M-0334-00 GF 12-Oct-22
37 M KAIG3-RFI-SW-M-0334-01 GF 19-Oct-22
38 SS KAIG3-RFI-TG-SS-0448-00 4 11-Oct-22
39 E KAIG3-RFI-BO-E-0507-00 2B 5-Oct-22
40 E KAIG3-RFI-MB-E-0590-00 4B 17-Oct-22
41 E KAIG3-RFI-MB-E-0591-00 4B 17-Oct-22
42 E KAIG3-RFI-SM-E-0598-00 2B 10/3/22
43 E KAIG3-RFI-SW-E-0606-00 6A 10/11/22
44 LC KAIG3-RFI-CF-LC-0817 2A 10/1/22
45 LC KAIG3-RFI-NA-LC-0846 2R 10/18/22
46 LC KAIG3-RFI-NA-LC-0849 2R 10/18/22
Action Taken
Anti termite for plain concrete for
internal foundation between axis
02-AB to 02-AZ zone 2R (as
highlighted) at CRESCENT
Steel reinforcements for Cafeteria
(undercroft) Wall (W18 & 19) as
highlighted, upto 869.100 zone 2A
(KAIG3-SCR-CF-S-0194-00 with
attachments)
Solvent Base Primer Coating prior to
Membrane Water proofing on
Blinding of Decant Sump-D4 Inside
Water Play garden, at Water Garden
as highlighted area in attached
drawing's.
Single layer 4mm thk Modified
Bituminous Water Proofing
Membrane on Blinding of Decant
Sump-D4 Inside Water Play garden,
at Water Garden as highlighted area
in attached drawing's.
Concreting for Infill wall (inner) at
zone 2A Between 02C-02D from
863.55 to 869.16 (As Highlighted)
Inspection for 2nd Coat Epoxy
(Nitocote EP405), for Inner Surfaces
of tank of Wet Well F, Inside Water
Garden as highlighted area in
attached drawing's.
Concreting for Kicker of Infill wall for
Zone 1A between Axis 01C-01D (PC
5-7) (as highlighted) 869.10
Concreting for Mass concrete under
Strip footing (outer) at Zone 1M
Between PC 71-73-75-77 (as
highlighted) TOC 865.430
Concreting for Mass concrete under
Strip footing ( INNER ) at Zone 1M
Between PC 72-74 & PC 76-78(as
highlighted)
Inspection for 2nd Coat Epoxy
(Nitocote EP405), for All Inner
Surfaces of tank Wet Well E, Inside
Water Garden as highlighted area in
attached drawing's.
Concreting for Mass concrete (2nd
layer) under Strip footing (inner) at
Zone 1M Between PC 72-74 & 76-78
(as highlighted) TOC 865.430,
865.930
Installed Aluminum Caps between
Axis 02/D - 02/E.
Installed Aluminum Caps between
Axis 02/H - 02/I.
Installed ETFE Cushions (without
aluminum caps) between axis
01-I/01-J.
Inspection of Plaster Guide Point
and Plaster Accessories for Pump
Room 6089 at Zone 1C axis 01I (as
highlighted) upto 876.00
"Mock up inspection of Copping for
Seating Area (1) at Zone-G (SA-11) -
As Highlighted"
Mockup for Stone Coping on Seat
walls for all External Gardens
Installed Inside Butterfly Garden at
highlighted area in attached
Drawing'[Link] Butterfly Garden, as
highlighted in attached drawing's &
Photos.
Excavation & Surface preparation
for Planting area Inside Outer
Canopy 2, at Physic garden, as
highlighted area in attached
drawing's.
Excavation & Surface preparation
for Planting area Inside Outer
Canopy 3, at Physic garden, as
highlighted area in attached
drawing's.
Inspection for Installation of MV
Line Junction Pit - C/MV/12,
G/MV/10, H/MV/05 - as highlighted
Inspection for Installation of Precast
Slab for MV Line Pit - C/MV/03 at
Zone-C - As Highlighted (SCR: KAIG3-
SCR-SW-S-0174-00)
Excavation & Bed Preparation for
Electrical Line of Low Voltage,
Crossing Near the Entrance of Mist
Garden, inside water Garden, as
highlighted area in attached
drawing's.
