Construction Drainage Guide
Construction Drainage Guide
WAFFLE NOTES 1. Surface drainage of the site shall be controlled from the start of site preparation
and construction. The drainage system shall be completed by the finish of
1. Plumber to lay waste pipes below ground surface at minimum grades. Risers to be construction of the building.
ACN 162 735 917
staked firmly. If plumbing risers are located within ribs then maintain minimum rib
FIRST FLOOR, 25-27 RAILWAY ROAD, BLACKBURN, VIC. 3130 2. Surface drainage shall be constructed to avoid water ponding against or near the
width of 110mm by cutting ends off void formers and lapping reinforcement as
PHONE: (03) 9894 4222 FAX: (03) 9894 4424 footing. The ground in the immediate vicinity of the perimeter footing, including
required. Void formers to be cut and taped around plumbing risers.
Email: [email protected] the ground uphill from the slab on cut and fill sites, shall be graded to fall 50mm
2. External service trenches are to be kept away from the house by a distance of at away from the footing over a distance of 1m and shaped to prevent ponding of
SITE PREPARATION NOTES least the depth of the trench. water. Any perimeter paving shall also be suitably sloped away from the footings.
1. Top soil containing grass roots or other organic material shall be
removed from the area on which the waffle raft is to rest. 3. Place up to 50mm of quarry sand or quarry product over the building area within 3. Where perimeter paving slabs are constructed they must have a 10mm layer of
the edge and any internal load bearing beams. ableflex or similar between the paving slab and the footing/wall. An agricultural
2. Cut and fill site to form a level bench as per architectural drawings. drain or similar must be installed at the outer edge of the perimeter of the paving
4. Vapour barrier to be placed under void formers and ribs. Prepare waffle raft within slab and is to be diverted to the legal point of discharge.
3. Where shallow surface fill exists, or is to be placed to level the site formwork in accordance with footing plan and detail sheets.
the following conditions must be satisfied: 4. Watering and garden beds are not permitted adjacent to building(s) and adjacent
3.1. Sand Fill. Up to 600mm of sand fill only may exist or be placed 5. Vapour Barrier shall be 0.2mm thick polyethylene sheeting with adequate to perimeter paving slabs. Subsurface drains shall not be used within 1.5m of the
below the waffle raft provided that it has been well impermeability, and durability to ultraviolet deterioration and impact during building unless designed by a qualified engineer familiar with this type of design.
compacted in 150mm layers by a vibrating roller. construction. Lapping shall be not less than 200mm at joints and penetrations by
3.2. Non Sand Fill. Up to 300mm of non sand fill may exist or be pipes or plumbing shall be taped. In accordance with AS2870 C5.3.3, the barrier is 5. Bulk excavations incorporating cut and fill must have an agricultural drain (or swale
placed below the waffle raft provided that it has been well against vapour, not water, minor punctures are not important. drain) at the base of the cut into the natural clay and all surface and sub-surface
compacted in 150mm layers by a static roller. water is to be diverted from the footing to the legal point of discharge. Provision of
3.3. Controlled Fill. Controlled fill shall be placed in accordance 6. Prepare waffle void formers within formwork boards in accordance with footing a dish drain to the top of all batters will prevent the occurrence of scouring on the
with AS. 3798 following specific engineering advice. plan and detail sheets. Void formers to be spaced using appropriate plastic spacers. batter faces.
3.4. Where the above conditions cannot be complied with, the
waffle raft will require to be supported on piers. This office 7. Use appropriate plastic based bar chairs to ensure 20mm minimum top cover to 6. The base of trenches shall be sloped away from the building. Trenches shall be
should be contacted for further information regarding the size slab mesh. Slab fabric shall be lapped by one full panel of fabric in both directions backfilled with clay in the top 300mm within 1.5m of the building. Compacted clay
and location of piers. and laps staggered to avoid a build up of mesh. Trench mesh in beams shall be should be used for backfilling where pipes pass beneath the footing system the
placed with 40mm cover top and bottom and spliced, where necessary, by a lap of trenches will be backfilled full depth with clay or concrete to restrict the ingress of
4. The construction process may be made easier if the fill material 500mm. At T- and L- intersections the trench mesh shall be overlapped by the water beneath the footing system.
extends one metre outside the building line. The area within one width of the fabric.
metre of the slab edge shall be graded away from the slab to 7. Penetrations of the edge beams of raft or perimeter strip footings shall be avoided
prevent water resting against the slab. 8. Concrete shall be not less than 20 MPa grade (unless noted otherwise) with 20mm where practicable, but where necessary shall be detailed to allow for movement.
nominal maximum aggregate size and 100mm slump. Concrete should be cured for
GENERAL NOTES at least 7 days prior to placing brickwork. 8. Drains attached to/or emerging from underneath the building shall incorporate
1. Do not scale these drawings. All dimensions to be taken from architectural flexible joints immediately outside the footing and commencing within one metre
drawing. 9. Refer to sections 5 and 6 of AS. 2870-(current edition) for full set of detailing and of the building perimeter to accommodate a total range of differential movement
2. The owner's attention is drawn to appendix B of AS. 2870 (current edition) construction requirements. in any direction equal to the estimated characteristic surface movement of the site
`performance requirements and foundation maintenance'.
3. Refer to soil report, architectural drawings and detail sheets for additional
(ys). In the absence of a specific design guidance the fittings or other devices that
construction and maintenance requirements which form part of this 10. Shrinkage cracking to any concrete surface can occur as part of the natural curing are provided to allow for movement shall be set at the mid position of their range
design. process. This is not considered a structural defect and can be expected to occur of possible movement at the time of installation, so as to allow for movement
4. Whilst every effort has been expended to locate and design for services in within the guidelines specified in the Residential Slabs and Footing Code (AS2870), equal to 0.5ys in any direction from the initial setting. This requirement applies to
and around the proposed development, it remains the contractors in particular Appendix C, Table C2. all stormwater, sewer drains and discharge pipes.
responsibilty to ensure no services are damaged or exposed during the
proposed works.
