Saudi Aramco Substation Standards SAES-P-119
Saudi Aramco Substation Standards SAES-P-119
Contents
1 Scope ................................................................ 2
2 Conflicts and Deviations ................................... 2
3 References........................................................ 2
4 Acronyms and Definitions ................................. 4
5 General ............................................................. 6
6 Substation Buildings ......................................... 8
7 Substation Yard .............................................. 13
8 Substation Bus Configurations ........................ 21
Revision Summary................................................. 22
1 Scope
This standard presents the mandatory requirements for the design and installation of
onshore and when specifically specified in this standard, offshore power substations.
This document may not be attached to nor made a part of purchase orders.
2.1 Any conflicts between this document and other applicable Mandatory Saudi
Aramco Engineering Requirements (MSAERs*) shall be addressed to the
EK&RD Coordinator.
* Examples of MSAERs are Saudi Aramco Materials System Specifications (SAMSSs),
Engineering Standards (SAESs) and Standard Drawings (SASDs).
2.2 Any deviation from the requirements herein shall follow internal company
procedure SAEP-302.
3 References
The selection of material and equipment, and the design, construction, maintenance, and
repair of equipment and facilities covered by this standard shall comply with the latest
edition of the references listed below unless otherwise noted.
5 General
Exception to 5.2:
5.4 Location of substation and substation equipment shall comply with SAES-B-055.
Substations shall be located in non-classified areas as defined by SAES-B-068.
5.5.3 The following status conditions shall be displayed, but not limited to:
a) Loss of circuit breaker tripping supply (Minimum one alarm per bus)
b) Loss of switchgear protection supply (Minimum one alarm per bus)
c) Loss of SF6 gas pressure in circuit breaker and each individual gas
compartment. High pressure alarm, as per manufacturer
recommendation, for adjacent gas compartments with different gas
pressure under normal operation.
d) Low circuit breaker operating air pressure
e) Power transformer combustible gas present
f) Power transformer pressure relief valve operated
g) Power transformer Buchholz relay alarm
h) Power transformer Buchholz relay trip
i) On load tap changer oil flow relay trip
j) Power transformer high winding temperature
k) Power transformer loss of reference potential on Automatic
Voltage Regulator (AVR)
l) Power transformer loss of cooling fan supply voltage
Alarms are equipment specific. Some substations will not have all of
these alarms, or may require more as deemed necessary.
5.6 Tap changer, automatic voltage regulator, protection and circuit breaker control
panels shall be located inside the substation building when associated equipment
is located in an outdoor transformer yard or switchyard (for example,
transformer with an automatic tap changer or outdoor circuit breaker).
Exception to 5.6:
Built-in control panels within the SF6 dead tank circuit breakers shall be installed
with the breakers outside.
6 Substation Buildings
6.2 Substation buildings shall have smoke detection systems and firestops per
SAES-B-014.
6.3 Substation buildings shall be provided with one exit door every 15 meters in the
long wall opposite to the transformers yard side.
6.4 Passageways shall have an unobstructed width of 1.12 meter and shall provide a
minimum 2.3 meter headroom.
The exterior cable buses should have the minimum bend angles as most
of bends angles should be accommodated inside the substation.
6.5.2 Cable buses shall not be routed through the space, shown as Space (y)
in Figure 1 and Figure 2, which is directly in front of the adjacent large
transformer containing more than 7,570 liter of insulated oil.
6.5.4 The elevation of the bottom of the lowest interior cable tray shall be a
minimum of 2.67 meter above the main substation floor.
6.6 Substation service-entrance and branch circuit feeders’ conductors other than
grounding conductors shall enter or exit through the building walls, and enter
the equipment from the top.
Exceptions to 6.6:
- Substation building housing GIS equipment rated 69 kV and above, and its auxiliary
room/building housing the GIS auxiliary power system.
6.7 Maximum substation building length and width shall be limited to 75 and 15 meters
respectively.
Exception to 6.7:
6.8 Minimum horizontal clearances around GIS rated 69 kV and above shall be as
per Table 1.
Exceptions to 6.8:
6.9 Structural design calculations to verify the buildings blast design capacity shall
be conducted in accordance with SAES-B-014.