Inspection for Installation of MV
Line Interface Pit - K/MV/04 - as
highlighted
Excavation for MV line Pit C-
06,41,01,07,27,08,26- as highlighted
SCR
Inspection and Compaction Test for
6th layer Backfilling to create slope
Formation for EDPM Bedding for
Devonian Garden,Zone 2M Axis
02AO-02AP (as highlighted) 6th of
7th layer ,SP #146
Inspection of Blinding Concrete
under LV Line Pit - G/LV/18,
G/LV/22, G/LV/58, G/LV/13,
G/LV/20 at Zone-G - as highlighted
Excavation and Bed preparation for
Irrigation Lines (Dia 50 & 110 mm)
along the Boundary wall inside
Butterfly Garden, as highlighted area
in attached drawing's.
Excavation and Bed preparation for
Fire Fighting Lines (Pipe dia 50 & 80
mm), inside Butterfly Garden, as
highlighted area in attached
drawing's.
Inspection and Compaction Test for
5th layer Backfilling for Energy
Center 2 (As Highlighted) Zone 5A
Axis 12-13/A (5th of 8th) SP#146
Inspection of Excavation for Storm
Water Line from Outfall E to Wadi at
Zone-3 - As Highlighted
Surface Preparation prior to start
backfilling Sub-base for Parking Area
@ Zone-G - as highlighted
Surface Preparation Prior Backfilling
under SOG (at bottom of Blinding
levels of Wall) inside Site Tower 3
(As Highlighted)
Inspection and Compaction Test for
1st layer Backfilling to create slope
Formation for EDPM Bedding for
Devonian Garden for Devonian
Garden (As Highlighted) Zone 2M
( 1st of 2nd Layer )
'Fire Fighting Networks Sand Cover
& Pipes Protection (30 cm above
Pipes). As per highlighted Area in
the attached Dwg.
Inspection for Installation of Non-
Potable Water Line Pit - NPW-ISC-
29, POC-24, POC-25, POC-26 at Zone
D - as highlighted
Pre insulated chilled Water Pipes
(S&R)
200mmØ( laying ,Aligment ,Leveling
and fit up) From point
(E:647442.829 N:2713735.292) to
(E:647340.156 N:2713743.732) &
150mmØ From point (E:647340.156
N:2713743.732) to (E:647341.892
N:2713756.442). At zone F.
Pre insulated chilled Water Pipes
(S&R)
200mmØ( laying ,Aligment ,Leveling
and fit up) From point
(E:647442.829 N:2713735.292) to
(E:647340.156 N:2713743.732) &
150mmØ From point (E:647340.156
N:2713743.732) to (E:647341.892
N:2713756.442). At zone F.
Inspection for Installed Galvanized
Steel Angles along the Tunnel, at
Grid (A/1-21), Inside Butterfly
Garden, as highlighted in attached
drawings.
Installation of Weatherproof
Box( 400x400mm -1pc. & 10x10 mm
- 1 pc.) and straight PVC conduit
32mm (1pc.) in column between
Span 74 and 75 for Power (CAM-
153) System at Boundary Wall at
Zone D as per highlighted drawing
and KAIG3-SCR-BO-LC-0016-00.
Installation of Cable Tray (EM -
200mm (CT203) at Management
and Maintenance Bldg. (GF 5000C
Passage Grid no. bet.10&11/E to
15&16/E) as per attached
highlighted drawing.
Installation of Cable Trunk (UPS -
100mm , LTG & SP - 100mm) at
Management and Maintenance
Bldg. GF 5000C Passage (Grid no.
bet.10&11/E to 15&16/E) and GF
5000B Lobby (Grid no.15/E to 15/D
& 15/D to 18/D) as per attached
highlighted drawing.
Installation of PVC Conduit (Dia.
25mm) and boxes for Lighting
System (LED EXIT, C/CE, C, C7,
IT/CE, CT, CT/CE, CB, Presence
Detector) at the South Small Mosque
First Floor (between Column Grid
no 1/D, 8/D, 1/G & 8/G) as per
attached highlighted drawing.
