In-Process Inspection Report for Vent Tube

The document is a Process Inspection Report for a Vent Tube manufactured by Fiem Industries Ltd. It details various inspection methods and specifications, including appearance, feed weight, and other quality parameters, with observations recorded at different times throughout the day. The report highlights issues such as short moulds, cuts, air bubbles, excess flash, and cracks, along with quantities checked, accepted, and rejected.

Uploaded by

Mubarak Ali
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
50% found this document useful (2 votes)
1K views2 pages

In-Process Inspection Report for Vent Tube

The document is a Process Inspection Report for a Vent Tube manufactured by Fiem Industries Ltd. It details various inspection methods and specifications, including appearance, feed weight, and other quality parameters, with observations recorded at different times throughout the day. The report highlights issues such as short moulds, cuts, air bubbles, excess flash, and cracks, along with quantities checked, accepted, and rejected.

Uploaded by

Mubarak Ali
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

F/PM/QA/04

PROCESS INSPECTION REPORT Rev No/Date:


00/05.08.18

CUSTOMER : DATE :……………………………


Part Name Vent Tube Mould No. 4034HLA1261-22XX
Part No. 4034HLA1261-22XX Cavity No. -42
Operator Name
Pranab Machine No.: 2B
Batch No.
Compund Name: BT-60(22XX)
OBSERVATION/ TIME REMARKS
[Link]. DESCRIPTION INSP. METHOD SPECIFICATION FIRST

PRESSURE
1 Pressure Gauge
(Kg/Cm2)
CURING TIME
2 Timer
(Sec)
TEMPRATURE (⁰
3 Temp. Contr.
C)
FEED WT.
4 W. Scale
(Gram )
5 DIM (mm) DVC

6 DIM (mm) DVC

7 DIM (mm) DVC

8 DIM (mm) DVC


HARDNESS
9 [Link]
(Shore A)
INSULATION
10 RESISTANCE (MΩ)
MEGOHMMETER

11 CYCLE TIME (Sec) STOPWATCH

12 APPEARANCE VISUAL NOT ALLOWED

SHORT MOULD,

CUT/CRACK,

AIR BUBBLES,

EXCESS FLASH,

GENERAL REMARKS :

INSPECTED BY : APPROVED BY :
PROCESS INSPECTION REPORT F/PM/QA/04 Rev No/Date:
001/29.08.22

CUSTOMER : Fiem Industries Ltd. DATE :……………………………


Part Name Vent Tube Mould No. 4034HLA1261-22XX
Part No. 4034HLA1261-22XX Cavity No. - 42
Operator Name Pranab Machine No.: 2B
Batch No. Compund Name: BT-60 (22XX)
OBSERVATION/ TIME
[Link]. DESCRIPTION INSP. METHOD SPECIFICATION 8:00 AM 8:30 AM 9:00 AM 9:30 AM 10:00 AM 10:30 AM 11:00 AM 11:30 AM 12:00 PM 12:30 PM Remarks

1 APPEARANCE VISUAL SHORT MOULD,

2 APPEARANCE VISUAL CUT

3 APPEARANCE VISUAL AIR BUBBLES,

4 APPEARANCE VISUAL EXCESS FLASH,

5 APPEARANCE VISUAL CRACK

6 FEED WEIGHT [Link] VISUAL

CHECKED QTY-

OK QTY-

REJECTED QTY-

DEFECT NAME
OBSERVATION/ TIME

[Link]. DESCRIPTION INSP. METHOD SPECIFICATION 1:00 PM 2:00 PM 2:30PM 3:00PM 3:30PM 4:00PM 4:30PM 5:00PM 5:30PM 6:00PM Remarks

1 APPEARANCE VISUAL SHORT MOULD,

2 APPEARANCE VISUAL CUT

3 APPEARANCE VISUAL AIR BUBBLES,

4 APPEARANCE VISUAL EXCESS FLASH,

5 APPEARANCE VISUAL CRACK

6 FEED WEIGHT [Link] VISUAL

CHECKED QTY-

OK QTY-

REJECTED QTY-

DEFECT NAME
GENERAL REMARKS :
INSPECTED BY : APPROVED BY :