Diving Operations Risk Assessment Guide
Diving Operations Risk Assessment Guide
: ISM/FRM/SAFE-004
Rev. No.: 02
Date: 10.05.2015
Page: 01
RISK ASSESSMENT
LOW
HARM TO PEOPLE First Aid case, No health Medical Treatment Case, Slight Restricted Work Case, Short Lost Time Injury, Medium Multiple Serious Injuries. Death, Long
Effect Health Effect Term Health Effect Term Health Effect Term Health Effect.
ENVIRONMENTAL IMPACT (To water, land or Negligible Impact, Small Spill Minor Impact, Spill > 1 ltr Moderate Environmental Serious Environmetal Major Environmental Impact
Air) < 1 ltr Impact Impact (Localised) (Widespread)
ASSET DAMAGE (Vessel, Property, Plant / Negligible Asset Damage Minor Asset Damage Moderate Assets Damage Serious Assets Damage Major Asset Damage Work / activity may continue provided risk control measures identified in the risk assessment are
Equipment) implemented.
BUSINESS No Media Interest, Negligible Localised Media Interest, Minor National Media Interest, National Media International Media Coverage, Major
MEDIUM
DISRUPTION/REPUTATION(Company & Disruption Disruption Moderate Disruption Coverage, Serious Disruption
Client) Disruption
COST OF LOSS IMPACT < 50.000 USD >50.000 USD > 250.000 USD > 500.000 USD > 1.000.000 USD
C factors are present LOW LOW MEDIUM MEDIUM HIGH ALARP must be demonstrated for all other consequences and authorisation to proceed must be
HIGH
UNLIKELY Rare combination of factors given by Senior Management
B required for an undesired event to occur LOW LOW LOW MEDIUM MEDIUM
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
Mobilisation
DSV must be compliant for diving
Injury/damage property/environmental operations as per IMCA and
Non compliance of DSV for diving operations 4 D H Project Manager 2 C L
impact/legal impact client requirements
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
Personnel injury, Safety /Security meeting prior
Master/onboard
Material Deliveries . Unfamiliar Visitors Theft 3 C M to mobilisation 3 B L
safety officer
Supervise activity
Use certified and tested
equipment and qualified
Environmental Pollution personnel
Safety meeting prior to task Master/onboard
Bunkering Vessel. Spillage (inc. overflows during bunkering) Fire 4 D H 4 B M
Supervise activity safety officer
Vessel bunkering plan to be
followed
Pre mob meeting/lifting
plan/competent
personnel/PTW/TBT/appropriate
PPE/RA posted onsite/adequate
communication/insurance/safety Master/onboard
Unplanned lifting operations Injury/damage property/environmental impact 4 D H Induction/training/certifiedlifting 2 C L
safety officer
equipments by external client
approved agency
Competent
personnel/PPE/PTW/TBT/RA
posted onsite/adequate Master/onboard
Incorrect sea fastening of diving & project equipments Injury/damage property/environmental impact 5 D H 5 B M
communication/MPI of safety officer
welds/insurance/safety
induction
Industrial rated portable ladders
must be available [Link] Master/onboard
Incorrect usage of portable ladders Injury/damage property 4 D H 4 B M
methods must be followed. safety officer
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
PTW/TBT/RA posted
onsite/welding operations shall Master/onboard
Welding operations Injury/property damage/delays 4 D H 4 B M
be carried out as per client safety officer
requirements.
Adequate knives shall be used as
Master/onboard
Inadequate knives Injury 3 D M per client requirements. 3 B L
safety officer
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
Communication systems/regular Master/chief
Inadequate management of alone working Injury/death contacts with nominated person engineer/onboard
5 D H 5 B M
shall be established. safety officer
Adequate PPE as per client Master/project
Inadequate PPE Injury/death 5 D H requirement available onsite manager/onboard 5 B M
safety officer
Safety signage and
posters/barricading available Master/onboard
Absense of safety signage and posters/barricading Injury/property damage/delays 3 C M [Link] life saver rules must 3 B L
safety officer
be followed.
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
Vessel crew must maintain high
standards of cleanliness and Master/onboard
Unhygienic Workplace Illness/unfit to work/delays 3 C M personal heigene. regular HSE 3 B L
safety officer/Medic
inspections must be carried out.
competent
personnel/PPE/PTW/TBT/RA
posted onsite/adequate project
incompetent diving personnel/inadequate dive plan & communication/client approved
injury/damage property 4 D H Manager/Diving 4 B M
procedures dive plans and Superintendent
procedures/insurance of
vessel,cargo and crew/safety
induction
Lifting / Lowering
Initial Risk Residual Risk
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
Use certified and tested
Injury to personnel equipment and qualified
Damage to Assets personnel maintenance
Failure of Brake 4 D H supervisor 4 C M
Collision with Structure Follow Diving procedures
Task Briefings Vessel
Management System
Drop load on deck Use certified and tested
Injury to personnel equipment and qualified
Hydraulic Hose Burst Pollution 4 D H personnel maintenance supervisor 4 C M
Delay in Operation schedule PMS
Drop load on deck Use certified and tested
Injury to personnel equipment and qualified
Collision with bell personnel
Failure of Boom 4 D H supervisor 4 C M
Injury to Divers Maintenance system
Delay in operation Equipment checks
Use certified and qualified
Injury to personnel personnel
Damage to Assets Weather report / checks
Operator Error 4 D H supervisor 4 C M
Collision with Structure Operating Checks
Supervision
Regular rest periods
Drop load on deck Use certified and tested
Injury to personnel equipment and qualified
Collision with bell personnel
Lifting Equipment Failure 4 D H supervisor 4 C M
Injury to Divers IMCA Guidelines
Delay in operation PMS System in place
Risk Assessment done
Medical Lock Runs
correct operating instructions
shall be followed by competent
[Link]
communication shall be made
between divers inside the
Injury to personnel. Fatality.
chamber and chamber
Unaware regarding procedures Injury to personnel 5 D H Diving supervisor 5 B M
[Link] must be
taken from diving supervisor to
operate medical [Link]
instructions must be posted
onsite. relevant PPE must be
used.
