0% found this document useful (0 votes)
335 views33 pages

Debit Note Tata

The document outlines the Work Method Statement for surveying, excavation, backfilling, and anti-termite treatment for a construction project. It details the procedures, equipment, and safety measures required for each phase of the work, including the establishment of benchmarks, excavation techniques, and the application of anti-termite chemicals. Additionally, it emphasizes the importance of proper documentation and adherence to standards throughout the project.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
335 views33 pages

Debit Note Tata

The document outlines the Work Method Statement for surveying, excavation, backfilling, and anti-termite treatment for a construction project. It details the procedures, equipment, and safety measures required for each phase of the work, including the establishment of benchmarks, excavation techniques, and the application of anti-termite chemicals. Additionally, it emphasizes the importance of proper documentation and adherence to standards throughout the project.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd

RP INTERIOR PROJECT PVT LTD.

One Bangalore Luxury Project Private Ltd,

Document Title WORK METHOD STATEMENT


Effective
Document Number SROBLP-RPI-GENE-GE-QU-MST-001 Date
31.05.2024
Revision Number 00

SURVEYING WORK

Scope:

The scope includes the guidelines to be adopted for setting out and surveying works.

Equipments:

Calibrated auto-level, total station / theodolite and other appropriate survey equipment’s

and accessories.

Procedure:

1. Prior to use, ensure that all survey equipment’s (including hire equipment’s) have

valid calibration certificates.

2. Take over base co-ordinates furnished by clients / consultants and set up bench mark

datum.

3. Establish 2 station points (having specific Northing and Easting) at accessible locations

away from periphery of the building to be constructed. Ensure that bench mark shall

remain undisturbed till the completion of project.

4. Construct masonry pillars for the established permanent bench marks with

embedded steel plates at top. Plaster and finish the top surface neatly.

5. Recheck the benchmark co-ordinates and put paint/ marks on top.

6. Establish control pillars for individual structures as above with reference

to benchmarks.

7. Run the traverse on all sides of structure and establish set out stations on grid lines.

8. Mark grid lines with reference to temporary benchmarks in both X and Y direction

with paint.
RP INTERIOR PROJECT PVT LTD.

One Bangalore Luxury Project Private Ltd,

Document Title WORK METHOD STATEMENT


Effective
Document Number SROBLP-RPI-GENE-GE-QU-MST-001 Date
31.05.2024
Revision Number 00

10. Plot detail survey plan showing site boundary, all reference points / pillar locations in

Auto-cad.

11. Superimpose building points given in architectural points over the plotted survey plan.

12. Refer this auto-cad drawing transfer centre line and out-lines points of walls, columns

and footings on the PCC.

13. Also transfer reduced levels from temporary bench mark for such at raft top, footing,

tie-beams etc.

Records :

1. Joint measurement and records surveying and levelling works.

2. Any other records as per contract requirements.


RP INTERIOR PROJECT PVT LTD.

One Bangalore Luxury Project Private Ltd,

Document Title WORK METHOD STATEMENT


Effective
Document Number SROBLP-RPI-GENE-GE-QU-MST-001 Date
31.05.2024
Revision Number 00

EXCAVATION AND BACKFILLING


NOTES:

1) All backfill materials shall be free from roots, grass and rubbish. It shall be reasonably well graded
and of maximum size 80 mm. All lumps and clods of size larger than 80 mm shall be broken down
using wooden mallet.

2) Material brought from outside sources shall be approved by Quality Engineer at the place

of source and shall be visually checked each time during its delivery and unloading at site

throughout the period of backfilling work.

Storage of Raw Material:

a) Soil for backfilling:

1) Excavated materials which in the opinion of Site Engineer are useful shall be stacked in

regular heaps, bunds with regular slopes. Such stacking shall be done within the lead (50 m or as

specified).

2) Stacks of soil shall be properly levelled for providing natural drainage.

3) All softer material shall be laid along the centre of heaps. The harder and more weatherresisting
materials shall be stacked so as to form the casing on the sides and the top of heaps of softer
material.

4) Soft and hard rock shall be stacked separately.

5) Murrum, Sand and Rubble brought from outside shall be stacked separately in regular heaps

of height not more than 1.5m. Stacking shall be done as near to the place of filling as possible

to avoid excess lead. Berm width shall not be less than 0.8m.

6) For borrowed material, stacking shall be done truck-load wise all along the edge of excavated

pits. Material shall not be stacked against an existing wall.

7) Toe boards shall be provided to prevent stacked material from falling back into the excavated

pits.
RP INTERIOR PROJECT PVT LTD.

One Bangalore Luxury Project Private Ltd,

Document Title WORK METHOD STATEMENT


Effective
Document Number SROBLP-RPI-GENE-GE-QU-MST-001 Date
31.05.2024
Revision Number 00

6) Equipment and Tools:

a) Excavation and backfilling Equipment’s:

loader-excavator

Excavator

Jack hammers

Dumpers

Concrete cutter (If required)

Surface compactor

Tandem rollers

Vibratory roller / 10T Power roller

Dewatering pumps of suitable capacity

b) Surveying Equipments: (with valid calibration certificates)

Total station equipment

Auto level

Levelling staff

Spirit Level

DGPS

Paint & Brushes

c) Tools:

Crowbars

Pick axes

Spades

Wedges
RP INTERIOR PROJECT PVT LTD.

One Bangalore Luxury Project Private Ltd,

Document Title WORK METHOD STATEMENT


Effective
Document Number SROBLP-RPI-GENE-GE-QU-MST-001 Date
31.05.2024
Revision Number 00

Hammer

Line dori (50m)

Measuring tape (50m)

d) Temporary Facilities:

Platforms

Night lamps

Procedures for Excavation and Backfilling works

Pre Excavation Procedures:

Setting out:

1) It shall be ensured that drawing indicating setting out points is available on site. Also

necessary surveying equipment as mentioned shall be available on site in good operational

condition.

2) Setting out work shall be carried out using Total station Instrument/ DGPS. Setting out of centre
lines shall be done correctly as per drawing. Levels of reference bench marks shall be with respect to
a Permanent Bench Mark, which shall be made to draw excavation profile. All marking on these shall
be painted red and well preserved.

3) All excavation levels shall be determined from the reference bench marks and got

approved from Site Engineer before actual excavation work starts.

4) Site Engineer shall check and approve in writing the entire setting out profile, before which

no excavation work shall commence.

