SQM 1.00 8500.00 Supply of Noise Barrier Including All Taxes, Transportation and Complete As Per Approved Specifications and Drawings

This document provides a rate analysis for noise barriers and their installation. It includes: 1) Details on the specifications of absorptive noise barrier panels, including their acoustic and structural performance standards, materials, and dimensions. 2) A cost estimate for supplying and installing one square meter of noise barrier, totaling 9,900 per square meter. 3) Transportation and material costs for various construction materials needed at site or at a plant, including crushed metal, sand, asphalt, and emulsions.

Uploaded by

Riya Jenner
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
70 views5 pages

SQM 1.00 8500.00 Supply of Noise Barrier Including All Taxes, Transportation and Complete As Per Approved Specifications and Drawings

This document provides a rate analysis for noise barriers and their installation. It includes: 1) Details on the specifications of absorptive noise barrier panels, including their acoustic and structural performance standards, materials, and dimensions. 2) A cost estimate for supplying and installing one square meter of noise barrier, totaling 9,900 per square meter. 3) Transportation and material costs for various construction materials needed at site or at a plant, including crushed metal, sand, asphalt, and emulsions.

Uploaded by

Riya Jenner
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

RATE ANALYSIS

Noise barrier Providing and fixing absorptive noise barriers With the acoustic and non - acoustic
performance as per EN 14388 Table – 1, Acoustic performance as per EN 1793 part 1 & 2 for
minimum sound absorption Dlα value of 20.00dB and minimum air-born sound insulation DL
value of 26.00dB, In-situ acoustic performance as per EN 1793-6 of minimum DLSI value of
30.00dB, The panel shall be corrugated sandwich panel of 100mm thk x 500mm height x 1000
4000mm long stacked one above the other as per the site requirement, with the Metal
perforated cover on one side and non-perforated cover on other side with the Acoustic materia
packed/ sandwiched in between the covers. With a maximum weight of no more than 30kg per
meter square, the corrugation of the front and back panel shall be as per IS 277: 2003 of
minimum grade B. with a zinc coating of minimum 120gsm micron only for the GI panels. The
front perforated panel shall be of IS 2405-2 with the perforation of minimum 30% the weight o
the panel spread across the 70% area. The non-acoustic performance. Following self-weight as
per EN-1794-part 1 annex B, Wind load and static load as per EN-1794-part 1 annex A & IS
875 Part III (1.5times the load) as per the installation area, Resistance to brush wood fire as p
EN-1794-part 3 class A, light reflection properties as per EN-1794-part 2 annex D class 3,
Impact of stone as per 1794-part 1 annex C following the all the requirements in C.2, Safety in
collision as per 1794-part 1 annex D. The panel shall be powder coated as per IS 13871 – 1993
with Grade B of minimum gloss less than 20 and the DFT shall be minimum 60 microns. The
noise barrier structure design shall follow IS 800 satisfying the deflection criteria and load
consideration of Dead load as per actuals & live load as per IS 875 part III and IS 875 Part 4
where ever applicable. The Installation of the noise barrier poles shall be on the Earthen
shoulder or crash barrier, along the stretch or given length where ever applicable. The
installation of the noise barrier pole on the crash barrier shall be from behind, if installed on
above it shall be subjected to the collision test as per the MoRTH and 1794-part 1 annex D and
result should be pass Necessary maintenance hatches, paths, & doorways shall be applicable
where ever necessary as per the engineer in charge and as per detail drawing.

Unit = Square meter


RA for 1 Sqm
Description Unit Qty Rate
a) Material
Supply of noise barrier including all Sqm 1.00 8500.00
taxes, Transportation and complete
as per approved specifications and
drawings.