SHEET NUMBER
1
2
BCTA HOMES EAST MELBOURNE
Associated Details 1 3
Associated Details 2 4
Overhang Details
Tree Influence Diagram
5
6
Revision Date Description Drawn Title Sheet Sheet No. 1 Job No: 2215220/1
Articulation Details 1
Articulation Details 2
7
8
2215220/1 09/11/21 AMDT - Trench grated added ANDREW W. BCTA
HOMES EAST MELBOURNE
Articulation Details 3 9 2215220 01/10/21 Construction Issue Design LOT 1148, HEGGART CRESCENT, OFFICER SOUTH
Structural Notes 10 ANDREW W. SITE CLASSIFICATION
Roof Support Plan 11 CLASS P (MOD. M)
Structural Details 12 Date FOOTING SYSTEM SUSPENDED WAFFLE RAFT
Drainage Notes 13
Roof & Site Drainage 14 09/11/2021 CLASSIFIER CLICK ENGINEERING (AUST) PTY LTD
Drainage Details 15 Scale --- Checked by, for and on behalf of Click Engineering (aust) Pty Ltd SOIL REPORT NUMBER 2214650 NB01-autocad pdf (general documentation).pc3
100mm DIA. SEWER PIPE IL. 1890mm
930
BOUNDARY
150 MIN THICK SLAB FOR HOT WATER SERVICE, CHAMFER WAFFLE BOXES TO LOCALLY WIDEN EDGE BEAM
INTEGRATED WITH HOUSE SLAB. 3-L11TM TOP CREATE 400x400 PILE CAP ON TO FORM 600x600 FOOTING
400
300
(50 COVER). REINFORCEMENT TO CONTINUE BACK TRIM VOID FORMERS ALL INTERNAL PILES ADDITIONAL SL82 BOTTOM
T
INTO SLAB AS INDICATED. SIZE AND LOCATION IN TO SUIT (TYPICAL)
CU
L
)
)
)
FIL
00
00
ACCORDANCE WITH ARCHITECTURAL DRAWINGS
00
00
00
00
00
(6
(6
(7
(7
(7
(7
(7
LOCATION OF DEEPENED
REBATE AS PER DETAIL.
400
400
400
400
400 A
BOUNDARY
MIN. 3
O
PL
BOUNDARY
PL
LBW LBW
300
LBW
A
LOCALLY WIDEN EDGE BEAM 400
3
TO FORM 900x600 FOOTING
ADDITIONAL SL82 BOTTOM 400
LBW
400 400
LOCATION OF 1N12 TOP 150 MIN. THICK SLAB FOR COOLING UNIT,
TO PRINCIPAL RIBS REFER INTEGRATED WITH HOUSE SLAB.
400
300
TO SHEET 3
LOCALLY DEEPENED SLAB SL82 TOP & BOTTOM. 30mm COVER VAPOUR
LOCATION OF DEEPENED 400x400x400 MIN. DEEP BARRIER TO CONTINUE BENEATH SLAB.
REBATE AS PER DETAIL. TO CREATE PILE CAP
BOUNDARY 1270
300
NOTE:
THIS LOT WAS VACANT AT THE TIME OF DESIGN POINT LOADS:-
PLO - POINT LOAD OVER NOTE:
ALL SCREW IN PILES LOCATED WITHIN SHADED AREAS
ARE TO BE FOUNDED AS INDICATED BUT ALSO AT LEAST
SLAB AND FOOTING PLAN POINT LOADS FOUNDED DIRECTLY ONTO WAFFLE SLAB PANELS
MUST NOT EXCEED 10kN SAFE WORKING LOAD.
INDICATIVE LOCATION OF WASTEPOINT, 2000mm MIN BELOW THE NATURAL GROUND LINE OR IF SO, THIS OFFICE SHOULD BE CONTACTED FOR FURTHER
SCREW IN PILE SCHEDULE CONSULTING.
REFER TO SIMONDS ARCHITECTURAL DIRECTLY ONTO WEATHERED ROCK DUE TO EXISTING
DRAWINGS FOR EXACT LOCATION OR PROPOSED TREES. RED SCREW-IN PILE AS PER MANUFACTURERS
SPECIFICATIONS, TAKEN DOWN THROUGH ANY NOTE:
EXISTING FILL AND DRIVEN TO A SAFE WORKING AT A RE-ENTRANT CORNER WHERE AN EXTERNAL BEAM
NOTE: LOAD OF 80kN. CONTINUES AS AN INTERNAL BEAM, THE EXTERNAL BEAM DETAILS
NOTE: WHERE EXISTING OR PROPOSED TREES ARE WITHIN THE
AT THE TIME OF THIS DESIGN IMMATURE TREES EXISTED WITHIN ZONE OF INFLUENCE OF ANY FOOTINGS (i.e. WITHIN BUT ALSO BELOW THE ANGLE OF REPOSE OF ANY SHALL BE CONTINUED FOR A LENGTH OF 1m INTO THE INTERNAL
THE NATURE STRIP ADJOINING THIS SITE. WE HAVE ASSUMED A EXISTING SEWER OR STORMWATER PIPES IN THE BEAM.
0.75xTHEIR MATURE HEIGHT), THEN THE FOOTINGS ARE TO BE
MAXIMUM MATURE HEIGHT OF 10m FOR THESE TREES AND HAVE EASEMENTS (MINIMUM DEPTHS SHOWN IN BRACKETS).
DEEPENED AND FOUNDED DIRECTLY ONTO WEATHERED
DESIGNED SUSPENDED BEAMS AND BORED PIERS ACCORDINGLY.
BEDROCK IF PRESENT OR 2000mm BELOW NATURAL GROUND NOTE:
TREE REMOVAL OR PLACEMENT OF TREE ROOT BARRIERS IS LINE, WHICHEVER IS SHALLOWER. ALTERNATIVELY THESE TREES FILL NOTE: CONSULTATION WITH THE GEOTECHNICAL ENGINEER HAS BEEN SOUGHT
REQUIRED IF THE EXPECTED MATURE HEIGHT OF EXISTING TREES COULD BE REMOVED OR TREE ROOT BARRIERS PLACED. ALL LOOSE SURFACE FILL, ALL ROOTS AND ALL ORGANIC TO ENSURE THAT THE UNDERLYING SITE CLASSIFICATION IS NOT
IS GREATER THAN 10m AND THIS OFFICE SHOULD BE CONTACTED N.B. ARBORIST ADVICE AND/OR COUNCIL PERMIT IS REQUIRED MATERIAL ARE TO BE REMOVED FROM THE BUILDING AFFECTED BY THE PROPOSED SITE WORKS. THE PROPOSED SITE WORKS
FOR FURTHER ADVICE. FAILURE TO REMOVE TREES OR PLACE TREE PRIOR TO PLACEMENT OF TREE ROOT BARRIERS, CUTTING TREE PLATFORM. SITE IS TO BE CUT AND/OR FILLED (OR SITE HAVE BEEN TAKEN INTO ACCOUNT AT THE TIME OF THIS FOOTING
ROOT BARRIERS IS LIKELY TO RESULT IN FOUNDATION FAILURE. ROOTS, OR REMOVING TREES. SCRAPED) TO FORM A LEVEL BENCH. ANY EXISTING AND DESIGN.