Excavation:

1) It shall be ensured that all necessary equipment, tools, instruments, material and

consumables including temporary facilities like platform, walkways etc. as mentioned are

available at site.

2) All skilled / unskilled manpower along with supervisory personnel for carrying out work shall
RP INTERIOR PROJECT PVT LTD.

One Bangalore Luxury Project Private Ltd,

Document Title WORK METHOD STATEMENT


Effective
Document Number SROBLP-RPI-GENE-GE-QU-MST-001 Date
31.05.2024
Revision Number 00

have sufficient experience on similar works.

3) Excavation drawings shall clearly indicate in plan (preferably by dotted line) the part of soil

to be excavated and also levels to which excavation needs to be carried out.

During Excavation Procedures:

1) The excavation shall be done to correct lines, dimensions and levels as per drawing. Adequate

side slopes shall be maintained during excavation of loose soil to prevent soil from sides of

excavated pits from falling back into the pits.

2) Wherever required, proper shoring and strutting shall be provided to maintain and prevent

sides of excavations from collapsing.

3) No heavy equipment shall be allowed within 6m from edge of excavation or within a

distance equal to depth of excavation, whichever is less.

4) Excavated materials shall not be deposited within 1.5 m from edge of the excavation.

5) Any material obtained from the excavation which in the opinion of the Site Engineer is

useful, shall be stacked separately in regular stacks as directed by Site Engineer. Any excavated

material, which is not suitable for backfilling shall be carted away from the work place as per

directions of Site Engineer.

6) Planks placed over trenches for crossing shall not be slippery and of width not less than

75 mm wide.

7) Necessary barricades shall be erected and maintained around excavated areas. Also warning

lamps at night shall be provided to ensure safety.

8) Pits shall not be excavated to final founding level, if concreting work is not to be carried

out immediately. Last 15 cm shall be excavated prior to providing blinding layer with lean

concrete (PCC). PCC shall be of proportion [Link] or as specified by Consultant.


RP INTERIOR PROJECT PVT LTD.

One Bangalore Luxury Project Private Ltd,

Document Title WORK METHOD STATEMENT


Effective
Document Number SROBLP-RPI-GENE-GE-QU-MST-001 Date
31.05.2024
Revision Number 00

9) If by mistake, excavation is carried out below the level mentioned on the drawing, the

same shall be made up to correct level by filling with concrete.

10) If any bottom of excavation is left exposed and is deleteriously affected by atmosphere or

water, it shall be dewatered and excavated to sound base. Base of excavation shall then be

filled up to the required level with lean concrete. (Grade M-15 or as specified by Consultant)

11) Removal of buried piping, cables or any other underground services shall not be done

without prior permission of Site Engineer and all measures shall be taken to protect such

lines till their removal.

12) Adequate precautions as per Consultant’s advice shall be taken to ensure that the excavation

operations do not damage the adjoining structures or dislocate underground services.

13) Any trees coming in the alignment of the excavation shall be cut after obtaining prior

approval of concerned authorities and any specific requirement laid out by them shall be

complied with. Cut trees shall then be removed from site as per instruction of Site

Engineer.

14) Roots of trees not coming in the portion of excavation pits but whose removal is essential

shall be removed and hollows shall be filled up during backfilling.

15) Suitable drainage arrangements shall be provided to prevent surface water entering

excavated pits. Water within the pits shall be bailed out or dewatering shall be carried out

using pumps of adequate capacity to keep excavations free of water. Water removed shall

be disposed off, away from the excavated area.

16) Where water table is high, lowering of water table shall be carried out by well point

system so that general water table is below excavation level.

17) Excavation in rock shall be carried out either by chiselling with pneumatic drills or by

blasting. Chiselling shall be carried out to obtain correct slopes, shape and pattern of
RP INTERIOR PROJECT PVT LTD.

One Bangalore Luxury Project Private Ltd,

Document Title WORK METHOD STATEMENT


Effective
Document Number SROBLP-RPI-GENE-GE-QU-MST-001 Date
31.05.2024
Revision Number 00

excavation pits as per drawings.

18) Blasting shall be resorted to when excavation is to be done in hard rock, when chiselling

becomes uneconomical. Blasting shall be carried out by the licensed blaster. License from

statutory bodies shall be obtained prior to undertaking of blasting work.

19) Blasting shall be controlled blasting unless specified otherwise. Controlling shall be done by

covering portion of rock to blasted with steel plates or woven mesh of wire ropes, meshed

at 200 x 200 mm spacing and then loaded it with sand bags. Loading shall be adequate to

prevent rock pieces from blowing away.

20) Such blasting shall be preferably carried out during lunch time if the work is carried out

within the premises of existing office, factory or working place. Blasting operation shall not

be carried out during night time.

22) Depth, dimension and levels of excavated pits shall be approved and recorded by the

Site Engineer in the field book with signature of concern persons. Nature of the soil at the

excavated pit bottom shall be examined by Site Engineer. If there is doubt regarding safe

bearing capacity (SBC) of soil, Consultant’s opinion shall be taken and appropriate test shall

be carried out to determine safe bearing capacity of soil. Further excavation shall be carried

out in such cases, if the consultant advice to do so.

23) After approval from Site Engineer, bed of the excavated pits shall be firmly consolidated and

levelled by watering and mechanized compacting. Compaction shall be carried out using

surface vibrators in case of small pits and by roller if the area is large. Defective spot shall be

dug and filled with concrete.

24) Concrete foundation work shall start only after Site Engineer gives the permission to do so in

writing. Laying plain cement concrete shall be carried out after the compaction of sub base
RP INTERIOR PROJECT PVT LTD.

One Bangalore Luxury Project Private Ltd,

Document Title WORK METHOD STATEMENT


Effective
Document Number SROBLP-RPI-GENE-GE-QU-MST-001 Date
31.05.2024
Revision Number 00

has been carried out to the satisfaction of Site Engineer. However, it shall be ensured that

base is in moist condition before laying PCC.

Backfilling:

1) Backfilling work shall not start until Site Engineer gives written approval to do so.

2) Back filling shall be done in layers of thickness not exceeding 30 to 40cm depending on

compaction equipment and method (loose soil before compaction). The soil layer shall then

be watered adequately and compacted to minimum 95% of Standard Proctor Density for soil

other than sand and 85% in case of sand. Compaction shall be carried out at optimum

moisture content (OMC). Soil after compaction shall be free from pockets underneath.

