Debit Note Tata
Debit Note Tata
SURVEYING WORK
Scope:
The scope includes the guidelines to be adopted for setting out and surveying works.
Equipments:
Calibrated auto-level, total station / theodolite and other appropriate survey equipment’s
and accessories.
Procedure:
1. Prior to use, ensure that all survey equipment’s (including hire equipment’s) have
2. Take over base co-ordinates furnished by clients / consultants and set up bench mark
datum.
3. Establish 2 station points (having specific Northing and Easting) at accessible locations
away from periphery of the building to be constructed. Ensure that bench mark shall
4. Construct masonry pillars for the established permanent bench marks with
embedded steel plates at top. Plaster and finish the top surface neatly.
to benchmarks.
7. Run the traverse on all sides of structure and establish set out stations on grid lines.
8. Mark grid lines with reference to temporary benchmarks in both X and Y direction
with paint.
RP INTERIOR PROJECT PVT LTD.
10. Plot detail survey plan showing site boundary, all reference points / pillar locations in
Auto-cad.
11. Superimpose building points given in architectural points over the plotted survey plan.
12. Refer this auto-cad drawing transfer centre line and out-lines points of walls, columns
13. Also transfer reduced levels from temporary bench mark for such at raft top, footing,
tie-beams etc.
Records :
1) All backfill materials shall be free from roots, grass and rubbish. It shall be reasonably well graded
and of maximum size 80 mm. All lumps and clods of size larger than 80 mm shall be broken down
using wooden mallet.
2) Material brought from outside sources shall be approved by Quality Engineer at the place
of source and shall be visually checked each time during its delivery and unloading at site
1) Excavated materials which in the opinion of Site Engineer are useful shall be stacked in
regular heaps, bunds with regular slopes. Such stacking shall be done within the lead (50 m or as
specified).
3) All softer material shall be laid along the centre of heaps. The harder and more weatherresisting
materials shall be stacked so as to form the casing on the sides and the top of heaps of softer
material.
5) Murrum, Sand and Rubble brought from outside shall be stacked separately in regular heaps
of height not more than 1.5m. Stacking shall be done as near to the place of filling as possible
to avoid excess lead. Berm width shall not be less than 0.8m.
6) For borrowed material, stacking shall be done truck-load wise all along the edge of excavated
7) Toe boards shall be provided to prevent stacked material from falling back into the excavated
pits.
RP INTERIOR PROJECT PVT LTD.
loader-excavator
Excavator
Jack hammers
Dumpers
Surface compactor
Tandem rollers
Auto level
Levelling staff
Spirit Level
DGPS
c) Tools:
Crowbars
Pick axes
Spades
Wedges
RP INTERIOR PROJECT PVT LTD.
Hammer
d) Temporary Facilities:
Platforms
Night lamps
Setting out:
1) It shall be ensured that drawing indicating setting out points is available on site. Also
condition.
2) Setting out work shall be carried out using Total station Instrument/ DGPS. Setting out of centre
lines shall be done correctly as per drawing. Levels of reference bench marks shall be with respect to
a Permanent Bench Mark, which shall be made to draw excavation profile. All marking on these shall
be painted red and well preserved.
3) All excavation levels shall be determined from the reference bench marks and got
4) Site Engineer shall check and approve in writing the entire setting out profile, before which
Excavation:
1) It shall be ensured that all necessary equipment, tools, instruments, material and
consumables including temporary facilities like platform, walkways etc. as mentioned are
available at site.
2) All skilled / unskilled manpower along with supervisory personnel for carrying out work shall
RP INTERIOR PROJECT PVT LTD.
3) Excavation drawings shall clearly indicate in plan (preferably by dotted line) the part of soil
1) The excavation shall be done to correct lines, dimensions and levels as per drawing. Adequate
side slopes shall be maintained during excavation of loose soil to prevent soil from sides of
2) Wherever required, proper shoring and strutting shall be provided to maintain and prevent
4) Excavated materials shall not be deposited within 1.5 m from edge of the excavation.
5) Any material obtained from the excavation which in the opinion of the Site Engineer is
useful, shall be stacked separately in regular stacks as directed by Site Engineer. Any excavated
material, which is not suitable for backfilling shall be carted away from the work place as per
6) Planks placed over trenches for crossing shall not be slippery and of width not less than
75 mm wide.
