TAKING - OFF SHEET
PROJECT : 11064 (MARRIS) / JALAN SUSUR PANTAI BATU HITAM / SEC. 0.00- 0.15
NO DESCRIPTION
BOX CULVERT 600mm x 600mm (WITHOUT DRY WEATHER FLOW)
1200
150mm Crusher Run
600 80 Sand
150mm
80 600 80
100
600
Geotextile G10
Wrap
80
Box culvert without dry
weather flow
150mm Sand Bedding
150mm Crusher Run
Drain Size:
Width = 0.60 m Box Cul. Wall Thk. = 0.08 m
Depth = 0.60 m Box Cul. Slab Thk. = 0.08 m
Length = 95.00 m Crusher Run Thk. = 0.30 m
Sandbase = 0.30 m
Lid 0.10 m
Excavation Works
95.00 m x 0.76 m x 1.38 m = 99.64 m3
Crusher Run
Volume:-
95.00 m x 0.76 m x 0.30 m = 21.66 m3
Sand Bedding
Volume:-
95.00 m x 0.80 m x 0.30 m = 22.80 m3
Sandfill
Volume:
95.00 m x 0.60 m x 1.38 m = 78.66 m3
Sand Total = 101.46 m3
Cement Mortar Jointing
Total Joints:
95.00 m / 1.00 m/no = 95.00 joints
Box Culvert Perimeter:
0.60 m + 0.60 m + 0.60 m + 0.60 m
= 2.40 m
Qty of mortar for jointing:
2.40 m x 0.10 m x 0.08 m x 95.00 joints
= 1.82 m3
Geotextile Wrapping
Box Culvert Perimeter:
1.52 m + 1.56 m = 3.08 m
Qty of Geotextile:
95.00 m x 3.08 m = 292.60 m2
Page :
QUANTITY
eotextile G10
Wrap
100.00 m3
22.00 m3
102.00 m3
2.00 m3
293.00 m2
TAKING - OFF SHEET
PROJECT : 11064 (MARRIS) / JALAN SUSUR PANTAI BATU HITAM / SEC. 0.00- 0.15
NO DESCRIPTION
BOX CULVERT 900mm x 900mm (WITHOUT DRY WEATHER FLOW)
80
3.56
100mm Pavement
200mm Crusher Run
1060
1.00
600
900 900 1.06
250mm BRC-B10
Geotextile G10
Wrap 50mm Concrete Bedding G15
Drain Size:
Width = 0.60 m Box Cul. Wall Thk. = 0.08 m
Depth = 0.60 m Box Cul. Slab Thk. = 0.08 m
Length = 6.00 m Crusher Run Thk. = 0.30 m
Sandbase = 0.30 m
Lid 0.10 m
Excavation Works
6.00 m x 0.76 m x 1.38 m = 6.29 m3
Crusher Run
Volume:-
6.00 m x 0.76 m x 0.30 m = 1.37 m3
Sand Bedding
Volume:-
6.00 m x 0.80 m x 0.30 m = 1.44 m3
Sandfill
Volume:
6.00 m x 0.60 m x 1.38 m = 4.97 m3
Sand Total = 6.41 m3
Cement Mortar Jointing
Total Joints:
6.00 m / 1.00 m/no = 6.00 joints
Box Culvert Perimeter:
0.60 m + 0.60 m + 0.60 m + 0.60 m
= 2.40 m
Qty of mortar for jointing:
2.40 m x 0.10 m x 0.08 m x 6.00 joints
= 0.12 m3
Geotextile Wrapping
Box Culvert Perimeter:
1.52 m + 1.56 m = 3.08 m
Qty of Geotextile:
6.00 m x 3.08 m = 18.48 m2
Page :
QUANTITY
600
80
80
1200
80
100
7.00 m3
2.00 m3
7.00 m3
1.00 m3
19.00 m2