3) After the compaction of final layer of soil, at least 3 cores shall be taken from the areas

directed by Site Engineer and the soil shall be tested in laboratory for the degree of

compaction achieved. Results shall be matched above.

4) If the soil is excessively wet, it shall be allowed to dry sufficiently before compaction.

(Approximately OMC should be maintained)

5) Compaction shall be done with suitable mechanical equipment such as plate vibrator, vibratory

or tandem roller, or 10 Tonnes Power Roller as suitable for the area to be compacted. In case

of space restrictions, compaction of soil layers should be done using plate compactors with

thickness of each layer limited to 100 mm. Overall compacted thickness of soil shall be as per

specifications / drawing.

6) Backfilling around water retaining structures shall be done only after testing of structures

against leakage is done.

Records : Checklist for back filling works (Checklist no.EG03-P-01-F-28)

Reference Documents : ITP and soil testing procedures


RP INTERIOR PROJECT PVT LTD.

One Bangalore Luxury Project Private Ltd,

Document Title WORK METHOD STATEMENT


Effective
Document Number SROBLP-RPI-GENE-GE-QU-MST-001 Date
31.05.2024
Revision Number 00

ANTI TERMITE WORK

1. PURPOSE

The purpose of this procedure is to follow proper activities to carry out Anti termite treatment

works. This purpose of this treatment is to create a chemical barrier between the ground from

where the termites come and wood work, cellulosic materials and other contents of the

buildings which may form food for the termites.

2. SCOPE

It includes Anti termite treatment and creating a chemical barrier by using emulsifiable

concentrate 20% or equivalent for plinth beams and all- round the column pits, trenches,

back fill, plinth filling, junction wall and floor, at external perimeter of building from natural

ground level new soil level for all buildings. The work shall be carried out strictly in

accordance with IS 6313(Part-2)2013, specifications and corresponding approved drawings.

3. REFERENCES

Following documents in totality or in part shall form the reference documents:

Code for pre-construction anti termite treatment is IS 6313 part II – 2013.

4. METHODOLOGY

4.1 Materials

1. Approved Specialized agency with skilled labours having experience in anti-termite

treatment to be employed

2. The chemical emulsion (Imidacloprid) concentration and the rate of application shall be as

specified by the Codes/Specifications/or as specified by the manufacturer

Site preparation

The removal of stumps, logs or roots from back filling /plinth filling soil at building site Reduces
RP INTERIOR PROJECT PVT LTD.

One Bangalore Luxury Project Private Ltd,

Document Title WORK METHOD STATEMENT


Effective
Document Number SROBLP-RPI-GENE-GE-QU-MST-001 Date
31.05.2024
Revision Number 00

the hazards from termites. The sub floor area should be kept free from all debris in which new

colonies of termites might be established. In order to ensure uniform distribution of the

treating solution and to assist penetration some site preparation may be necessary as

follows:

All sub floor levelling and grading should be completed, all cuttings and excavations should be

completed with backfilling in place, borrowed fill must be free from organic debris and should

be well compacted. Treatment to be carried out when the soil is dry by suitable hand operated

sprayer to facilitate uniform disposal of chemical emulsion to form an effective chemical

barrier around the building Treatment should not be carried out when it is raining or when the

soil is wet with rain or sub-soil water.

4.2 Procedure

4.2.1 Treatment of top surface of plinth filling

The top surface of the consolidated earth within plinth walls to be treated with chemical

Emulsion uniformly on the soil before the sand bed/Soling is laid to form a chemical

barrier at the rate of 5 litres /m2 by using 12 mm dia. Ms rod, holes to be made at a

Minimum of 50 mm to 75 mm deep at 150 mm centres both ways.

4.2.2 Treatment for RCC foundations and Basement.

a) For RCC foundations, the concrete is dense being a richer Mix, the termites are unable

to penetrate it, it is therefore, unnecessary to start the treatment from the bottom of

Excavations. The treatment shall start at a depth of 500 mm below the ground level

except when such ground level is raised or lowered by filling or cutting after the

foundations have been cast. In such cases, the depth of 500 mm shall be determined

from the new soil level. The treatment to be carried out after the ramming operation is
RP INTERIOR PROJECT PVT LTD.

One Bangalore Luxury Project Private Ltd,

Document Title WORK METHOD STATEMENT


Effective
Document Number SROBLP-RPI-GENE-GE-QU-MST-001 Date
31.05.2024
Revision Number 00

completed by rodding the earth with a 12 mm Dia. MS rod at 150 mm centre to centre

close to the vertical surfaces area around RCC foundations/Columns at the Rate of 7.50

Litres per Sqm.

b) In some places if plinth level is 500 mm more than Natural Ground level, the entire GL.

4.2.3 Junction of walls and floors

1. Small channel of 30 x 30mm to be made at the junctions of walls and columns with

the floor and the rod holes will be made in the channel area for a depth of 100 mm and

150mm apart and the rod moved backward and forward to enlarge the hole and the

chemical emulsion to be poured along the channel at the rate of 7.50 litres per sqm of

the vertical wall or column surface so as to soak the soil right to the bottom.

2. The soil to be tamped back into the place after this operation.

4.2.4 Soil along external perimeter of building:

1. The earth along the external perimeter of the building to be rodded at intervals

of 150mm and to a depth of 300mm.

2. The rods to be moved backward and forward parallel to the wall to enlarge the hole

and chemical emulsion to be poured along the wall at the rate of 7.50 litres per sqm

of vertical surfaces.

3. After the treatment, the earth to be tamped back into the place. The earth outside the

building to be graded on completion of building; this treatment to be carried out on

completion of such grading.

Records : Checklist no. EG03-P-01-F-29

Reference Documents : Technical Specifications of anti-termite treatment, IS code, product-data

sheet for anti-termite treatment chemical.


RP INTERIOR PROJECT PVT LTD.

One Bangalore Luxury Project Private Ltd,

Document Title WORK METHOD STATEMENT


Effective
Document Number SROBLP-RPI-GENE-GE-QU-MST-001 Date
31.05.2024
Revision Number 00

RCC WORK
RCC work can be divided into 3 parts:

Reinforcement Steel

Formwork

Procedures for Concreting

Scope

Steel reinforcements are used, generally, in the form of bars of circular cross section in concrete

structure. They are like a skeleton in human body. Plain concrete without steel or any other

reinforcement is strong in compression but weak in tension. Steel is one of the best forms of

reinforcements, to take care of those stresses and to strengthen concrete to bear all kinds of

loads. Bar-bending-schedule:

Bar-bending-schedule is the schedule of reinforcement bars prepared in advance before cutting and

bending of rebar. This schedule contains all details of size, shape and dimension of rebar to be cut.