7) Necessary barricades shall be erected and maintained around excavated areas. Also warning
8) Pits shall not be excavated to final founding level, if concreting work is not to be carried
out immediately. Last 15 cm shall be excavated prior to providing blinding layer with lean
9) If by mistake, excavation is carried out below the level mentioned on the drawing, the
10) If any bottom of excavation is left exposed and is deleteriously affected by atmosphere or
water, it shall be dewatered and excavated to sound base. Base of excavation shall then be
filled up to the required level with lean concrete. (Grade M-15 or as specified by Consultant)
11) Removal of buried piping, cables or any other underground services shall not be done
without prior permission of Site Engineer and all measures shall be taken to protect such
12) Adequate precautions as per Consultant’s advice shall be taken to ensure that the excavation
13) Any trees coming in the alignment of the excavation shall be cut after obtaining prior
approval of concerned authorities and any specific requirement laid out by them shall be
complied with. Cut trees shall then be removed from site as per instruction of Site
Engineer.
14) Roots of trees not coming in the portion of excavation pits but whose removal is essential
15) Suitable drainage arrangements shall be provided to prevent surface water entering
excavated pits. Water within the pits shall be bailed out or dewatering shall be carried out
using pumps of adequate capacity to keep excavations free of water. Water removed shall
16) Where water table is high, lowering of water table shall be carried out by well point
17) Excavation in rock shall be carried out either by chiselling with pneumatic drills or by
blasting. Chiselling shall be carried out to obtain correct slopes, shape and pattern of
RP INTERIOR PROJECT PVT LTD.
18) Blasting shall be resorted to when excavation is to be done in hard rock, when chiselling
becomes uneconomical. Blasting shall be carried out by the licensed blaster. License from
19) Blasting shall be controlled blasting unless specified otherwise. Controlling shall be done by
covering portion of rock to blasted with steel plates or woven mesh of wire ropes, meshed
at 200 x 200 mm spacing and then loaded it with sand bags. Loading shall be adequate to
20) Such blasting shall be preferably carried out during lunch time if the work is carried out
within the premises of existing office, factory or working place. Blasting operation shall not
22) Depth, dimension and levels of excavated pits shall be approved and recorded by the
Site Engineer in the field book with signature of concern persons. Nature of the soil at the
excavated pit bottom shall be examined by Site Engineer. If there is doubt regarding safe
bearing capacity (SBC) of soil, Consultant’s opinion shall be taken and appropriate test shall
be carried out to determine safe bearing capacity of soil. Further excavation shall be carried
23) After approval from Site Engineer, bed of the excavated pits shall be firmly consolidated and
levelled by watering and mechanized compacting. Compaction shall be carried out using
surface vibrators in case of small pits and by roller if the area is large. Defective spot shall be
24) Concrete foundation work shall start only after Site Engineer gives the permission to do so in
writing. Laying plain cement concrete shall be carried out after the compaction of sub base
RP INTERIOR PROJECT PVT LTD.
has been carried out to the satisfaction of Site Engineer. However, it shall be ensured that
Backfilling:
1) Backfilling work shall not start until Site Engineer gives written approval to do so.
2) Back filling shall be done in layers of thickness not exceeding 30 to 40cm depending on
compaction equipment and method (loose soil before compaction). The soil layer shall then
be watered adequately and compacted to minimum 95% of Standard Proctor Density for soil
other than sand and 85% in case of sand. Compaction shall be carried out at optimum
moisture content (OMC). Soil after compaction shall be free from pockets underneath.
3) After the compaction of final layer of soil, at least 3 cores shall be taken from the areas
directed by Site Engineer and the soil shall be tested in laboratory for the degree of
4) If the soil is excessively wet, it shall be allowed to dry sufficiently before compaction.
5) Compaction shall be done with suitable mechanical equipment such as plate vibrator, vibratory
or tandem roller, or 10 Tonnes Power Roller as suitable for the area to be compacted. In case
of space restrictions, compaction of soil layers should be done using plate compactors with
thickness of each layer limited to 100 mm. Overall compacted thickness of soil shall be as per
specifications / drawing.