ANY PLACED FILL MATERIAL IS TO CONFORM AND BE PLACED
IN ACCORDANCE WITH AS2870-2011 CL.6.4.2 AND IS NOT TO IN ACCORDANCE WITH NCC VOL.2 SECTION 3.1. SITE BATTERS MUST
WAFFLE PARAMETERS REINFORCEMENT LEGEND EXCEED 300mm. ANY IMPORTED PLACED FILL IS TO BE A NOT EXCEED:
SLAB THICKNESS - 85mm SLAB MESH - SL82 DENOTES STARTING POINT FOR LAYING WELL GRADED COMPACTIBLE MATERIAL. PLACED FILL IS TO · SAND AND SILT, 1:2
BOX HEIGHT - 225mm INTERNAL RIB - 1-N12 BOTTOM OF VOID FORMERS. CONTINUE PAST THE EDGE OF THE BUILDING BY AT LEAST · STIFF CLAY, 1:1 FOR CUT - 1:2 FOR FILL BATTER
OVERALL DEPTH - 310mm EXTERNAL RIB - Refer to details for 1m AND IS TO BE PLACED IN ACCORDANCE WITH IF THIS CANNOT BE ACHIEVED ON SITE THEN RETAINING WALLS
MAX. RIB CENTRES - 1200mm width and DENOTES 3-L11TM (OR 3-N12 BARS) x AS2870-2011 CL.6.4.2. IF THE BUILDING PLATFORM IS SOFT WILL BE REQUIRED AND THIS OFFICE IS TO BE CONTACTED FOR
INTERNAL RIB WIDTH - 110mm reinforcement 2000mm LONG TIED TO UNDERSIDE OF OR THE TOTAL DEPTH OF FILL IS GREATER THAN 300mm FURTHER CONSULTATION
SLAB MESH. BARS MAY BE DELETED WHERE THEN THIS OFFICE IS TO BE CONTACTED FOR REDESIGN.
ADDITIONAL REINFORCEMENT REQUIREMENTS FOR EDGE SLAB MESH LAPS AT INTERNAL CORNERS.
BEAMS WITH WIDTHS EXCEEDING 400mm Drawn Sheet No. 2 Job No: 2215220/1
SHADED AREA DENOTES AREA WHERE VOID ANDREW W. HOMES EAST MELBOURNE
STEM WIDTH ADDITIONAL BEAM BASE ADDITIONAL FORMERS ARE SET DOWN. REFER TO Design
mm TOP STEEL WIDTH mm BOTTOM STEEL DETAILS. LOT 1148, HEGGART CRESCENT, OFFICER SOUTH
ANDREW W.
ACN 162 735 917
110-150mm - 300-330mm - LBW Date
LOAD BEARING WALL 1st FLOOR, 25-27 RAILWAY RD,
151-220mm 1-N12 331-440mm 1-N12 BLACKBURN, VIC. 3130
CUT 09/11/2021
221-330mm
331-440mm
2-N12
3-N12
441-550mm
551-660mm
2-N12
3-N12 FILL
INDICATIVE LOCATION OF CUT FILL LINE Scale 1:100 Slab and Footing Plan E: [email protected]
P: (03) 9894 4222
ARCHITECTURAL DRAWINGS
150 MAX. REBATE
WIDTH 150
NOTE: SET DOWN VOID FORMERS BY
85mm
THICK
(i.e. ALL RIBS SPANNING 20mm cover
85mm
THICK
BETWEEN PAD FOOTINGS AS
85mm
THICK
SHOWN ON SHEET 2.)
310
225
MIN.
400
310
310
225
225
VOID FORMER VOID FORMER
TYPICAL DOUBLE STOREY WAFFLE SLAB CROSS SECTION SCALE 1:20 TYPICAL PRINCIPAL RIB CROSS SECTION SCALE 1:20
ARCHITECTURAL
WIDTH EXCAVATING STEPPED DOWN
CONTINUOUS FLASHING
DRAWINGS.
AREAS DEEPER. SET DOWN
WEEPHOLES @ 1000 CTRS
BELOW 150(MAX) WIDE
85mm
ALL RIBS SPANNING BETWEEN PAD
THICK
BRICK REBATE
SL82 TOP
20mm cover
VOID FORMER
310
225
VOID FORMER
310
225
MIN.
VOID FORMER
150
VAPOUR BARRIER
4-L11TM (OR 4/N12 BARS)
3-L11TM (OR 3/N12 BARS) TOP & BOTTOM 50mm MAXIMUM DEPTH OF
1N12 x 300 LONG BOTTOM (TRIM CENTRAL 1/N12 BAR BOTTOM 400 PACKING SAND OR GRANULAR
60MIN. COVER WIRE OVER PILE) 1N12 x 300 LONG MIN. LEVELLING LAYER
150 150 60MIN. COVER
SCREW-IN PILE DRIVEN TO
300 1090max. 110 A SAFE WORKING LOAD
MIN. (in both directions) AS PER PLAN ON SHEET 2.
310
225
WIDTH VOID FORMER VOID FORMER
VAPOUR BARRIER
4-L11TM (OR 4/N12 BARS)
TOP & BOTTOM 50mm MAXIMUM DEPTH
1N12 x 300 LONG 400 OF PACKING SAND OR
SL82 TOP
20mm cover
NOTE 60MIN. COVER MIN. GRANULAR LEVELLING LAYER
REFER TO SLAB PLAN
FOR MINIMUM
REINFORCEMENT SCREW-IN PILE AS PER
REQUIREMENTS MANUFACTURERS SPECIFICATIONS SCREW-IN PILE DRIVEN TO
A SAFE WORKING LOAD AS
PER PLAN ON SHEET 2.