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
diving equipment operating
instructions/procedures/checklis project
unawareness of diving equipments operating ts available onsite/dive system
injury/property damage/death/legal impact 5 D H Manager/Diving 5 B M
instructions/procedures/checklists familiarisation superintendent
competent
personnel/PPE/PTW/TBT/RA
posted onsite/adequate project
incompetent diving personnel/inadequate dive plan &
injury/damage property 4 D H communication/client approved Manager/Diving 4 B M
procedures
dive plans and Superintendent
procedures/insurance/safety
induction
air diving system must be
compliant with IMCA and client
[Link]
project
noncompliance of air diving system as per IMCA and client documents and certifications
delay in job 3 C M manager/Diving 3 B L
requirements must be available onsite as well Superintendent
as in base office.
Diver Tending
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
Secure safety chain across “A”
f
Set up Dive Station
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
Make sure diver has a good grip
diver injury/deck crew injury/property on theBasket.
Slip,Trip, fall 4 D H Diver and tender to ensure that Diving supervisor 4 B M
damage/delays
there is enough slack prior to
entry.
Environmental forces
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
Check test tubes and
instructions are compatible to
use for the job. Ensure all whips
or hoses are in good order.
Mismatched tubes. H.P. whip or fittings may rupture causing eye or Check all hose and fittings.
Instructions and specification leaflet does not match [Link] body [Link] readings causing impure air Wear PPE.
3 C M Diving supervisor 3 B L
analysys equipments supplied to diver. Ensure H.P fittings used where
required.
Wear eye protection.
Carefully replace all parts back
into test box.
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
Navigation
VESSEL OPERATION
Manoeuvring in fields
Use certified and tested
Loss of Reference Collision with a structure equipment and qualified
System Injury to personnel personnel
4 D H Master 4 C M
Drive off Delay in operation IMCA Annual Audit
Vessel Checks completed
Risk Assessment done
Mooring by Line
Damage to Platform Use certified and tested
Drift into Structure equipment and qualified
Line Parting 4 D H Master 4 C M
Injury to Personnel personnel maintenance system
equipment checks
Mooring by Anchor
Use certified and tested
Loss of Position equipment and qualified
Collision with Pipeline personnel Operating Checks
Anchor Slippage 4 D H Maintenance system Master 4 C M
Collision with a Structure
Consult anchor pattern charts,
Anchor Watch
Fabrication on Deck
Interface Co-ordination
Injury to deck personnel Procedure
Damage to Assets Use certified and tested
Failure of Containment 3 C M equipment and qualified Master 3 B L
Delay in operation
personnel
PMS System in place
Risk Assessment done
Confined Space Entry
Initial Risk Residual Risk
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
PTW/RA posted [Link]
carried [Link]
[Link] of atmosphere
to ensure it is breathable and
[Link] physical isolations are in
[Link] and warning Master/onboard
Lack of Oxygen/toxic gases/flood suffocation/poisoning/drown/Death 5 D H 5 B M
signage [Link] safety officer
[Link] life saver
guidelines shall be followed.
PTW System
safety
familiarisation/induction/trainin
g for PTW Master/onboard
unfamiliar with PTW system injury/property damage/delays 4 D H 4 B M
[Link]/contractor agreed safety officer
PTW system shall be followed
Working at Heights
proper PPE used/PTW/TBT
carried out/RA posted Master/onboard
falls/dropped objects injury/death/property damage 5 D H [Link] life saver guidelines 3 C M
safety officer
shall be followed.
Weather conditions
ensure pre weather warnings in
[Link] considerations of
weather conditions before start
of any [Link] Master/onboard
adverse weather conditions injury/property damage/delays 4 D H 4 B M
[Link]/[Link] standards safety officer
shall be followed.
Electrical works
LOTO system shall be
[Link]/induction shall Master/onboard
LOTO not followed/electrical shock/PTW system not follwed. injury/burns/death/property damage 5 D H be carried [Link]/PTW/TBT safety officer/chief 5 B M
shall be [Link] posted engineer
onsite
Hot works
Client/contractor agreed PTW
system shall be
PTW System not follwed/fire hazard/TBT not carried out/PPE not [Link]/TBT/RA in [Link] Master/onboard
injury/burns/death/property damage 5 D H 5 B M
used/FF system not present/fire watchman not present onsite. watchman must be prasent safety officer
onsite with FF extinguishers.
Cold works
client/contractor agreed PTW
shall be [Link] shall be Master/onboard
PTW not followed/PPE not used/TBT not carried out injury/prperty damage/delays 3 C M 3 B L
carried [Link] to be used. safety officer
Initial Risk Residual Risk
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
Video and As Built Survey.
Brief diver what he has to do.
Wear protective clothing
applicable to the job.
Good communications.
Be aware of current changes.
Cut divers umbilical resulting in loss of gas
Snagging of divers umbilical. Emergency procedures in place.
supply.
Potential for electrical shocks from underwater light. Stand by diver fully dressed.
Electrocution. 3 D M Diving supervisor 3 B L
Cuts, abrasions and stings from Barnacles or Marine life. Post this TRA in a conspicuous
Injury to diver.
place for all relevant personnel
to refer to.
SIMOPS
no vessel shall be allowed to
come alongside during diving
ops without client & contractor
Diving Superintendent Master/Diving
vessel coming alongside during diving ops. injury to diver/property damage/delays 4 D H [Link] 4 C M
Superintendent
communication should be
maintained with other vessels.
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
Adverse Weather
Report,
Bridge Manning and
Engine Manning as per
HSSE Document while
boat is within 500 meter
zone
All life saving devices
in position and certified
Life jackets always
worn while outside
No personnel is
allowed outside in night. No
Bad personnel will be
Operation Hazard/Property damage/personnel
Weather, 4 D H allowed outside the Master 4 C M
injury
High Wind accommodation area
unless authorized by
the Master of the
vessel advises so.