Installation of straight UPVC
Conduit (Dia. 160mm) Medium
Voltage Ductbank (H/MV/29 to
H/MV/06) at the Site Work as per
attached highlighted drawings.
Installation of PVC conduit (dia.
25mm) and Box for Voice and Data
(Telephone & WIFI) at the Crescent
-2 Cafeteria (Undercroft Level
Mechanical Room) as per attached
highlighted drawing.
Installation of PVC Conduit (Dia.
25mm) and Boxes for Voice & Data
(DATA & Telephone) at the North
Adminstration First Floor Crescent -
2 as per attached highlighted
drawing.
Installation of PVC Conduit (Dia.
25mm) and Boxes for Fire Alarm
(Break Glass, Flashing Beacon &
Fire Telephone) at the North
Adminstration First Floor Crescent -
2 as per attached highlighted
drawing.
SN NO. Trade RFI NO. Zone Building Submitted Date
South Small
1 SU KAIG3-RFI-SM-SU-3233-00 2B 2-Nov-22
Mosque
North Admin
2 SU KAIG3-RFI-NA-SU-3236-00 2R 2-Nov-22
Building
3 S KAIG3-RFI-CO-S-10003-00 1A Crescent 1-Nov-22
South Small
4 S KAIG3-RFI-SM-S-10009-00 2B 2-Nov-22
Mosque
5 S KAIG3-RFI-CO-S-10021-00 1A Crescent 2-Nov-22
North Admin
6 S KAIG3-RFI-NA-S-10026-00 2R 7-Nov-22
Building
7 S KAIG3-RFI-CO-S-10040-00 2K Crescent 3-Nov-22
8 S KAIG3-RFI-CO-S-10041-00 2K Crescent 7-Nov-22
9 S KAIG3-RFI-CO-S-10049-00 1A Crescent 3-Nov-22
10 S KAIG3-RFI-AG-S-10203-00 4B Crescent 14-Nov-22
11 S KAIG3-RFI-CO-S-10342-00 2H Crescent 24-Nov-22
12 S KAIG3-RFI-PC-S-10354-00 4 Central Bridge 26-Nov-22
13 S KAIG3-RFI-PC-S-10355-00 4 Central Bridge 26-Nov-22
14 S KAIG3-RFI-LM-S-10384-00 1G Large Mosque 27-Nov-22
15 A KAIG3-RFI-CO-A-01239-00 2K Crescent 2 2-Nov-22
Site
16 A KAIG3-RFI-SW-A-01248-00 2B Works/Boundary 6-Nov-22
Wall
17 A KAIG3-RFI-LM-A-01270-00 1G Large Mosque 14-Nov-22
18 A KAIG3-RFI-CO-A-1281-00 1G Crescent 1 16-Nov-22
Site
19 A KAIG3-RFI-SW-A-1283-00 2B Works/Boundary 17-Nov-22
Wall
Site
20 A KAIG3-RFI-SW-A-1284-00 2B Works/Boundary 17-Nov-22
Wall
21 LS KAIG3-RFI-PG-LS-01724-00 4D Physic Garden 7-Nov-22
Road between
22 C KAIG3-RFI-RD-C-7290-02 FK45 24-Nov-22
Tower 2 3
23 C KAIG3-RFI-SW-C-8584-00 6B Site Works 2-Nov-22
24 C KAIG3-RFI-SW-C-8585-00 3B Site Works 2-Nov-22
Devonian
25 C KAIG3-RFI-VG-C-08655-00 2M 6-Nov-22
Garden
26 C KAIG3-RFI-CO-C-08671-00 4 Crescent 7-Nov-22
27 C KAIG3-RFI-SW-C-08680-00 G3 Site Works 7-Nov-22
28 C KAIG3-RFI-CC-C-08707-00 H Child Care 8-Nov-22
29 C KAIG3-RFI-CO-C-08730-00 2C Crescent 10-Nov-22
30 C KAIG3-RFI-SW-C-8798-00 C3 Site Works 13-Nov-22
31 C KAIG3-RFI-SW-C-8806-00 L5 Site Works 14-Nov-22
Promenade &
32 C KAIG3-RFI-PC-C-8808-00 6 14-Nov-22
Canopies