VOID FORMER
NOTE
WHEN DEPTH OF FILL EXCEEDS 750
mm PLACE SL82 MESH IN MIDDLE
OF DEEP EDGE BEAM. FILL DEPTH
NOT TO EXCEED 1200mm MAX
SECTION
750 MAX.
A
SCALE 1:20 S2
NOTE
REFER TO SLAB PLAN FOR
MINIMUM EDGE BEAM 930 1990
MIN.
150
REQUIREMENTS
PROPOSED
BOUNDARY
RESIDENCE
MIN.
700
1000
SCREW-IN PILE AS PER TRENCH
1890
MANUFACTURERS SCREW-IN PILE DRIVEN TO
SPECIFICATIONS A SAFE WORKING LOAD AS
PER PLAN ON SHEET 2.
30° FAILURE LINE
100mm DIA.
SEWER PIPE 45° FAILURE LINE
VOID FORMER M12 CHEMSET 101 PLUS AT 400 CTRS VOID FORMER
110mm MIN. EMBEDMENT
50mm MINIMUM EDGE DISTANCE
20mm
MAX.
NOTE:
These standard overhang details may be adopted providing none of
the below listed items have been breached. If one or more of the
items have been breached this office should be contacted to provide
a SITE SPECIFIC DESIGN SOLUTION.
2m WIDE EASEMENT
0.0
10
6
8
10
.7
4
.8
0.
.9
.8
99
99
78°56'40" 32.00
10
99
99
9
.5
99
w
9
.6
99
0
.8
99
8
.8
99
5
.9
HEGGART CRESCENT
99
.9
99
168°56'40" 12.50
348°56'40" 12.50
5
.7
.6
99
99
0
.8
9.8
99
.9
01
5
RL
.8
0.
99
E
10
.9
AP
99
CR
99.6
ES
SIT
. 0
100
6
4
2
.7
.8
.6
ET
99
99
4
99
7
.9
.5
.6
99
6
99
.9
99
99
258°56'40" 32.00
NOTE:
GWW
"PLANTING OF TREES SHOULD BE AVOIDED NEAR A FOUNDATION OF CURRENT ZONE OF INFLUENCE OF DRYING
A BUILDING OR NEIGHBOURING BUILDING ON REACTIVE CLAY SITES EFFECT ON CLAY SOILS DUE TO EXISTING
AS THEY CAN CAUSE DAMAGE DUE TO DRYING OF THE CLAY AT TREES
SUBSTANTIAL DISTANCES. TO REDUCE, BUT NOT ELIMINATE, THE
POSSIBILITY OF DAMAGE, TREE PLANTING SHOULD BE RESTRICTED
TO A DISTANCE FROM THE THE HOUSE AS FOLLOWS: EXPECTED ZONE OF INFLUENCE OF DRYING
· 1.5 x MATURE HEIGHT FOR CLASS E SITES. EFFECT ON CLAY SOILS DUE TO MATURE Drawn Sheet No. 6 Job No: 2215220/1
· 1 x MATURE HEIGHT FOR CLASS H1 AND H2 SITES . TREES ANDREW W. HOMES EAST MELBOURNE
· 0.75 x MATURE HEIGHT FOR CLASS M SITES." Design LOT 1148, HEGGART CRESCENT, OFFICER SOUTH
IMMATURE TREE - GROWTH TO BE MONITORED. ANDREW W.
AUSTRALIAN STANDARD 2870-2011 APPENDIX B2.3 c ACN 162 735 917
BRICKWORK ARTICULATION
JOINT LOCATION
F.L.
C.L.
F.L.
ELEVATION A
1080
ELEVATION B
PROVIDE SUPPORT FOR WALL PANELS BY FIXING CAVITY NOTE:
WALL TIES TO EVERY FOURTH COURSE ON EACH SIDE ARTICULATION JOINTS TO BE IN ACCORDANCE WITH THE
OF ARTICULATION JOINTS. CEMENT CONCRETE & AGGREGATES AUSTRALIA
TECHNICAL NOTE 61.
COMPRESSIBLE FOAM JOINT FILLER
AND MASTIC BACKING
LEGEND:
BRICKWORK ARTICULATION
JOINT LOCATION
ELEVATION C
ELEVATION D
PROVIDE SUPPORT FOR WALL PANELS BY FIXING CAVITY NOTE:
WALL TIES TO EVERY FOURTH COURSE ON EACH SIDE ARTICULATION JOINTS TO BE IN ACCORDANCE WITH THE
OF ARTICULATION JOINTS. CEMENT CONCRETE & AGGREGATES AUSTRALIA
TECHNICAL NOTE 61.
COMPRESSIBLE FOAM JOINT FILLER
AND MASTIC BACKING
LEGEND:
BRICKWORK ARTICULATION
JOINT LOCATION
NOTE:
ALL BEAMS TO HAVE 90mm MIN. END
BEARING UNLESS SPECIFIED OTHERWISE.
NOTE:-
THE DESIGN/DOCUMENTATION BY ENRIK
TGT ENGINEERING HAS BEEN LIMITED TO THE
REQUESTS OF THE CLIENT. ANY ITEMS NOT
TGT
SHOWN ON THESE DRAWINGS TO BE BY THE
BUILDING DESIGNER OR OTHER CONSULTANTS.
DOUBLE STUDS:-
TGT
TGT
PROVIDE 2-90 x 45 MGP10 STUDS LOCATED UNDER
ENDS OF ALL MEMBERS SPECIFIED ON THIS
DOCUMENTATION UNLESS NOTED OTHERWISE.
ALL BEAMS AND SUPPORTS NOT SPECIFIED ON THIS
DOCUMENTATION ARE TO BE DESIGNED BY OTHERS.
ROOF TRUSSES:-
PREFAB TIMBER ROOF TRUSSES, DESIGN, CENTRES,
FIXING AND BRACING BY OTHERS. GIRDER TRUSS
LOCATIONS HAVE BEEN ASSUMED AND MUST BE
CONFIRMED WITH FINAL TRUSS LAYOUT DRAWINGS
TO CONFIRM THE SUPPORTING MEMBER SIZES.