Personnel head count
every morning and
evening
Satellite phone /
GMDSS operating on
the vessel
Weather forecast to be
provided to the captain
of the vessel
Email address of the
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
to obtain
Anchor may get permission from OIM
in case of Anchoring operations , Anchor may hit pipe fouled; prior to anchoring of
4 D H Master 4 C M
lines at sea bed pipeline may get vessel
damaged Layout of platform
along with pipelines to
be provided to Master
of the vessel
Fuel and ChemicalLoading at Port
Trained Crew for
loading of Chemicals
MSDS of all
Chemicals
Light arrangement for
24 hrs operation
Proper PPE is to be
used
Pumps and valves
are never left
unattended
Spillage of
Radio communication
Chemical or fuel,
Environment is to be maintained. No
toxic and corrosive 3 C M Master 3 B L
al Impact unauthorized
hazardous
person will be allowed
chemical
near the loading point.
All clearance
required for loading of
corrosive fluid will be
taken
While vessel at port
for loading chemicals
and acid; main activity
during day would be
loading hazardous
chemicals & during
i h h i l l di
Vessel DP operations
While vessel
operating within the
500m zone at least one
competent & certified
engineer will remain in
engine room to control
and respond to any
generator and/or
propulsion engine
failures.
All checks shall be
done once before
entering the 500 meter
zone of the platform and
Initial Risk Residual Risk
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
Level of reliability
will be checked
Possible collision through Vessel
DP failure 4 D H maintenance register Master/DPO/CE 4 C M
with Platform
and classification
documentation will be
checked.
Environmental
limitations will be
informed with
reference to available
thruster’s power,
available electrical
power, in addition to
current position,
reaction time for
disconnect and Drive
off will also be
considered.
Alarms and actions
will be specified before
Crane Operations
Mechanical
maintenance team will
be there on platform
Possible spares that
may be required will be
available on platform. Crane
scheduled
1- May create maintenance will be
hazard for platform completed before if its
Crane Master/Diving
and Vessel safety. expiry date falls near
malfunction While picking up any 4 D H Superintendent/Cran 4 B M
2- With crane boom the job end date
load e operator
up helicopter can't Proper planning for
approach platform load release will be in
place for emergency
disconnect.
Crane operator is
on standby at all times
Competent crane
operator will be
employed for the
Initial Risk Residual Risk
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
Cane lifting
equipment and operator
certified
Lifting capacity of
crane known
Pre-job safety
meeting and signal
discussed
Signal man identified
Tag line used. ERP reviewed and
emergency contact
number including that
of hospital is updated
Proper PPE is Master/Diving
Crane 1- Safety hazard
4 C M mandatory for all men Superintendent/Cran 4 A L
Operations safe work practices not followed 2- Loss of property
present on board and e operator
on platform
Radio
communication is
available and tested
before the
commencement of
operation
Signal man will not
be working on tag line
MSDS available on
platform and boat
First aid available at
platform and on
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
All equipment will be
function tested
Experienced and
trained manpower
Equipment operating
limits clearly defined
Critical parameters
are displayed and
monitored by
1- Potential
supervisors and
loss of
mechanic
productivity
500 mtr checklist will be strictly
Equipment failure 2- Vessel may 4 D H Master/CE/DPO 4 B M
followed to
hit Platform
identify if any equipment
while
is not working before
drifting
coming inside the 500
mtr zone. Ensure critical
spares are available
and listed.
Pumps and engines
are serviced prior to
arrival on job
Electrical and
electronics
i t
personnel transfer
1- Crane operator
certified
2- Wind limit specified
3- Signal man in place
4- Radio communication
maintained with boat. 1_ Pre job
Chance or slip / trip / May result injury to safety Master/Crane
4 D H 4 B M
fall personnel meeting to address Operator
transfer
2- Proper PPE
3- Wind speed limit to
decide if personal
transfer can be
enabled or not in such
Transfer ofDiesel andWater in field
Initial Risk Residual Risk
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
Certified hoses
Sufficient Length to
allow safe transfer of
water and diesel. Proper
Environmental
1- Hose rupture communication and
Pollution 4 C M Master/CE 4 B M
2- Contamination understanding for the
Delay in Job
transfer
vessel will be on
DP or anchor and
other boat will come
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
No hot work
permitted in the area
where the inflammable
fluid is stored
Hot work to be done
under permit to work
system
No hot work is
allowed without OIM permition
when vessel is
within 500 meter of the
platform
Correct type of fire
extinguisher is located
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
a) Only certified rigging to be
used.
b) Inspect rigging/load before
a) Rigging failure. a) Diver/deck crew injury. use.
c) Perform test lift before going diving supervisor/
b) Unstable load. b) Equipment damage. 4 D H 3 C M
overboard. d) Deck supervisor
c) Fouled rigging. c) Project delay.
Emergency procedures in
place.
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
a) Use correct slings and rigging
with SWL.
b) Use tag lines.
c) Be aware of pinch points. diving
d) Do not stand under the load. supervisor/Diver/
a) Load falling from rigging. a) Injury to deck personnel.
4 D H e) Emergency procedures in Deck 3 C M
b) Load swinging about. b) Injury to the diver.
place. supervisor/crane
f) Review TRA for changes. operator
g) Stand by diver fully
dressed.
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
a) Be a safe distance away whilst
Pressurising jacks.
b) Properly connect all link hoses
and test.
a) Possible impact to diver faceplate c) Secure hot line tail with diving
a) Danger of stud bolt shearing due to manufactures defect.
causing trauma. 4 D H lanyard. supervisor/diver/ 3 C M
b) Burst link hoses.
b) Injury to diver. d) Do not go above makers Deck supervisor
recommended pressure rating.
e) Approved procedures in
place.
diving
a) Damage to equipment.
a) Broken fittings. 4 D H supervisor/diver/ 3 C M
b) Loss time in production.