Commentary Notes:
- SAES-B-014 has specific requirements for buildings in near or associated with plants
and may require a Building Risk Assessment Study that may affect the construction
of the building.
- Provision of a below grade level for cable access ways into substations and
switchgear rooms is not considered multi-story construction.
6.10 Substation interior and exterior lighting shall be provided as per SAES-P-123.
Saudi Aramco: Company General Use
©Saudi Aramco 2019. All rights reserved. Page 9 of 24
Document Responsibility: Electrical Substations Equipment Standards Committee SAES-P-119
Issue Date: 3 February 2019
Next Planned Update: 3 February 2022 Substations
6.11 All interior substation lighting shall be fed from different buses of Secondary-
Selective low voltage switchgear.
Commentary Note:
6.14 Duplex convenience outlets shall be provided throughout the substation building.
A minimum of one outlet shall be provided for each 6 meters of wall space at
1 meter above the floor. A minimum of two outlets per substation shall be
provided.
6.16 Substation roof drainage shall not be to the transformer yard side of the
substation building.
6.17.2 The ground below the building shall be at or above finished grade.
6.17.4 Shall not drain to the transformer yard side of the substation building.
6.17.5 The side wall of the building adjacent to the transformer yard shall be
solid and fire-rated (same as the building wall that separates the space
from the transformer yard) and it shall meet the general requirements
of IEEE 979.
Commentary Note:
Note that paragraph 6.6 does not allow cable or electrical raceways to
enter/exit through the floor, except GIS installations as per exception to
6.6.
6.18 The concrete floor in front of switchgear shall be flush with the roller level of
lower breaker carriage rack and have a smooth surface to facilitate removal and
rolling of breaker. This floor area shall be surface hardened for rolling stock.
6.19 Underneath switchgear and controlgear, one of the following shall be provided
to ensure the equipment is maintained on an even plane:
6.19.2 The floor shall be horizontal in both planes with a maximum surface
height variation less than 5 mm per 3 meters.
6.20 Substation buildings shall have a minimum 2 hour fire rating and be constructed
in accordance with SAES-M-100, and where required by SAES-O-Series as
vital equipment.
6.21 A battery room and battery handling facilities shall be provided for stationary
batteries in accordance with SAES-P-103.
6.22 Circuit breaker testing facilities and operating tools shall be provided and
installed in the substation in accordance with SAES-P-116.
Since providing for future double-ending will require additional floor space,
this should be addressed in the design basis or project proposal documents.
6.24 Substation buildings shall have a telephone and data communications. This shall
include connection to the plant local area network. SAES-P-126 mandates a
dedicated (stand lone) Ethernet network for the power system automation.
6.25 Substation buildings shall have provisions for mounting and protecting as-built
key one-line diagrams for ready reference of operating personnel.
6.26 Substation buildings shall have Distributed Control System (DCS) Input/Output
(I/O) ports available. Design, installation, and interconnection to plant DCS
system shall be per the applicable SAES-Z-Series.
6.28.1 Arc pressure surge release outside substation building shall be cooled
in the absorber before it is released. The duct shall be oriented in
horizontal plane, and the exhaust shall be extended at least 2 meters
beyond the periphery of the switchgear. The duct outlet shall exhaust
into a restricted access area extended a minimum of 3 meters directly
in front of the exhaust outlet and 1.5 meters to each side.
6.29 Substation buildings housing GIS equipment rated 69 kV and above shall be
provided with overhead traveling crane suitable for maintenance purposes per
TES-P-119.19.
6.30 Substation building housing GIS equipment rated 69 kV and above shall be
constructed with underground cable basement with concrete walls from all sides.
The building basement floor shall be at least 1.0 meter above the ground water
table level, and it shall be in accordance with TES-P-119.19 and TES-P-119.21.
Commentary Note:
In areas with high underground water level, two-story GIS building should be
used i.e. one single story for cable room, and one single story for main GIS room.