6) Backfilling around water retaining structures shall be done only after testing of structures
1. PURPOSE
The purpose of this procedure is to follow proper activities to carry out Anti termite treatment
works. This purpose of this treatment is to create a chemical barrier between the ground from
where the termites come and wood work, cellulosic materials and other contents of the
2. SCOPE
It includes Anti termite treatment and creating a chemical barrier by using emulsifiable
concentrate 20% or equivalent for plinth beams and all- round the column pits, trenches,
back fill, plinth filling, junction wall and floor, at external perimeter of building from natural
ground level new soil level for all buildings. The work shall be carried out strictly in
3. REFERENCES
4. METHODOLOGY
4.1 Materials
treatment to be employed
2. The chemical emulsion (Imidacloprid) concentration and the rate of application shall be as
Site preparation
The removal of stumps, logs or roots from back filling /plinth filling soil at building site Reduces
RP INTERIOR PROJECT PVT LTD.
the hazards from termites. The sub floor area should be kept free from all debris in which new
treating solution and to assist penetration some site preparation may be necessary as
follows:
All sub floor levelling and grading should be completed, all cuttings and excavations should be
completed with backfilling in place, borrowed fill must be free from organic debris and should
be well compacted. Treatment to be carried out when the soil is dry by suitable hand operated
barrier around the building Treatment should not be carried out when it is raining or when the
4.2 Procedure
The top surface of the consolidated earth within plinth walls to be treated with chemical
Emulsion uniformly on the soil before the sand bed/Soling is laid to form a chemical
barrier at the rate of 5 litres /m2 by using 12 mm dia. Ms rod, holes to be made at a
a) For RCC foundations, the concrete is dense being a richer Mix, the termites are unable
to penetrate it, it is therefore, unnecessary to start the treatment from the bottom of
Excavations. The treatment shall start at a depth of 500 mm below the ground level
except when such ground level is raised or lowered by filling or cutting after the
foundations have been cast. In such cases, the depth of 500 mm shall be determined
from the new soil level. The treatment to be carried out after the ramming operation is
RP INTERIOR PROJECT PVT LTD.
completed by rodding the earth with a 12 mm Dia. MS rod at 150 mm centre to centre
close to the vertical surfaces area around RCC foundations/Columns at the Rate of 7.50
b) In some places if plinth level is 500 mm more than Natural Ground level, the entire GL.
1. Small channel of 30 x 30mm to be made at the junctions of walls and columns with
the floor and the rod holes will be made in the channel area for a depth of 100 mm and
150mm apart and the rod moved backward and forward to enlarge the hole and the
chemical emulsion to be poured along the channel at the rate of 7.50 litres per sqm of
the vertical wall or column surface so as to soak the soil right to the bottom.
2. The soil to be tamped back into the place after this operation.
1. The earth along the external perimeter of the building to be rodded at intervals
2. The rods to be moved backward and forward parallel to the wall to enlarge the hole
and chemical emulsion to be poured along the wall at the rate of 7.50 litres per sqm
of vertical surfaces.
3. After the treatment, the earth to be tamped back into the place. The earth outside the
RCC WORK
RCC work can be divided into 3 parts:
Reinforcement Steel
Formwork
Scope
Steel reinforcements are used, generally, in the form of bars of circular cross section in concrete
structure. They are like a skeleton in human body. Plain concrete without steel or any other
reinforcement is strong in compression but weak in tension. Steel is one of the best forms of
reinforcements, to take care of those stresses and to strengthen concrete to bear all kinds of
loads. Bar-bending-schedule:
Bar-bending-schedule is the schedule of reinforcement bars prepared in advance before cutting and
bending of rebar. This schedule contains all details of size, shape and dimension of rebar to be cut.
Procedure:
1) Material received at site should have ISI certification mark or the supplier should be pre-approved
from QA&QC department after verification of physical and chemical properties as specified in IS
2) For diameter up to 12 mm, one sample per diameter per supplier/manufacturer for every 60
Ton must be tested in an independent/external laboratory. For diameter above 12 mm, one
sample per diameter per supplier/manufacturer for every 100 Ton must be tested in an
independent/external laboratory.
3) Proper equipment / jig should be available for straightening the coiled steel and mandrel
4) Use of latest revisions of drawings and bar bending schedules should be done.
5) Bent bars of identical size, shape and type must be bundled together and labelled correctly
before placing.