Deck supervisor
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
a) Make sure impact is clear
diving
from umbilical before recovery.
a) Entanglement with umbilical. a) Diver being pulled off the job. 4 D H supervisor/diver/ 3 C M
b) Good communications.
Deck supervisor
Hydratight Equipment
Step-1 Check Whips, Jacks, Hot Line, Pump, Quick Connects and Reaction Nuts.
a) Check all Quick Connects.
b) Check Oil level in pump.
c) Check Hot Line and reel.
d) Check all jacks for damage.
e) Check reaction nuts threads.
f) Enough personnel to lift diving supervisor/
a) Lifting equipment. a) Back injury or strain. 4 D H equipment. Deck supervisor/Dive 3 C M
g) Emergency procedures in Techs
place.
h) Review TRA for changes.
i) Training of personnel.
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
a) Firmly tend diver’s umbilical.
b) Check umbilical when diving
a) Umbilical entanglement. a) Unable to recover diver. 4 D H connecting hoses. supervisor/Diver/ 3 C M
Deck supervisor
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
a) Divers to be aware of nipping
possibility. diving
a) Finger nipping. b) Tensioning tools to be
a) Minor injury. supervisor/Diver/
b) Hydraulic hose leak. 3 D M checked before 2 B L
b) Tool malfunction. Deck supervisor/Dive
c) Seal failure. deployment to the diver. Techs
a) Emergency procedures in
place.
Step-3 Tensioning tool air powered hydraulic pump operated ondeck.
a) All equipment to be checked
before use.
b) Equipment to be certified in
a) Hydraulic leak on deck. date before use diving supervisor/
b) Air supply hose failure/ a) Possible injury. 4 D H (where necessary). Deck supervisor/Dive 3 B L
connection failure. c) Whip checks to be used on air Techs
supply hoses.
d) Emergency procedures in
place.
H₂S Emergency Alert
On detection of H²S
a) Have all air bottles charged
and checked off.
b) Have all monitors turned on Master/Diving
a) Breathing gear not checked.
a) Loss of Consciousness. at all times. Superintendent/divin
b) Air bottles not charged. 5 D H 3 C M
b) Fatality. c) All personnel muster at g supervisor/deck
c) Monitors turned off.
station for head count. supervisor
d) Cast off from location.
e) Place vessel up wind
Diving Operations
Initial Risk Residual Risk
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
a) Abort diving operations and
inform diver of situation.
Instruct to return to stage.
b) Supervisor switch diver to HP
air bank supply.
c) Deck crew and Supervisor don
breathing apparatus.
d) Stand by diver don helmet Master/Diving
and maintains Superintendent/
a) Loss of consciousness. positive pressure via free flow.
a) Diver inhaling H²S 5 D H diving 3 C M
b) Fatality. e) Diver on reaching surface supervisor/diver/
keeps helmet on and maintains deck supervisor
positive pressure via
free flow.
f) Flush chamber outer lock with
reduced HP air bank supply prior
to diver entering.
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
a) Only certified rigging to be
used.
b) Inspect rigging/load before diving
a) Rigging failure. a) Diver injury.
use. supervisor/deck
b) Unstable load. b) Equipment damage. 4 D H 3 C M
c) Perform test lift before over supervisor/crane
c) Fouled rigging. c) Project delay.
boarding. operator
a) Emergency procedures in
place.
Overboard and lower to the bottom.
a. Good communications during
operation.
b) Tag lines used to control the
load.
c) Clear directions passed to
crane operator.
d) Divers not located below the
diving
a) Deck crew injury. load.
a) Uncontrolled load when over boarding. supervisor/diver/dec
b) Diver injury. 4 D H e) Light sticks on load. 3 C M
b) Unseen load by the divers. k supervisor/crane
c) Equipment damage. f) Beacon on crane wire.
operator
g) Slow and easy crane
movements.
h) Emergency procedures in
place
i) Review procedures and TRA
for changes.
j) Initiate ERP in case of
Position the load on the bottom.
a) Divers sight the load.
b) Load position under diver diving
a) Poor visibility leading to diver entanglement / a) Diver injury. direction. supervisor/deck
4 D H d) Controlled crane movements. 3 C M
impact by load. b) Equipment damage. supervisor/crane
a) Emergency procedures in operator
place.
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
Connection of H.P hose to bottle bank.
a) Check correct fittings on H.P
whip and bottle bank.
b) Check H.P whip is in good diving
a) Connection not correctly fitted. a) Injury to personnel. 4 D H condition and fit for working supervisor/deck 3 C M
pressure. supervisor/dive techs
c) Secure H.P at the bottle bank.
Check equipment.
a) Full standby checks with
Supervisor. diving
a) Equipment not working. b) Check bail out bottle charge supervisor/deck
b) Empty bail out bottle. prior to checks.
a) Breakdown of equipment. 3 D M supervisor/standby 2 B L
c) No communications. c) Check all equipment on hand diver/deck support
d) Failure to rescue diver. such as fins/harness/knife/ team
flashlight.
Initial Risk Residual Risk
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
Understand stand by checks with Supervisor.
a) Fully understand what is diving
required and be ready at all supervisor/deck
a) Non rescue of diver in trouble.
a) Potential hazard to self and diver. 5 D H times during operation. supervisor/standby 3 C M
b) Fatality.
diver/deck support
team
Maintain readiness and be aware of diver’s location and job task.
a) Be in a state of readiness at all diving
times. supervisor/deck
a) Fatality. b) No more than 30 seconds to
a) Not being ready or dressed 5 D H supervisor/standby 3 C M
b) Loss of time entering water. enter the water. diver/deck support
team
Maintain contact with Diving Supervisor.
a) Listen to what Supervisor diving
a) Not understanding what to do. a) Fatality. 5 D H says. supervisor/stand by 3 C M
diver
On orders from Supervisor to rescue diver.
a) Be in a state of readiness at all
diving
a) Non rescue of diver in trouble. times.
a) Not being ready or dressed 5 D H supervisor/stand by 3 C M
b) Fatality. b) No more than 30 seconds to
diver
enter the water.
