Daily Timeline 07 May 2024

The document provides a progress report for the Sunshine Project by Stylers Intl. for the month of March 2024. It details the percentage of work completed each day for various buildings and tasks, including waterproofing, door installation, flooring, and more. Many tasks are reported as 100% complete or in progress with expected completion by the end of March 2024.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

Topics covered

  • Office Block,
  • Orientation of Doors,
  • Progress Report,
  • Paver Process,
  • False Ceiling,
  • Completion Status,
  • Management Areas,
  • Drinking Area,
  • Pending Activities,
  • Tentative Completion Date
0% found this document useful (0 votes)
31 views7 pages

Daily Timeline 07 May 2024

The document provides a progress report for the Sunshine Project by Stylers Intl. for the month of March 2024. It details the percentage of work completed each day for various buildings and tasks, including waterproofing, door installation, flooring, and more. Many tasks are reported as 100% complete or in progress with expected completion by the end of March 2024.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

Topics covered

  • Office Block,
  • Orientation of Doors,
  • Progress Report,
  • Paver Process,
  • False Ceiling,
  • Completion Status,
  • Management Areas,
  • Drinking Area,
  • Pending Activities,
  • Tentative Completion Date

16-May-24

Sunshine Project by Stylers Intl.


Civil Works Progress report FMO March 2024
On going Activities

Overall %
Workdone Initial Completion Extended Timeline
Building Name Levels Description 1-Apr 2-Apr 3-Apr 4-Apr 5-Apr complete COB Status
till 31-3-24 Date BL1
Today

Orientation of doors 100% 100% Completed


GF 21-3-24 3-Apr-24
Attach washrooms (Fixtures) 100% 100% Completed

Mill building Orientation of doors 100% 100% Completed

FF Worker washrooms (Vanity and fixtures) 100% 100% 21-3-24 3-Apr-24 Completed

Management washrooms (Vanity and fixtures) 100% 100% Completed

UB-2 Rooftop Waterproofing 100% 100% 15-3-24 Completed

OFFice block Floor's grinding 100% 100% Completed

Brickwork 100% 100% Completed


ETP GF 25-3-24
Flooring on passage 100% 100% Completed

Parapet 100% 100% Completed

UB2 Rooftop Waterproofing 100% 100% In Progress

Orientation of doors 87% 87% 174.0% In progress

Waterproofing 90% 5% 5% 100% 1% 0.5% 0.5% 0.5% 202.5% In Progress

Installation of Alum+Glass above coping beam 95% 0% 0% 0% 0% 0% 96% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 195.5% 31-3-24 Almost completed
16-May-24

Sunshine Project by Stylers Intl.


Civil Works Progress report FMO March 2024
On going Activities

Overall %
Workdone Initial Completion Extended Timeline
Building Name Levels Description 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar 21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar complete COB Status
till 14-3-24 Date BL1
Today

Orientation of doors 80% 5% 5% 2% 3% 5% 100% Completed


21-3-24 3-Apr-24
GF Attach washrooms (Fixtures) 90% 2% 1% 2% 2% 1% 0% 2% 100% Completed

Male management tile work 0% 31-3-24

Orientation of doors 50% 10% 10% 15% 10% 2% 2% 1% 0% 0% 0% 100% Completed

FF Worker washrooms (Vanity and fixtures) 85% 2% 3% 2% 2% 1% 2% 3% 1% 2% 2% 100% 21-3-24 3-Apr-24 Completed

Mill building Management washrooms (Vanity and fixtures) 72% 2% 3% 4% 6% 6% 4% 3% 100% Completed

Orientation of doors 5% 1% 5% 10% 1% 0% 0% 0% 0% 5% 20% 20% 0% 20% 5% 0% 0% 0% 92% In progress

Installation of glazing works 60% 5% 2% 1% 2% 1% 0% 0% 0% 0% 0% 0% 0% 0% 2% 0% 0% 0% 74% In progress

SF Gypsum Work 42% 5% 5% 8% 3% 1% 1% 1% 0% 1% 0% 0.25% 0% 0.25% 2.00% 3% 1% 2% 76% 31-3-24 In progress