6) Steel surface should be free from grease, oil, mud, mould oil, loose mill scales, excessive rust
7) Binding wires must be bent inwards or loose ends cut so that they do not come in cover
8) Beam-column junctions reinforcement steel bars should bunched or spaced properly to avoid
congestion.
9) Enough space between bars should be available to place and compact concrete.
10) Radius of bend given to dowel at construction joints must be as per drawing or as specified by
structural consultant.
11) For long duration of storage, bar must be protected by corrosion resistant passivator /
converter coat.
12) Bars of different types and diameters must be stored separately and clear identification between
13) Reinforcement bars received at site should be stored on hard concreted platform and clear
above the ground with the use of timber sleeper, concrete sleeper or any other means.
Reinforcement should be kept covered by tarpaulins or plastic sheets to avoid excessive corrosion
14) Cover blocks should be of non-corrosive material such as plastic or concrete/mortar but not
wooden or broken tile, broken bricks or stone. Especially PVC made cover spacers should be used
in the works.
RP INTERIOR PROJECT PVT LTD.
15) Binding wire should be 16 or 18 gauge conforming to IS 280. It should be free from rust,
16) Splices should be provided as far as possible away from sections of maximum stress and must be
staggered.
17) Where more than one-half of the bars are spliced at a section or where splices are made at
points of maximum stress, special precaution should be taken, such as increasing the length of lap
and / or using spirals or closely spaced stirrup around the length of the splice. (Staggered laps) or
Following check points should be considered before accepting the consignment of steel.
1) The type of steel i.e. mild steel/high strength deformed or twisted/TMT/corrosion resistant steel.
3) The effective depths, top and bottom cover in slab as per drawing.
6) The lap length and hook length / angle of bars as per drawing.
RP INTERIOR PROJECT PVT LTD.
Formwork
General:
Formwork is dye or mould used to shape the wet concrete until it sets and attains sufficient strength
Contractor shall prepare formwork scheme and consultant approval shall be obtained.
First inspection shall be done at the time receipt, second inspection after first 5 repetitions and
First inspection shall be done at the time before first installation, thereafter every 2 repetitions.
General:
Before using all the wooden chavis / struts / falis and wailings etc. it must be ensured that they are
Procedures:
1) Sequence and mode of construction shall be pre decided to make optimum use of
available formwork.
2) All staging members (props) shall rest on compacted ground / continues wooden plank for the
construction of first slab. Where steel props are used they shall be braced in both directions
using steel tubes and couplers. In addition, cross bracing shall be provided as per design. Props
shall be
RP INTERIOR PROJECT PVT LTD.
erected in plumb.
3) Props shall rest on cleaned slab surface. Packing below props shall be avoided. For staircase, props
4) If pins provided by manufacturers are not used (if pins are lost or misplaced) then use of
5) Spans shall be erected as per correct spacing given in design and shuttering plates shall be placed
6) Gaps (Gabadi) in formwork shall be restricted to 5% of area of slab. Gaps less than 5mm should
be sealed with masking tape or cement grease or equivalent with approved gap sealer / sealant. If
gap found more than 5mm, ply rib of required size or equivalent should be used. Ensure that ply and
7) Independent scaffold shall be erected for fixed forms, reinforcement placing, concrete pour etc.
Adequate camber, if specified on drawing, shall be given to the erected formwork. (Camber at the
beam bottom shall be provided at the rate of 1mm per Running Meter of clear length.)
8) Beam side forms shall be erected in plumb. Width of beam / shear walls shall be maintained
using tie bolts / spacers of correct diameter and length. Tie bolts shall be enclosed in PVC conduits
with provision of removable plastic cones with coil nut at ends.
9) For footings, gap between side ply and PCC shall be sealed to make joints leak proof. For vertical
members, a platform shall be erected not touching the side forms of vertical members for concrete
purpose.
10) For all concrete works, forms shall be kept above concrete level and inside of forms shall be
11) For all erected formwork, levels shall be checked with auto level. Fine correction shall be done in
level through adjustable steel props or adjustable prop heads. It is recommended that Site Engineer
RP INTERIOR PROJECT PVT LTD.
12) After placing of reinforcement in position, form surface shall be cleaned before concreting.
Wooden planks shall be provided over reinforcement as walkways to carry concrete to edged
beams.