POINT LOADS:-
ROOF SUPPORT PLAN POINT LOADS FOUNDED DIRECTLY ONTO WAFFLE SLAB
PANELS MUST NOT EXCEED 10kN SAFE WORKING LOAD.
IF SO, THIS OFFICE SHOULD BE CONTACTED FOR FURTHER
CONSULTING.
P1
RB2
FLOOR JOISTS:-
ID
RB1
TGT
TRIMMERS ETC. TO BE IN ACCORDANCE WITH THE
AI
ST
BBO
SLBS
RB2
BBO
MEMBER SCHEDULE
P1
BBO LBW LBW LBW C1 B1
C1
TRUSSES TIMBER ROOF TRUSSES @ 600 CTRS TO
SLBS BBO BBO MANUFACTURERS SPECIFICATIONS
B1 250 UB 37
LOWER ROOF & FIRST FLOOR SUPPORT PLAN Drawn Sheet No. 11 Job No: 2215220/1
ANDREW W. HOMES EAST MELBOURNE
Design LOT 1148, HEGGART CRESCENT, OFFICER SOUTH
ANDREW W.
ACN 162 735 917
Date 1st FLOOR, 25-27 RAILWAY RD,
09/11/2021 BLACKBURN, VIC. 3130
RB 2
1 RB B1
P1
MINIMUM 45MM
BEARING FOR EACH BEAM SCALE 1:10
REQUIRED TO BE
CONFIRMED ON SITE
C1
NOTE:
C1
10mm THICK BASE PLATE 10mm THICK BASE PLATE
6CFW. TO THE COLUMN. 6CFW. TO THE COLUMN.
2-M12 CHEMSET 101 BOLTS 2-M12 CHEMSET 101 BOLTS
TO SLAB.
TO SLAB. 30 TYP. 75 MIN. 30 TYP. 30 TYP. 30 TYP.
MIN.
50
50
PLAN VIEW PLAN VIEW
1. THE BUILDER SHALL IMPLEMENT AN EFFECTIVE EROSION CONTROL PLAN TO ENSURE 1. SURFACE DRAINAGE OF THE SITE SHALL BE CONTROLLED FROM THE START OF SITE 1. ALL WORKS TO BE CARRIED OUT IN ACCORDANCE WITH THE LOCAL CITY
THAT THERE IS NO DISCHARGE OF SEDIMENT FROM THE SITE. PREPARATION AND CONSTRUCTION. THE DRAINAGE SYSTEM SHALL BE COMPLETED COUNCIL STANDARD SPECIFICATIONS AND UNDER THE SUPERVISION OF THE
PRIOR TO THE SLAB BEING POURED. CITY ENGINEER OR THEIR REPRESENTATIVES.
2. EXCAVATIONS AND EXPOSURE OF SOILS SHOULD ONLY OCCUR ON THE ACTUAL HOUSE
PLATFORM, RATHER THAN THE ENTIRE SITE. VEGETATION INCLUDING GRASS SHOULD BE 2. SURFACE DRAINAGE SHALL BE CONSTRUCTED TO AVOID WATER PONDING AGAINST OR 2. CONTRACTORS ARE TO VERIFY ALL EXISTING INFORMATION BEFORE
KEPT WHERE POSSIBLE, DURING THE CONSTRUCTION PERIOD. NEAR THE FOOTING. THE GROUND IN THE IMMEDIATE VICINITY OF THE PERIMETER COMMENCEMENT OF ANY WORK IN PARTICULAR THE LEGAL POINT OF
FOOTING, INCLUDING THE GROUND UPHILL FROM THE SLAB ON CUT AND FILL SITES, DISCHARGE. IF ANY DISCREPANCY EXISTS BETWEEN THE ACTUAL LEGAL POINT
3. ALL STORMWATER SHOULD BE RE-DIRECTED FROM THE CONSTRUCTION AREA VIA SHALL BE GRADED TO FALL 1:20 MINIMUM AWAY FROM THE FOOTING AND SHAPED TO OF DISCHARGE ON SITE, THIS PLAN AND/OR INFORMATION SUPPLIED BY
APPROPRIATE GRADING OF THE SITE AND/OR PLACEMENT OF OPEN DRAINS. PREVENT PONDING OF WATER. ANY PERIMETER PAVING SHALL ALSO BE SUITABLY COUNCIL, THEN THIS OFFICE SHOULD BE CONTACTED FOR FURTHER ADVICE.
SLOPED AWAY FROM THE FOOTINGS. IT IS EMPHASISED THAT THE LEGAL POINT OF DISCHARGE IS TO BE
4. A FORMAL CONSTRUCTION ACCESS POINT SHOULD BE ESTABLISHED. FORMAL CONFIRMED PRIOR TO ANY WORKS, INCLUDING FOUNDATIONS, SITE
CROSSOVER PROTECTION SHOULD BE PLACED. A CRUSHED ROCK BASE, WITH 3. WHERE PERIMETER PAVING SLABS ARE CONSTRUCTED THEY MUST HAVE A 10mm LAYER EXCAVATIONS AND RUNNING OF OTHER SERVICES, ETC.
APPROPRIATE DEPTH TO STOP SOILS FROM SURFACING, SHOULD BE PLACED FOR OF ABLEFLEX OR SIMILAR BETWEEN THE PAVING SLAB AND THE FOOTING/WALL. AN
DELIVERY AND CONSTRUCTION VEHICLE ACCESS. AGRICULTURAL DRAIN OR SIMILAR MUST BE INSTALLED AT THE OUTER EDGE OF THE 3. OBTAIN ALL BUILDING SET-OUT DETAILS AND DIMENSIONS FROM
PERIMETER OF THE PAVING SLAB AS PER DETAIL AND IS TO BE DIVERTED TO THE LEGAL ARCHITECTURAL DRAWINGS.