Paint work on walls 16% 3% 5% 1% 5% 2% 1% 1% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 1% 0% 2% 39% In progress

Management/worker washrooms 31% 4% 4% 2% 1% 1% 0.5% 0.3% 0.0% 0.0% 0.0% 0.0% 0.25% 0.3% 5.0% 2% 1% 1% 53% In progress

UB-1 GF/FF Toilet Block, floor work 22% 6% 5% 2% 2% 5% 1% 1% 1% 0.25% 0.25% 1% 1% 1% 1% 48% 31-3-24 In progress

UB-2 Rooftop Waterproofing 100% 100% 15-3-24 Completed

OFFice block Floor's grinding 40% 10% 10% 10% 10% 20% 100% Completed

Brickwork 94% 2% 2% 1% 0% 0% 0% 1% 100% Completed


ETP GF 25-3-24
Flooring on passage 95% 2% 1% 0% 0% 0% 2% 0% 100% Completed

Parapet 91% 5% 1% 0.25% 1% 1% 1% 1% 100% Completed

Internal and external brickwork 40% 5% 5% 1% 2% 2% 0% 1% 0% 0% 0% 56% In Progress

Admin Block GF/FF Flooring 26% 0% 0% 0% 0% 0% 0% 0% 1% 0.25% 0.25% 0.25% 0% 0% 0% 0% 0% 0% 27% 30-4-24 In Progress

Waterproofing 0% 5% 5% 5% 5% 5% 10% 2% 4% 10% 5% 10% 4% 2% 2% 3% 5% 5% 87% In Progress


Roads
1% 0.5% 0.3% 0.0% 0.25% 0.25% 0% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.00% 0.00% 0.00% 4% In Progress
Paver
Sewerage 85% 1% 2% 0% 0% 0% 0% 0% 0.25% 0% 0% 0% 0.25% 0% 0.25% 0.00% 0.00% 0.00% 89% In Progress
Infrastructure 30-4-24
SWD 65% 2% 3% 1% 1% 1% 1% 1% 0.25% 0.25% 0.25% 0% 0% 1% 1% 2% 1% 1% 81% In Progress
Process
80% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 80% In Progress
Drain

Front Boundary wall


and Gate Offices 35% 5% 3% 4% 2% 2% 1% 1% 0.25% 0.25% 0.50% 0.50% 0.50% 0.50% 0.50% 1% 1% 1% 56% 30-4-24 In Progress

External staircases 65% 2% 5% 1% 1% 2% 1% 1.00% 0.25% 0.25% 0.25% 0.25% 0.50% 0.50% 0.50% 0% 0% 0% 81% 31-3-24 In Progress
with Jali work No.
1,2,3

External staircases
with Jali work No. 40% 1% 4% 5% 4% 6% 1% 1% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 1% 2% 1% 66% 30-4-25 In Progress
4,5,6
0.0025 0.0025 0.0025
0 0 0.0025
16-May-24

Sunshine Project by Stylers Intl.


Civil Works Progress report FMO March 2024
On going Activities

Workdone 9 -Apr to 16 Apr Eid Overall %


Building Name Levels Description 1-Apr 2-Apr 3-Apr 4-Apr 5-Apr 6-Apr 7-Apr 8-Apr 17-Apr 18-Apr 19-Apr 20-Apr 21-Apr 22-Apr 23-Apr 24-Apr 25-Apr 26-Apr 27-Apr 28-Apr 29-Apr 30-Apr complete COB Initial Completion Extended Timeline Extended Timeline Status
till 31-3-24 Holydays Today Date BL1 BL2

Installation of Alum+Glass 94% 0% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 100.1% Almost completed

Paint work on internal doors and windows 85% 0% 0.0% 1.0% 1.0% 1.0% 1.0% 1.0% 0.5% 0.5% 0.5% 0.5% 0.5% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 94.0% 3-Apr-24 In progress
GF
Paint work on walls 90% 0% 0% 0% 0% 0% 0% 0% 0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 90.7% Only Cooridor remaining