Follow diver’s umbilical.
a) Good communications. diving
b) Good tending of umbilical. supervisor/stand by
a) Loss of time to reach diver.
a) Fouled umbilical. 5 D H c) Approach diver carefully. diver/Deck 3 C M
b) Fatality.
supervisor/Deck
support team
Check diver’s condition.
a) See if diver is OK and
responding.
b) Check divers umbilical is clear.
c) If diver OK, escort back to diving
a) Not knowing what to do. a) Fatality. 5 D H stage and complete stops if supervisor/stand by 3 C M
required. diver
d) Keep visual check with diver
at all times.
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
a) See if diver is conscious.
b) If not free flow divers hat.
c) Ask for diver’s pneumo to be
turned on, that
may be used to give the diver
air.
d) Check divers umbilical is clear.
e) Instruct surface to pull diver diving
and standby back to stage. supervisor/stand by
b) Decompression sickness.
a) Fatality. 5 D H f) Diver and standby to ride diver/Deck 3 C M
c) Omitted stops.
stage together. supervisor/Deck
g) Inform medic to be at dive support team/medic
area on reaching
surface.
h) DDC to be in readiness.
i) Emergency contingency
plan in place.
Diver Tending
Dressing in Diver.
a) Good house keeping around
diving area.
b) Keep area free of debris and
oil spills and use proper PPE.
diving
c) Emergency procedures in
supervisor/Deck
place.
a) Slip/trip hazard. a) Injury to personnel. 4 D H supervisor/Deck 3 C M
d) Stand by diver fully dressed.
support team/stand
c) Post this TRA in a
by diver
conspicuous place for all
relevant personnel to refer
to.
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
a) Keep umbilical coiled up on
rack when diver returning to
surface. diving
b) Assist diver out of stage. supervisor/Deck
a) Slip or trip hazard. a) Injury to diver/personnel. 4 D H c) Keep area clear of debris. supervisor/Deck 3 C M
d) Keep area well light up at support team/stand
night. by diver
e) Secure work area on
completion.
Decompression.
Initial Risk Residual Risk
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
a) On reaching surface diver and
DMT into DDC. diving
a) Shock. b) Complete full neurological supervisor/Deck
b) Loss of Blood. examination.
a) May not be able to complete in water decompression. 4 D H supervisor/Deck 3 C M
c) Unconsciousness. c) Report all injuries. support team/stand
d) Omitted decompression. d) Carry out decompression as by diver/DMT/medic
per company procedures.
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
a) Ensure maintenance checks
completed.
b) Check all oil levels before
starting. diving
a) No oil in compressor. c) Check air intakes in good supervisor/Deck
a) Damage to compressor. position.
b) Bad atmosphere from exhaust fumes or other 4 D H supervisor/Deck 3 C M
b) Contamination of breathing air. d) Check all machine guarding in
contaminants. support team/Dive
place. Techs
e) Emergency procedures in
place.
f) Review TRA for changes.
g) Give Training.
Check item being filled in good condition and in test date.
a) All cylinders in good
condition. diving
b) All cylinders in test date. supervisor/Deck
a) Explosion. a) Injury to personnel. c) Display notices H.P Air.
4 D H supervisor/Deck 3 C M
b) Burst cylinders. b) Damage to equipment. d) Post this TRA in a conspicuous support team/Dive
place for all Techs
relevant personnel to refer to.
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
a) Visually inspect all pipework.
b) Repair or replace as
necessary.
c) gas analyst on all gas received
backed
up with purification certificate.
diving
a) Broken pipework. a) Rapidly escaping gas. d) Emergency procedures in
supervisor/Deck
b) Damaged framework. b) Injury to personnel. place.
4 D H supervisor/Deck 3 C M
c) Gas rack marked incorrectly. c) Fire. e) Review TRA for changes.
support team/Dive
d) Wrong gas being connected. d) Wrong gas being supplied to diver. f) Post this TRA in a
Techs
conspicuous place for all
relevant personnel to refer
to.
g) Control systems in
place.
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
Open cylinder valve slowly.
a) Stand to side of valve being diving
opened. supervisor/Deck
a) Explosion.
a) Burst hoses. 4 D H b) Wear safety glasses. supervisor/Deck 3 C M
b) Fire.
support team/Dive
Techs
Close cylinder valve until required for use.
a) Display sign valves or bottle diving
rack is off/on. supervisor/Deck
a) Not knowing valve is Open/Closed. a) No gas when required. 3 C M b) Check rack before diving. supervisor/Deck 2 B L
support team/Dive
Techs
Recover Diver
Job completed or diver running out of bottom time.
a) Keep to company or client
standards on
decompression limits.
b) Keep reminding diver to check
his umbilical.
c) Good communications.
d) Firmly tend divers’ umbilical.
e) Treat any delay in
decompression as per
diving manual.
a) Diver running over his f) Go to next deeper table and
bottom time as per report incident.
Company or IMCA g) Commit Stand by Diver if diving
a) Likelihood of D.C.S or cajoled into
recommendations. necessary. supervisor/Deck
extending decompression time
b) Fouled umbilical. 3 C M h) Check all supplies to dive supervisor/Deck 2 B L
by senior personnel.
c) Diver fouled. stage. support team/Dive
b) Unable to recover diver.
d) Loss of breathing gas. i) Check adequate gas supplies Techs
e) Loss of power or air before dive.
supplies to dive stage. j) Emergency plans in
place.
k) Control systems in
place.
l) review TRA for changes..
d) Stand by diver dressed in.
m) Post this TRA in a
conspicuous place for
all relevant personnel
to refer to.
Diver leaving bottom.
a) rate of ascent as per diving
manual.
a) Ascent rate too fast.
a) Likelihood of D.C.S. 3 C M b) Do not speed up to diving supervisor 2 B L
b) Ascent rate too slow.
compensate lost time,
add to decompression time.
