Measurement of Horizontal Distance
Measurement of Horizontal Distance
Distance by pacing.
Pacing consists of counting the number of steps or paces in a required distance. A
pace is defined as the length of a step in walking. It may be measured from heel to
heel or from toe to toe. In surveying, pacing means moving with measured steps;
and if the steps are counted, distances can be determined if the length of a step is
known. Counting strides instead of paces is sometimes preferred by surveyors. A
stride is equivalent to two paces or a double step.
To pace a distance, it is necessary to first determine the length of one’s pace. This
is referred to as the pace factor. There are two methods that can be used to
calibrate one’s pace. One method is to determine the average length of an
individual’s normal step. The other method is to adjust one’s pace to some
predetermined length, such as 1 meter.
The length of a pace varies with different persons. This can be determined by
walking along a line of known length on level ground at a uniform gait, and
counting the number of paces it takes to negotiate the stretch. It is advisable to do
this in at least five or more trials in order to determine the average number of
paces. The pace factor is then determined by dividing the known distance by
the average number of paces required to traverse it. It is expressed in meters
per pace. Any known distance may then be approximately calculated by
determining the number of paces (preferably the average) one takes to
negotiate it and multiplying this by one’s pace factor.
The length of a pace will vary with the speed of pacing, the roughness of the
ground, the weight of clothing and shoes used, fatigue on the part of the pacer, the
slope of the terrain, as well as the age and gender of the individual. The pace will
also differ when going uphill or downhill.
Distance by taping.
The use of a graduated tape is probably the most common method of measuring
or laying out horizontal distances. Taping consists of stretching a calibrated tape
between two points and reading the distance indicated on the tape. It is a form of a
direct measurement which is widely used in the construction of buildings, dams,
bridges canals, and many other engineering as well as non-engineering activities.
Distance by tachymetry.
Tachymetry (or tacheometry) is another procedure of obtaining horizontal
distances it is based on the optical geometry of the instrument employed and is an
indirect method of measurement. A transit or a theodolite is used to determine
subtended intervals and angles on a graduated rod or scale from which distances
are computed by trigonometry. Tachymetric measurements are performed either
by the stadia method or the subtense bar method.
2. Subtense bar method. The subtense bar which is precisely 2 meters long,
consists of a rounded steel tube through which runs a thin invar rod. At each
end of the frame the target marks are housed. It is mounted horizontally on a
tripod and placed perpendicular to the line of sight by means of a sighting
device on top of the bar.
The procedure for determining the distance between two points consists of
setting up the subtense bar at the distant station and measuring the horizontal
angle subtended by the distance between the two targets. A theodolite, set up
at the other end of the line to measured, is used in measuring the subtending
angle.
The subtense bar method is often used in obtaining distances over very rough
or inaccessible terrain such as across canyons, wide rivers, ravines, and even
across busy city streets.
Distance by graphical and mathematical methods.
By graphical or mathematical methods, unknown distances may be determined
through their relationship with known distances geometrically. However, before
any distances are determined, the scale must first be established.
1. Head tapeman- the person responsible for the accuracy and speed of all linear
measurements with the tape. He determines and directs the marking of points
or stations, orders the clearing out of obstructions along lines to be measured,
and is the person who carries the zero end of the tape ahead.
2. Recorder- keeps a record of all measurements, sketches, and observations
taken during the process of measurement. He also checks by pacing all
measurements made by the tapemen for possible errors, mistakes, and
blunders.
3. Flagman- the person whose duty is to hold the range pole (or flagpole) at
selected points. He also helps the tapemen in making measurements and
assists in clearing out obstructions along the line to be measured.
4. Rear tapeman- the person whose duty is to assist the head tapeman during a
taping operation. He is the one who holds the 30-m end or any intermediate
meter mark of the tape during a measurement.
Breaking tapes.
It is standard practice to hold the tape horizontally above ground and to plumb at
one or both ends when taping on sloping or uneven terrain surfaces.
Slope taping.
Taped measurements may be made directly along the slopes when the ground is
of uniform inclination and fairly smooth, rather than break tape every few meters.
