Evershine Developers Compliance Report

Uploaded by

Prisci Ida
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
94 views20 pages

Evershine Developers Compliance Report

Uploaded by

Prisci Ida
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Compliance Report

COMPLIANCE REPORT

Part A - Specific Conditions:


Conditions: Construction phase

Sr. Conditions Compliance


No.

1 All required sanitary and hygienic measures Mobile STP was provided in construction phase
should be in place before starting construction and proper care regarding sanitary
sanitary and hygienic
activities and to be maintained throughout the condition was maintained throughout the
construction phase. construction phase.
After expiry of validity of EC construction work
has been stopped. Labour camps have been empty
and associated infrastructure was dismantled.

2 Soil and ground water samples will be tested to Soil testing was done, according to the reports all
ascertain that there is no threat to the parameters are within limit and so there is no
groundwater quality by leaching of heavy threat to groundwater quality by leaching of
metals and other toxic contaminants. heavy metals and other toxic contaminants.
(Reports are enclosed).

3 A First Aid Room will be provided at the First Aid box is provided at the construction site
project site both during construction and and will be provided during the operation phase
operation of the project. too.

4 Adequate drinking water and sanitary facilities Adequate portable water facility for drinking
should be provided for construction workers at purpose was provided for the workers at the site
the site. The safe disposal of wastewater and during construction phase.
solid Wastes generated during the construction
phase should be ensured.

5 Disposal of muck including excavated material There is no measure


measure excavation except pile
during construction phase should not create foundation work. The excavated earth, generated
any adverse effects on the neighboring is used for the leveling of plot and for filling the
communities and be disposed off taking the plinth.
necessary precautions for general safety and
Health aspects of people.

6 Diesel power generating sets used during As per EP act.


construction phase should be of "enclosed
type” to prevent noise and should conform to
rules made under Environment (Protection)
Act 1986, prescribed for air and noise
emission standards.

Half Yearly Post Monitoring Report (July, 2016 – December, 2016) Page 1
M/S. Evershine Developers “Evershine Global City”
(Formerly known as Palghar Land Development Corporation)
Compliance Report

7 Ambient noise levels should conform to Care has been taken regarding noise levels with
residential area standards both during day and conformation to the residential area.
area.
night when measured at boundary wall of the
Use of well-
well-maintained equipment fitted with
premises, increments pollution loads on the
silencers.
ambient air and noise quality should be closely
monitored during construction phase. Providing noise shields near the heavy
construction operations.
Construction activities are limited to daytime
hours only.
Also use of Personal Protective Equipment
(PPE) like ear muffs and ear plug during
construction activities.

8 Vehicles hired for bringing construction The PUC checked/authorized vehicles are allowed
material at site should be in good condition and on the site for transfer of material.
should have valid "Pollution Under
Check"(PUC) certificate and to conform to
applicable air and noise emission standards.

9 Construction spoils including bituminous There is no generation of hazardous waste at site


material and other hazardous materials must but proper care would be taken following the
not be allowed to contaminate watercourses norms to dispose off the bituminous and other
and the dump sites for such material must be hazardous material at site.
secured so that they should not leach into the
The clause will be followed.
ground water.

10 Any hazardous waste generated during Condition is noted.


construction phase should be disposed off as
per applicable Rules & norms with necessary
approvals of the Maharashtra State Pollution
Control Board.

11 Regular supervision of the above and other Regular supervision is taken by our site engineer
measures for monitoring should be in place to take care of the construction activity and of the
and through the construction phase so as to surroundings. 05 nos
nos. of officers are provided for
avoid disturbance to the surroundings. monitoring.
monitoring.

Half Yearly Post Monitoring Report (July, 2016 – December, 2016) Page 2
M/S. Evershine Developers “Evershine Global City”
(Formerly known as Palghar Land Development Corporation)
Compliance Report

Operation Phase:

1 Necessary permission of competent authority Necessary permission of competent authority will


will be taken to store diesel in the premises for be taken to store diesel in the premises for
operation of DG set. operation of DG set.
set.

2 Diesel power generating sets proposes as D.G. sets are provided with silencer & acoustic
source of back-up power for lifts and common enclosures. The stacks are provided as per MPCB
area illumination should be of "Enclosed Type" norms.
and conform to rules made under Environment
(Protection) Act 1986, prescribed for air and
noise emission standards as per CPCB
guidelines. Exhausts should be discharged by
stack, raised to 4 meters above the rooftop.

3 During nighttime the noise levels measured at Noise level was found to be within the limit.
the boundary of the building shall be restricted
to the permissible levels to comply with the
prevalent regulations.