Procedure:

1) Material received at site should have ISI certification mark or the supplier should be pre-approved

from QA&QC department after verification of physical and chemical properties as specified in IS

1786. Bars should be marked to identify categories.

2) For diameter up to 12 mm, one sample per diameter per supplier/manufacturer for every 60

Ton must be tested in an independent/external laboratory. For diameter above 12 mm, one

sample per diameter per supplier/manufacturer for every 100 Ton must be tested in an

independent/external laboratory.

3) Proper equipment / jig should be available for straightening the coiled steel and mandrel

for bending and cutter machine for cutting steel bars.


RP INTERIOR PROJECT PVT LTD.

One Bangalore Luxury Project Private Ltd,

Document Title WORK METHOD STATEMENT


Effective
Document Number SROBLP-RPI-GENE-GE-QU-MST-001 Date
31.05.2024
Revision Number 00

4) Use of latest revisions of drawings and bar bending schedules should be done.

5) Bent bars of identical size, shape and type must be bundled together and labelled correctly

before placing.

6) Steel surface should be free from grease, oil, mud, mould oil, loose mill scales, excessive rust

scales, and loose concrete.

7) Binding wires must be bent inwards or loose ends cut so that they do not come in cover

zone and/or protrude out of concrete.

8) Beam-column junctions reinforcement steel bars should bunched or spaced properly to avoid

congestion.

9) Enough space between bars should be available to place and compact concrete.

10) Radius of bend given to dowel at construction joints must be as per drawing or as specified by

structural consultant.

11) For long duration of storage, bar must be protected by corrosion resistant passivator /

converter coat.

12) Bars of different types and diameters must be stored separately and clear identification between

tested and untested steel should be marked at site.

13) Reinforcement bars received at site should be stored on hard concreted platform and clear

above the ground with the use of timber sleeper, concrete sleeper or any other means.

Reinforcement should be kept covered by tarpaulins or plastic sheets to avoid excessive corrosion

and other contamination.

14) Cover blocks should be of non-corrosive material such as plastic or concrete/mortar but not

wooden or broken tile, broken bricks or stone. Especially PVC made cover spacers should be used

in the works.
RP INTERIOR PROJECT PVT LTD.

One Bangalore Luxury Project Private Ltd,

Document Title WORK METHOD STATEMENT


Effective
Document Number SROBLP-RPI-GENE-GE-QU-MST-001 Date
31.05.2024
Revision Number 00

15) Binding wire should be 16 or 18 gauge conforming to IS 280. It should be free from rust,

oil, paint, grease or any other deleterious material.

16) Splices should be provided as far as possible away from sections of maximum stress and must be

staggered.

17) Where more than one-half of the bars are spliced at a section or where splices are made at

points of maximum stress, special precaution should be taken, such as increasing the length of lap

and / or using spirals or closely spaced stirrup around the length of the splice. (Staggered laps) or

as suggested by structural consultant.

Checklist before accepting consignment of steel:

Following check points should be considered before accepting the consignment of steel.

1) The type of steel i.e. mild steel/high strength deformed or twisted/TMT/corrosion resistant steel.

2) The grade of steel based on chemical and physical requirement.

3) The rolling margin.

4) The original steel certificate issued by steel supplier.

5) The physical and chemical properties in manufacturer’s test certificate.

6) Bend Re-bend test at site.

Following check points should be checked after placing of steel:

1) The cutting and bending are in order.

2) Spacing between bars as per drawing

3) The effective depths, top and bottom cover in slab as per drawing.

4) Position of top steel bars in case of cantilever slabs.

5) Corrosion inhibiting layer applied over the steel bars if specified.

6) The lap length and hook length / angle of bars as per drawing.
RP INTERIOR PROJECT PVT LTD.

One Bangalore Luxury Project Private Ltd,

Document Title WORK METHOD STATEMENT


Effective
Document Number SROBLP-RPI-GENE-GE-QU-MST-001 Date
31.05.2024
Revision Number 00

7) The welding of bars as per drawing or as per standard details.

8) Deviation due to any reason is verified by design office.

Formwork

General:

Formwork is dye or mould used to shape the wet concrete until it sets and attains sufficient strength

to carry its own weight and retains its shape.

Contractor shall prepare formwork scheme and consultant approval shall be obtained.

Inspection for New Formwork Material:

First inspection shall be done at the time receipt, second inspection after first 5 repetitions and

There after every 2 repetitions.

For Old Formwork Material:

First inspection shall be done at the time before first installation, thereafter every 2 repetitions.

General:

Before using all the wooden chavis / struts / falis and wailings etc. it must be ensured that they are

Randha (planer) finished so that no undulations come on RCC surface.

The rejected material must be removed from site or stored separately.

Procedures:

A) Procedures to be followed before and during erecting formwork:

1) Sequence and mode of construction shall be pre decided to make optimum use of

available formwork.

2) All staging members (props) shall rest on compacted ground / continues wooden plank for the

construction of first slab. Where steel props are used they shall be braced in both directions

using steel tubes and couplers. In addition, cross bracing shall be provided as per design. Props

shall be
RP INTERIOR PROJECT PVT LTD.

One Bangalore Luxury Project Private Ltd,

Document Title WORK METHOD STATEMENT


Effective
Document Number SROBLP-RPI-GENE-GE-QU-MST-001 Date
31.05.2024
Revision Number 00

erected in plumb.

3) Props shall rest on cleaned slab surface. Packing below props shall be avoided. For staircase, props

should be placed vertical and wedges should be provided to maintain verticality.

4) If pins provided by manufacturers are not used (if pins are lost or misplaced) then use of

minimum 12 dia. tor steel pins shall be allowed.

5) Spans shall be erected as per correct spacing given in design and shuttering plates shall be placed

tightly abutting each other.

6) Gaps (Gabadi) in formwork shall be restricted to 5% of area of slab. Gaps less than 5mm should

be sealed with masking tape or cement grease or equivalent with approved gap sealer / sealant. If

gap found more than 5mm, ply rib of required size or equivalent should be used. Ensure that ply and

ply rib is maintained at same line and level.

7) Independent scaffold shall be erected for fixed forms, reinforcement placing, concrete pour etc.

Adequate camber, if specified on drawing, shall be given to the erected formwork. (Camber at the

beam bottom shall be provided at the rate of 1mm per Running Meter of clear length.)