The measured slope distance is then reduced to its corresponding horizontal
distance by simple computations. To perform the computations, either the
difference in elevation between the two ends of the tape (or terminal points of the
line) or the angle of inclination of the slope measurement must first be determined.
In slope taping, a check is made by measuring once up the slope and once down
the slope. The average of the two measurements is reduced to the equivalent
horizontal distance and is taken as the final value of the measured distance.
d=sCos ∝
d= √ s2 −h2
Corrections in taping.
Taping operations could either be of the following: taping to determine an unknown
length, or taping for the purpose of laying out a required or specified length.
Regardless of which of these two categories is involved there are some
corrections which are applied to the original measurements to determine the
correct and more accurate length. Corrections to taping are applied by the use of
the following rules:
1st Rule: When a line is measured with a tape that is “too long”, the corrections
are applied to the observed length by adding.
2nd Rule: When a specified or required length is to be laid out with a tape that is
“too long” the corrections are subtracted from the known length to determine the
corrected length to be laid out.
3rd Rule: When measuring or laying out lengths with a tape that is “too short”, the
corrections are applied opposite to those stated in the first two rules.
The following conditions which could exist during a taping operation may require
the application of corrections.
1. The tape used is not of standard or nominal length due to either faults in their
manufacture, or damage caused by kinks, bends, cuts, and splices on the tape.
2. Ends of the tape are not held at the same level when “breaking tape” along
inclined or rough terrain surfaces, or when undertaking slope taping.
3. Inaccuracy in keeping the tape along a straight line during the measurement or
in laying out of lengths.
4. Tape is not of nominal length due to the difference in temperature prevailing
during the actual measurement and the temperature for which the tape is
standardized.
5. Shortening or lengthening of the tape due to the application of a pull on its
ends which differs significantly from the pull applied on the tape during
standardization.
6. Distance between the end points of an unsupported length of tape is less than
the specified nominal length due to the effect of sag or a strong blowing side
wind.
Illustrative examples.
1. A measurement is made along a line that is inclined by a vertical angle of
15º25’ as measured using a hand level and clinometer. The slope
measurement is 756.52 m. What is the corresponding horizontal distance?
(729.30 m)
2. A horizontal distance of 325.75 m is to be established along a line that slopes
at a vertical angle of 13º06’. What slope distance should be laid out? (334.45
m)
3. A line XYZ is measured on the slope in two segments. The first segment XY
measures 824.45 m and the second segment YZ measures 1244.38 m. If the
difference in elevation between points X and Y is 4.25 m and that between Y
and Z is 6.47 m, determine the horizontal length of the measured line. (2068.80
m)
4. The length of a line AB measured with a 50 m tape is 465.285 m. When the
tape is compared with a standardized invar tape it is found to be 0.016 m too
long in almost the same conditions of support, tension, and temperature that
existed during measurement of the line. Determine the correct length of AB.
(465.434 m)
5. A rectangular lot was measured using a 50 m steel tape which was found to be
0.025 m too short. If the recorded length and width of the lot are 180.455 m
and 127.062 m, respectively, determine the following:
a. Actual dimensions of the lot. (180.365 m, 126.998 m)
b. Error in area introduced due to the erroneous length of tape. (22.979 m2)
6. A building 38 m x 45 m is to be laid out with a 50 m long metallic tape. If during
standardization the tape is found to be only 49.950 m, determine the following:
a. Dimensions to be laid out, using this tape, in order that the building shall
have the desired dimensions. (38.038 m, 45.045 m)
b. Using the same tape what should the diagonals read? (58.957 m)
Correction due to slope.
When distances are measured along the slope, the equivalent horizontal distance
may correspondingly be determined by applying an approximate slope correction.
2
h
C h=
(s+ d)
For gentle slopes, it is safe to assume that the slope distance (s) is approximately
equal to the horizontal distance (d) or
2
h
C h=
2s
The slope correction should be subtracted from the measured slope distance to
obtain the equivalent horizontal distance.