On water stops.
Initial Risk Residual Risk
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
a) Consider using surface
decompression and
refer to diving manual for table.
b) Attempt to get hot water to
a) Unable to maintain a stable depth due to weather. the diver.
a) Likelihood of D.C. S. diving
b) Diver getting cold. 3 C M c) Wear wet suit or clothing 2 B L
b) Omitted decompression. supervisor/diver
c) Undressing whilst on stops. pertaining to the temperature.
d) Do NOT undress during water
stops.
Reaching surface.
a) Diver to keep a good watch
out for ladder
on surface.
b) Ensure the ladder is long
a) Hitting ladder. enough in the
b) Slipping off ladder. water for diver to stand on. diving
a) Injury to diver. 4 D H 3 C M
c) Falling out of stage. c) Keep hand inside the stage on supervisor/diver
d) Hands on outside of stage. recovery.
d) Have hand hold brackets
inside the stage.
e) Tend divers’ umbilical firmly.
Oxygen Equipment
Using hoses and fittings for Oxygen.
a) Thoroughly check all hoses
and fittings for oxygen use are
a) Fire on barge or vessel. Oxygen cleaned. diving
a) Fire. b) Property Damage. b) Do not use any oil. supervisor/Dive
b) Explosion. c) Damage to equipment. 4 D H c) Emergency procedures in 3 C M
Techs/Deck
c) Contamination. d) Injury to personnel. place. supervisor
e) Burns. d) Review TRA for
changes.
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
a) Keep Full and Empty cylinders
separated.
b) Keep Oxygen apart from
other gases.
c) Keep in well-ventilated area.
d) Never store below deck.
e) Warning signs to be displayed
a) Fire on barge or vessel.
NO diving
a) Fire. b) Property Damage.
SMOKING OR NAKED FLAME. supervisor/Dive
b) Explosion. c) Damage to equipment. 4 D H 3 C M
f) Protect all cylinders with Techs/Deck
c) Ignition. d) Injury to personnel.
protection caps. supervisor
e) Burns.
g) Keep all cylinders properly
secured.
h) Keep cylinders cool.
c) Post this TRA in a
conspicuous place for
all relevant personnel
to refer to.
Use Hazard Signs.
a) Display signs NO SMOKING OR
a) Fire on barge or vessel. NAKED FLAME.
a) Fire. diving
b) Property Damage. b) Display signs in prominent
b) Explosion. supervisor/Dive
c) Damage to equipment. 4 D H positions. 3 C M
c) Welding. Techs/Deck
d) Injury to personnel. c) Display signs in ENGLISH and
d) Smoking. supervisor
e) Burns. other LANGUAGES of personnel
onboard
Oxygen to be Regulated at Source.
a) Regulate all HP Oxygen to Low
a) Fire on barge or vessel. Pressure below 500 psi.
b) Keep all hoses properly diving
a) Fire. d) Property Damage.
secured away from welding supervisor/Dive
b) Explosion. e) Damage to equipment. 4 D H 3 C M
areas. Techs/Deck
c) Ignition. f) Injury to personnel.
supervisor
g) Burns.
Opening Cylinders.
a) Open all cylinders and oxygen
racks slowly.
a) Fire on barge or vessel. b) Do not use ball valves. diving
a) Fire. b) Property Damage. c) Use needle valves on oxygen. supervisor/Dive
b) Explosion. c) Damage to equipment. 4 D H d) Good housekeeping around 3 C M
Techs/Deck
c) Ignition. d) Injury to personnel. oxygen equipment. supervisor
e) Burns. e) No grease to be used on any
fittings.
Burning on Deck
Initial Risk Residual Risk
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
a) Supervisor to ensure task
briefing is clear.
b) Hot Work Permit to be raised.
c) Personnel qualified for the
task.
d) Full PPE to be worn during
burning ops.
e) Check all hoses for damage.
f) Check burning torch for leaks.
a) Burns. g) Check the gas regulators and diving
a) Heat. valves are in good condition,
b) Eye injury. supervisor/Dive
b) High pressure gas. 4 D H and are working. 3 C M
c) Fire. Techs/Deck
c) Flammable gas. h) Ensure check valves are fitted.
d) Explosion. supervisor
i) Ensure flash arrestors are
fitted to equipment
j) Appoint a fire watch in
adjacent areas.
k) Ensure a fire extinguisher is
close to hand.
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
a) Route hoses to avoid diving
walkways. supervisor/Dive
a) Trip hazard. a) Injury. 4 D H b) Display warning signs. 3 C M
Techs/Deck
c) Emergency plan in supervisor
place
Hoses in use.
a) Check hose condition and
specifications before using
b) Check hose fittings before
use.
c) Install whip checks at all
joins/connections.
d) Do not over-tighten hose
fittings.
e) Always wear eye protection
when working
with LP/HP air or gas.
f) Vent hoses away from self.
g) Be aware of others in the diving
vicinity when supervisor/Dive
a) LP/HP air, gas or particulate. a) Injury 4 D H 3 C M
installing/dis-assembling hoses. Techs/Deck
h) Install warning signs on HP supervisor
hoses in use.
a) Emergency plan in
place.
i) Review procedures
frequently.
j) Initiate ERP incase of
emergency.
k) Post this JSA in a
conspicuous place for all
relevant personnel to refer to.
ROV Operations
Pre-dive checks.
Initial Risk Residual Risk
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
a) Good communications
between ROV deck
and control personnel.
b) Thruster guards where
appropriate.
c) Operate ROV controls only
when authorised.
d) Good briefing before pre-dive
a) Unsafe practices - personal checks ROV Supervisor/ROV
a) Moderate to severe
injury in vehicle thruster or 4 D H commenced. Techs/onboard 3 C M
trauma.
by manipulator. e) Access restricted to ROV safety officer
personnel.
f) Review procedures
frequently.
g) Initiate a follow-up
Project JSA's.
h) Post this TRA in a
conspicuous place for
all relevant personnel
ROV deployment and recovery.
a) Follow operating procedures.
b) ROV personnel training where
required.
a) Potential to injury to c) Operating instructions
a) Equipment malfunction available.
personnel. ROV Supervisor/ROV
b) Human error. d) Review procedures
b) Damage to 4 D H Techs/onboard 3 C M
c) Unsafe practice. frequently.
equipment. safety officer
d) Man overboard. e) Post this TRA in a
c) Project delay.
conspicuous place for
all relevant personnel
to refer to.
