ANNEX I
Pre-commissioning Test Schedule
Name of the Substation: Dewjaan 33/11kV Substation, BPDB.
Month November
Sl Test Test
Test Items 1 2 2 Witness By
No. Day/ Date 12 13 14 15 16 18 19 20 21 22 23 24 Equipment Team
7 5 6
2 Power Transformer (TR-1, TR-2) Test Multimeter,
Detailed Specification & Installation Completion Clip on
2.1 Meter
Check
Insulation
2.2 Test as per Form 2 Tester
CPC-100
3 CT and PT Test (33 kV & 11 kV) Insulation Team 1
Detailed Specification & Installation Completion Tester
3.1 Check CPC 100
3.2 Test as per Form 2 CT Analyzer
4 DC System and Earthing System Test
Detailed Specification & Installation Completion Multimeter
4.1 Check Earth
[Link]
4.2 Test as per Form 2
Busbar, Cable, Conductor, LA, Insulator Contact Resis. Team 3
5 Tester
Test (33 kV & 11 kV)
Insulation
Detailed Specification & Installation Completion
5.1 Check
Tester
Hipot
5.2 Test as per Form 2 Tester
Isolator and Earth Switch Test (33 kV & 11 Contact Resis.
6 Tester
kV)
Detailed Specification & Installation Completion Insulation Team1
6.1 Check Tester
Hipot
6.2 Test as per Form 2 Team3
Tester
8 Protection Relay Test (33 kV & 11 kV) Team2
8.1 Detailed Specification & Installation Completion CMC 356
Month November
Sl Test Test
Test Items 1 2 2 Witness By
No. Day/ Date 12 13 14 15 16 18 19 20 21 22 23 24 Equipment Team
7 5 6
Check
8.2 Test as per Form 2
PCM Panel and Switchgear Panel Test (33 Team2
9
kV & 11 kV)
Insulation
Detailed Specification & Installation Completion
9.1 Check
Tester
Multimeter
9.2 Test as per Form 2
All Pre-commissioning Test Completion
11
Check
12 Pre-commissioning Test Report Submission
Team-1 Primary testing (all equipment test)
Team-2 Secondary Test ( Relay, Control & Protection
Team-3 Hi-Pot Test
Team-4 Operation check and co-ordination