Promenade &
33 C KAIG3-RFI-PC-C-8809-00 6 Canopies 14-Nov-22
Creteceous
34 C KAIG3-RFI-CG-C-08837-00 0 15-Nov-22
Garden
35 C KAIG3-RFI-SW-C-8881-00 BL45 Site Works 16-Nov-22
36 C KAIG3-RFI-LG-C-08896-00 1L 1M Pilocene Garden 17-Nov-22
37 C KAIG3-RFI-PA-C-8907-00 K5 Picnic Area 17-Nov-22
38 C KAIG3-RFI-PA-C-8908-00 K5 Picnic Area 17-Nov-22
39 C KAIG3-RFI-SW-C-8910-00 G4 Site Works 17-Nov-22
40 C KAIG3-RFI-SW-C-8980-00 L6 Site Works 20-Nov-22
41 C KAIG3-RFI-CC-C-08993-00 2N Child Care 20-Nov-22
42 C KAIG3-RFI-SW-C-9039-00 D2 Site Works 22-Nov-22
43 C KAIG3-RFI-SW-C-9059-00 B4 Site Works 24-Nov-22
44 C KAIG3-RFI-SW-C-9099-00 F4 Site Works 28-Nov-22
45 E KAIG3-RFI-SW-E-00640-00 3A Site Works 7-Nov-22
Management
46 E KAIG3-RFI-MB-E-0642-00 4B 9-Nov-22
Building
Management
47 E KAIG3-RFI-MB-E-0644-00 4B 9-Nov-22
Building
Discovery
48 E KAIG3-RFI-DG-E-0645-00 4C 10-Nov-22
Garden
49 E KAIG3-RFI-TT-E-0653-00 4D Site Tower 16-Nov-22
50 E KAIG3-RFI-TT-E-0653-01 4D Site Tower 27-Nov-22
51 E KAIG3-RFI-TT-E-0654-00 4D Site Tower 16-Nov-22
52 E KAIG3-RFI-TT-E-0654-01 4D Site Tower 28-Nov-22
53 E KAIG3-RFI-PG-E-0662-00 4D Physic Garden 27-Nov-22
54 E KAIG3-RFI-PG-E-0663-00 4D Physic Garden 27-Nov-22
55 E KAIG3-RFI-TT-E-0667-00 4D Site Tower 2 27-Nov-22
Management
56 LC KAIG3-RFI-MB-LC-0873-00 4B 9-Nov-22
Building
Management
57 LC KAIG3-RFI-MB-LC-0874-00 4B Building 9-Nov-22
58 LC KAIG3-RFI-TT-LC-0879-00 4D Site Tower 2 16-Nov-22
59 LC KAIG3-RFI-TT-LC-0879-01 4D Site Tower 2 28-Nov-22
60 LC KAIG3-RFI-TT-LC-0880-00 4D Site Tower 2 16-Nov-22
61 LC KAIG3-RFI-TT-LC-0880-01 4D Site Tower 2 28-Nov-22
62 LC KAIG3-RFI-TT-LC-0881-00 4D Site Tower 2 16-Nov-22
63 LC KAIG3-RFI-TT-LC-0881-01 4D Site Tower 2 28-Nov-22
64 LC KAIG3-RFI-TT-LC-0884-00 4D Site Tower 2 16-Nov-22
65 LC KAIG3-RFI-TT-LC-0884-01 4D Site Tower 2 28-Nov-22
66 LC KAIG3-RFI-LM-LC-0888-00 1G Crescent 1 19-Nov-22
67 LC KAIG3-RFI-LM-LC-0893-00 1G Large Mosque 24-Nov-22
68 LC KAIG3-RFI-LM-LC-0893-01 1G Large Mosque 26-Nov-22
69 LC KAIG3-RFI-LM-LC-0893-02 1G Large Mosque 29-Nov-22
Action Taken
Level and Location for South Small Mosque Staircase ( Step , Riser ,
Landing ) from ground to 1st Floor, zone 2B at Axis F-G & 6-8 ,Level
from 869.25 to 873.150 ( KAIG3-SCR-SM-S-0205-00 ),(As
Highlighted)
Level and Location for Staircase ( Step , Riser , Landing ) from ground
to 1st Floor of North Administration Building , Zone 2R , Axis 02BB,
02/1 ( As Highlighted ) From 870.9 to 873.725
Concreting for Infill Wall (outer) at Zone 1A at Zxis 01B-01C as
highlighted.