5. WHERE FILL IS TO BE STOCKPILED, THEN A SEDIMENT FENCE SHOULD BE PLACED POINT OF DISCHARGE.
AROUND THE FILL. 4. IT IS THE CONTRACTOR'S / CLIENT'S RESPONSIBILITY TO CHECK THE LOCATION
4. WATERING AND GARDEN BEDS ARE NOT PERMITTED ADJACENT TO BUILDING(S) AND AND DEPTHS OF ALL EXISTING UNDERGROUND SERVICES WHETHER SHOWN
6. A SILT FENCE, HAY BALES OR SEDIMENT SANDS SHOULD BE PLACED ACROSS THE LOWEST ADJACENT TO PERIMETER PAVING SLABS. PLUMBING AND DRAINAGE SUBSURFACE ON THIS DRAWING OR NOT, PRIOR TO THE COMMENCEMENT OF
POINT OF THE SITE IN ORDER TO STOP ANY SEDIMENT FROM LEAVING THE SITE, AND TO DRAINS SHALL NOT BE USED WITHIN 1.5m OF THE BUILDING UNLESS DESIGNED BY A EXCAVATIONS.
PROTECT ADJACENT SITES. QUALIFIED ENGINEER FAMILIAR WITH THIS TYPE OF DESIGN.
5. LEVELS AND CONTOURS SHOWN ARE TO AN ARBITRARY DATUM.
7. CONSTRUCTION VEHICLES, WHICH COLLECT SEDIMENT DUE TO THEIR PROCESS, EG 5. BULK EXCAVATIONS INCORPORATING CUTS GREATER THAN 400mm MUST HAVE AN
BACKHOES, SHOULD BE WASHED DOWN BEFORE LEAVING THE SITE. AGRICULTURAL DRAIN AT THE BASE OF THE CUT, INTO THE NATURAL CLAY AND ALL 6. EXISTING WORKS DAMAGED DURING CONSTRUCTION ARE TO BE
SURFACE AND SUB-SURFACE WATER IS TO BE DIVERTED FROM THE FOOTING TO THE REINSTATED TO ORIGINAL CONDITION BY CONTRACTOR TO THE
8. ANY SEDIMENT INADVERTENTLY LEAVING THE SITE, SHOULD BE COLLECTED FROM THE LEGAL POINT OF DISCHARGE. IN SOME INSTANCES A DISH DRAIN TO THE TOP OF SOME SATISFACTION OF THE OWNER.
ROAD USING WASHING AND COLLECTION METHODS, PRIOR TO IT ENTERING A BATTERS MAY BE REQUIRED TO PREVENT THE OCCURRENCE OF SCOURING ON THE
STORMWATER DRAIN. BATTER FACES. 7. BACKFILL TRENCHES BENEATH PAVEMENT WITH F.C.R.
9. THE STORMWATER INLET POINT SHOULD BE PROTECTED AGAINST SILT INGRESS VIA; SILT 6. THE BASE OF TRENCHES SHALL BE SLOPED AWAY FROM THE BUILDING. TRENCHES SHALL 8. SUBGRADE TO BE STRIPPED OF TOP SOIL AND THOROUGHLY COMPACTED
NETTING, HAY BALES OR ANY APPROVED PROPRIETY SYSTEM. BE BACKFILLED WITH CLAY IN THE TOP 300mm WITHIN 1.5m OF THE BUILDING. BEFORE PLACING PAVEMENT. PAVEMENT TO BE 100mm THICK CONCRETE
COMPACTED CLAY SHOULD BE USED FOR BACKFILLING WHERE PIPES PASS BENEATH THE WITH 1 LAYER OF SL72 MESH PLACED WITH 30mm TOP COVER ON 50mm
FOOTING SYSTEM THE TRENCHES WILL BE BACKFILLED FULL DEPTH WITH CLAY OR COMPACTED DEPTH OF CRUSHED ROCK BEDDING.
SITE CLASSIFICATION: CONCRETE TO RESTRICT THE INGRESS OF WATER BENEATH THE FOOTING SYSTEM.
CLASS P (MOD. M) 7. PENETRATIONS OF THE EDGE BEAMS OF RAFT OR PERIMETER STRIP FOOTINGS SHALL BE
AVOIDED WHERE PRACTICABLE, BUT WHERE NECESSARY SHALL BE DETAILED TO ALLOW
9. 90mm DIA. MINIMUM AGGI DRAINS TO BE PLACED AT THE BASE OF ALL CUT
BATTERS (EXCEEDING 400mm) AND RETAINING WALLS, AND CONNECTED TO
CHARACTERISTIC SURFACE MOVEMENT (Ys): MAIN STORMWATER PIPES VIA SILT PITS, UNLESS NOTED OTHERWISE.
FOR MOVEMENT.
20mm to 40mm 8. DRAINS ATTACHED TO/OR EMERGING FROM UNDERNEATH THE BUILDING SHALL
10. ALL WAFFLE EDGE & INTERNAL BEAMS ARE TO BE EXCAVATED DOWN 100mm
MIN. BELOW THE 45° LINE OF INFLUENCE TO ANY NEW OR EXISTING
INCORPORATE FLEXIBLE JOINTS IMMEDIATELY OUTSIDE THE FOOTING AND ADJACENT SERVICE TRENCHES BUT ALSO INTO THE RECOMMENDED
COMMENCING WITHIN 1m OF THE BUILDING PERIMETER TO ACCOMMODATE A TOTAL FOUNDING MATERIAL AS NOTED IN THE SOIL REPORT. THESE EXCAVATIONS
MIN. REQUIREMENTS RANGE OF DIFFERENTIAL MOVEMENT IN ANY DIRECTION EQUAL TO THE ESTIMATED MAY BE FILLED WITH BLINDING CONCERETE TO UNDERSIDE OF THE FOOTINGS
CHARACTERISTIC SURFACE MOVEMENT OF THE SITE (ys). IN THE ABSENCE OF A SPECIFIC OR INTERNAL BEAMS.
