FES EQUIPMENT SERVICES SDN. BHD.
(503539-A)
Lot 9895, Jalan Kampung Jawa, Section 35, Bandar Shah
Alam, 40470, Selangor Darul Ehsan, Malaysia.
Tel : +603-3373 7835 Fax : +603-3371 3513
Email : enquiry@[Link]
SETTING HOISTING LIMIT AND PERFORM LOAD TEST
Client BUMI ARMADA
Name of MV ARMADA FIRMAN 2
Crane S/N 1465
Crane Model 8/10K
Job Number B 0101 801
REV DOCUMENT HISTORY EFFECTIVE DATE ORIGINATOR
00 Initial release 30/12/2019 Hasnol Syafiq
JOB ATTEND BY
NAME DESIGNATION DATE ONBOARD
HASNOL SYAFIQ BIN MOHAMAD RASLI SERVICE ENGINEER 30/12/2019
Important:
This document, or any part thereof, remains the property of FES Equipment Services Sdn. Bhd. and
must not be used or copied in any form without prior written permission from FES Equipment Services
Sdn. Bhd. It is only to be used for the purpose for which it has been issued. It must not be given to any
third party and must be returned or destroyed upon completion of the purpose of which it has been
issued.
FES EQUIPMENT SERVICES SDN. BHD. (503539-A)
Lot 9895, Jalan Kampung Jawa, Section 35, Bandar Shah
Alam, 40470, Selangor Darul Ehsan, Malaysia.
Tel : +603-3373 7835 Fax : +603-3371 3513
Email : enquiry@[Link]
CONTENTS
1. PEDESTAL CRANE SPECIFICATION 2
2. DAILY PROGRESS REPORT 3-4
Work package No Prepared By Date Prepared Page No
MV ARMADA FIRMAN 2 Hasnol Syafiq 30 December 2019 Page 1 of 5
FES EQUIPMENT SERVICES SDN. BHD. (503539-A)
Lot 9895, Jalan Kampung Jawa, Section 35, Bandar Shah
Alam, 40470, Selangor Darul Ehsan, Malaysia.
Tel : +603-3373 7835 Fax : +603-3371 3513
Email : enquiry@[Link]
1.0 PEDESTAL CRANE SPECIFICATION
MV ARMADA FIRMAN 2 Description
Manufacture Load Chart
Favelle Favco
Serial Number & Model
1465 (8/10K)
Crane Capacity
Main Hoist : 30.0 T
Aux Hoist : 5.0 T
Boom Length
50.4 meter
Engine Running Hours
3168.0 HRS
(Record on 30/12/2019)
Robway RCI-4100IS Calibration Data
(Record on 30/12/2019)
An1 Ld1u Ld1d Ld2u Ld2d
Lo_r 549.0 0.0 314.0 0.0 509.0
Lo_c 13.0 0.0 0.1 0.0 0.0
Hi_r 2772 1000 1384 1000 2139
Hi_c 75.0 1000 7.6 1000 4.0
Work package No Prepared By Date Prepared Page No
MV ARMADA FIRMAN 2 Hasnol Syafiq 30 December 2019 Page 2 of 5
FES EQUIPMENT SERVICES SDN. BHD. (503539-A)
Lot 9895, Jalan Kampung Jawa, Section 35, Bandar Shah
Alam, 40470, Selangor Darul Ehsan, Malaysia.
Tel : +603-3373 7835 Fax : +603-3371 3513
Email : enquiry@[Link]
2.0 DAILY PROGRESS REPORT
Description of Work Remarks
Sunday
Date : 29 November 2019
Day :1
- Mob to Labuan from KLIA
Monday
Date : 30 November 2019
Day :2
- Mob to MV Armada Firman 2 from Jetty Tangga Besi at 08:00hrs
- Return back to Jetty Tangga Besi due to MV Armada Firman 2 long
side to Jetty for offloading cargo
- Mob again to MV Armada Firman 2 from Jetty Tangga Besi at
09:50hrs. Arrived at 10:00hrs
- Reporting to Captain and Chief Engineer on attending job
- Standby due to crane busy offloading cargo off board till 12:00hrs
- Monitor load reading during lifting activities using main hook block
and aux hook block. No abnormal condition were found
- Standby due to MV Armada Firman 2 long side to anchorage area
at 13:00hrs
- Record Robway RCI-4100IS calibration data
- Perform stall brake test for luff band brake and luff disc brake. All
brake in good condition. Pressure gauge reading as per crane
specification. Luff ratchet working in good condition
- During dismantle luff limit switch cover, found that the limit switch
were loosen from it basement. Found that the screw attached the
limit switch were missing. Plan to check spare screw on board.
Temporary attached back the luff limit switch on its bracket slot
Work package No Prepared By Date Prepared Page No
MV ARMADA FIRMAN 2 Hasnol Syafiq 30 December 2019 Page 3 of 5
FES EQUIPMENT SERVICES SDN. BHD. (503539-A)
Lot 9895, Jalan Kampung Jawa, Section 35, Bandar Shah
Alam, 40470, Selangor Darul Ehsan, Malaysia.
Tel : +603-3373 7835 Fax : +603-3371 3513
Email : enquiry@[Link]
- Setting luff out limit motion cut off and alarm at angle 17.0 degree
- Setting aux hoist limit motion cut off and alarm
- Setting main hoist limit motion cut off and alarm. Unable to set
main hoist up limit. In-progress troubleshoot the wiring
- Boom rest the boom and housekeeping work area at 18:00 hrs
- Prepared reporting. Job done at 20:00 hrs
Tuesday
Date : 31 November 2019
Day :3
- Planning for tomorrow job :
1. Troubleshoot main hoist up limit motion cut off problem
(motion not cut)
2. Set luff in motion cut off and alarm
3. Install back screw on luff limit switch
4. Waiting for water bag and shackle (approximately arrived on
board on 01.01.2020 as per info from client)
Work package No Prepared By Date Prepared Page No
MV ARMADA FIRMAN 2 Hasnol Syafiq 30 December 2019 Page 4 of 5
FES EQUIPMENT SERVICES SDN. BHD. (503539-A)
Lot 9895, Jalan Kampung Jawa, Section 35, Bandar Shah
Alam, 40470, Selangor Darul Ehsan, Malaysia.
Tel : +603-3373 7835 Fax : +603-3371 3513
Email : enquiry@[Link]
Report prepared by:
HASNOL SYAFIQ BIN MOHAMAD RASLI
SERVICE ENGINEER
FES EQUIPMENT SERVICES SDN BHD
END OF PROCEDURE
If there are any changes required to this document, kindly contact Mr. Hasnol Syafiq.
email: hsyafiq@[Link] (FES Equipment Services Sdn Bhd)
Work package No Prepared By Date Prepared Page No
MV ARMADA FIRMAN 2 Hasnol Syafiq 30 December 2019 Page 5 of 5