Steel Reinforcements for South Small Mosque Staircase ( Step , Riser
, Landing ) from ground to 1st Floor, zone 2B at Axis F-G & 6-8 ,Level
from 869.25 to 873.150 ( KAIG3-SCR-SM-S-0205-00 ),(As
Highlighted)
Concreting for Infill wall (inner) at Zone 1A at Axis 01A-01B-01C-01D
(As Highlighted) level upto 872.00
Concreting for Staircase ( Step , Riser , Landing ) from ground to 1st
Floor of North Administration Building , Zone 2R , Axis 02BB, 02/1
( As Highlighted ) From 870.9 to 873.725
Shuttering for Infill wall (Inner) of Zone 2K at Axis 02AG-02AF ( As
Highlighted)
Concreting for Infill wall (Inner) of Zone 2K at Axis 02AG-02AF ( As
Highlighted)
Concreting for Diaphragm wall Beam at zone 1E Axis 01P (as
highlighted)
Concrete Pouring for Blinding under Foundations of Internal Garden,
Inside Aviary Garden, As per Highlighted in attached Drawing's.
Antetermite under Blinding under S.O.G of ETFE pump Room #
6098 in Zone 2H , Axis 02AA (as highlighted)
Two Layers of 4mm thick Modified Bituminous WaterProofing
Membrane for Central Bridge Abutment Rc Footing , Axis 02AL-
02AK, Zone 4 Level upto 864.60 (As Highlighted)
Protection Layer of 4mm thick Bituminous Protection Board for
Central Bridge Abutment Rc Footing , Axis 02AL-02AK, Zone 4 Level
upto 864.60 (As Highlighted)
Concreting for Large Mosque Lower Second Floor Beam ( 137A ) for,
Zone 1G , Axis ( 2-5 / E ) Level upto 879.50 (As Highlighted)
Installed Aluminum Caps between Axis 02/AG - 02/AH.
Grouting for Stone Cladding of Boundary walls (Both faces) @ Span
74 and 75 and Columns C74, C75 and C76 (All Sides), as Attached
Highlighted Drawing's.
Block Works Laying for Large Mosque,Ground Floor Axis 1-2/C-F at
Zone 1G Upto Bottom of Lintel Beam (as highlighted) KAIG3-SCR-
LM-A-0173-00
Installed Base Extrusion and Base Seal between Axis 01/S - 01/T.
Grouting for Stone Cladding of Boundary wall (Outer Side) at Span
17 & 18, As per Attached Highlighted Drawing's.
Grouting for Stone Cladding of Boundary wall (Outer Side) at Span
15 & 16, As per Attached Highlighted Drawing's.
Surface Preparation prior to Waterproofing for Fountain 1 (6 no's),
inside Physic Garden as highlighted area in attached drawing's.
Excavation and Soil Preparation prior to start backfilling Layers for
Roads, Starting from ST.0+000 to 0+300 at Zone F&K - as highlighted
INSPECTION FOR MANHOLE BASE INSTALLATION AND UPVC PIPE
CONNECTION FOR - FW-A-3-3 (As Highlighted)
INSPECTION FOR INSTALLATION OF ALL RINGS (RISER) AND SLAB
FOR FW-A-3-3, FW-A-3-4, FW-A-3-5 (As Highlighted)
Inspection and Compaction test for 1st layer Backfilling to create
slope Formation for EPDM Bedding in Devonian Garden at Zone 2M
(As Highlighted) (1st of 3rd layer) SP# 146
Inspection and Compaction Test for 2nd Layer of Subgrade
Backfilling above Rc Foundation Abutment Bridge at Zone 4 (As
highlighted) ( 2nd of 8th Layer ) SP # 146
Surface Preparation prior to start backfilling for Parking Area @
Zone-G - as highlighted
' Sand Cover & Pipes Protection (30 cm above Pipes) For Pre-
insulated Chilled Water Pipes (dia 100mmØ & dia 150mmØ) at Zone
H. From Point (648100.9898 E & 2714189.5670 N) to Point
(648080.8758 E & 2714226.973 N) . As per highlighted Area in the
attached D
Surface preparation prior start backfilling for Internal Building at
Zone 2C Axis 02G to 02J (As highlighted)
Inspection of Blinding Concrete under MV Line Pit - C/MV/10 at
Zone-C - as highlighted (KAIG3-SCR-SW-E-0088-00)
'Potable Water Pipes Sand Cover & Pipes Protection (30 cm above
Pipes). As per highlighted Area in the attached Dwg.
