SSRN 5031370
SSRN 5031370
Through XT
– Lost circulation
– Swabbing
– Underbalanced pressures
Loss of Hydrostatic Pressure
• Hydrostatic pressure is the number one defense against kicks.
• When tripping out of the hole, a volume (of steel) is being removed from the
well.
• As the steel is removed, the fluid level & hydrostatic pressure in the well drops.
• If the hydrostatic pressure drops below the reservoir pressure, the exposed zone
will flow. Therefore it is extremely important to fill the hole with fluid while
tripping out of the hole.
• The volume of fluid needed to fill the well should be equivalent to the volume of
steel (tubing) pulled out of the well.
Losses
• Loss of circulation leads to a drop of both the fluid level and hydrostatic pressure in a well
c. A high pump rate will be required to overcome any losses into the thief zone (S)
d. It may be necessary to use a fluid containing LCM (lost circulation material). Such as sized salt
particles, to stop the losses into the thief zone
e. The circulation system will have to permit pumping down the work string/completion annulus
and the completion/casing annulus at the same time to have enough flow rates to overcome any
losses into the thief zone
Completion Operations
Outlines
I. Overview
II. Introduction to Well Control
III. Introduction to Barriers
IV. Risk Management
V. Circulating System
VI. Testing
VII. Influx Characteristics & Behavior
VIII.Shut In Procedures
IX. Well Control Methods
X. Contingency Planning
• Hydrostatic Pressure:
HP is the pressure developed by column of fluid at given TVD.
“Hydro” means fluid & “static” means stationary. HP is pressure created by
stationary column of fluid.
• Fracture Pressure
Definition: The maximum amount of pressure a formation can
withstand before the formation breaks down as a fracture is
initiated, followed by loss of fluid, also defined as Formation
breakdown pressure.
PRESSURE BASIC & BASIS
1. Fundamentals of Fluids & Pressure
Pressure is defined as Force per unit area exerted by fluid i.e.
Pressure = Force ÷ Area
Using concept, the formula can be changed:
Force = Pressure × Area
Area = Force ÷ Pressure
2. Basic laws of physics concerning fluids & gas
– Liquids are not compressible
– Gases are compressible
– Liquids & gases are both FLUIDS
– Pressure in a fluid is transmitted equally in all directions.
Define
a. Fluid gradient b. Specific gravity c. Hydrostatic pressure
PRESSURE BASIC & BASIS
3. Fresh Water
Fresh water weighs the same per unit volume anywhere in
the world that is why it’s called “Universal Fluid”& used as
STANDARD for comparison with other fluid.
Available Information:
• The tubing/casing annulus is filled with 9.2 ppg brine full.
• The well is S/I at surface with CITHP of 600 psi.
• There is a gas cap of 0.6 SG gas down to 4000 ft fluid level
• 32° API oil from fluid level’ to 12000 ft.
9. Volume
Find annular volume above packer in bbl
of the following well.
3½”, 9.2 ppf Tubing:
9⅝”, 47 ppf Casing:
9750 ft MD (9120 ft TVD) Packer:
= 0.0577 x 9750
= 562.6 bbls
PRESSURE BASIC & BASIS
0 - 1500 3K
1501 - 3500 5K
3501 - 7500 10 K
7501 - 12500 15 K
Well barriers: are envelopes of one or more dependent well barrier elements to
prevent fluids or gases from flowing unintentionally from a formation, into another
formation or back to surface.
Well Barrier Element: is defined as a component part of a well designed to
prevent fluids or gases from flowing unintentionally from a formation, into another
formation or to escape at surface.
Independent barriers: means each barrier shall be able to be closed and contain
the well bore fluids by its own control system irrespective of any power failure.
Overbalance: Greater pressure than formation pressure
Underbalance: Less pressure than formation pressure
Inflow Test: Bleed pressure from above & monitor build-up
Positive Plug: Hold pressure from up & down
• Barrier Theory
Minimum Barrier Requirements
A. A minimum of two independent and tested barriers shall be
available at all times to prevent flow to the environment.
B. As far as possible the barriers should be tested in the
direction of flow of the well.
C. The barriers must be capable of being operated
independently of each other.
D. If one barrier fails it must be possible to put compensatory
measures into effect immediately. During this phase, efforts
to re-establish the barrier and return the well to double
barrier protection, are the only type of work permitted.