4 Noise barriers should be provided at Care has been taken regarding noise levels with
appropriate locations so as to ensure that the conformation to the residential area. 8000 nos. of
noise levels do not exceed the prescribed trees are provided on
on the road sides to act as
standards. noise barrier.
Use of well-
well-maintained equipment fitted with
silencers.
For D.G. sets are with Acoustic enclosures

5 Weep holes in the compound walls shall be Weep holes are provided in the compound wall to
provided to ensure natural drainage of ensure natural drainage of rainwater in the
rainwater in the catchment area. catchments area.

6 The sewage treatment plant should be certified The sewage treatment plant is done by an expert.
by an independent expert for efficiency as well 3.6 MLD Capacity STP’s are installed and in
as adequacy and should submit a report in this working conditions.
regard to the Ministry before the project is
commissioned for operation. The wastewater
should be treated to tertiary level and after
treatment reused for flushing of toilets and
gardening. Discharge of treated sewage, if any,
shall conform to the norms & standards
prescribed by Maharashtra State Pollution
Control Board.

Half Yearly Post Monitoring Report (July, 2016 – December, 2016) Page 3
M/S. Evershine Developers “Evershine Global City”
(Formerly known as Palghar Land Development Corporation)
Compliance Report

7 Oil & Grease Trap shall be provided to remove Oil & Grease Trap shall be provided in RWH to
oil and grease from the surface run off and remove oil and grease from the surface run off
suspended matter shall be removed in a and suspended matter is to be removed in a
settling tank before its utilization for rainwater settling tank before its utilization for rainwater
harvesting. harvesting.

8 The solid waste generated should be properly Garbage is collected manually from each of the
collected & segregated Wet garbage should be building and carted to collection spot through
composted and dry/inert solid waste should be trolleys. The garbage collected from flats is
disposed of for land filing. segregated into wet and dry garbage. The wet
garbage treated in OWC for composting. Also the
dry and inert waste handover to local municipal
authority.

9 Any hazardous waste including biomedical There will be no generation of hazardous waste or
waste should be disposed of as per applicable bio medical waste.
waste.
Rules & norms with necessary approvals of the
Maharashtra State Pollution Control Board.

10 The green belt design along the periphery of The green belt is provided along the periphery
the plot shall achieve attenuation factor and landscaping is done as per the required
conforming to the day and night noise norms. (Photographs
(Photographs enclosed).
standards prescribed for residential land use
The open spaces inside the plot should be
suitably landscaped and covered with
vegetation of indigenous variety.

11 Incremental pollution loads on the ambient air Ambient air quality, noise and water quality is
quality, noise and water quality should be periodically monitored by MoEF approved
periodically monitored after commissioning of laboratory. (Reports enclosed).
the project.

12 The ground water levels and its quality should The ground water level is monitored by MoEF
be monitored regularly in consultation with approved laboratory. (Reports enclosed). There is
Central Ground Water Authority. no ground water extraction proposed or done on
site.

13 A report on energy conservation measures A report on energy conservation measures has


should be prepared incorporating details about been prepared incorporating details about
building materials & technology, R & U Factors building materials & technology, R & U Factors
etc. and submitted to the Ministry in three etc.
etc. and is enclosed with this.
months’ time.

14 The values of R & U for the building envelope Condition is complied.


should meet the requirements of the hot &
humid climate location. Details of the building
envelop should be worked out and furnished in
three months time.

Half Yearly Post Monitoring Report (July, 2016 – December, 2016) Page 4
M/S. Evershine Developers “Evershine Global City”
(Formerly known as Palghar Land Development Corporation)
Compliance Report

Part B:
B: General Conditions

1. The environmental safeguards contained in the Condition is noted.


documents should be implemented in letter
and spirit.

2. Provision should be made for the supply of Provision was made for the supply of kerosene or
kerosene or cooking gas and pressure cooker cooking gas and
and pressure cooker to the laborers
laborers
to the laborers during construction phase. during construction phase.
After expiry of validity of EC construction work
has been stopped. Labour camps have been empty
and associated infrastructure was dismantled.

3. All the laborers to be engaged for construction All the laborers


laborers for construction works were
were
works should be screened for health and medically tested for health and adequately treated
adequately treated before the issue of work before the issue of work permits.
permits.
After expiry of validity of EC construction
construction work
has been stopped. Labour camps have been empty
and associated infrastructure was dismantled.

4. Six monthly monitoring reports should be Six monthly reports are submitted and attached.
submitted to the Ministry and its Regional
Office.

5. Officials from the Regional Office of MOEF, Condition is noted.


Nagpur who would be monitoring the
implementation of environmental safeguards,
should be given full cooperation, facilities and
documents / data by the project proponents
during their inspection. A complete set of all
the documents submitted to MoEF should be
forwarded to the CCF, Regional Officer of MoEF,
Nagpur.