13) Scaffolding shall be either single scaffolding or double scaffolding as specified. Making of holes in
masonry should be avoided. For night work adequate lighting arrangement shall be provided.
length.
15) In no case part of column below beam bottom level should be cast along with slab / beam
concreting. All columns must be cast exactly up to beam bottom level. If small top portion of column
concreting is balance then the same should be concreted separately before taking up beam bottom
shuttering.
16) To avoid leakages of slurry from shuttering at column / beam junctions, studs / struts from
beam
sides should be taken down over the column side and should be gripped between two horizontal
chavi, on both sides of columns with bolts, nuts and clamps. No nailing is permitted.
1) Just prior to concreting all levels shall be rechecked. It shall be ensured that all fittings are tight.
All tolerances in form work shall fall within the limits mentioned in acceptance criteria.
2) During concreting, strict supervision shall be maintained on overall erected formwork. If any
immediately.
C) De-shuttering of formwork:
1) De-shuttering shall be done only with the prior approval of QA&QC Department. Recommended
RP INTERIOR PROJECT PVT LTD.
de-shuttering periods are mentioned in table below. But this may vary depending on type of cement
being used, strength of concrete achieved on the day of de-shuttering, type of form used etc.
2) Sequence of removal of props and other components shall be done as per instruction of
PROCEDURE:
1) All the mix designs shall be approved by TATA REALTY. and our structural consultants where
ever required. It is essential to carry out laboratory trials and complete data of trials shall be
2) No additional water, other than the amount required to produce the specified
grade of concrete as per mix design, shall be added to the truck mixer drum before discharge unless
3) Any concrete poured should get finally set within maximum 24 hours.
4) Any concrete of a specified Grade shall meet the characteristic strength in 28 days. Any concrete
being supplied to our site, which does not achieve minimum characteristic strength at 28 days, shall
5) Batch sheets, moisture correction calculation/sheet shall be submitted along with challans for
6) Ready-mixed concrete shall be transported from the mixer/batching plant to the point of placing
as rapidly as practicable by methods that will maintain the required workability and will prevent
segregation, loss of any constituents or ingress of foreign matter or water. Concrete shall be
transported in a truck-mixer or agitators unless TATA REALTY agrees to the use of non-agitating
vehicles.
7) For the assessment of compliance of ready-mixed concrete, the sampling may be carried out.
Slump and temperature to be recorded in pour control sheet.
8) In case of failure of strength (as estimated by cube strength), Cores shall be drilled out from the
structure with strength failure and shall be tested for compressive strength and equivalent cube
strength must meet the requirements of relevant BIS standard. No other NDT shall be
entertained. The cost of Core drilling and testing shall be borne by the supplier of concrete.
Further the results shall be forwarded to TATA REALTY’s structural consultant for his opinion and
binding on both the parties – TATA REALTY and the Supplier of concrete.
9) If the equivalent cube strength of the drilled cores does not meet the requirements of BIS
codes, then the matter shall be referred to TATA REALTY’s structural consultant and as per the
recommendation of the Structural Consultant, the structure shall be demolished and reworked or
strengthened. The cost for such demolition/ breaking, reworking including cost of labour and
material such as steel reinforcement, concrete, electricity etc. or the cost of strengthening the
Dewatering of area to be concreted shall be carried out if required. Also area shall be cleaned of any
1) Necessary latest drawings shall be made available on site Checking of form work, supports
and scaffolding shall be done.
3) Checking of various activities such as reinforcement, cover blocks, embedded electrical conduits,
4) Sequence of concreting and location of stopper shall be decided and clearly marked on
7) Checklist QA/QC card should be appropriately filled taking into account all the points
8) In case of site produced concrete, concreting shall be preferably done on weight basis. However,
if volume batching has to be resorted to, conversion into volume shall be done by calculating DLBD
of coarse / fine aggregates and also taking into account Bulkage Factor for sand.
RP INTERIOR PROJECT PVT LTD.
9) For PCC volumetric batching, Pharmas of correct sizes shall be prepared and maintained in
proper condition in such cases.
10) Sufficient concrete handling, compaction (vibrators) and curing arrangements with respect to
size of the pour, depth of pour, spacing of reinforcement etc. must be ensured before starting
concrete if site produced concrete or before ordering concrete from approved supplier.