FOR SEWER ARTICULATION DESIGN GUIDANCE THE FITTINGS OR OTHER DEVICES THAT ARE PROVIDED TO ALLOW
FOR MOVEMENT SHALL BE SET AT THE MID POSITION OF THEIR RANGE OF POSSIBLE
MOVEMENT AT THE TIME OF INSTALLATION, SO AS TO ALLOW FOR MOVEMENT EQUAL
SEWER EXIT POINTS & ORG RISERS TO 0.5ys IN ANY DIRECTION FROM THE INITIAL SETTING. THIS REQUIREMENT APPLIES TO PERFORMANCE OF FOOTING SYSTEMS
SITE ALL STORMWATER, SEWER DRAINS AND DISCHARGE PIPES. AND THE OWNERS RESPONSIBILITY FOR SITE MAINTENANCE:
CLASS
SWIVEL EXPANDER EXPANDER LAGGING THE DRAINAGE DESIGN INDICATED ON THESE DRAWINGS ARE INTENDED TO
PROTECT THE STRUCTURE DURING CONSTRUCTION AND A SHORT PERIOD AFTER
HANDOVER. THE OWNER NEEDS TO CONSIDER A LONG TERM LANDSCAPING
'M' 0 0 NOTE 1 MIN. 20mm SOLUTION.
THE PERFORMANCE OF FOOTING SYSTEMS ON REACTIVE SITES DEPENDS IN PART
'H1' 1 1 NOTE 1 MIN. 40mm ON THE ADOPTED ROUTINE OF POST-CONSTRUCTION MAINTENANCE.
'H2' 2 1 MIN. 40mm NOTE: TO AVOID EXTREME MOISTURE CONDITIONS, IT IS ESSENTIAL THAT OWNERS
NOTE 1 BECOME AWARE OF THEIR RESPONSIBILITY TO CARE FOR AND ADEQUATELY
THE DRAINAGE DESIGN AS INDICATED ON THESE DRAWINGS RELATES ONLY TO
'E' 2 1 NOTE 2 MIN. 40mm UNPAVED AREAS AROUND THE PERIMETER OF THE BUILDING. IF PAVING OR MAINTAIN A REACTIVE CLAY SITE.
LANDSCAPING IS TO BE INSTALLED AROUND THE PERIMETER AT A LATER DATE GUIDANCE TO THE OWNER IS GIVEN IN CLAUSES 1.3.2 AND 1.3.3 AND A CSIRO
NOTE 1 - MAX DEPTH OF SEWER TO UNDERSIDE OF SLAB TO BE 900mm FOR CLASS M THEN THE DRAINAGE REQUIREMENTS NEED TO BE REVIEWED & UPGRADED TO BUILDING TECHNOLOGY FILE 18 (FORMERLY KNOWN AS INFORMATION SHEET
& 600mm FOR CLASS H1 & H2, OTHERWISE EXPANDER JOINT REQUIRED. ENSURE THAT ALL RUNOFF IS COLLECTED & DISPERSED ACCORDINGLY. 10-91), ENTITLED: FOUNDATION MAINTENANCE AND FOOTING PERFORMANCE:
NOTE 2 - EXPANDER REQUIRED ON ALL RISERS. PROPERTY OWNERS, CURRENT & FUTURE SHOULD BE MADE AWARE OF THIS A HOMEOWNER’S GUIDE
REQUIREMENT. IF THE HOMEOWNER’S MAINTENANCE ROLE IS TO BE DIMINISHED, OR HIGHER
EXPECTATIONS OF PERFORMANCE ARE DEMANDED, THEN THE FOOTING SYSTEM
MIN. REQUIREMENTS AND OR DRAINAGE SYSTEM SHOULD BE DESIGNED ACCORDING TO ENGINEERING
PRINCIPLES.
EXPANSION JOINT CAPACITY
SITE CLASS EXPANDER MOVEMENT RANGE SWIVEL ROTATION RANGE
Drawn Sheet No. 13 Job No: 2215220/1
'E' 150mm 15° ANDREW W. HOMES EAST MELBOURNE
Design LOT 1148, HEGGART CRESCENT, OFFICER SOUTH
'H1&H2' 70mm 15° ANDREW W.
ACN 162 735 917
Date 1st FLOOR, 25-27 RAILWAY RD,
MIN. 20mm LAGGING BLACKBURN, VIC. 3130
'M' NOT APPLICABLE 09/11/2021
THROUGH FOOTING
Scale --- Drainage Notes E: [email protected]
P: (03) 9894 4222
0.
10
00.09.99 .8
8 4 .7
6
NORTH 10 1 9 99 78°56'40" 32.00 99
.8 99
9
.5
99
RISER RISER
w
ALFRESCO
FFL: 99.975 9
.6
99
PROPOSED 80
9.
.88 9
99 RESIDENCE
RISER
5
.9 FINISHED FLOOR LEVEL
99
HEGGART CRESCENT
97
FFL:100.11
.
99
168°56'40" 12.50
PORCH
RISER
FFL: 99.89
348°56'40" 12.50
FAL
2m WIDE EASEMENT
L
1 .7
0
.6
5
99 99
80
SQ
TRENCH GRATE
9.8
.
99
01 85 .9
C
0. .
PV
90 L
0 . 99 R
1 PE
.U
99 RA
DIA
C
99.6
ES
mm SIT MAX.
.0
100 PROPOSED
100 IL. 98.97 TBC PRIOR
TO CONSTRUCTION
GARAGE IO. .6
2
FINISHED FLOOR LEVEL 99
6
.7
4 FFL:99.975 4 RISER
99 RISER
ET
.9 .8 66 .5
7
.9
6 99 99 .
99
99
99
IL. 99.465 258°56'40" 32.00
T.B.M. NOTE:
THE SOIL IS TO BE GRADED AWAY L.P.O.D
G.I. NAIL
ELECTRICITY PIT
FROM THE PROPOSED FOOTING.
ROOF AND SITE DRAINAGE PLAN INDICATIVE LEGAL POINT OF DISCHARGE
TO CONNECT TO A PROPERTY INLET INSIDE
RIGHT REAR BOUNDARY IN ACCORDANCE
RL. 100.00 WITH PROPERTY SERVICE INFORMATION.
IN ACCORDANCE WITH NCC VOL.2 SECTION 3.1. SITE NOTE: NOTE: FILL NOTE:- NOTE:
THE SOIL IS TO BE GRADED TO FALL 1:20 RISERS MAY BE ADDED, REMOVED OR
BATTERS MUST NOT EXCEED: ALL SURFACE WATER DRAINAGE DURING WHERE ADDITIONAL FILL IS PLACED OVER
MINIMUM AWAY FROM THE FOOTING AND RELOCATED TO SUIT THE SITE CONDITIONS AT
· SAND AND SILT, 1:2 CONSTRUCTION IS THE RESPONSIBILITY OF THE NATURAL SURFACE, THE NATURAL
SHAPED TO PREVENT PONDING OF WATER. ANY THE DISCRETION OF BUILDER AND OR PLUMBER.