6. In the case of any change(s) in the scope of the Condition is noted. And accordingly the proposal
project, the project would require a fresh has been submitted.
appraisal by this Ministry.

7. The Ministry reserves the right to add Condition is noted.


additional safeguard measures subsequently, if
found necessary, and to take action including
revoking of the environment clearance under
the provisions of the Environment (Protection)
Act, 1986 to ensure effective implementation of
the suggested safeguard measures in the time

Half Yearly Post Monitoring Report (July, 2016 – December, 2016) Page 5
M/S. Evershine Developers “Evershine Global City”
(Formerly known as Palghar Land Development Corporation)
Compliance Report

bound and satisfactory manner.

8. All other statutory clearance such as the The storage of the diesel is being done by
approvals for storage of diesel from Chief comply
complying the conditions of Petroleum Act, 1959.
Controller of Explosives, Fire Department, Civil
All necessary clearance and approval will be
Aviation Department (if required), State Forest
obtained from competent authorities as and when
Department, Wildlife Act, 1972 CRZ Rules, etc.
required.
shall be obtained by project proponents from
the competent authorities.

9. A copy of the environmental clearance letter Yes, condition is followed.


would be marked to the local NGO(s), if any for
their information.

10. The project proponent should advertise in at The advertisement has been published in two
least two local Newspapers widely circulated in local Newspapers widely circulated in the region,
the region, one of which shall be in the one in a Marathi Newspaper Nav Shakti dtd.
vernacular language informing that the project 22/03/2007 & English Newspaper, Free Press
has been accorded environmental clearance Journal dtd. 22/03/2007 informing that the
and copies of clearance letters are available project has been accorded environmental
with the Maharashtra State Pollution Control clearance. The copies of the advertisement are
Board and may also be seen on the website of attached with this report.
the Ministry of Environment and Forests at
[Link] The advertisement
should be made within 7 days from the day of
issue of the clearance letter and a copy of the
same should be forwarded to the Regional
Office of this Ministry at Nagpur.

11. These stipulations would be enforced among Condition is noted.


others under the provisions of the Water
(Prevention & Control of Pollution) Act, 1974,
the Air (Prevention and Control of Pollution)
act, 1981 the Environment (Protection) Act,
1986 and the Public Liability (Insurance) Act,
1991.

12. The project authority will enter in to MOU with Condition is noted.
all buyers of the property, if any, to ensure
operation and maintenance of the assets
handed over to the society formed by the

Half Yearly Post Monitoring Report (July, 2016 – December, 2016) Page 6
M/S. Evershine Developers “Evershine Global City”
(Formerly known as Palghar Land Development Corporation)
Compliance Report

residents / owners of the buildings.

13. Under the provisions of Environmental Environmental Clearance is already obtained.


(Protection) Act, 1986, legal action shall be
Obtained Consent to Establish.
initiated against the project proponent if it was
found that construction of the project had
started without obtaining environmental
clearance.

Half Yearly Post Monitoring Report (July, 2016 – December, 2016) Page 7
M/S. Evershine Developers “Evershine Global City”
(Formerly known as Palghar Land Development Corporation)
DATA SHEET

MONITORING THE IMPLEMENTATION OF ENVIRONMENTAL SAFEGUARDS


Ministry of Environmental and Forests
Regional Office, West Central Zone, Nagpur.

Monitoring Report

PART – I
DATA SHEET

1. Project type: river - valley/ mining/ Industry Residential and Commercial Project
/ thermal / nuclear/ Other (specify)

2. Name of the project “Evershine Global City”


City”

3. Clearance letter (s) / OM/ no and date: File No. : 21-


21-544/2006-
544/2006-IA-
IA-III.
III. Dated
13.03.2007.

4. Location Old-
Old- Survey No. 1, 5 to 8, 10 to 16, 67 to 69, 71, 92
to 93, 172 to 178, 185, 190 to 211, 219 to 224, 1A),
New-
New- Survey No. 5, 5B, 5F, 5G, 5D, Village -
Dongare, Taluka-
Taluka-Vasai, Dist-
Dist-Thane. Maharashtra.

a. District (s) Mumbai

b. State (s) Maharashtra

5. Address for correspondence

a. Address of concerned project Chief Engineer Evershine Developers Pvt. Ltd.


