Overview of Project Management
Overview of Project Management
Management
What is a Project?
“Unique process consisting of a set of coordinated
and controlled activities with start and finish dates,
undertaken to achieve an objective conforming to
specific requirements, including constraints of time,
cost, quality and resources”
• A Project is a planned set of activities
• A Project has a scope
• A Project has time, cost, quality and resource
constraints
What is Project Management?
• The art of organising, leading, reporting and
completing a project through people
What is Project Management?
• A project is a planned undertaking
• A project manager is a person who causes
things to happen
• Therefore, project management is causing a
planned undertaking to happen.
Exercise 1
• Write down three attributes of a good Project
Manager
Project Manager Role
• A Good Project Manager
o Takes ownership of the whole project
o Is proactive not reactive
o Adequately plans the project
o Is Authoritative (NOT Authoritarian)
o Is Decisive
o Is a Good Communicator
o Manages by data and facts not uniformed
optimism
o Leads by example
o Has sound Judgement
o Is a Motivator
o Is Diplomatic
o Can Delegate
Stakeholder Engagement
Stakeholder
“A person or group of people who have a vested
interest in the success of an organization and the
environment in which the organization operates”
Exercise 2
• Write down three typical project stakeholders
Exercise 2 - Typical Stakeholders
• Sponsor
• Funding Body
• Customer
• Suppliers
• End User
• Environmental Agency
• Maintenance Team
• Neighbours/Community/Shareholders
• Fusion Community
• Interfaces
Stakeholder Engagement process
• Identify Stakeholders
• Assess needs
• Define actions
• Establish communication channels
• Gather feedback
• Monitor and review
The Project Process
Proj ect Justification Design Approval Readiness for
Strategic and Budgetary Gate 1 Gate 2 - Approval of Manufacture
Gate 0 - Approve Project Definition Gate 3
Approval Undertake Design Final Documents - Approval to
place Contract
Initiate Project
Prepare Technical Design
Ensure Machine Compatibility Prepare
Safety Case Modification
Undertake Tender
Project
set-up Project
Major
Definition Conceptual
Project Scheme
Design
Proposals Design Detailed Tender
Appoint Project Sponsor Design Invitation &
Assess Project Priority
Assess Budget Implications
Est. Proj. Deliverables and Objectives
Raise/Extend/Update initial TCD-R/PERF Assessment
Prepare Outline Conceptual Design
Appoint Project Leader
Define Design Constraints Prepare Extend TCD-Rs/PERFs
Approve Project Set-up
Interface Requirements Spec. (IRP) Prepare Sub-system Detailed Design Hold
Finalise Conceptual Design Detailed Design Review (DDR)
EFDA/CSU/JOC Management Hold Conceptual Design Review (CDR) Clear Sub-system DDR Issues
Clear CDR Issues Use TCD-I/MMAC for Sub-system DD Approval
Initiate Modification Safety Case Prepare Final Documents including:
Update PMP - Design Documents., Machine Compatibility *** These will comprise:
Approve Proceed to Detailed Design Documents., Safety Case Modification - Technical Specification
- Drawings
Project Team/IRP/EFDA/CSU/JDC Project Team/Interfaces/EFDA/CSU/JDC - Contractual Requirements
Obtain
WHEN PRINTED
Acceptance of Completed Project
**** This includes Project Team/ICM
supporting documentation
Project Team/EFDA/CSU
Key Points in Project Set-up and Definition
ITER-Like
Wall Project
[Link].0
Bulk W Bulk Metal Torus Installation Contractual Prepare & Ship Bulk Metal Tiles Erosion/Deposition
Divertor Tiles Group Management JET Be Install Prep. Assemby & Calib.
[Link].0 [Link].0 [Link].0 [Link].0 [Link].0 [Link].0 [Link].0
R&D Engineering D&M ILW Tile Removal FZJ Contract Install Prep.