6.31 Substation building housing GIS equipment rated 69 kV and above located in
remote area and away from any facility shall be provided with toilet as per
TES-P-119.19. The toilet shall be separated from the main GIS building by at
least two-hour fire-resistant barrier. The exhaust duct from toilet shall not be
Saudi Aramco: Company General Use
©Saudi Aramco 2019. All rights reserved. Page 12 of 24
Document Responsibility: Electrical Substations Equipment Standards Committee SAES-P-119
Issue Date: 3 February 2019
Next Planned Update: 3 February 2022 Substations
7 Substation Yard
7.1.3 The intent of the above requirements is met by gate(s) which can be
opened to provide the required clearance.
7.2 Transformer clearances and fire barriers shall meet the general requirements of
IEEE 979 and shall be as follows:
7.2.1 For transformers containing 7,570 liters and less of insulated oil:
Clearance shall be per 7.1 above.
7.2.2 For transformers containing more than 7,570 liter of insulated oil:
a) Separation from buildings:
If the building has a fire rating; 6.1 meters or greater (Figure 1).
b) Separation from any other substation yard equipment, for
example, transformers, reactors, capacitor banks:
If no fire barrier or barrier fire rating is less than 1 hour: greater
than a minimum of 9.1 meters of clear space (Figure 2).
2 hours Firewall
Building
Building
Substation
2 hours Firewall
X
<X <X
Generic
Space (y)
2m
600 mm
1 hour Firewall
Building 2 hours
Substation
Firewall
600 mm
300 mm
2m
6.1m
6.1m
6.1m
9.1 m
Space (y)
6.1m
Figure 2
7.3 Transformer oil containment and/ or drainage systems shall be provided for oil
filled equipment containing more than 2,500 liters of oil. The systems shall be
as follows:
7.3.2 For power transformers 2.5 MVA and above, the following oil
containment/drainage system shall be provided:
a) Oil containment and drainage systems shall meet the general
requirements of IEEE Std. 980 and the specific requirements of
SAES-S-020.
b) Oil containment systems shall be designed to withstand a
minimum 3 hours fire occurring within the bounds of the
containment system.
c) Oil containment shall be in the form of a concrete pit constructed
around the transformer foundation to contain 110% of
transformer oil. The perimeter of the spill containment shall be
located beyond the portion of the electrical equipment containing
oil, based on the height of bushing and conservator. The pit shall
Saudi Aramco: Company General Use
©Saudi Aramco 2019. All rights reserved. Page 15 of 24
Document Responsibility: Electrical Substations Equipment Standards Committee SAES-P-119
Issue Date: 3 February 2019
Next Planned Update: 3 February 2022 Substations
7.4 Transformer Neutral Ground Resister (NGR) shall be located in the substation
yard. NGR shall be constructed as per 14-SAMSS-531 and shall not be mounted
on a transformer.
7.5 Fire water system design shall be in compliance with SAES-B-017 and
SAES-B-019 for transformer, substation, and substation yard protection.
Fire water hydrants shall not be located within the fence line of a substation
yard. Fire water hydrants nozzle installed directly outside the fence shall be
pointed toward the road to receive truck connection.
7.6 The substation yard shall be completely paved as a plant area in accordance with
the requirements of SAES-Q-006. The thickness of the combined asphalt layers
shall not be less than 10 cm.
Commentary Note:
The high surface resistivity of an asphalt-aggregate mixture under both wet and
dry conditions reduces the number of ground grid conductors required to obtain
safe step and touch potentials during ground faults.
with Saudi Aramco Standard Drawing AB-036319 and shall be posted on the
fence at intervals not to exceed 6 meters.
7.8 Equipment located in the substation yard shall not be accessible from the roof of
the substation building.
7.9.2 Outdoor units shall be equipped with self-closing covers which are
weatherproof when the covers are closed.
7.9.3 Outdoor receptacles shall be fed from a Ground Fault Circuit Breaker
with 5 mA trip or from Equipment Protection Device (EPDs) with
nominal 30 mA trip. Receptacles with integral ground fault protection
are not acceptable).
7.10 The Outdoor Substation switchyard (69 kV and above) shall be in accordance
with the following:
Commentary Note:
The Outdoor Substation construction is prohibited for new installations and only
allowed for expanding existing substations.