Male management tile work 0.0% 31-3-24

MB

FF Paint work on walls 84% 1% 1% 1% 1% 1% 1% 1% 1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 93.7% In progress

Installation of glazing works 66% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 68.5% In progress

Gypsum Work 56% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 69.2% In progress


2nd f
Paint work on walls 44% 1% 1% 1% 1% 1% 1% 1% 1% 0.5% 0.5% 0.5% 0.5% 1% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 55.5% In progress

Management/worker washrooms 48% 2% 5% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 1% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 60.3% In progress

UB-1 GF/FF Toilet Block, floor work 55% 3% 2% 1% 1% 1% 1% 1% 1% 0.5% 0.5% 0.5% 0.5% 1% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 73.0% 31-3-24 In progress

Internal and external brickwork 56% 0% 0% 0.00% 0% 0% 0% 0% 0% 0% 0% 0% 0% 1% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 61.5% In Progress
30-4-24
Flooring 25% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 1% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 30.8% In Progress
Admin Block GF/FF
Internal and external Glazing work 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 1% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 5.5%

CC jali 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 1% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 5.5%
Roads 10% 1% 1% 1% 1% 1% 1% 1% 1% 0.5% 0.5% 0.5% 0.5% 1% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 25.5% In Progress
Paver
Sewerage 89% 0.0% 0.0% 0.0% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 94.2% In Progress
Infrastructure 30-4-24
SWD 78% 1% 1% 1% 1% 1% 1% 1% 1% 0.5% 0.5% 0.5% 0.5% 1% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 89.5% In Progress
Process 81% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 1% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 86.0% In Progress
Drain

Front Boundary wall


and Gate Offices 58% 1% 2% 2% 2% 2% 2% 2% 1% 0.5% 0.5% 0.5% 0.5% 1% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 79.0% 30-4-24 In Progress

External staircases 75% 0.25% 0.25% 1% 1% 1% 1% 1% 1% 0.5% 0.5% 0.5% 0.5% 1% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 89.5% 31-3-24 In Progress
with Jali work No.
1,2,3

External staircases
with Jali work No. 58% 1% 1% 1% 1% 1% 1% 1% 1% 0.5% 0.5% 0.5% 0.5% 1.0% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 72.5% 30-4-24 In Progress
4,5,6
16-May-24

Sunshine Project by Stylers Intl.


Civil Works Progress report FMO March 2024
On going Activities

Workdone Overall %
complete COB Initial Completion
Extended Timeline Extended Timeline
Building Name Levels Description till 30-04-24 1-May 2-May 3-May 4-May 5-May 6-May 7-May Date BL1 BL2 Status
Today

Installation of Alum+Glass 85% 1.0% 1.0% 1.0% 1.0% 1.0% 1.0% 91.0% Almost completed

Paint work on internal doors 80% 2.0% 2.0% 2.0% 2.0% 2.0% 2.0% 92.0% In progress
30-Apr-24
Paint work in Ozone Area 0% 0.0% 0.0% 0.0% 0.0% 0.0% 1.0% 1.0% 2.0% In progress
Only Cooridor final
GF WASHING HALL Paint work on walls 91% 1.0% 1.0% 1.0% 1.0% 1.0% 1.0% 96.7% 15-May-24 remaining
Sealer Coating on walls 0% 0.0% 0.0% 0.0% 0.0% 1.0% 1.0% 1.0% 3.0% In progress

Repairing 90% 1.0% 1.0% 1.0% 1.0% 1.0% 1.0% 1.0% 97.0% 30-Apr-24 In progress

Male management washrooms Tile & Marble work 90% 1% 1% 1% 1% 1% 1% 1% 97.0% 31-3-24 In progress
MB
Paint work on internal doors and windows 94% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 94.7% In progress
GF 15-May-24
Paint work on walls 91% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 91.4% Only Cooridor remaining

FF Paint work on walls 94% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 0.1% 94.4% 15-May-24 In progress