General:
1) The concrete pipeline of pump shall be checked to ensure whether there is any leakage of
2) During concreting it must be checked whether there is any slurry leakage from the shuttering and
corrective measures should be taken immediately because this may affect finishing because of
3) Variation in pipe diameter of pump and number of bends in the pipeline should be restricted
to minimum.
4) The supports/props must be checked during concreting to avoid bulging and potential failure
5) Pouring height must be restricted as per the site condition with suitable methods to avoid
segregation of concrete.
6) Availability of sufficient equipment and manpower for compaction of concrete must be ensured
7) Vibrator needle size shall be appropriate as per the spacing of the reinforcement and
9) Over vibration of concrete should be avoided, which may lead to deposition of slurry at the top
leading to crazing cracks any time during hardening. Over vibration may also lead to bleeding
1) Before unloading of any truck at the site, the RMC supplier shall supply a certificate/batch sheet
(a computerized sheet) along with moisture correction for the concrete, mentioning proportions of
all the ingredients, w/c ratio, dosage of plasticizer and relevant admixtures etc.
2) The maximum water cement ratio, as specified in the approved mix design shall not be exceeded.
3) The information provided by RMC supplier shall be cross checked at site, and in all cases slump
shall be taken prior to concreting. The accuracy of the measuring equipment shall be within + 2
percent of the quantity of cement and mineral admixtures being measured and within + 3 percent
4) Concrete which needs to be pumped shall have workability between 120 to 150 mm or as
specified when the transit mixer arrives. Any concrete shall be designed for a minimum three hours’
retention/open time. The workability of the concrete shall be controlled on a continuous basis
during production and any corrective action necessary shall be taken. No additional water, other
than the amount required to produce the specified grade of concrete as per mix design, shall be
added to the truck mixer drum before discharge unless specifically requested and signed for by
THDL & TVHL’s. Representative. Re-dosing or split dosing shall be allowed subject to the written
permission of trained technicians and Engineers from THDL & TVHL’s. In any case, the total dose
should not exceed the maximum dose of admixture declared by Supplier or recommended by
Admixture supplier.
6) It shall be ensured that the retardation time achieved by the use of admixtures does not exceed
the time required for transit and actual placement of concrete. This shall be achieved by checking
the time of dispatch of transit mixer mentioned on challan. Any Concrete is being designed with the
help of water reducing agents and retarders for a stipulated retention time. So the concrete must be
RP INTERIOR PROJECT PVT LTD.
consumed within the same time as considered in design. Our all concrete mixes must be designed
for 3 hours retention time, so concrete must be consumed within 3 Hours from the time of
batching. If the workability of concrete is higher than desired workability and segregation &
bleeding is observed, we should allow some time to elapse before discharge till workability drops to
the range of 120 to 150 mm. If workability is less, then re-dosing or split dosing shall be allowed but
in any case, the total dose should not exceed the maximum dose of admixture declared by Supplier
of concrete or recommended by Admixture supplier. We must avoid over dosing which may cause
7) Temperature of concrete at the time of pumping shall be less than 40ºC or as mutually agreed
8) The cohesiveness and mixing of the concrete should be checked, there should be no
9) Concrete carrying pipes shall not be allowed to rest on top reinforcement which is likely to
bend. Leakage of slurry from concrete pipeline should be checked and rectified.
Footings
2) Demarcation of foundation should be done with correct orientation of column as per centre
line plan.
3) All footings shall rest on PCC of M15/M10 Grade concrete, having minimum thickness of 150mm
4) Concrete shall be cast in max 450mm layers and vibrated by 60mm vibrating needle. Columns and
Shear walls
1) Platform erected for labour for concreting shall be independent of column shuttering.
2) If required, Grade of concrete for column starters shall be one grade higher than that of column
RP INTERIOR PROJECT PVT LTD.
concrete.
3) Minimum height of starters shall be 4” to 9” and shuttering shall be of fabricated steel / steel
channels or plywood. (Planks or fali should not be used in sides of starters.) Concrete within shall be
4) Formwork for starters of column / shear walls when erected shall be checked using theodolite
/ line dori for the correctness of dimensions and orientation (including offsets if any).
6) Column concreting shall be done up to lowest level of beam bottom at the junction.
