METHOD STATEMENT
FOR
TUBEWELL INSTALLATION
The purpose of this method statement is to have an appropriate methodology to carry out the
Drilling of Bore Well at proposes site.
2.0 Scope
This method statement illustrates comprel ines for mobilization of
‘ives
ities and gui
materials & machineries, drilling activity, testing and commissioning of bore well.
3.0 Tools and Equipment
= Truck Mounted Vertical Drilling Machine
* Lory Crane
= Hand Tools
4.0 Methodology
4.1 Mobilization
Mobilization of drilling machine and associated tools shall be mobilized to meet the
requirements of the drilling system proposed. It should have the capacity to drill, construct
and develop permanent casing and screen.43
44
45
FOUNDTEST DRILLI IN BHD (1121180-V)
No. §, Jalan PTP 1/1, Taman Perindustrian Tasik Perdana, 47120 Puchong, Selau
‘Tel: 03-80S15333 Fax: 03-8051905S Website: [Link] drills
1 Darul Ehsan.
ny
Dimension of Bore Well
The bore hole shall be drilled in 279.4 mm (11 inches) diameter in the upper soil and
Weathered rock material until reaching the hard formation. On reaching the hard formation
each borehole is to be cased and its diameter reduced to 200 mm (8 inches). The 200 mm
borehole shall be drilled by down-the-hole (DTH) hammer drilling to certain depth.
Design of Well
The tube well is to be constructed and designed as a screened well. However, in section
where the formation is unstable, casing of 152 mm (6 inches) diameter (uPVC pipe and
screen) shall be installed inside the 8 inches diameter borehole. The length of the casing
and screen shall be placed at the horizon where aquifers are located,
Screen and Rubber Packing / Gravel Pack
The slot size of the uPVC screen will be 2 mm. The rubber packing / gravel pack shall be
placed in the annular space between the borehole and the well casing or screen and from
the bottom of the lowest screen section to the level being 5 m to 10 m above the top screen.
Depends on formation. Then, above the rubber packing / gravel pack shall be backfill will
impervious clay and cement grouted with conerete to keep from surface contamination,
Water Samples
Water samples will be taken at the end of the test to the laboratory analysis with 25
parameters water quality analysis test reportNo. 5, Jalan PTP 1/1, Taman Perindustrian Tasik Perdana, 47120 Puchong, Selangor Darul Ehsan,
"Tek: 03-8051
+. FOUNDTEST DRILLING SDN BHD (1121180-V)
Fax: 03-80519955 Website: hitp://[Link]. my
4.6 Drilling of Bore Well
* Mobilization of truck mounted drilling machine and drilling equipment at site
* Power engine and compressor check list shall be prepared prior to commence the activity.
= Lonyo
ine shall be used for offloading of drilling pipes, casing pipe, uPVC casing pipes
and tool box.
Make sure no leakages found prior to start any kind of drilling activities.
* Setting of drilling machine at drilling point by using of hydraulic jack fitted with drilling
machine truck.
* Drilling mast shall be done vertical position by using of hydraulic system.
* Alignment and verticality of drilling mast shall be done by using of level which fitted in
the mast.
* Lift the 3 inch dia x 5.5 meters long drilling rod by using of wire rope hook is fitted winch.
* Tag line shall be used while lifting the drilling rod and controlled by drilling crew.
* Drilling rod shall be fitted in the rotary head which mounted in the Mast.
= 12 inch dia x 1 feet drill bit shall be lifted the same way mentioned above by using of winch
and screwed with drill bit.
= Temporary water tank capacity 5000 liters shall be installed at site near the drilling point
for drilling purpose.
* Flexible water hose connection with pump from water tank to rotary head shall be made
and to be secured properly by using of appropriate clamps to avoid incident due to pressure.
= Then drilling activity shall be carried out and simultaneously water to be pumped through
drilling bit to cut soil easily and also to control the dust in the pollution,
* Drilling shall be done in the soil formation until reached hard layer or hard rock formation.
* After pull out of the drill bit, continue with installation of temporary casing (9 inch diameter
x3 meters long) to avoid the alluvium formation from collapse. This temporary casing put
it until hard layer or rock formation,Find FOUNDTEST DRILLING BHD (1121180-V)
No. §, Jalan PTP 1/1, Taman Perindustrian Tasik Perdana, 47120 Puchong, Selangor Darul Ehsan,
"Tel 03-80515333 Fax: 03-80519955 Website: [Link] drilling. my
Fe
"The temporary casing shall be lifted by winch and to be installed in the drill hole with one
meter projection on the ground to use the casing clamp to hold the casing pipe for further
installation.
= Then lift the second casing pipe by winch fitted in the truck mounted drilling machine and
place on the top of the first casing pipe which already placed in the drilled hole.
"Then rotary head shall be used for tightening of the casing pipe.
Tag line shall be used for lifting of the c:
ng pipe to avoid any damage of property and
any injury.
= Then lift the two casing pipe joined together by casing head and remove the casing clamp.
* After removal of casing clamp, lower down the casing pipe with maintaining of 1 meter
projection above ground to continue the next casing pipe installation.
* The same sequence shall be followed for the installation of all casing pipes.
* In hard formation, the hammer bit shall be used (8 inch diameter x 1 meter long hammer
bit) with high air compressor for further drilling. The rock cutting samples will come out
during the cutting of hammer activity.
"The canvas shall be put on the drilling machine (around drilling bit) where drilling bit
passing through the casing pipe to avoid cutting particles flying.
= During in this method that use of air compressor, the water bearing zone will be detected
during the hammer of hard rock layer forms
jon.
+ The water bearing zone or fractured zone that detected during drilling will be recorded to
use in well design or well development.
* Pull out all the rods and hammer bit to install permanent uPVC Casing and Screen (6 inch
dia x 5.5 meter long pieces).
* The temporary casing pipe shall be removed by using of winch and rotary head by the same
procedure followed for installation
= After install the uPVC casing, continue with flushing activity to clean and take out all the
cutting debris inside the tube well. During this flushing the dis
sharge of water that
produced from the tube well will be recorded to determine the volume of water.Fin’ FOUNDTEST DRILLING SDN BHD (1121180-V)
No. §, Jalon PTP 1/1, Taman Perinchustrian Tasik Perdana, 47120 Puchong, Selangor Darul Ehsan,
Tel: 03-80515333 Fas: 03-80519955 Website: [Link] drilling. my
After complete the flushing activity, the plinth concrete shall be done as a foundation
around the uPVC casing pipe to avoid any damage of the casing.
Then 4 inch stainless steel submersible pump shall be joined with 50 mm dia, specification
PN 125 poly pipe and to be installed together in the bore hole till suitable water level.
Nylon rope shall be installed together with pump to avoid loss of pump in the bore hole
during installation activity.
The tube well cover plate shall be installed on well head.
Then control box with ELCB of submersible pump shall be installed 2 meter distance from
the well head or suitable location.
2.
Then efficiency test shall be carried out after completion of control box installation
5.0 Conduct Wel
fficiency Test
Pumping tests have to be conducted to determine the efficiency of the well. This is very important
to avoid over pumping that can affect surrounding areas like settlement of land. The
efficiency of a well must be over 70% (Department of Minerals and Geosciences requirement).
On termination of the development process, before starting the test, allow the water level to recover
to its original position (static water level). For the test, two methods shall be undertaken. The first
shall be a four (4) steps drawdown test within a duration of 60 minutes for each step. The pumping
rates of the four steps shalll progressively increase with approximate equal increments. The second
test shall be a 24 hours constant discharge test whereby the drawdown in water level and recovery
reading will be recorded. The maximum volume that can be abstracted from the tube well will be
decided from this test. This rate (volume) can be used for a long-time abstraction without di
The long-time dry condition just give the slightly affect to groundwater abstraction,
6.0 Pump Installation
All electrical works comprising wiring and connection to the nearest elect
al supply, install
of pedestal mounted and weathered proof control panel; cabling for pump set, signal cable
including all necessary as water level monitoring and start or stop.No §Jabn FTP, Daa san
ma “Te-oRsosisaas Fax OM80S1008S "Webster deli
cs FOUNDTEST DRILLI BHD (1121180-
7.0 Production Well Schematic
Well Cap PVC Concrete Pad
60 cm x 60 cm x Sem
Collar
Cement grout
PVC Blank
6 Inches
Class D Sirim
Rubber
Packer
a
X XXX XX
CaN ROG
X Coroilatds MaideiaNe)
XXX XXX XK
ihe,
XXX X XXX
XXX KKK XX
XXX XXX
XXX XK XK XK
PVC Screen
6 Inches
Class D Sirim
Open Hole
‘Binches
Drilling dlameter Using Hammer
11 Inches
Drilling Diameter Using Drag Bit