A slope is classified as gentle when it is not greater than 20%. This means a rise
or fall of 20 units in a horizontal distance of 100 units. A plus or minus sign must
be given to indicate if the slope is rising or falling, respectively.
slope= ( hd )100 %
For steep slopes ranging from between 20% and 30%, the slope correction is,
2 4
h h
C h= + 3
2s 8s
For very steep slopes such as those greater than 30%, the slope correction is,
C h=s(1−cosθ)
and L' =L ±C p
where: Cp = total elongation in tape length due to pull or the correction due to
incorrect pull applied on the tape (m)
Pm = pull applied to the tape during measurement (kg)
Ps = standard pull for the tape or pull for which the tape is calibrated (kg)
L = measured length of line (m)
A = cross – sectional area of the tape (cm2)
E = modulus of elasticity of the tape material (kg/cm2)
L’ = corrected length of the measured line (m)
By measuring the thickness and width of a steel tape by means of a caliper, its
cross-sectional area can be determined. The cross-sectional area may also be
calculated by dividing the total weight (W) of the tape by the product of its length
(L) and the unit weight of steel which is approximately 7.866 x 10 -3 kg/cm3. This is
given by the equation,
W
A=
L(Unit weight)
The cross-sectional area of most light and heavy steel tapes which are 30 m long
vary from about 0.02 to 0.06 cm 2. The modulus of elasticity of a steel tape usually
varies from 2.00 x 106 to 2.10 x 106 kg/cm2.
The errors due to pull variations can be eliminated by using a spring balance to
measure and maintain the standard pull, or by exerting a specific amount of pull
consistently and applying corrections for the deviation from the standard pull.
Illustrative examples.
1. Slope distances AB and BC measures 330.49 m and 660.97 m, respectively.
The difference in elevation is 12.22 m for points A and B and 10.85 m for points
B and C. Using the approximate slope correction formula for gentle slopes
determine the horizontal length of line ABC. Assume that the line AB has a
rising slope and BC a falling slope. (991.15 m)
2. A line AB cannot be measured directly because of an obstruction on line.
Accordingly, the two lines AC and CB were measured as 2,400.850 m and
1,320.420 m, respectively. Point C was set at a perpendicular distance of 155
m from point D on line AB. Using the approximate slope correction formula for
steep slopes, determine the length of AB. (3707.134 m)
3. A steel tape with a coefficient of linear expansion of 0.0000116/ºC is known to
be 50 m long at 20ºC. The tape was used to measure a line which was found to
be 532.28 meters long when the temperature was 35ºC. Determine the
following:
a. Temperature correction per tape length. (0.0087 m)
b. Temperature correction for the measured line. (0.0926 m)
c. Correct length of the line. (532.37 m)
4. A steel tape, known to be of standard length at 20ºC, is used in laying out a
runway 2500.00 m long. If its coefficient of linear expansion is 0.0000116/ºC,
determine the temperature correction and the correct length to be laid out when
the temperature is 42ºC. (0.64 m) (2499.36 m)
5. A heavy 50-m tape having a cross-sectional area of 0.05 cm 2 has been
standardized at a tension of 5.5 kg. if E = 2.10 x 10 6 kg/cm2, determine the
elongation of the tape if a pull of 12 kg is applied. (0.0031 m)
6. A 30-m steel tape weighing 1.45 kg is of standard length under a pull of 5 kg,
supported for full length. The tape was used in measuring a line 938.55 m long
on smooth level ground under a steady pull of 10 kg. assuming E = 2.0 x 10 6
kg/cm2 and the unit weight of steel to be 7.9 x 10 -3 kg/cm3, determine the
following:
a. Cross-sectional area of the tape. (0.06118 cm2)
b. Correction for increase in tension. (0.04 m)
c. Correct length of the line measured. (938.59 m)
Normal tension.
The applied pull which will lengthen the tape to equal the shortening caused
by sag is referred to as the normal tension. Its magnitude can be computed for
a particular tape or it can be measured out in the field as follows:
a. Stretch the tape on a concrete pavement (or level ground) by applying its
prescribed standard pull, and mark its ends on the pavement.
b. Hold the tape above the ground by supporting it only at its ends, then, pull the
tape until the ends coincide with the marked points on the pavement.