7) Concrete key shall be made at top surface of column for better bond with next pour/ 20mm metal
packing shall be done on top of concrete surface for proper bonding with next pour / chipping of top
8) If reinforcing bars are congested at the junction of column and beam, a special concrete mix
2) Walking platforms shall be provided for easy movement of labour without disturbing
the reinforcement.
3) Level marking / ghodi having height equal to thickness of slab shall be used while slab
concreting is in progress.
4) Concreting area for the day shall be well demarcated and concreting shall commence from the
farthest end and proceed towards direction of hoist. In case of pumping, proper planning should
5) Slab top levels shall be checked during and after finishing with levelling instrument for controlling
RP INTERIOR PROJECT PVT LTD.
6) Beams and slabs having depth more than 150 mm shall be vibrated by 25/40/60 mm needle
depending on size of beams and spacing of reinforcement, whereas slabs having thickness of less
than 150 mm shall preferably be vibrated by surface vibrator. The spacing of inserting the vibrating
7) Care shall be taken not to over/under vibrate the concrete. While withdrawing vibrator needle
8) Concrete shall be placed in layers not exceeding 450mm deep in deep beams and placed to the
full depth in slabs and small beams. Each layer shall be placed and well compacted before the
preceding layer has taken its initial set and in a manner that will entirely prevent any cold joint
9) If concrete is being placed by pump or crane bucket, concrete should not be poured directly in
to the beams.
10) If grade of concrete for slab and columns is different, column portion shall be cast first before
slab concreting starts. Care shall be taken to prevent formation of cold joint at junction i.e. portion
adjoining columns shall be cast before initial setting starts in columns. Welded wire mesh or
equivalent shall be used as stoppers to prevent excess concrete from columns to flow into beams.
11) Construction joint in beams shall be provided as per drawings or in absence of such drawings,
where shear force is zero. Cement sand slurry of 1:1 or bonding agent shall be used at
construction joints to create better bonding between old and new concrete. At construction joints,
RP INTERIOR PROJECT PVT LTD.
new concrete shall be over-vibrated for proper bonding with old. Wooden stoppers with step shall
12) Slab panels shall be covered with wet Hessian cloth, tarpaulin or plastic sheets immediate after
Curing
1) Curing is the process of preventing the loss of moisture from the concrete whilst maintaining a
satisfactory temperature regime. For all concrete works, curing shall be start immediately after
deshuttering and for slab and raft surface immediately after initial setting of concrete by sprinkling
or covering with wet hessian cloth.
2) Exposed surfaces of concrete shall be kept continuously in a damp or wet condition by ponding or
by covering with a layer of sacking, canvas, hessian or similar materials and kept constantly wet for
at least 7 days from the date of placing concrete in case of ordinary Portland Cement and at least 10
3) The period of curing shall not be less than 10 days for concrete exposed to dry and hot
Protection of concrete
1) Newly placed concrete shall be protected from rain, sun and wind by approved means viz:
2) Concrete placed below the ground level shall be protected against contamination from falling
3) The area in and around the actual place of the concreting shall be kept sufficiently dry, by
constructing sufficiently watertight forms / cofferdam around the area to be concreted, to prevent
1) Curing shall be done keeping the concrete surface wet by covering it with moist double
Hessian cloth
Slabs
1) Curing of slabs shall be done as mentioned above 2) Ponds shall be made within 24 hours of slab
casting and till then slab shall be cured by spraying water.
3) Ponds shall be made at column locations first to cover from all sides and then to cover other
portions of slab.
4) Care shall be taken to see to it that ponds are completely filled with water throughout
5) Vertical faces of the beams and area of slab outside ponds shall be cured by covering with wet
Hessian cloth.
6) In case where ponding is not done, whole slab should be covered with wet hessian cloth and
Footings
1) Flat portion of footings shall be cured by covering it with wet double Hessian cloth.
2) For flat portions of Rafts, curing shall be done in a similar way as that for slab and vertical faces
General:
1) Backfilling shall be started after footings are cured. Backfilling shall be carried out in layers of
300mm to 450mm thick good quality murrum, which shall be well watered (up to Optimum
4) Date of casting should be displayed on concrete surface with identification after de-shuttering to
RP INTERIOR PROJECT PVT LTD.
monitor curing.