8) Beam side forms shall be erected in plumb. Width of beam / shear walls shall be maintained
using tie bolts / spacers of correct diameter and length. Tie bolts shall be enclosed in PVC conduits
with provision of removable plastic cones with coil nut at ends.

9) For footings, gap between side ply and PCC shall be sealed to make joints leak proof. For vertical

members, a platform shall be erected not touching the side forms of vertical members for concrete

purpose.

10) For all concrete works, forms shall be kept above concrete level and inside of forms shall be

marked to indicate concrete level.

11) For all erected formwork, levels shall be checked with auto level. Fine correction shall be done in

level through adjustable steel props or adjustable prop heads. It is recommended that Site Engineer
RP INTERIOR PROJECT PVT LTD.

One Bangalore Luxury Project Private Ltd,

Document Title WORK METHOD STATEMENT


Effective
Document Number SROBLP-RPI-GENE-GE-QU-MST-001 Date
31.05.2024
Revision Number 00

gets mock up for walls and column.

12) After placing of reinforcement in position, form surface shall be cleaned before concreting.

Wooden planks shall be provided over reinforcement as walkways to carry concrete to edged

beams.

13) Scaffolding shall be either single scaffolding or double scaffolding as specified. Making of holes in

masonry should be avoided. For night work adequate lighting arrangement shall be provided.

14) Stirrup head should be opened only up to 60 % of its total

length.

15) In no case part of column below beam bottom level should be cast along with slab / beam

concreting. All columns must be cast exactly up to beam bottom level. If small top portion of column

concreting is balance then the same should be concreted separately before taking up beam bottom

shuttering.

16) To avoid leakages of slurry from shuttering at column / beam junctions, studs / struts from
beam

sides should be taken down over the column side and should be gripped between two horizontal

chavi, on both sides of columns with bolts, nuts and clamps. No nailing is permitted.

B) Procedures to be followed after erecting formwork:

1) Just prior to concreting all levels shall be rechecked. It shall be ensured that all fittings are tight.

All tolerances in form work shall fall within the limits mentioned in acceptance criteria.

2) During concreting, strict supervision shall be maintained on overall erected formwork. If any

sinking or displacement is observed during concreting, remedial measures shall be adopted

immediately.

C) De-shuttering of formwork:

1) De-shuttering shall be done only with the prior approval of QA&QC Department. Recommended
RP INTERIOR PROJECT PVT LTD.

One Bangalore Luxury Project Private Ltd,

Document Title WORK METHOD STATEMENT


Effective
Document Number SROBLP-RPI-GENE-GE-QU-MST-001 Date
31.05.2024
Revision Number 00

de-shuttering periods are mentioned in table below. But this may vary depending on type of cement

being used, strength of concrete achieved on the day of de-shuttering, type of form used etc.

2) Sequence of removal of props and other components shall be done as per instruction of

QA&QC Department’s recommendation.

De-shuttering period after casting shall be as per IS 456.

PROCEDURE:

PROCEDURES FOR CONCRETING

Step 1 – Mix Design Approval:

SPECIFICATION FOR SUPPLY OF READY MIX CONCRETE


RP INTERIOR PROJECT PVT LTD.

One Bangalore Luxury Project Private Ltd,

Document Title WORK METHOD STATEMENT


Effective
Document Number SROBLP-RPI-GENE-GE-QU-MST-001 Date
31.05.2024
Revision Number 00

1) All the mix designs shall be approved by TATA REALTY. and our structural consultants where

ever required. It is essential to carry out laboratory trials and complete data of trials shall be

submitted for approval.

2) No additional water, other than the amount required to produce the specified

grade of concrete as per mix design, shall be added to the truck mixer drum before discharge unless

specifically requested and signed for by TATA REALTY representative.

3) Any concrete poured should get finally set within maximum 24 hours.

4) Any concrete of a specified Grade shall meet the characteristic strength in 28 days. Any concrete

being supplied to our site, which does not achieve minimum characteristic strength at 28 days, shall

be considered as failure and no other acceptance criteria shall be entertained.

5) Batch sheets, moisture correction calculation/sheet shall be submitted along with challans for

every pour of concrete.

6) Ready-mixed concrete shall be transported from the mixer/batching plant to the point of placing

as rapidly as practicable by methods that will maintain the required workability and will prevent

segregation, loss of any constituents or ingress of foreign matter or water. Concrete shall be

transported in a truck-mixer or agitators unless TATA REALTY agrees to the use of non-agitating

vehicles.

7) For the assessment of compliance of ready-mixed concrete, the sampling may be carried out.
Slump and temperature to be recorded in pour control sheet.

8) In case of failure of strength (as estimated by cube strength), Cores shall be drilled out from the

structure with strength failure and shall be tested for compressive strength and equivalent cube

strength must meet the requirements of relevant BIS standard. No other NDT shall be

entertained. The cost of Core drilling and testing shall be borne by the supplier of concrete.

Further the results shall be forwarded to TATA REALTY’s structural consultant for his opinion and

his decision shall be


RP INTERIOR PROJECT PVT LTD.

One Bangalore Luxury Project Private Ltd,

Document Title WORK METHOD STATEMENT


Effective
Document Number SROBLP-RPI-GENE-GE-QU-MST-001 Date
31.05.2024
Revision Number 00

binding on both the parties – TATA REALTY and the Supplier of concrete.

9) If the equivalent cube strength of the drilled cores does not meet the requirements of BIS

codes, then the matter shall be referred to TATA REALTY’s structural consultant and as per the

recommendation of the Structural Consultant, the structure shall be demolished and reworked or

strengthened. The cost for such demolition/ breaking, reworking including cost of labour and

material such as steel reinforcement, concrete, electricity etc. or the cost of strengthening the

structure shall be borne by the supplier.

Step 2 – Site Preparation

Dewatering of area to be concreted shall be carried out if required. Also area shall be cleaned of any

dirt, debris, waste material, binding wires etc.

Step 3 – Pre Concreting Checks

1) Necessary latest drawings shall be made available on site Checking of form work, supports
and scaffolding shall be done.

3) Checking of various activities such as reinforcement, cover blocks, embedded electrical conduits,

plumbing lines, inserts etc. shall be done as per drawing.

4) Sequence of concreting and location of stopper shall be decided and clearly marked on

drawings available on site.

5) Availability of necessary raw materials and equipment shall be ensured.