b) Fixing charges

c) Overhead & Contractor Profit


@10% on (a) Material & (b) Fixing
charges

d) Cost for 1 Sqm a+b+c

Rate per Sqm


RATE ANALYSIS

absorptive noise barriers With the acoustic and non - acoustic


N 14388 Table – 1, Acoustic performance as per EN 1793 part 1 & 2 for
rption Dlα value of 20.00dB and minimum air-born sound insulation DLr
itu acoustic performance as per EN 1793-6 of minimum DLSI value of
hall be corrugated sandwich panel of 100mm thk x 500mm height x 1000 to
one above the other as per the site requirement, with the Metal
ne side and non-perforated cover on other side with the Acoustic material
n between the covers. With a maximum weight of no more than 30kg per
rugation of the front and back panel shall be as per IS 277: 2003 of
th a zinc coating of minimum 120gsm micron only for the GI panels. The
l shall be of IS 2405-2 with the perforation of minimum 30% the weight of
ss the 70% area. The non-acoustic performance. Following self-weight as
nnex B, Wind load and static load as per EN-1794-part 1 annex A & IS
the load) as per the installation area, Resistance to brush wood fire as per
A, light reflection properties as per EN-1794-part 2 annex D class 3,
r 1794-part 1 annex C following the all the requirements in C.2, Safety in
part 1 annex D. The panel shall be powder coated as per IS 13871 – 1993
mum gloss less than 20 and the DFT shall be minimum 60 microns. The
e design shall follow IS 800 satisfying the deflection criteria and load
load as per actuals & live load as per IS 875 part III and IS 875 Part 4
. The Installation of the noise barrier poles shall be on the Earthen
rier, along the stretch or given length where ever applicable. The
e barrier pole on the crash barrier shall be from behind, if installed on
cted to the collision test as per the MoRTH and 1794-part 1 annex D and
Necessary maintenance hatches, paths, & doorways shall be applicable
as per the engineer in charge and as per detail drawing.

Amount

8500.00

500.00

900.00

9,900.00

9,900.00
MATERIAL LEAD CHART & RATE
RATE OF MATERIAL AT SITE

1 Lead For B.T. Material From Sayla /Sevalia to avg Site 110 Km
2 Lead For Asphalt From Koyli Refinery to avg Site 120 Km
3 Lead For Sand In Km From Sabarmati River to avg Site 25 Km
4 Lead For Emulsion In Km From Hinkol ,Manjusar GIDC Savli to 130 Km

Sr. Carting Cost


No. Material description Lead Cost @ Source Cost at site
Up to 5 Km. Above 5 Km
B.T. Crushed Metal
1 110 329.50 58.71 502.95 891.16
53 to 26.5 mm
B.T. Crushed Metal
2 110 325.50 58.71 502.95 887.16
26.5 to 4.75 mm
3 Sand (M 209 P. 2) 25 196.00 58.71 97.40 352.11
B.T. Crushed Metal
4 110 353.00 58.71 502.95 914.66
22.4 to 45 mm
B.T. Crushed Metal
5 110 349 58.71 502.95 910.66
2.36 to 22.4 mm
6 Stone Dust 110 105 58.71 502.95 666.66

RATE OF MATERIAL AT PLANT (For DBM, BC)

Lead For B.T. Material In Km 95 Km


Lead For Asphalt In Km 105 Km

Sr. Carting Cost Cost at Plant


Material description Lead Cost @ Source
No Up to 5 Km. Above 5 Km site
B.T. Crushed Metal
1 95 342.50 58.71 431.10 832.31
26.5 to 37.5 mm
B.T. Crushed Metal
2 95 389.50 58.71 431.10 879.31
19 to 26.5 mm
B.T. Crushed Kapchi
3 95 371.50 58.71 431.10 861.31
13.2 to 19 mm
B.T. Crushed Grit Kapchi
4 95 307.50 58.71 431.10 797.31
4.75 to 13.2 mm
B.T. Crushed Grit 2.36
5 95 285.00 58.71 431.10 774.81
to 4.75 mm
B.T. Crushed Grit
6 95 360.00 58.71 431.10 849.81
13.2 to 9.5 mm
B.T. Crushed Grit
7 95 337.50 58.71 431.10 827.31
9.5 to 4.75 mm
8 Stone dust 95 105.00 58.71 431.10 594.81
Bitumen VG 30
9 105 49532 137.21 335.00 50004.21
issue rate as on 16/08/2022
Emulsion SS 1
10 115 79466 137.21 368.50 79971.71
issue rate as on 16/08/2022
Emulsion RS 1
11 115 36719 137.21 368.50 37224.71
issue rate as on 16/08/2022
Diaphragm Wall Rate analysis 1000 mm thick

Unit SOR
Description No. L B H Qty Unit Amount
Rate Reference
Mobilization &
Demobilozation of 500,000
Machineries
It No 26075 A
Guide Wall Excavation 4 203 0.10 1.2 97.44 Cum 118.67 11,563
P 23
It No 27014 P
Guide Wall - M20 4 203 0.10 1.8 146.16 Cum 3934.79 575,109
62

Guide Wall - Reinforcement


Kg/ It No 27043 C
- Vertical 4064 1.8 0.39 2853 Kg 43.992 125,506
Rmt P 299
@ 8 - 200 c/c

Guide Wall - Reinforcement


Kg/ It No 27043 C
- horizontal - @ 8 10 812 0.39 3166.8 Kg 43.992 139,314
Rmt P 299
- 200 c/c

Excavation D. Wall 2 203 1.0 19 7714 Cum 1505.84 11,616,057

Sr no 27041
Concrete - M40 2 203 1.0 19 7714 Cum 3567.68 27,521,084
A

Total Cost 40,488,633

Cost of Diaphragm Wall per Sqm 10,497.44