Painting Works Inspection Plan

This document outlines a test plan for inspecting painting work for an elevator refurbishment project. It details three inspection points: 1) receiving and storing paint products, 2) preparing painting surfaces, and 3) final painting inspection. Responsibilities are assigned to the contractor and inspection team for holding, witnessing, and reviewing each inspection point. General notes provide guidance on surveillance, witnessing hold points. Inspection checklists provide acceptance criteria for each task.

Uploaded by

Mudabbir Hussain
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
464 views5 pages

Painting Works Inspection Plan

This document outlines a test plan for inspecting painting work for an elevator refurbishment project. It details three inspection points: 1) receiving and storing paint products, 2) preparing painting surfaces, and 3) final painting inspection. Responsibilities are assigned to the contractor and inspection team for holding, witnessing, and reviewing each inspection point. General notes provide guidance on surveillance, witnessing hold points. Inspection checklists provide acceptance criteria for each task.

Uploaded by

Mudabbir Hussain
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
  • Inspection Test Plan Overview
  • Inspection Checklist - Pre-Commissioning
  • Inspection Checklist - Commissioning
  • Inspection Checklist - Post-Commissioning
  • Final Acceptance Test

FUTURE LIFT INSPECTION TEST PLAN DAT E APPROVED

DISCIPLINE
ITP-CIV-002 CIVIL
PAINTING WORK
PROJECT TITLE WBS/BI/JO/NO CONTRACTOR / SUBCONTRACTOR
Refurbishment and Modernization of Ithra Elevator 4300009686 Future Lifts/Al-Yamama

INSPECTION RESPONSIBILITY
ASSIGNMENTS
ITEM PROJECT PHASE & QUALITY QUALITY
NO. ACTIVITY CODE TASK / ACTIVITY PROCEDURE RECORD REMARKS
CNTRCTR ITHRA

1.0 RECEIVING INSPECTION


Paint Products Receiving & Project
1.1 Storage Inspection Specification FL-CIV-IC-002 H W

2.0 INSTALLATION

2.1 Painting Surface Preparation Project FL-CIV-IC-003 H H


Specification

Project
2.2 Final painting inspection Specification FL-CIV-IC-004 H H

GENERAL NOTES
1 Surveillance: QA /QA Organization to monitor work in progress without notice from Construction Organization

2 Witness: QA/QC organization shalt be notified of the Timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization representative
is not present.

3 Hold: QA/QC organization shall be notified of the Timing of Inspection or test in advance. Inspection or test shall not be carried out without the QA/ QC organization representative in attendence

LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection
FUTURE LIFT INSPECTION CHECKLIST - FL-CIV-IC-002 DAT E APPROVED DISPLINE
Paint Products Receiving & Storage Inspection ITP-CIV-002 CIVIL -FL-CIV-IC-002

PROJECT TITLE WBS/BI/JO/NO CONTRACTOR / SUBCONTRACTOR


Refurbishment and Modernization of Ithra Elevator 4300009686 Future Lifts/Al-Yamama

EQUIPMENT ID NUMBERSNC EQUIPMENT DESCRIPT ION PAINT EQPT CODE SYST EM ID PLANT NO
S0502Y MATT FINISH N/A N/A ITHRA TOWER MUSEUM

LAYOUT DRAWING NUMBER N/A [Link]. N/A PURCHASE ORDER NUMBER N/A EC/PMCC/MCC NO. N/A
SCHEDULED INSPECT ION DAT E&T IME : ACT UAL INSPECT ION DAT E&T IME :
QUANT IT Y ISP.
SAUDI ARAMCO USE O NLY

SAUDI ARAMCO T IP NUMBER : SAUDI ARAMCO ACT IVIT Y NUMBER WORK PERMIT REQ?
ITP-CIV-002
SAUDI ARAMCO INSPECT ION LEVEL : CONTRACTOR INSPECT ION LEVEL :
1.1
NO
W H
ITEM ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP
No. DATE
A Materials Receiving Inspection and Storage
The Contractor shall deliver, handle and store equipment and material units
with the following requirements:
1. Name or title of material./2. Specification numbers if applicable./3.
Manufacturer's stock number and date of manufacture./4. Manufacturer's
name./5. Contents by volume for major pigment and vehicle constituents./6. Project
A1 Thinning instructions./7. Application instructions.
Specification
8. Color name and number.