6) Appropriate de-shuttering agent should be applied on formwork.

7) Checklist QA/QC card should be appropriately filled taking into account all the points

are maintained properly at site.

8) In case of site produced concrete, concreting shall be preferably done on weight basis. However,

if volume batching has to be resorted to, conversion into volume shall be done by calculating DLBD

of coarse / fine aggregates and also taking into account Bulkage Factor for sand.
RP INTERIOR PROJECT PVT LTD.

One Bangalore Luxury Project Private Ltd,

Document Title WORK METHOD STATEMENT


Effective
Document Number SROBLP-RPI-GENE-GE-QU-MST-001 Date
31.05.2024
Revision Number 00

9) For PCC volumetric batching, Pharmas of correct sizes shall be prepared and maintained in
proper condition in such cases.

10) Sufficient concrete handling, compaction (vibrators) and curing arrangements with respect to

size of the pour, depth of pour, spacing of reinforcement etc. must be ensured before starting

concrete if site produced concrete or before ordering concrete from approved supplier.

Step 4- During Concreting Checks

General:

1) The concrete pipeline of pump shall be checked to ensure whether there is any leakage of

slurry, which may affect the pumpability of concrete.

2) During concreting it must be checked whether there is any slurry leakage from the shuttering and

corrective measures should be taken immediately because this may affect finishing because of

honeycombing and final performance of the concrete and aesthetics.

3) Variation in pipe diameter of pump and number of bends in the pipeline should be restricted

to minimum.

4) The supports/props must be checked during concreting to avoid bulging and potential failure

of shuttering because of the weight of wet concrete.

5) Pouring height must be restricted as per the site condition with suitable methods to avoid

segregation of concrete.

6) Availability of sufficient equipment and manpower for compaction of concrete must be ensured

7) Vibrator needle size shall be appropriate as per the spacing of the reinforcement and

workability of the concrete. Influence radius should be checked by visual observation

9) Over vibration of concrete should be avoided, which may lead to deposition of slurry at the top

leading to crazing cracks any time during hardening. Over vibration may also lead to bleeding

resulting in plastic settlement and subsequent cracks.


RP INTERIOR PROJECT PVT LTD.

One Bangalore Luxury Project Private Ltd,

Document Title WORK METHOD STATEMENT


Effective
Document Number SROBLP-RPI-GENE-GE-QU-MST-001 Date
31.05.2024
Revision Number 00

Ready Mix Concrete:

1) Before unloading of any truck at the site, the RMC supplier shall supply a certificate/batch sheet

(a computerized sheet) along with moisture correction for the concrete, mentioning proportions of

all the ingredients, w/c ratio, dosage of plasticizer and relevant admixtures etc.

2) The maximum water cement ratio, as specified in the approved mix design shall not be exceeded.

3) The information provided by RMC supplier shall be cross checked at site, and in all cases slump

shall be taken prior to concreting. The accuracy of the measuring equipment shall be within + 2

percent of the quantity of cement and mineral admixtures being measured and within + 3 percent

of the quantity of aggregate, chemical admixture and water being measured.

4) Concrete which needs to be pumped shall have workability between 120 to 150 mm or as

specified when the transit mixer arrives. Any concrete shall be designed for a minimum three hours’

retention/open time. The workability of the concrete shall be controlled on a continuous basis

during production and any corrective action necessary shall be taken. No additional water, other

than the amount required to produce the specified grade of concrete as per mix design, shall be

added to the truck mixer drum before discharge unless specifically requested and signed for by

THDL & TVHL’s. Representative. Re-dosing or split dosing shall be allowed subject to the written

permission of trained technicians and Engineers from THDL & TVHL’s. In any case, the total dose

should not exceed the maximum dose of admixture declared by Supplier or recommended by

Admixture supplier.

6) It shall be ensured that the retardation time achieved by the use of admixtures does not exceed

the time required for transit and actual placement of concrete. This shall be achieved by checking

the time of dispatch of transit mixer mentioned on challan. Any Concrete is being designed with the

help of water reducing agents and retarders for a stipulated retention time. So the concrete must be
RP INTERIOR PROJECT PVT LTD.

One Bangalore Luxury Project Private Ltd,

Document Title WORK METHOD STATEMENT


Effective
Document Number SROBLP-RPI-GENE-GE-QU-MST-001 Date
31.05.2024
Revision Number 00

consumed within the same time as considered in design. Our all concrete mixes must be designed

for 3 hours retention time, so concrete must be consumed within 3 Hours from the time of

batching. If the workability of concrete is higher than desired workability and segregation &

bleeding is observed, we should allow some time to elapse before discharge till workability drops to

the range of 120 to 150 mm. If workability is less, then re-dosing or split dosing shall be allowed but

in any case, the total dose should not exceed the maximum dose of admixture declared by Supplier

of concrete or recommended by Admixture supplier. We must avoid over dosing which may cause

delay in setting of concrete

7) Temperature of concrete at the time of pumping shall be less than 40ºC or as mutually agreed

between TATA REALTY’s and Supplier of Concrete.

8) The cohesiveness and mixing of the concrete should be checked, there should be no

lumps, bleeding or segregation in the concrete.

9) Concrete carrying pipes shall not be allowed to rest on top reinforcement which is likely to

bend. Leakage of slurry from concrete pipeline should be checked and rectified.

Footings

1) PCC should be done in level as per given size in drawing.

2) Demarcation of foundation should be done with correct orientation of column as per centre

line plan.

3) All footings shall rest on PCC of M15/M10 Grade concrete, having minimum thickness of 150mm

/ 75mm or as per drawing.

4) Concrete shall be cast in max 450mm layers and vibrated by 60mm vibrating needle. Columns and
Shear walls

1) Platform erected for labour for concreting shall be independent of column shuttering.

2) If required, Grade of concrete for column starters shall be one grade higher than that of column
RP INTERIOR PROJECT PVT LTD.

One Bangalore Luxury Project Private Ltd,

Document Title WORK METHOD STATEMENT


Effective
Document Number SROBLP-RPI-GENE-GE-QU-MST-001 Date
31.05.2024
Revision Number 00

concrete.

3) Minimum height of starters shall be 4” to 9” and shuttering shall be of fabricated steel / steel

channels or plywood. (Planks or fali should not be used in sides of starters.) Concrete within shall be

suitably vibrated and cured.

4) Formwork for starters of column / shear walls when erected shall be checked using theodolite

/ line dori for the correctness of dimensions and orientation (including offsets if any).

