BOQ FOR CANOPY LANDSCAPE
ITEM DESCRITION UNIT QTY RATE AMOUNT
A-SUB STRUCTURE 1
[Link] & EARTH WORK
1.1 Site clearing & removing the top soil of the whole area in which the
should be rest on it in 200 mm thick. M2 140.0 10 1,400.00
1.4 Pit excavation for footing in ordinary soil to a depth not exceeding
3000mm from reduced level M3 9.0 120 1,080.00
1.5 Back fill around foundation & under hard core with selected & non
expansive granular material brought from outside well rolled and
compacted in layers not exceeding 200 mm. M2 120.0 80 9,600.00
1.6 Back fill around Isolated footing with selected material from site
waste and compact in layers not exceeding 200mm thick. M3 6.5 200 1,300.00
1.7 25 cm thick basaltic or equivalent stone hard core well rolled,
consolidated and blinded with crushed stone. M2 140.0 80 11,200.00
SUB TOTAL 24,580.00
[Link] WORK
2.1 50 mm thick c-5 lean concrete, minimum cement content 150 kg/m3
under masonry and footing for the
A. STONE MASONARY M2 23.0 15 345.00
2.2 C-30 reinforced concrete minimum cement content 400 kg/m3
filled in to formwork and vibrated around steel reinforcement. (form
work and reinforcement measured separately)
A. in 10 cm thick reinforced concrete asphalt M2 38.0 150 5,700.00
2.4 Mild steel reinforcement according to structural drawings rice shall
include cutting bending, placing in position and tying wire.
A, dia 8 dmm K.G 1,000.0 5 5,000.00
SUB TOTAL 11,045.00
3. MASONARY WORK
3.1 Hard equivalent stone masonry well embedded in cement mortar
1:3 ratio.
A, ditto but below NGL M3 20.0 180 3,600.00
B, ditto but above NGL M3 10.0 180 1,800.00
c, ditto but for open ditch M3 9.4 180 1,692.00
SUB TOTAL 7,092.00
B. SUB & SUPER STRUCTURE 2
[Link] WORK
C-25 reinforced concrete minimum cement content 360 kg/m3 filled
in to formwork and vibrated around steel reinforcement. (form work
and reinforcement measured separately)
A, in steel post footing M3 4.0 260 1,040.00
B. in 15 mm solid slabs M2 -
C. in intermediate beams M3 -
Provide, cut and fix in position sawn zigba wood or steel formwork
which ever appropriate.
A, in steel post footing M2 12.4 160 1,980.00
B. in 15 mm solid slabs M2 - -
C. in intermediate beams M2 -
Mild steel reinforcement according to structural drawings rice shall
include cutting bending, placing in position and tying wire.
A, dia 8 mm K.G 400.0 5 2,000.00
B. dia 10 mm K.G 200.0 5 1,000.00
C. dia 12mm K.G 5 -
D. dia 14 mm K.G 5 -
SUB TOTAL 6,020.00
2. PLASTERING
Lay 40*20*100 cm mass concrete curbstone throughout the walk
ML 80.0 40 3,200.00
way sides price shall include concrete work.
Apply two coats of plastering in cement and sand mortar (1:3) finish
internal hallows block walls, for columns, and beams
M2 30.0 75 2,250.00
SUB TOTAL 5,450.00
3 PAINTING
Apply two coats of approved type and color plastic paint :-
A, internal beams, column and walls M2 50.0 35 1,750.00
[Link] one coat of Gypsum paint to internal beam column and M2 50.0 30 1,500.00
SUB TOTAL 3,250.00
4. FLOOR FINISHING
Fix 30x30 terrazo tiles on walkways wich beded on cement mortar
7.1 ratio of (1:3) price shall include cement screed , polishing and all M2 126.0 50 6,300.00
necessary work.
SUB TOTAL 6,300.00
5 ADDITIONAL WORK
DEMMOLISHING EXISTING CONCRETE CANNOPY SLAB LS 1.0 22000 22,000.00
SUB TOTAL 22,000.00