ROV operations electrical fault.
a) Competent personnel.
b) Safe working practices.
a) Injury to ROV c) Certified equipment.
personnel. d) Statutory testing.
a) Electrical fault – shock. b) Fire. e) ROV system conforms to "Safe
Use of ROV Supervisor/ROV
b) Failure of Routine Control c) Damage to
4 D H Electricity Underwater "ACOP”. Techs/onboard 3 C M
Documents. equipment.
f) Emergency safety officer
c) Electrical fault – arcing. d) Injury to divers.
e) High capacitive procedures in place.
discharge possible. g) Routine Control
Document's backed
up.
ROV operations - mechanical/hydraulic fault.
Initial Risk Residual Risk
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
a) Maintain equipment
maintenance schedules.
b) Contingency procedures.
a) Stranded vehicle. c) Emergency procedures
b) Fouls crane. in place. ROV Supervisor/ROV
a) Vehicle dead in water. c) Fouls bell. 4 D H d) Review procedures Techs/onboard 3 C M
d) Fouls vessel. frequently. safety officer
e) Delays project. e) Post this TRA in a
conspicuous place for all
relevant personnel to refer to.
Poor visibility.
a) Field layout diagrams if
available.
b) Survey repeat in ROV control
van.
c) Good comms between deck,
dive control and
a) Diver injury. ROV control van. ROV Supervisor/ROV
a) ROV fouling structures,
b) Equipment 4 D H d) Emergency procedures Techs/onboard 3 C M
equipment divers.
damage. in place. safety officer
e) Review procedures
frequently.
f)Post this TRA in a
conspicuous place for all
relevant personnel to refer to.
Bell Launch/Recovery
Pre-dive checks. Pre-dive briefing.
a) Checklist used for pre-dive
checks.
b) Training given for personnel
unfamiliar with
a) Valves operated incorrectly. a) Loss of vital Dive
the dive system.
b) Valves left in incorrect services to the Supervisor/onboard
4 D H c) Dive Supervisor to monitor 3 C M
positions. bell/divers. safety officer/Deck
operations.
c) Diver confusion. b) Project delay. Supervisor
d) Emergency procedures
in place
e) Control systems in
place.
Bell launch.
Initial Risk Residual Risk
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
a) Dive Supervisor to control
operations.
b)Use standard IGOPL
a) Unclamping bell with procedures for bell ops.
pressure in TUP trunking. c) Train personnel where
a) Diver injury. Dive
b) Nipping/crushing injuries required.
b) Deck crew injury. Supervisor/onboard
during bell launch. 4 D H d) Ensure safety barriers are 3 C M
c) Equipment safety officer/Deck
c) Proximity to remotely erected around
damage. Supervisor
operated rotating dangerous machinery.
machinery. e) Emergency procedures
in place.
f) Control systems in
place
Bell recovery.
a) Dive Supervisor to control
operations.
b)Use standard IGOPL
a) Clamping bell. procedures for bell ops
b) Nipping/crushing injuries. a) Diver injury. c) Train personnel where Dive
during bell recovery. b) Deck crew injury. required. Supervisor/onboard
4 D H d) Ensure safety barriers are 3 C M
c) Proximity to remotely c) Equipment safety officer/Deck
operated rotating damage. erected around Supervisor
machinery. dangerous machinery.
a) Emergency
procedures in place.
b) Control systems in
place
Underwater Jetting
Diver on worksite HP water jet to diver.
a) Divers clear of downline.
b) Good communications
between
divers/Supervisor. Dive
a) Diver being struck by
a) Diver injury. c) Water jet cold when sent to Supervisor/onboard
downline/ jetting 4 D H 3 C M
b) Diver entanglement. diver. safety officer/Deck
equipment.
a) Emergency procedures in Supervisor
place.
b) Stand by diver fully
dressed.
Downline/water jet secured on worksite.
a) HP water jet secured before
being made hot Dive
a) Diver pulled off worksite
a) Diver injury. b) Emergency procedures in Supervisor/onboard
when the water jet is made 4 D H 3 C M
b) Diver entanglement. place. safety officer/Deck
hot.
Supervisor
HP water jetting.
Initial Risk Residual Risk
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
a) Water jet gun to be checked
on deck before
lowering to the diver.
b) Trigger function to be
checked.
c) Trigger must NEVER be tied
back.
d) The gun front lance must be
a) Water jet trigger tied open.
long enough to
b) Water jet retro not working.
prevent the diver from shooting
c) Leaking connections.
himself in the Dive
d) Water jet front lance too
foot/body. Supervisor/onboard
short. a) Diver injury. 4 D H 3 C M
e) All hose connections must be safety officer/Deck
e) Water jets trigger not
checked and Supervisor
working.
whip checks used on deck.
f) Excessive noise produced
f) Ensure the water noise is
by the water jet.
within acceptable
levels for the diver.
g) Emergency procedures in
place.
h) Control systems in place.
i) Review procedures
frequently.
j) Initiate ERP in case of
Emergency Recovery of Diving Bell and HRC Evacuation.