Installation of glazing works 68% 68.5% In progress

Gypsum Work 69% 1% 1% 1% 1% 1% 1% 1% 76.2% In progress


2nd f 30-Apr-24 16-May-24
Paint work on walls 56% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 59.0% In progress

Management/worker washrooms 60% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 63.8% In progress

Biomass and remaining portion of boiler


UB-1 GF/FF (Paver and boiler respectively) 73% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 76.5% 31-3-24 In progress

UB-2 GF/FF Toilet Block, floor work 73% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 76.5% 31-3-24 In progress
10-May-24
Internal and external brickwork 62% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 65.0% In Progress
30-4-24 4/30/2024
Flooring 31% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 34.3% In Progress
Admin Block GF/FF 10-May-24
Internal and external Glazing work 5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 9.0%

CC jali 5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 9.0%


10-May-24
Roads Roads
Paver Paver 45% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 48.5% In Progress

Sewerage Sewerage 94% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 97.7% In Progress
10-May-24
SWD SWD 90% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 93.0% In Progress
Infrastructure 30-4-24
Septic/Collection
Chamber
Saptic Tank 90% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 93.0%

Process Drain Process Drain 86% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 89.5% In Progress
10-May-24
Front Boundary wall
and Gate Offices
Front Boundary wall and Gate Offices 79% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 82.5% 30-4-24 In Progress

External staircases External staircases with Jali work No. 1,2,3 89% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 93.0% 31-3-24 10-May-24 In Progress
with Jali work No.
1,2,3
External staircases External staircases Railing work No. 1,2,3 60% 2.0% 2.0% 2.0% 2.0% 2.0% 2.0% 2.0% 74.0% 31-3-24 10-May-24 In Progress
Railing work No.
1,2,3

External staircases
with Jali work No. External staircases with Jali work No. 4,5,6 72% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 76.0% 30-4-24 11-May-24 In Progress
4,5,6

External staircases
Railing work No. External staircases Railing work No. 4,5,6 34% 1% 1% 1% 1% 1% 1% 1% 38% 30-4-24 12-May-24 In Progress
4,5,6
5/16/2024
Sunshine Project by Stylers Intl.
Civil Works
Pending Activities
Building Name Levels Description Workdone Remarks Tentative Completion Date
False Ceiling Sheeting VO not finalized 15-Apr-24
Sample not approved and BML will
GF Installation of Trim on expansion joint 31-Mar-24
install new sample in couple of days
Installation of Fire rate door's accessories. Will start soon 10-Apr-24
Drinking area at grid T Not finalize yet 30-Apr-24
Sample not approved and BML will
Mill building FF Installation of Trim on expansion joint 31-Mar-24
install new sample in couple of days

PD Washing Area Drawings not finalize


Sample not approved and BML will
SF Installation of Trim on expansion joint 30-Apr-24
install new sample in couple of days
Drinking area Not finalize yet
Biomass and remaining portion of boiler
Start after MEP clearance
UB-1 GF/FF (Paver and boiler respectively) 30-Apr-24
Internal Brickwork (Boiler) After installation of Boiler
UB-2 Powerhouse Grating Will start in couple of days 10-Apr-24
Installation of Rungs and MS Stairs in procurement phase
MS Railing on stairs and walkways In production phase
ETP GF 5-Apr-24
Electricwork Not started yet

Tilework
Admin Block GF CC Jali will start after grey work completion 30-Apr-24
Internal and external glazing works
Roadnetwork Paver
Tanks Septic/Collection Chamber
Infrastructure In progress 30-Apr-24
External
Staircases
Thurt boring
5/16/2024
Punch list Sunshine Project by Stylers Intl.
Civil Works
Pending Activities
Floor Name Levels Description Remaining work Hand Over Date
Glass work 2 doors 2 windows 1st May 2024
Main Store
House keeping 2nd May 2024
Glass work 2 doors 4 windows 1st May 2024
2nd floor Fabric Store
House keeping 1st May 2024
Glass work 3 doors 2 windows 1st May 2024
Cuting Hall
House keeping 1st May 2024