7.11 Exposed equipment insulators, except for surge arresters, shall have a minimum
leakage distance of 40 mm per kV line-to-line of the nominal system voltage.
7.12 Surge arresters shall be installed on systems with nominal operating voltages of
13.8 kV and above at the following locations:
7.12.1 At interface points between overhead lines, open bus, and underground
lines. This include open bus transition used to connect underground
cables to air type transformer bushings.
7.13.2 Surge arrester shall be of the composite insulation type with silicone
rubber compound external insulation over a hermetically sealed
fiberglass core.
Specific Note(s):
S1 The Maximum Continuous Operating Voltage is 10 and 12.7 for solidly-grounded and
resistance / un-grounded respectively.
7.15 The substation type air core series reactor shall meet the requirement of
58-TMSS-02.
8.2 The bus configuration of 33 or 34.5 kV GIS shall be single-bus with normally
open bus-section circuit breaker.
8.3 The mandatory requirements for selecting and configuring GIS bus designs for
substations operating at 69 kV or above are defined in Table 4.
Commentary Note:
380 Breaker-and-a-Half S1
E1
Breaker-and-a-Half S1
2-2-8 2-2-8 or 2-1-6
S2
Double-Bus-Single-Breaker Double-Bus-Single-Breaker
230
- Ring-Bus S3
- Radial-Bus S5
2-2-8 2-1-6
S2
Double-Bus-Single-Breaker Double-Bus-Single-Breaker
Ring-Bus Ring-Bus S3
69 to 132
- Inverted-PI S4
- Radial-Bus S5
Specific Note(s):
S1 Breaker-and-a-Half Configuration:
Spare bay breakers shall not be installed.
Layout shall accommodate future addition of necessary breakers to complete bay configuration.
No sectionalizers shall be installed
Redundant generation sources and redundant utility sources shall not be connected to the
same bay.
S2 Double-Bus-Single-Breaker Configuration:
(2-2-8) arrangement consists of two (2) sectionalizers, two (2) couplers, and
eight (8) disconnectors, or
(2-1-6) arrangement consists of two (2) sectionalizers, one (1) coupler, and
six (6) disconnectors configured in Z shape.
Bus sectionalizer and bus coupler shall be operated normally closed.
Redundant feeders or redundant power sources shall not be connected to the same bus
segment or connected to the bus segments connected by the bus coupler.
S3 Ring-Bus Configuration:
Redundant generation sources and redundant utility sources shall not be connected to
adjacent positions.
All breakers shall be operated normally closed.
The number of positions for onshore and offshore applications shall be limited to four (4), and
six (6), respectively.
S4 Inverted-PI Configuration:
Limited to two (2) primary and two (2) secondary feeders.
No breakers shall be installed in the secondary feeders.
The bus coupler shall be operated normally closed.
S5 Radial-Bus Configuration:
Acceptable for substations dedicated to feed gas or oil production wellsites.
The configuration shall include spare incoming breaker for future alternate supply.
E1 Breaker-and-a-Half Configuration is permitted only in cases where number of breakers/switches
is less than required for Double-Bus-Single Breaker Configuration or when there is three (3) utility
incoming circuits.
Revision Summary
5 November 2012 Major revision.
27 April 2014 Editorial revision to synchronize substation receptacle requirement with SAES-P-100
requirement.
17 February 2015 Minor revision by adding 600 mm dike between transformer fire wall and substation building
and detailing the grading and oil containment pits for power transformers.
30 July 2017 Major revision by revising substations bus configurations and mandate GIS modular design for
33 kV and above, increase substation length, and other improvements.
1 January 2018 Editorial revision to modify paragraphs 6.6.
3 February 2019 Major revision to eliminate the standard requirement of Life-Cycle Cost (LCC) Analysis as the
selection of Substation Bus Configurations will be standardized based on mainly the type of
connection sources, i.e., power generation and utility vs. utility supply only. The main focus in
this review is 230 kV substations. In 230 kV GIS substations, breaker-and-a-half scheme will
be standardized for substations having both generation and utility supplies, while double-bus-
single-breaker scheme will be standardized for substations having utility supplies only.