'Potable Water Pipes Sand Cover & Pipes Protection (30 cm above
Pipes). As per highlighted Area in the attached Dwg.
'Fire Fighting Networks Sand Cover & Pipes Protection (30 cm above
Pipes). As per highlighted Area in the attached Dwg.
Excavation and Bed Preparation for soak away drainage pipes at
Gardens Zone 2J 2K as per attached highlighted approved DWG
Surface Preparation prior to start backfilling for RO water line Pit
ROW-ISC-13, POC-14 at Zone-B&L - As Highlighted
Excavation and Bed Preparation for soak away drainage pipes
at ,Zone 1L & 1M , ( As per highlighted )
Inspection for Casting the Blinding Concrete under Beam of Seating
Area 3-25 at Zone-K - As Highlighted
Inspection for Casting the Blinding Concrete under Beam of Seating
Area 3-23 at Zone-K - As Highlighted
Surface Preparation prior to start backfilling for LV Line Pit G/LV/18,
G/LV/22, G/LV/58, G/LV/13 at Zone- G (As Highlighted)
Inspection of Blinding Concrete under Heating & Chilled Water Line
Isolation Pit for L/DC/13 at Zone-L - as highlighted
Sand bedding for Drainage Pipes at Child Care at Zone 2N ( As
Highlighted )
Inspection of Blinding Concrete under MV Line Pit - D/MV/35,
D/MV/34, D/MV/09, D/MV/36, D/MV/16, D/MV/10 at Zone-D - as
highlighted
Inspection of Excavation for RO Water Line Pit POC-01 & POC-02 at
Zone-B - As highlighted
Inspection of Sand covering for protection of pipe for Heating and
Chilled Water Line at Zone-F - As highlighted (Stock Pile# 159)
Installation of straight UPVC Conduit (Dia. 160mm) Medium Voltage
Ductbank no. CC/D-MV/37 (C/MV/21 to C/MV/15) at the Site Work
as per attached highlighted drawings.
Installation of Cable Tray (Emergency - 225mm,200mm & 100mm)
at the Management and Maintenance Building (GF 5044 General
Dining,GF 5032 Private Dining,GF 5079C Distribution,GF 5079B
Office) as per attached highlighted Red Line for as built drawing.
Installation of Cable Trunk (Lighting & Small Power - 100mm) at the
Management and Maintenance Building (GF 5044 General Dining,GF
5032 Private Dining,GF 5079C Distribution,GF 5079B Office) as per
attached highlighted Red Line for as built drawing.
Installation of direct buried UPVC conduit 32mm (stub-up &
straight) for Lighting at the Discovery Garden as per attached
highlighted Red Line for as Built Drawing.
Installation of straight PVC Conduit (Dia. 25mm) & Boxes for Lighting
System (LED N, W1, W1/E) at Ground & First Floor Site Tower No. 2
as per attached highlighted drawing.
Installation of straight PVC Conduit (Dia. 25mm) & Boxes for Lighting
System (LED N, W1, W1/E) at Ground & First Floor Site Tower No. 2
as per attached highlighted drawing.
Installation of straight UPVC Conduit (Dia. 110mm) for Low Voltage
System (Power, Emergency) at Ground Floor Site Tower No. 2 as per
attached highlighted drawing.