5) Concrete for columns shall be cast and vibrated in layers of 450mm.

6) Column concreting shall be done up to lowest level of beam bottom at the junction.

7) Concrete key shall be made at top surface of column for better bond with next pour/ 20mm metal

packing shall be done on top of concrete surface for proper bonding with next pour / chipping of top

surface for removal of laitance.

8) If reinforcing bars are congested at the junction of column and beam, a special concrete mix

of higher grade using 10mm aggregates may be used therein.

Slab and Beams

1) Concrete from hoist shall be unloaded on MS tray

2) Walking platforms shall be provided for easy movement of labour without disturbing

the reinforcement.

3) Level marking / ghodi having height equal to thickness of slab shall be used while slab

concreting is in progress.

4) Concreting area for the day shall be well demarcated and concreting shall commence from the

farthest end and proceed towards direction of hoist. In case of pumping, proper planning should

be done for placing of concrete.

5) Slab top levels shall be checked during and after finishing with levelling instrument for controlling
RP INTERIOR PROJECT PVT LTD.

One Bangalore Luxury Project Private Ltd,

Document Title WORK METHOD STATEMENT


Effective
Document Number SROBLP-RPI-GENE-GE-QU-MST-001 Date
31.05.2024
Revision Number 00

the thickness of slab.

6) Beams and slabs having depth more than 150 mm shall be vibrated by 25/40/60 mm needle

depending on size of beams and spacing of reinforcement, whereas slabs having thickness of less

than 150 mm shall preferably be vibrated by surface vibrator. The spacing of inserting the vibrating

needle in concrete shall be as follows:

25mm needle – 150mm c/c

40mm needle – 300mm c/c

60mm needle – 450mm c/c

7) Care shall be taken not to over/under vibrate the concrete. While withdrawing vibrator needle

no holes shall be visible in concrete.

8) Concrete shall be placed in layers not exceeding 450mm deep in deep beams and placed to the

full depth in slabs and small beams. Each layer shall be placed and well compacted before the

preceding layer has taken its initial set and in a manner that will entirely prevent any cold joint

forming between the layers

9) If concrete is being placed by pump or crane bucket, concrete should not be poured directly in

to the beams.

10) If grade of concrete for slab and columns is different, column portion shall be cast first before

slab concreting starts. Care shall be taken to prevent formation of cold joint at junction i.e. portion

adjoining columns shall be cast before initial setting starts in columns. Welded wire mesh or

equivalent shall be used as stoppers to prevent excess concrete from columns to flow into beams.

11) Construction joint in beams shall be provided as per drawings or in absence of such drawings,

where shear force is zero. Cement sand slurry of 1:1 or bonding agent shall be used at

construction joints to create better bonding between old and new concrete. At construction joints,
RP INTERIOR PROJECT PVT LTD.

One Bangalore Luxury Project Private Ltd,

Document Title WORK METHOD STATEMENT


Effective
Document Number SROBLP-RPI-GENE-GE-QU-MST-001 Date
31.05.2024
Revision Number 00

new concrete shall be over-vibrated for proper bonding with old. Wooden stoppers with step shall

be provided at construction joints in such a way so as to facilitate their easy removal.

12) Slab panels shall be covered with wet Hessian cloth, tarpaulin or plastic sheets immediate after

concreting, after initial set occurs, to prevent formation of shrinkage cracks.

Step 5- Post Concreting Checks

Curing

1) Curing is the process of preventing the loss of moisture from the concrete whilst maintaining a

satisfactory temperature regime. For all concrete works, curing shall be start immediately after
deshuttering and for slab and raft surface immediately after initial setting of concrete by sprinkling
or covering with wet hessian cloth.

2) Exposed surfaces of concrete shall be kept continuously in a damp or wet condition by ponding or

by covering with a layer of sacking, canvas, hessian or similar materials and kept constantly wet for

at least 7 days from the date of placing concrete in case of ordinary Portland Cement and at least 10

days where mineral admixtures or blended cements are used.

3) The period of curing shall not be less than 10 days for concrete exposed to dry and hot

weather conditions & 14 days where blended cement is used.

Protection of concrete

1) Newly placed concrete shall be protected from rain, sun and wind by approved means viz:

Hessian cloth, plastic sheets etc.

2) Concrete placed below the ground level shall be protected against contamination from falling

earth, during placing.

3) The area in and around the actual place of the concreting shall be kept sufficiently dry, by

constructing sufficiently watertight forms / cofferdam around the area to be concreted, to prevent

loss of mortar through walls.


RP INTERIOR PROJECT PVT LTD.

One Bangalore Luxury Project Private Ltd,

Document Title WORK METHOD STATEMENT


Effective
Document Number SROBLP-RPI-GENE-GE-QU-MST-001 Date
31.05.2024
Revision Number 00

Columns / Shear walls

1) Curing shall be done keeping the concrete surface wet by covering it with moist double

Hessian cloth

2) Curing shall continue for at least 10 days.

Slabs

1) Curing of slabs shall be done as mentioned above 2) Ponds shall be made within 24 hours of slab
casting and till then slab shall be cured by spraying water.

3) Ponds shall be made at column locations first to cover from all sides and then to cover other

portions of slab.

4) Care shall be taken to see to it that ponds are completely filled with water throughout

the recommended period for curing.

5) Vertical faces of the beams and area of slab outside ponds shall be cured by covering with wet

Hessian cloth.

6) In case where ponding is not done, whole slab should be covered with wet hessian cloth and

care should be taken to keep it moist always.

Footings

1) Flat portion of footings shall be cured by covering it with wet double Hessian cloth.

2) For flat portions of Rafts, curing shall be done in a similar way as that for slab and vertical faces

shall be cured similar to the columns.

General:

1) Backfilling shall be started after footings are cured. Backfilling shall be carried out in layers of

300mm to 450mm thick good quality murrum, which shall be well watered (up to Optimum

Moisture Content) and compacted by using mechanical vibrator.

4) Date of casting should be displayed on concrete surface with identification after de-shuttering to
RP INTERIOR PROJECT PVT LTD.

One Bangalore Luxury Project Private Ltd,

Document Title WORK METHOD STATEMENT


Effective
Document Number SROBLP-RPI-GENE-GE-QU-MST-001 Date
31.05.2024
Revision Number 00

monitor curing.

5) If honeycombs observed are of repairable nature (which do not require demolition of member, in

the opinion of Structural Consultant), the same shall be rectified by using approved non shrink

mortar mixed with bonding chemical.

