METHOD STATEMENT ELECTRICAL ACCESS CONTROL SYSTEM
METHOD STATEMENT FOR
INSTALLATION OF ACCESS
CONTROL SYSTEM
Page 1|5
METHOD STATEMENT ELECTRICAL ACCESS CONTROL SYSTEM
1.0 Scope
This method statement details the method of installation of Access Control System.
Note
A separate Method Statement Ref. ETA/MS/E- 038 shall be submitted for testing and
commissioning of the Door Entry System (CCTV System, Access Control System,
Audio Intercom, Video Intercom)
2.0 Material
2.1 All materials shall be as per approved material submittals.
2.2 Type of cable shall be as per approved shop drawings / system manufacturer’s
recommendation.
2.3 Type and location of Card readers, Door contacts, Magentic locks, Exit Push
button shall be as per approved shop drawing.
3.0 Applicable Location
3.1 Tower E1, E2, E3, W1, W2, W3 (Entry to the Building from the Podium Areas
upto Level 2)
4.0 Method
4.1 Storage
4.1.1 All materials received at site shall be inspected and ensured against
approved material submittal.
4.1.2 Any discrepancies, damages etc. shall be notified immediately for
further action.
4.1.3 Material found not suitable for the project are to be removed from site
immediately.
4.1.4 Cables shall be stored with the factory packing on the flat surface.
4.1.5 Materials shall be stacked properly as per manufacturer’s
recommendation and covered to prevent dust and water / moisture.
4.1.6 Access Control System Equipment to be stored as per manufactures
recommendation mentioned / marked in the packing.
4.1.8 Ambient condition of the storage place to be as per manufacturer’s
recommendation.
Page 2|5
METHOD STATEMENT ELECTRICAL ACCESS CONTROL SYSTEM
4.2 Installation
4.2.1 Control Cable
[Link] Ensure the relevant current / approved shop drawings are
available with installation team.
[Link] Transfer the cable to the work place with the help
manpower..
[Link] Check the cable drum for any external damage during
transportation and ensure the type of cable against area of
usage / application.
[Link] Type and size of the cable is as per approved shop
drawings.
[Link] In concealed application pull cables manually through
conduit installed as per approved shop drawings and
approved method statements.
[Link] Leave enough length of cable at both ends of panel and
devices for termination.
[Link] No through joints is allowed without the sanction of the
Consultants.
.
4.2.2 Access Control Equipments.
[Link] Ensure the relevant current / approved shop drawings are
available with installation team.
[Link] Transfer the equipment to the work place with the help of
manpower.
[Link] Location of the panel to be as per approved shop
drawing after coordinating with other services.
[Link] Fixing holes will be marked properly keeping back box
of the panel in place.
[Link] Fix back box properly and fix remaining panel
accessories.
4.2.3 Card Readers
[Link] Ensure the relevant current / approved shop drawings are
available with installation team.
Page 3|5
METHOD STATEMENT ELECTRICAL ACCESS CONTROL SYSTEM
[Link] Exact location of the Card Readers to be as per approved
Shop drawing.
[Link] For the Card readers, which needs to be fixed on the
wall, fix appropriate [Link] box.
[Link] Install the Card readers and terminate the cable properly.
4.2.4 Door Contacts
[Link] Ensure the relevant current / approved shop drawings are
available with installation team.
[Link] Exact location of the Door Contacts to be as per approved
Shop drawing.
[Link] Type of Door Contacts to be as per the location and type
of door i.e., either recessed or surface mounted
[Link] For the Door Contacts, which needs to be fixed on the
door, door supplier to provide appropriate provisions.
[Link] Install the Door Contacts and terminate the cable
Properly.
4.2.5 Locks
[Link] Ensure the relevant current / approved shop drawings are
available with installation team.
[Link] Exact location of the Locks to be as per approved
Shop drawing.
[Link] Type of Locks Contacts to be as per the location and type
of door i.e., either recessed or surface mounted
[Link] For the Locks, which needs to be fixed on the door, door
supplier to provide appropriate provisions.
[Link] Install the locks and terminate the cable Properly.
4.2.6 Exit Push Button
[Link] Ensure the relevant current / approved shop drawings are
available with installation team.
[Link] Exact location of the Push Button to be as per approved
Shop drawing.
Page 4|5
METHOD STATEMENT ELECTRICAL ACCESS CONTROL SYSTEM
[Link] For the Push Buttons, which needs to be fixed on the
wall, fix appropriate [Link] box.
[Link] Install the Push Buttons and terminate the cable properly.
5.0 Records
5.1 QC Installation Check List
5.2 Inspection request duly signed-off by NMX and Consultant.
6.0 Attachment
6.1 QC installation checklist of Access Control System.