In the unlikely event of an emergency on vessel. Recovery of diving bell and HRC evacuation of divers from vessel.
a) On shift personnel must
muster at bell
handling system.
a) Personnel not knowing their b) Dedicated off shift personnel
duties in an emergency. for HRC
a) Serious injury to divers in operations must also muster at
Which muster station to go to
bell the
for ON and OFF shift
b) Delay launching of HRC. bell handling system.
personnel. Dive
c) Delay in recovery of diving c) Other OFF shift personnel
b) Communications failure Supervisor/onboard
bell. 4 D H must 3 C M
between various safety officer/Deck
d) Delay in evacuation from muster at their designated
departments in rescue Supervisor
vessel. muster station unless advised
attempts i.e. Diving Supv &
e) Personal injury to rescue & otherwise.
team, Barge Foreman, Crane
deck crew. d) ON shift diving personnel will
Operator, Deck Foreman &
Rigger Forman etc. initiate
recovery of diving bell in
accordance
to procedures.
Initial Risk Residual Risk
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
e) In the event of HRC
evacuation,
dedicated OFF shift will get HRC
ready for deployment (see HRC
evacuation procedures).
f) Emergency response
procedures in place.
g) Ensure approved
procedures in place
and reviewed by
Diving
Superintendent.
h) Control systems in
place.
i) Post this TRA in a
conspicuous place
for all relevant
personnel to refer to. j) A
dedicated burning rig and
necessary tools must be
available at
all times.
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
k) On transfer of HRC,
dedicated
personnel to transfer to rescue
vessel
and connect emergency gas
package.
Diving Supt. to transfer if
possible.
l) Once HRC is transferred to
rescue
vessel, all remaining personnel
to
dedicated life raft stations.
m) Diving Supt. will rendezvous
with
rescue ship and oversee
operations
as soon as possible, if not
already on
vessel.
Check bell is correctly on and bell lift wire and umbilical are slack.
a) Winch operator pays enough
slack out
on umbilical.
a) Putting too much strain on b) Shut winch down when
a) Injury to occupants in the bell.
bell. enough slack Dive Superviso/Deck
b) Unable to obtain a seal with
b) Tilting the bell. 4 D H paid out. Supervisor/Dive 3 C M
bell and TUP.
c) Unable to mate bell to c) Post this TRA in a Techs
c) Could cause a fatality.
TUP. conspicuous place for all
relevant personnel to refer
to.
Remove outer side door protection. Check trunking valve is open with no gas escaping before opening outside door. Swing door clear as not to foul chamber.
Initial Risk Residual Risk
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
a) Remove cap and open ¼ turn
valve on
side trunk of bell to relieve
pressure if
a) Side door has pressure any.
a) Injury to outside personnel. b) Personnel stand clear Dive Superviso/Deck
behind it.
b) Crush Injury. 4 D H between bell and Supervisor/Dive 3 C M
b) Standing between bell and
c) Lifting strain. TUP when mating. Techs
TUP mating flanges.
c) Two personnel to take off
protection
frame. follow Manual handling
safe work practices.
Open collar clamp fully with safety interlock fully retracted. Flanges are clean and undamaged on TUP and bell.
a) Open locking clamps fully
until they stop.
b) Check interlocks are
a) Damage to locking a) Unable to mate bell. retracted.
c) Check ‘O’ ring and mating Dive Superviso/Deck
clamps. b) Interlock rendered useless.
4 D H surfaces. Supervisor/Dive 3 C M
b) Damage to interlock. c) Unable to gain seal on bell
d) Confirm with Sat control Techs
c) Damage to ‘O’ ring. with TUP.
ready to mate
bell to TUP.
e) Good round robin
communications
Skid bell to match chamber.
a) Stand clear between bell and
Dive Superviso/Deck
TUP when
a) Crush injury. a) Injury to personnel. 4 D H Supervisor/Dive 3 C M
mating.
Techs
When bell mated to TUP, close collar clamps till they stop.
a) Keep body parts and fingers
away from Dive Superviso/Deck
a) Crush injury. a) Injury to personnel. 4 D H collar clamps until stopped. Supervisor/Dive 3 C M
Techs
Close Top and Bottom interlocks and confirms with Sat control.
a) Ensure interlocks work
manually or
a) Not engaging interlock pneumatically.
properly. b) Ensure interlocks are fully Dive Superviso/Deck
b) Opening collar clamps. a) Injury to personnel. 4 D H engaged. Supervisor/Dive 3 C M
c) Loosing seal between bell c) Confirm with Sat control Techs
and TUP. interlocks are in.
d) Good round robin
communications.
Switch off power to skid hydraulics. Press trunking to 50’ and test for leaks.
Initial Risk Residual Risk
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
a) Ensure internal pressure
a) Unauthorised starting of interlock
winch/umbilical. working and turns power off.
Dive Superviso/Deck
b) Loss of seal between Fatality of occupants in b) Check with supervisor in Sat
5 D H Supervisor/Dive 3 C M
bell/TUP. chambers/bell. control.
Techs
c) Accidentally operating c) Good round robin
system. communications.
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
a) Open valves very slowly.
b) Ensure all hoses have been
secured. Dive
a) Fire or Explosion. a) Injury to personnel.
4 D H c) Display warning signs. Superviso/LST/Dive 3 C M
b) Burst whips. b) Property damage.
d) No Smoking or Naked flame Techs
Decanting Oxygen.
a) Keep all personnel away if not
required.
a) Fire or Explosion. b) Ensure all hoses have been Dive
a) Fire or Explosion. b) Injury to personnel 4 D H secured. Superviso/LST/Dive 3 C M
c) Property damage. c) No Smoking or Naked flame. Techs
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
a) Ensure function test of all
plant and equipment.
a) Equipment not working.
b) Ensure correct alignment. Dive
a) Inadequate checks. b) Bad air passing into
c) Ensure correct tags and Superviso/LST/Dive
b) All air intakes are clear. intakes. 4 D H 3 C M
WARNING signs in Techs/Deck
c) All cooling systems are on. c) Equipment over heating.
place. Supervisor
d) Property damage.
d) Ensure all PTW in place.
Potential Hazard Hazard Effect Consequence Probability Risk Control Measures Responsible Consequence Probability Risk
Note: - ACFM operations shall be carried out by competent personnel as per approved procedure.
PREPARED BY (SIGNATURE)
QHSE Depatment