6) If it is intended to have plaster or masonry against the concrete structure, the surface shall be

hacked (approx. 60/70 hacks each 2-3mm in depth, 1” length and 1” apart per [Link]) within 48 hrs.

After de-shuttering or it is preferable to use approved bonding agents instead of hacking.

7) Reinforcement bars projecting above cast concrete shall be cleaned, using wire brush.

8) Tie roads and PVC pipes must be removed immediately after de-shuttering.

9) Columns below natural ground should have 20mm additional covering or as recommended

by structural consultant and Winged Cover Kanda should be used to maintain alignment of

reinforcement and covering.

Step -6 Concrete Cube Sampling

Site Mixed Concrete:

The minimum frequency of cube casting shall be as per IS 456

Ready Mix Concrete:

For the assessment of compliance of ready-mixed concrete, the sampling may be carried out jointly

by THDL & TVHL’s. And the supplier with minimum frequency as specified in IS:4926 or otherwise
RP INTERIOR PROJECT PVT LTD.

One Bangalore Luxury Project Private Ltd,

Document Title WORK METHOD STATEMENT


Effective
Document Number SROBLP-RPI-GENE-GE-QU-MST-001 Date
31.05.2024
Revision Number 00

mutually agreed upon. However, it will not absolve the supplier of his responsibility from supplying

concrete as per the requirements given in standards (IS 456 and IS 4926) or otherwise mutually

agreed terms and Conditions. The point and time of sampling shall be at discharge from the

producer’s delivery vehicle or point of final placement.

The following steps should be observed:

(a) Check if moulds are cleaned & lightly oiled.

(b) In assembling the mould for use, the joints between the sections of mould shall be thinly

coated with mould oil and a similar coating of mould oil shall be applied between the contact

surfaces of the bottom of the mould and the base plate in order to ensure that no water escapes

during the filling.

(c) Ensure angle between adjacent internal faces & between internal faces shall be 90°C + 0.5°C.

(d) Thoroughly remix the sample shovelling into a heap

(e) Fill the mould with concrete in 50 mm layers

(f) 35 tamps for each of the three layers in 150 mm mould or vibrating table

(g) After filling each layer tamp sides with a wooden mallet to expel out any entrapped air

(h) The workability of concrete at time of filling cubes should be between 75 -100 mm.

(i) Remove surplus concrete & number the moulds for identification & record details.

(k) Cover each mould with damp cloth / Hessian cloth immediately after initial set.

(l) Store at a place free from vibration. Protect the cube moulds at all times from high / low

temperatures & driving winds.

(m) Complete Sampling & cube making certificates or records.

(n) After de-moulding the cubes shall be immediately submerged in clean, fresh water or saturated

lime solution and kept there until taken out just prior to test (Temperature 25°C to 30°C).
RP INTERIOR PROJECT PVT LTD.

One Bangalore Luxury Project Private Ltd,

Document Title WORK METHOD STATEMENT


Effective
Document Number SROBLP-RPI-GENE-GE-QU-MST-001 Date
31.05.2024
Revision Number 00

(o) The specimens shall not be allowed to become dry at any time until they have been tested.

(p) The testing machine may be of any reliable type, of sufficient capacity for the tests and capable

of applying the load at the rate of 14 N/mm2/minute. The permissible error shall be not greater than

± 2 % of the maximum load.

(q) The bearing surfaces of the testing machine shall be wiped clean and any loose sand or

other material removed from the surfaces of the specimen which are to be in contact with the

compression platens.

(r) The specimen shall be placed in the machine in such a manner that the load shall be applied

to opposite sides of the cubes as cast, that is, not to the top and bottom.

(s) Average of three values shall be taken as the representative of the batch provided the individual

variation is not more than ± 15 % of the average.

(u) If failure is observed during the testing of the first cube, stop testing the balance two cubes,

immediately inform the senior authority of THDL & TVHL’s. The supplier of the concrete and test the

balance two cubes in presence of the supplier’s authorized representative and have a joint record.

k) Appearance of fractured faces of concrete and type of fracture, if these are unusual.

Step -10 Repair Work

1) Honeycombing, especially severe honeycombing shall not be patched up without showing

the conditions to the QA/QC Engineer who would decide the remedy

2) Honeycombs of mild and moderate nature, in the concrete, where the reinforcement inside is

not exposed, shall be repaired with use of approved Non-shrink mortar mixed with bonding

chemical. The repaired patch of concrete shall be cured for 7 days or by using water curing or curing

compound as recommended by manufacturer.

3) For repair of honeycombs in concrete, where reinforcement is exposed, high strength mortar shall
RP INTERIOR PROJECT PVT LTD.

One Bangalore Luxury Project Private Ltd,

Document Title WORK METHOD STATEMENT


Effective
Document Number SROBLP-RPI-GENE-GE-QU-MST-001 Date
31.05.2024
Revision Number 00

be used for the repair work and cured for 7 days or by using curing compound as recommended by

manufacturer.

4) Brands of repair material and chemicals shall be approved by QA/QC Department for use to repair

surfaces of damaged concrete.

5) shrinkage cracks shall be grouted with approved non-shrink grout, whereas minor shrinkage

cracks shall be filled with cement slurry. Structural cracks to be grouted with the low viscous high

strength grout.

6) If a structural member requires to be demolished in the opinion of Structural Consultant,

the same shall be enclosed by forms from all sides before demolishing and supported

adequately.

7) All repair works shall be carried out in accordance with the manufacturer’s recommendations as

regards the preparation of surface, cleaning, hacking, applying bonding agents, admixtures, polymer

mortars etc.

Step 11: Guidelines for Acceptance of Finished Product (RCC)


RP INTERIOR PROJECT PVT LTD.

One Bangalore Luxury Project Private Ltd,

Document Title WORK METHOD STATEMENT


Effective
Document Number SROBLP-RPI-GENE-GE-QU-MST-001 Date
31.05.2024
Revision Number 00

NOTES: After removal of shuttering

1) Honeycombs should not be observed

2) No wooden pieces / debris should be observed embedded in RCC

3) Offsets should not be present

4) Deep pockets should not be observed beyond rebar in columns /

beams. For practical purpose Honeycombs should be recorded as:

1) Minor honeycomb – After removal of shuttering, minor aggregates exposed with slurry leakage.

2) Moderate honeycomb – After removal of shuttering, moderate aggregates exposed with slurry

leakage.

You might also like