Employer: Chennai Metro Rail Limited (CMRL) Contract: C4-E&M-05
Project: CMRL, Phase-II, Chennai, GC: AEON IMS/FSAF-08/Rev. D
HOT WORK PERMIT
PROJECT SITE: [Link]: …………
Hot work permits are to be used where a significant risk of fire or erroneous triggering of a fire detection system has been identified.
The type of heat, flame or spark producing operation for which this Permit may be used includes:
Welding – Cutting - Grinding - Soldering – Use of Bitumen boilers - Work using LPG – Burning off paint
PART A – ISSUE (Construction manager/Site Engineer) PART D - COMPLETION OF WORK
Permit is issued to: ......................................................... The work has been completed and the work area and
adjacent areas to which sparks and heat might have
spread such as opposite sides of floors and walls)
have been thoroughly inspected and found fire
for (specific work to be done) .........................................
immediately following completion
...................................................................................... 30 minutes later
1 hour after completion
Electrical equipment/supply switched back on
at (exact location of work) ............................................. Smoke detector/s have been re-activated
All equipment and material has been removed
………………………………………………………………………. Area restored
Other
Valid from: ……: ....... am/pm to: .....: ……. am/pm
Date: …..../………/20….….. The work has been completed, and I have undertaken
the checks and safety measures
I have ticked in Part D of this permit above.
I issue this permit subject to the minimum precautions Time…………………am/pm
Date: ………………20………..
I have listed in Part B below.
Signed: .........................................................
(Issuer) Signed: ..................................……….
(Subcontractor once completed work)
PART B - PRECAUTIONS
Before starting:
Combustible materials: removed
protected
Electrical equipment/supply isolated
Smoke detector/s: isolated PART E - CANCELLATION OF PERMIT (Construction
manager/Site Engineer/Safety representative)
Extinguisher/s: readily available
Personnel: instructed in fire precautions This permit to work is cancelled and the relevant
know nearest fire alarm staff have been notified. No more work under this
Location: protected and sign marked permit.
Work area screened to contain sparks
Other Date: ......./........./20.......... Time:….. : ……… am/pm
Following completion: Signed: .................................................
Work and adjacent areas to be checked immediately (Issuer)
30 minutes later
1 hour after completion
Smoke detector/s to be re-activated
Other
PART C – ACCEPTANCE (Sub-Contractor)
I accept this permit and will ensure the precautions ticked above in part B have been undertaken before starting work. I also
understand the checks and safety measures I am required to undertake after Completion of work.
Signed: .......................................…(Subcontractor undertaking work)
Verified After 6 hours
Signed: ……………………………………….(Issuer) Verified by: ……………………………………….(Safety)