PRODUCTIVITY RATES FOR ALL PROJECT WORKS:
(Rev 0, May 2000)
Item No. CREW SIZE Hourly
Production Rate
RF REINFORCEMENT
RF 01 Fix Rebar to footings & tie beams 1 STEEL FIXER 25
RF 02 Fix Rebar to walls, columns, beams, solid slabs 1 STEEL FIXER 20
RF 03 Fix rebar to ribs of hourdi slab 1 STEEL FIXER 18
RF 04 Fix rebar to mesh reinforcement 1 STEEL FIXER 15
RF 05 Fix rebar to hidden beams 1 STEEL FIXER 20
RF 01 Fix Rebar to footings & tie beams 1 STEEL FIXER 78
RF 02 Fix Rebar to walls, columns, beams, solid slabs 1 STEEL FIXER 38
RF 03 Fix rebar to ribs of hourdi slab 1 STEEL FIXER 35
RF 04 Fix rebar to mesh reinforcement 1 STEEL FIXER 15
RF 05 Fix rebar to hidden beams 1 STEEL FIXER
RFC 01 Steel cutting and bending 18.25 mm 1 STEEL FIXER 50.00
RFC 02 Steel cutting and bending 8 - 16 mm 1 STEEL FIXER 40.00
EXCAVATION
EX 1 Manual Excavation 1 HELPER
EX 2 Backfill + levelling 1HELPER
EX 3 Shaping of sloped earth for blinding for bases including compaction 1 MASON + 2 HELPER