A2 Provide adequate, enclosed and well ventilated storage facilities separate from
storage of other building materials in a designated storage space on the site Project
Specification

A3 Store paint material at a minimum ambient temperature of 7°C. Project


Specification
Materials that are not in use shall be stored in tightly covered containers and
kept in accordance with the manufacturers' recommendation, but shall not be Project
A4 exposed to temperatures greater than 35°C Specification

Containers of paint or components shall not be opened except for immediate


use. Materials older than the manufacturers recommended shelf life shall not
A5 be used and shall be removed from the site. Project
Specification

REMARKS:

REFERENCE DOCUMENTS:

Contractor / Third-Party Saudi Aramco

Construction Representative* PID Representative


Name, Initials and Date: Work is Complete and Ready for Inspection:

Mubashir Malik
[Link] Nawaz
QC Inspector Proponent
Name, Initials and Date:
Mudabbir [Link] Choudhry
Hussain
FUTURE LIFT INSPECTION CHECKLIST - FL-CIV-IC-003 DAT E APPROVED DISPLINE
ITP-CIV-002 CIVIL
Painting Surface Preparation
PROJECT TITLE WBS/BI/JO/NO CONTRACTOR / SUBCONTRACTOR
Refurbishment and Modernization of Ithra Elevator 4300009686 Future Lifts/Al-Yamama
EQUIPMENT ID NUMBERS EQUIPMENT DESCRIPT ION EQPT CODE SYST EM ID PLANT NO

LAYOUT DRAWING NUMBER [Link]. PURCHASE ORDER NUMBER EC/PMCC/MCC NO.

SCHEDULED INSPECT ION DAT E&T IME ACT UAL INSPECT ION DAT E&T IME QUANT IT Y ISP.
SAUDI ARAMCO USE O NLY

SAUDI ARAMCO T IP NUMBER : SAUDI ARAMCO ACT IVIT Y NUMBER WORK PERMIT REQ?
ITP-CIV-002
SAUDI ARAMCO INSPECT ION LEVEL : CONTRACTOR INSPECT ION LEVEL :
2.1
YES
H H
ITEM ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
A General Requirements
A1 Form oils, grease, laitance, etc. shall be removed by steam cleaning Project
with a water emulsifiable detergent added. Laitance can be removed Specification
by wire brushing.

The Contractor shall clean surfaces to be painted before applying paint Project
A2 or surface treatments. Specification

A3 The Contractor shall wash and protect surfaces not requiring painting Project
such as hardware, machined surfaces, lighting fixture, and similar in- Specification
place items. All inplace items shall be removed, if necessary

A4 Fill dents, cracks, hollow places, open joints and other irregularities Project
with approved filler material Specification

A5 Wind conditions shall be such as to allow complete clean up of dust Project


and dirt on areas to be coated Specification

A6 Surfaces shall be tested for dryness after rain, water blasting, or heavy Project
overnight fog. Specification

A7 Remove all loose concrete, sealants, and old coatings by abrasive Project
blasting. Remove approximately one inch of concrete beyond any Specification
visible contaminated surface.

B Environmental Condition
Apply water-base paints only when the temperature of surfaces to be Project
B1 painted and the surrounding air temperatures are between 10 and Specification
32°C,
Apply solvent-thinned paints only when the temperature of surfaces to Project
B2 be painted and the surrounding air temperatures are between 10 and Specification
35°C
No coating shall be applied when the substrate surface temperature is Project
below 3°C above the dew point (condensation level). No painting shall Specification
be applied above 90% relative humidity. No exterior painting shall be
B3 done during conditions of blowing sand or condensation

C Primer coat Application


Apply primer coat as per manufacturer's recommendation and Manufacturer's
C1 approved method of statement Recommendatio
n
REMARKS:

REFERENCE DOCUMENTS:

Contractor / Third-Party Saudi Aramco

Construction Representative* PID Representative

Name, Initials and Date: Work is Complete and Ready for Inspection:

Mubashir Malik
[Link] Nawaz
QC Inspector Proponent

Name, Initials and Date:


Mudabbir [Link] Choudhry
Hussain
FUTURE LIFT INSPECTION CHECKLIST -FL-CIV-IC-004 DAT E APPROVED DISPLINE
ITP-CIV-002 CIVIL
Paint Products Receiving & Storage Inspection
PROJECT TITLE WBS/BI/JO/NO CONTRACTOR / SUBCONTRACTOR
Refurbishment and Modernization of Ithra Elevator 4300009686 Future Lifts/Al-Yamama
EQUIPMENT ID NUMBERS EQUIPMENT DESCRIPT ION EQPT CODE SYST EM ID PLANT NO

LAYOUT DRAWING NUMBER [Link]. PURCHASE ORDER NUMBER EC/PMCC/MCC NO.