5) If honeycombs observed are of repairable nature (which do not require demolition of member, in
the opinion of Structural Consultant), the same shall be rectified by using approved non shrink
6) If it is intended to have plaster or masonry against the concrete structure, the surface shall be
hacked (approx. 60/70 hacks each 2-3mm in depth, 1” length and 1” apart per [Link]) within 48 hrs.
7) Reinforcement bars projecting above cast concrete shall be cleaned, using wire brush.
8) Tie roads and PVC pipes must be removed immediately after de-shuttering.
9) Columns below natural ground should have 20mm additional covering or as recommended
by structural consultant and Winged Cover Kanda should be used to maintain alignment of
For the assessment of compliance of ready-mixed concrete, the sampling may be carried out jointly
by THDL & TVHL’s. And the supplier with minimum frequency as specified in IS:4926 or otherwise
RP INTERIOR PROJECT PVT LTD.
mutually agreed upon. However, it will not absolve the supplier of his responsibility from supplying
concrete as per the requirements given in standards (IS 456 and IS 4926) or otherwise mutually
agreed terms and Conditions. The point and time of sampling shall be at discharge from the
(b) In assembling the mould for use, the joints between the sections of mould shall be thinly
coated with mould oil and a similar coating of mould oil shall be applied between the contact
surfaces of the bottom of the mould and the base plate in order to ensure that no water escapes
(c) Ensure angle between adjacent internal faces & between internal faces shall be 90°C + 0.5°C.
(f) 35 tamps for each of the three layers in 150 mm mould or vibrating table
(g) After filling each layer tamp sides with a wooden mallet to expel out any entrapped air
(h) The workability of concrete at time of filling cubes should be between 75 -100 mm.
(i) Remove surplus concrete & number the moulds for identification & record details.
(k) Cover each mould with damp cloth / Hessian cloth immediately after initial set.
(l) Store at a place free from vibration. Protect the cube moulds at all times from high / low
(n) After de-moulding the cubes shall be immediately submerged in clean, fresh water or saturated
lime solution and kept there until taken out just prior to test (Temperature 25°C to 30°C).
RP INTERIOR PROJECT PVT LTD.
(o) The specimens shall not be allowed to become dry at any time until they have been tested.
(p) The testing machine may be of any reliable type, of sufficient capacity for the tests and capable
of applying the load at the rate of 14 N/mm2/minute. The permissible error shall be not greater than
(q) The bearing surfaces of the testing machine shall be wiped clean and any loose sand or
other material removed from the surfaces of the specimen which are to be in contact with the
compression platens.
(r) The specimen shall be placed in the machine in such a manner that the load shall be applied
to opposite sides of the cubes as cast, that is, not to the top and bottom.
(s) Average of three values shall be taken as the representative of the batch provided the individual
(u) If failure is observed during the testing of the first cube, stop testing the balance two cubes,
immediately inform the senior authority of THDL & TVHL’s. The supplier of the concrete and test the
balance two cubes in presence of the supplier’s authorized representative and have a joint record.
k) Appearance of fractured faces of concrete and type of fracture, if these are unusual.
the conditions to the QA/QC Engineer who would decide the remedy
2) Honeycombs of mild and moderate nature, in the concrete, where the reinforcement inside is
not exposed, shall be repaired with use of approved Non-shrink mortar mixed with bonding
chemical. The repaired patch of concrete shall be cured for 7 days or by using water curing or curing
3) For repair of honeycombs in concrete, where reinforcement is exposed, high strength mortar shall
RP INTERIOR PROJECT PVT LTD.
be used for the repair work and cured for 7 days or by using curing compound as recommended by
manufacturer.
4) Brands of repair material and chemicals shall be approved by QA/QC Department for use to repair
5) shrinkage cracks shall be grouted with approved non-shrink grout, whereas minor shrinkage
cracks shall be filled with cement slurry. Structural cracks to be grouted with the low viscous high
strength grout.
the same shall be enclosed by forms from all sides before demolishing and supported
adequately.
7) All repair works shall be carried out in accordance with the manufacturer’s recommendations as
regards the preparation of surface, cleaning, hacking, applying bonding agents, admixtures, polymer
mortars etc.
1) Minor honeycomb – After removal of shuttering, minor aggregates exposed with slurry leakage.
2) Moderate honeycomb – After removal of shuttering, moderate aggregates exposed with slurry
leakage.