· STIFF CLAY, 1:1 FOR CUT - 1:2 FOR FILL BATTER BUILDER AND POST CONSTRUCTION THE OWNER'S SURFACE IS TO FIRST BE SLOPED AWAY
PERIMETER PAVING SHALL ALSO BE SUITABLY
IF THIS CANNOT BE ACHIEVED ON SITE THEN RETAINING RESPONSIBILITY. WATER MUST NOT BE ABLE TO POND FROM BUILDING FOOTPRINT.
SLOPED AWAY FROM THE FOOTINGS.
WALLS WILL BE REQUIRED AND THIS OFFICE IS TO BE NEAR OR DIRECTLY ADJACENT TO ANY FOOTINGS.
CONTACTED FOR FURTHER CONSULTATION
TEMPORARY DOWNPIPES TO BE USED
NOTE: DRAINAGE SYSTEM DURING CONSTRUCTION ONCE ROOF
FUTURE LANDSCAPING NOTE: REFER TO ARCHITECTURAL DRAWINGS FOR ALL ROOF DRAINAGE COVER ANDGUTTER ARE INSTALLED.
ALL SURFACE WATER DRAINAGE DURING CONSTRUCTION IS THE RESPONSIBILITY OF THE BUILDER.
AFTER HANDOVER THE OWNER IS TO MAINTAIN A MINIMUM REQUIREMENTS. THIS DESIGN BRIEF DOES NOT EXTEND TO GUTTER AND WATER MUST NOT BE ABLE TO POND NEAR OR DIRECTLY ADJACENT TO ANY FOOTINGS.
HEIGHT OF 150mm FROM THE FINISHED GROUND LEVEL, DOWNPIPE SIZING NOR DOES IT CONFIRM DOWNPIPE AND OR SPREADER IN ADDITION TO THE DOCUMENTED DESIGN, AT THE DISCRETION OF THE BUILDER, WHERE A SITE
LANDSCAPING OR PAVING LEVEL TO THE DAMP PROOF LOCATIONS/SPACING AS DEPICTED ON THE ARCHITECTURAL DRAWINGS. CUT LESS THAN OR EQUAL TO 400mm OCCURS (MEASURED FROM THE WAFFLE CUT LEVEL), SILT
COURSE. WHERE ADJOINING PAVED AREAS SLOPE AWAY FROM ALL THESE ELEMENTS MUST BE IN ACCORDANCE WITH AS3500.3 AND BE PITS AND AGRICULTURAL DRAINS MAY NEED TO BE INSTALLED TO PREVENT PONDING OF
THE BUILDING, THESE HEIGHTS MAY BE REDUCED TO 75mm CONFIRMED BY A LICENSED PLUMBER. SURFACE WATER AS REQUIRED.
CLASS P
IT IS ALSO THE RESPONSIBILITY OF THE BUILDER TO ENSURE NO RUNOFF IS ALLOWED TO ESCAPE
LEGEND:- DIRECTION OF FALL, AWAY FROM FOOTINGS THE SITE ONTO ADJOINING SITES OR PUBLIC AREAS.
100mm NOMINAL DIAMETER PVC PIPE 1:100 MIN. REFER TO DRAINAGE REQUIREMENTS ON SHEET 1 PROVISIONS SUCH AS PHYSICAL BARRIERS AND OR AGRICULTURAL DRAINS/SILT PITS MAY BE
FALL UNLESS OTHERWISE NOTED
RISER REQUIRED AGAIN AT THE BUILDERS DISCRETION.
(MOD. M)
90mm NOMINAL DIAMETER AGGI PIPE DOWNPIPE LOCATIONS SHOWN ARE INDICATIVE ONLY AND AND CAN BE MOVED TO
SUIT, PROVIDED THAT MINIMUM NUMBER SHOWN ARE PROVIDED. POST CONSTRUCTION IT IS THE OWNER'S RESPONSIBILITY TO MAINTAIN THE DRAINAGE SYSTEM
1 : 100 MIN. FALL
UNTIL A LONG TERM LANDSCAPING SOLUTION IS PROVIDED.
SWALE DRAIN 1 IN 100 MIN. FALL DOWNPIPE WITH SPREADER.
IO.
INDICATIVE LOCATION OF CUT FILL LINE
DIRECTIONAL FALL OF PAVING.
Drawn Sheet No. 14 Job No: 2215220/1
INSPECTION OPENING
UPVC OR PVC PIPE USED AS APPROVED BY THE CITY
ANDREW W. HOMES EAST MELBOURNE
SPOT LEVEL ENGINEER. UPVC TO BE SEWER QUALITY. Design LOT 1148, HEGGART CRESCENT, OFFICER SOUTH
ANDREW W.
JUNCTION PITS AS SPECIFIED COMPLETE WITH ACN 162 735 917
350 x 350 SILT PIT CONCRETE COVER AND STEPIRONS. Date 1st FLOOR, 25-27 RAILWAY RD,
09/11/2021 BLACKBURN, VIC. 3130
450 x 450 SILT PIT
TRENCH GRATE CONNECTED TO STORMWATER
GRATING PITS, COMPLETE WITH MEDIUM DUTY
GRATE AND STEPIRONS AS SPECIFIED. Scale 1:100 Roof & Site Drainage E: [email protected]
P: (03) 9894 4222
NATURAL SURFACE
NATURAL SURFACE
300mm
MIN.
BACKFILL WITH COMPACTED CLAY SOILS OR
EQUIVALENT TO FORM IMPERMEABLE LAYER TO
ALL TRENCHES WITHIN 1500mm OF THE BUILDING.
WHERE OUTSIDE THE 1500mm, USE EXCAVATED
MATERIAL AS NOTED BELOW.
AS3500.2 CL 5.4.2
FOOTING.
100 D
MIN.
MIN.
D
REINFORCEMENT
1000 AS PER DETAILS
FALL 1:20 = 50mm
OVER 1m MIN.
SERVICE PIPE LAGGING DETAIL PROPOSED WAFFLE RAFT