SCHEDULED INSPECT ION DAT E&T IME ACT UAL INSPECT ION DAT E&T IME QUANT IT Y ISP.
SAUDI ARAMCO USE O NLY

SAUDI ARAMCO T IP NUMBER : SAUDI ARAMCO ACT IVIT Y NUMBER WORK PERMIT REQ?
ITP-CIV-002 2.2
YES
SAUDI ARAMCO INSPECT ION LEVEL : CONTRACTOR INSPECT ION LEVEL :
H H

ITEM ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE


No.
A General requirements
Mixing and preparing paint materials according to the manufacturer's Project
A1 recommendations Specification
A2 Stir all materials before application to produce a mixture of uniform density
Project
Specification
A3 The number of coats and the film thickness of each coat required shall comply with
manufacturer's recommendation and approved method of statement Project
Specification

Surface temperature & humidity readings shall be recorded; Coatings shall not be
A4 applied if they fall outside the manufacturer's recommended limits. Project
Specification

A5 During coating relative humidity shall be less than 85%; Surface temperature above
10°C (50°F) and 3°C (5°F) above dew point; Surfaces shall be dry; Winds low to Project
moderate. Specification

A6 All visual holes or holidays shall be repaired. Only approved products shall be used.
Project
Specification
Finishing coats shall be applied according to the manufacturer's guidelines
considering the spreading rate and dry film thickness. Project
A7 Specification
B Color painting coat application

B1 All defects shall be repaired according to the touch up and repair procedures Project
accepted by the Inspector. Specification

All defects shall be corrected and all damage from inspections (i.e., adhesion testing,
B2 wet film thickness tests etc.), shall be repaired. Project
Specification
Apply first coat of color paint to surfaces that have been cleaned, pretreated and as
per manufacturer's recommendation and approved method of statement Project
B3 Specification

Allow sufficient time between successive coatings to permit proper drying. Do not
recoat until paint has dried to where it feels firm, does not deform or feel sticky
under moderate thumb pressure and the application of another coat of paint does Project
B4 not cause lifting or loss of adhesion of the undercoat. Specification

Apply final coat of colour paint as per manufacturer's recommendation and


approved method of statement Project
B5
Specification

Matching the final painting work with the approved sample for color, texture, and
B6 coverage. Project
Specification
REMARKS:

REFERENCE DOCUMENTS:

Contractor / Third-Party Saudi Aramco


Construction Representative* PID Representative
Name, Initials and Date: Work is Complete and Ready for Inspection:

Mubashir Malik
[Link] Nawaz
QC Inspector Proponent
Name, Initials and Date:
Mudabbir
Hussain [Link] Choudhry
FUTURE LIFT INSPECTION TEST PLAN DAT E APPROVED
DISCIPLINE
ITP-CIV-002 CIVIL
PAINTING WORK
PROJECT TITLE WBS/BI/JO/NO CONTRACTOR / SUBCONTRACTOR
Refurbishment and Modernization of Ithra Elevator
PROJECT PHASE & QUALITY QUALITY INSPECTION 4300009686
RESPONSIBILITY ASSIGNMENTS Future Lifts/Al-Yamama
ITEM NO.
ACTIVITY CODE
TASK / ACTIVITY
PROCEDURE RECORD REMARKS
CNTRCT ITHRA
R
1.0 RECEIVING INSPECTION
1.1 Paint Products Receiving & Storage Inspection Scope of Work FL-CIV-IC-002 H W
2.0 INSTALLATION
2.1 Final painting inspection Scope of Work FL-CIV-IC-003 H H

GENERAL NOTES
1 Surveillance: QA /QA Organization to monitor work in progress without notice from Construction Organization
2 Witness: QA/QC organization shalt be notified of the Timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization representative
is not present.
3 Hold: QA/QC organization shall be notified of the Timing of Inspection or test in advance. Inspection or test shall not be carried out without the QA/ QC organization representative in attendence
LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection