Gypsum Plastering Quality Checklist

This document is a gypsum plastering checklist used by Sonu Builders Private Limited for quality control inspections. It contains 14 items to check before, during, and after plastering work. The checklist ensures that materials are approved, surfaces are properly prepared, plastering is done correctly with the appropriate thickness and finish, and the final surface is free from defects. Upon completion of inspection, the checklist is signed off by those who inspected and approved the work.

Uploaded by

Santosh Yadav
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
4K views1 page

Gypsum Plastering Quality Checklist

This document is a gypsum plastering checklist used by Sonu Builders Private Limited for quality control inspections. It contains 14 items to check before, during, and after plastering work. The checklist ensures that materials are approved, surfaces are properly prepared, plastering is done correctly with the appropriate thickness and finish, and the final surface is free from defects. Upon completion of inspection, the checklist is signed off by those who inspected and approved the work.

Uploaded by

Santosh Yadav
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
  • Gypsum Plastering Checklist

SONU BUILDERS PRIVATE LIMITED

GYPSUM PLASTERING CHECKLIST

[Link]. Date:
PROJECT Building & Flat No.
CONTRACTOR Wall / Ceiling Identification
GFC [Link]. & Rev.
[Link]. Description of Activity YES NO N/A Remarks
Checks ( Before start of Plastering).
1 Was the Materials to be used in plastering Tested (or MTC Reviewed) and Approved?

2 Door, Window frames / Sub frames fixed properly (Checked for Plumb, Line, level Warping etc.)
3 Joints between Masonary & RCC Beam / Column filled properly with Non-Shrink grout & cured
4 Joint between Masonary & Door, window frame has been filled

5 Is Chicken / Fibre Mesh is fixed on the junction of RCC & Masonary work
6 All concrete surfaces were hacked properly before plastering. (50 no's / [Link].)
Is the whole surface is made free from Dirt, Dust, Oil, Grease, Masking tape, Patra Patti, Nails, Algae etc.
7
and cleaned properly
8 Is Pre – Wetting of Sub base has been done
9 Is Level Pads are provided on walls / beam soffit & slab soffit at determined intervals and reqd. thk.

10 Gypsum material is within expiry date?


Checks ( During & After Plastering )

11 Thickness, line,level and plumb of plastered surface were checked.

12 Plaster Cut (Jad) finishing has been done properly

Surface of finished plastered surface was found free from cracks, stains, brush marks, Impression of Level
13
pad or any other surface defects
Any visible Undulations, waviness during day, Night light; When measured is it within the tolerance limit? (+ -
14
2mm)

Inspected By Verified & Approved by


Name Name
Sign Sign
Date Date