Management Management & Replacement Management Management
[Link].0 [Link].0 [Link].0 [Link].0 [Link].0
Thomson Scattering
Core (LIDAR)
5.5.C.[Link].0
LIDAR Project LIDAR System Laser Collection Laser Path Control & LIDAR LIDAR Interfaces &
Management Concepts Systems Optics Optics Acquisition Port Engineering Services Integrated Testing
[Link].0 [Link].0 [Link].0 [Link].0 [Link].0 [Link].0 [Link].0 [Link].0 [Link].0
Key Project Overall Cluster Lasers Collection Laser Path Control System Shutters Water LIDAR
Milestones Co-ordination [Link].0 Optical Design Optical Design Interface Definition [Link].0 Services Interfaces
[Link].0 [Link].0 [Link].0 [Link].0 [Link].0 [Link].0 [Link].0
Key Project Performance Laser Collection Laser Control Labyrinth Interspace Mock-up
Deliverables Analysis Layout Windows Windows System [Link].0 Vacuum Facility
[Link].0 [Link].0 [Link].0 [Link].0 [Link].0 [Link].0 [Link].0 [Link].0
Key ITER LIDAR Laser Beam In-Vacuum Plasma Facing Acquisition Extension Tubes & LIDAR Basic Mock-up
Milestones & IPL Neutronics Combiner Collection Mirrors Laser Mirrors System Mirror Mounting Power Tests
[Link].0 [Link].0 [Link].0 [Link].0 [Link].0 [Link].0 [Link].0 [Link].0 [Link].0
Overall Scattering Ex-Vacuum Other Laser LIDAR External Port Optics Spectrometer Tokamak
Management Theory Collection Optics Mirrors Instrumentation Mounting Area Tests
[Link].0 [Link].0 [Link].0 [Link].0 [Link].0 [Link].0 [Link].0 [Link].0
Safety & HP R&D Collection Optics Laser Path Safety Bioshield Laser Final System
Management Tasks Mechanical Design Mechanical Design Interlocks [Link].0 Room Testing
[Link].0 [Link].0 [Link].0 [Link].0 [Link].0 [Link].0 [Link].0
Risk Radiation Spectrometer Beam Safety BSM Port Cell/ System Assembly
Management Effects Data System Dump System Penetrations Interspace & Dis-assembly
[Link].0 [Link].0 [Link].0 [Link].0 [Link].0 [Link].0 [Link].0 [Link].0
Engineering Calibration
Analysis System
[Link].0 [Link].0
Project Planning – WBS (1)
◼ Lowest Level of WBS is the Work Package
(WP)
◼ WP can be clearly defined allowing package
to be costed, scheduled and resourced
◼ WP contains a list of Tasks to be Performed
that form the basis for the Schedule
◼ WP allows assignment of responsibilities
(Work Package Manger, WPM)
Project Planning – WBS (2)
◼ WBS allows hierarchical build-up of costs
and schedule
◼ Cost and Schedule can be reported at any
level of the WBS
◼ WBS facilitates strong management during
project execution (Cost and Schedule
control)
◼ WBS can be used for many other things -
Document Management, Risk Management
etc.
Project Planning
◼ A word about Scheduling
– Schedules (task durations) can have a wide
variation
– There is no unique answer. Rather, there is a
statistical variation depending on assumptions
– Need to understand the basis of scheduling
(Most challenging; Most likely; Absolute certainty
- bet your life on it!)
– Most people are very optimistic/naive
Common schedule development
Accuracy of Timescale Estimates
100
90
80
Subsequent
70 Estimates
Probability
60
50
40
30 First
Estimate
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Timescale
Project Planning – Key Points
• Recognise that adequate project planning is
essential
• Produce a sound WBS
• Use the framework provided by the Project
Management Plan (PMP) template
• Involve the right people
• Allow enough time
• Be systematic
Project Risk Management
Project Risk – Definition (1)
“Project risk is an uncertain event or condition that, if it
occurs, has a positive or negative effect on a
project objective”
Project Risk – Definition (2)