Installation of straight UPVC Conduit (Dia. 110mm) for Low Voltage
System (Power, Emergency) at Ground Floor Site Tower No. 2 as per
attached highlighted drawing.
Installation of direct buried UPVC conduit (dia.75mm) Low Voltage
Ductbank (Emergency) in between Manhole ( 3x75mm -
MH/PG/EM/09 & MH/PG/EM/10, 4x75mm - MH/PG/EM/01 &
MH/PG/EM/02 ) at the Physic Garden as per attached highlighted
drawing.
Installation of direct buried UPVC conduit (dia.75mm) Low Voltage
Ductbank (Normal Power) in between Manhole (
3x75mm-MH/PG/LV/08 & MH/PG/LV/09, 7x75mm - MH/PG/LV/01
& MH/PG/LV/02 ) at the Physic Garden as per attached highlighted
drawing.
Installation of straight PVC Conduit (Dia. 25mm) & Boxes for Lighting
System (Presence Detector) at First & Second Floor Site Tower No. 2
as per attached highlighted drawing.
Installation of Cable Tray for Low Current (Fire Alarm : 100mm) at
Management and Maintenance Bldg. (GF 5044 General Dining,) as
per attached highlighted drawing.
Installation of Cable Tray for Low Current (TELECOM /ICT : 100mm)
at Management and Maintenance Bldg. (GF 5044 General Dining) as
per attached highlighted drawing.
Installation of straight PVC Conduit (Dia. 25mm) and Boxes for Fire
Alarm (Smoke Detector) at Ground, First & Second Floor Site Tower
No. 2 as per attached highlighted drawing.
Installation of straight PVC Conduit (Dia. 25mm) and Boxes for Fire
Alarm (Smoke Detector) at Ground, First & Second Floor Site Tower
No. 2 as per attached highlighted drawing.
Installation of straight PVC Conduit (Dia. 25mm) and Boxes for
Security (CAM) at Ground Floor Site Tower No. 2 as per attached
highlighted drawing.
Installation of straight PVC Conduit (Dia. 25mm) and Boxes for
Security (CAM) at Ground Floor Site Tower No. 2 as per attached
highlighted drawing.
Installation of straight PVC Conduit (Dia. 25mm) and Boxes for
Voice and Data (CAM) at Site Tower No. 2 as per attached
highlighted drawing.
Installation of straight PVC Conduit (Dia. 25mm) and Boxes for
Voice and Data (CAM) at Site Tower No. 2 as per attached
highlighted drawing.
Installation of straight UPVC Conduit (Dia. 75mm) Low Current (Fire
Alarm & Security) at Ground Floor Site Tower No. 2 as per attached
highlighted drawing.
Installation of straight UPVC Conduit (Dia. 75mm) Low Current (Fire
Alarm & Security) at Ground Floor Site Tower No. 2 as per attached
highlighted drawing.
Installation of PVC Conduit (Dia.25mm) & Boxes for Voice and Data
(CAM, Data Outlet for Door Controller) at the Large Mosque First
Floor (between Column Grid no. 1/D, 2/D, 1/F & 2/F) Crescent-01 as
per attached highlighted drawings.
Installation of PVC Conduit (Dia.25mm) & Boxes for Fire Alarm
(Transmitter Beam Detector, Receiver Beam Detector) at the Large
Mosque First Floor (between Column Grid no. 1.1/B, 5.1/B, 1.1/C &
5.1/C) Crescent-01 as per attached highlighted drawings.
Installation of PVC conduit (Dia. 25mm) & Boxes for Fire Alarm
(Transmitter, Beam Detector, Receiver Beam Detector) at the Large
Mosque First Floor (between Column Grid no. 1.1/B, 5.1/B, 1.1/C &
5.1/C) Crescent-01 as per attached highlighted drawings.
Installation of PVC conduit (Dia. 25mm) & Boxes for Fire Alarm
(Transmitter, Beam Detector, Receiver Beam Detector) at the Large
Mosque First Floor (between Column Grid no. 1.1/B, 5.1/B, 1.1/C &
5.1/C) Crescent-01 as per attached highlighted drawings.