The normal tension is the amount of pull required to make the end points coincide
with the marked points on the pavement. A spring balance should be used in
measuring this value.
Theoretically, the elongation due to increased tension can be made equal to the
shortening due to sag by equating the correction due to tension to the correction
due to sag. The formula for normal tension is derive as follows;
C p=C s
( Pm−P s ) L W 2 L
= 2
AE 24 P
2
2 W AE
P=
24 ( Pm−P s)
√ 0.204 W √ AE
2
W AE
P= =
24( P m−P s) √ P m−Ps
Let PN = P = Pm
0.204 W √ AE
P N=
√ P N −Ps
Where:
PN = normal tension or the pull which will eliminate the effect of sag (kg)
W = total weight of tape between supports (kg)
A = cross-sectional area of tape (cm2)
E = modulus of elasticity of tape material (kg/cm2)
PS = standard pull for the tape (kg)
Illustrative examples:
1. A 30-m tape is supported only at its ends and under a steady pull of 8 kg. if the
tape weighs 0.91 kg, determine the sag correction and the correct distance
between the ends of the tape. (0.016 m, 29.984 m)
2. A 50-m steel tape weighs 0.04 kg/m and is supported at its end points and at
the 8-m and 25-m marks. If a pull of 6 kg is applied, determine the following:
a. Correction due to sag between the 0-m and 8-m marks, 8-m and 25-m
marks, and the 25-m and 50-m marks. (0.00095 m, 0.00910 m, 0.02894
m)
b. Correction due to sag for one tape length. (0.03899 m)
c. Correct distance between the ends of the tape. (49.96101 m)
3. A 50-m steel tape weighs 0.035 kg/m is constantly supported at mid-length and
at its end points, and is used to measure a line AB with a steady pull of 6.5 kg.
if the measured length of AB is 1268.256 m, determine the following:
a. Correction due to sag between supports and for the whole tape length.
(0.019 m, 0.038 m)
b. Total sag correction for the whole length measured. (0.957 m)
c. Correct length of line AB. (1267.299 m)
4. A steel tape weighing 0.85 kg has a cross-sectional area of 0.05 cm 2. The tape
measures exactly 30.00 m when supported throughout its length under a
standard pull of 5.5 kg. If the modulus of elasticity is 2.10 x 10 6 kg/cm2,
determine the tension required to make the tape equal to its nominal length
when supported only at the end points. (16.75115 kg)
5. A steel tape having a cross-sectional area of 0.06 cm 2 and a modulus of
elasticity of 2.0 x 106 kg/cm2, weighs 0.03 kg/m. Its length is 30.00 m when
standardized at a pull of 5 kg and supported throughout its length. Determine
the tension at which the effect of sag will be eliminated by the elongation of the
tape due to increased tension. (17.786 kg)
Combined corrections.
The corrections for the effects of incorrect length of tape, temperature, tension,
slope, and sag may be combined as a single net correction per tape length. Each
correction is computed separately and it is important to identify which correction
tends to make the tape too long or too short.
If unequal lengths are laid out, as AB and AC in the figure below, then upon
measuring the distance BC, the angle BAC can be computed using any of the
following trigonometric equations. S= (
AB+ AC + BC
2 )
3. Laying off angles with tape. A method which employs a simple principle of
trigonometry is illustrated in figure 11-5. Along line AB a convenient length, AP,
is first laid out. Then PP’ is erected perpendicular to the line at P by using a
length which is determined by multiplying the length of AP (or L) by the natural
tangent of the angle to be laid off or PP’ = L(tan θ ).
Another method requires the determination of a chord length which will define
the desired angle. In figure 11-6, it is required to lay off an angle mPn (or θ )
from line PA. The chord length is first determined from the equation
d=2 Lsin ()θ
2
, where θ is the desired angle and L is any convenient length laid
along line PA. Then, point m is established by laying out from P, and along line
PA, a convenient length of tape. The tape is then swung through an arc and
accordingly the arc traced is marked on the ground. With m now as center, the
computed chord length is also laid out and swung through an arc, and its
intersection with the first arc establishes point n. Line mn is the required chord
length, and the angle mPn is the desired angle.