(with pin code & telephone / telex / fax
Heena Beena Shopping Center,
numbers)
Bandra (W), Mumbai.
b. Address of Executive Project Engineer
/Manager (with pin code / fax number)

Half Yearly Post Monitoring Report (July, 2016 – December, 2016) Page 1
M/S. Evershine Developers “Evershine Global City”
(Formerly known as Palghar Land Development Corporation)
DATA SHEET

6. Salient features

a. of the project Residential and Commercial Project


Total Plot Area = 9,32,440.00 [Link].
Area for Phase – I :
Plot area:
area: 9,32,440.00 sq. mtrs.
Total
Total Built Up Area: 8,45,591.43 sq. mtrs.
trs.
b. of the environmental management plans 1. Sewage Treatment
Treatment Plant:
Three Sewage Treatment Plants
Plants with capacity
of 3.6 MLD will be provided for treating the
wastewater.
wastewater.
Recycled
Recycled wastewater will be used for Flushing,
gardening etc.
etc. Excess treated sewage will be
disposed to TMC sewer line.
2. Water Management:
Rain Water Harvesting shall be provided to
recharge the ground water table.
3. Solid Waste Management:
Debris & excavated material generated will be
disposed by covered trucks
trucks to the authorized
site permission
permission from OWC.
OWC. Partly shall be sent
for recycling & partly
partly shall be used for
temporary work, road work, bins/tanks, site
office etc.
During Operation phase,
phase, the Solid waste to be
segregated
segregated at source and Dry waste will be
handed over to authorize Agency i.e handed
over to Municipal Corporation for further
disposal
disposal & sludge from STP will be used as
manure. Wet waste will be processed converted
to manure by processing in Organic Waste
Convertor.
Convertor.

7. Break Up of the project Area

a. Submerge area : forest & :non-forest Non Forest

b. Others Total Plot Area = 9,32,440.00


9,32,440.00sq.
,440.00sq. mtrs.
Plot area:
area: 9,32,440.00 sq. mtrs.
Total Built Up Area: 8,45,591.43 sq. mtrs.
trs.

Half Yearly Post Monitoring Report (July, 2016 – December, 2016) Page 2
M/S. Evershine Developers “Evershine Global City”
(Formerly known as Palghar Land Development Corporation)
DATA SHEET

8. Break up of the project affected: Not Applicable.


Applicable.
Population with enumeration of those
losing houses/dwelling units, only
agriculture land only, both dwelling units
and agriculture land and landless
labourers / artisan

a. SC, ST / Adivasis ---

b. Others ---

(Please indicate whether these figures are


based on any scientific and systematic
survey carried out or only provisional
figures, if a survey is carried out give
details and years of survey)

9. Financial details

a. Project cost as originally planned and Total cost:


cost: 1247.25 Cr.
subsequent revised estimates and the year
of price reference

b. Allocation made for environmental Capital EMP Cost:


Cost: 100 Cr.
management plans with item wise and
year wise break-up

c. Benefit cost ratio/ Internal rate of return


---
and the year of assessment

d. Whether ( c ) includes the cost of


environmental management as shown in ---
the above

e. Actual expenditure incurred on the project Rs. 1048.50 Cr.


so far

f. Actual expenditure incurred on the Rs. 94.56 Cr.


Cr.
environmental management plans so far

10. Forest land required

a. The status of approval for diversion of The land is of non-


non-forest type hence not
forest land for non-forestry use applicable.

Half Yearly Post Monitoring Report (July, 2016 – December, 2016) Page 3
M/S. Evershine Developers “Evershine Global City”
(Formerly known as Palghar Land Development Corporation)
DATA SHEET

b. The status of clearing and felling R.G. Area Provided: 140866 Sq. mt.
Clearing of trees is not proposed.

c. The status of compensatory afforestation,


---
if any

d. Comments on the viability & sustainability N.A.


of compensatory afforestation program in
the light of actual field experience so far

11. The status of clear felling in non-forest N.A.


areas (such as submergence area of
reservoir, approach roads), if any with
quantitative information

12. Status of construction

a. Date of commencement (Actual and/or 2007


planned)

b. Date of completion (Actual and/ of Construction has been stopped after expiry of
planned). validity of EC.

13. Reasons for the delay if the project is yet to


---
start.

14. Dates of site visits

a. The date on which the project was Not yet monitored.


monitored.
monitored by the regional office on
previous occasions, if any.

b. Date of site visit for this monitoring report 08.09.2016; 18.10.2016


18.10.2016

15. Details of correspondence with project File No. : 21-


21-544/2006-
544/2006-IA-
IA-III.
III. dtd. 13.03.2007.
13.03.2007.
authorities for obtaining action plans/
information on status on compliance to Address:
safeguards other than the routine letters Survey No. 5, 5B, 5F, 5G, 5D, Village - Dongare,
for logistic support for site visits. Taluka-
Taluka-Vasai, Dist-
Dist-Thane. Maharashtra.

Half Yearly Post Monitoring Report (July, 2016 – December, 2016) Page 4
M/S. Evershine Developers “Evershine Global City”
(Formerly known as Palghar Land Development Corporation)