E. In principle, tested and approved barriers shall not have a
leak rate greater than 0, before any work is conducted.
F. The owner of the well may accept deviation of the test from
this requirement in certain circumstances.
• A Xmas tree is to be changed out on a production well. A deep-set
positive plug has been set in the tailpipe below the packer. A second
plug will be set in the tubing hanger before the tree can be removed.
What is the correct first action to take before setting the second plug?
a. Inflow test the deep-set plug
b. Pressure up on the tubing to test the deep-set plug.
c. Pressure up on the annulus to test the deep-set plug from
below.
d. If the wellhead pressure is not rising, the second plug can be
run immediately.
• A newly completed well has a sliding sleeve (SSD) just above the
packer. The sleeve has just been closed with the tubing full of diesel
and the annulus full of brine. The tubing is open to the perforation.
How should the SSD be tested to ensure it is closed?
a. Flow the well
b. Pressure up the annulus
c. Bleed down the annulus
d. Bleed down the tubing
• Barrier Envelope:
A "Well Barrier Envelope" is defined as a combination of one
or more Well Barrier Elements that together constitute a
method of containment of fluids within a well that prevents
uncontrolled flow of fluids into another formation, or, to
escape at surface.
“Envelope” is a concept that is utilized in considering a barrier
as part of a total system that involves pressure or fluids.
The barrier itself (e.g. a wireline BOP) will not be of much
help if the complete system is not intact (Xmas tree,
completion string, extension tubing).
Wells in which the oil has to be lifted or pumped out (i.e.
artificial lift pumps, rod pumps) need the same control barriers
as wells in which the oil flows out of its own accord.
Example of Barrier Envelope
PACKER/TUBING ENVELOPE
Barrier elements include:
Casing below Packer
Packer
Tubing
Tubing Hanger
Xmas Tree
Tubing Hanger
Packer
A. Pressure has been observed in the
completion annulus. If the DHSV
is closed and the wellhead pressure
bled off, the annulus pressure falls
with it. A leak at which two barrier
elements could cause this?
The valve used to cut wireline should be UMV for two reasons:
• If the lower master is used and damaged, it requires the well to be
plugged before repair.
• If the swab is used and damaged the well cannot be used for production
as there is no longer double barrier protection from the production fluid.
• Barriers
Sequence of Barrier Operation (Braided Line)
• Barriers
Sequence of Barrier Operation (Braided Line)
A. Primary
• Grease head seal and lubricator system.
• Check valve if the wire breaks and is ejected from the lubricator.
• Xmas tree valves when installing into, or removing tools from, the riser.
B. Secondary
• Two Wireline BOP rams (in conjunction with a grease pump) that can
close and seal around the wire.
• Xmas tree swab valve, if the wire is broken and ejected.
C. Tertiary
• Wireline cutting valve (usually UMV designed for Wire cutting).
• Shear/seal valve or BOP installed directly onto the top of the Xmas tree.
• In general, tertiary barriers are rarely used unless a heavy-duty Wireline
operation is being carried out.
• Barriers
Sequence of Barrier Operation (Coiled Tubing)
• Barriers
Sequence of Barrier Operation (Coiled Tubing)
External pressure control is provided by:
A. Primary
• Stripper.
• Xmas tree valves when installing into, or removing tools from, the riser.
B. Secondary
• BOP.
C. Tertiary
• Shear/seal BOP mounted directly on top of the Xmas tree.
• Barriers
Sequence of Barrier Operation (Coiled Tubing)
Internal pressure control is provided by:
A. Primary
• Two check-valves in the BHA.
• Some well interventions are conducted without BHA check valves as it
is necessary to reverse circulate. In these cases the primary inside well
control is the BOP shear rams and a shear/seal BOP becomes the
secondary.
B. Secondary
• Shear and Blind rams incorporated within the BOP.
C. Tertiary
• Shear/seal BOP mounted directly on top of the Xmas tree.
Barrier Types
1. Mechanical Barrier:
2. Hydrostatic Barrier
Liquids with about 200 psi over balance higher than formation
pressure and lower than Fracture pressure
• Plugs which hold pressure from below - pump through plug (check valves)
• Plugs which hold pressure from above - test plug (standing valve)
• Plugs which hold pressure from both directions (positive plug)
• Plugs which hold pressure to set values - pump out plugs (shear plugs)
You should
• Check that the pressure ratting is correct.
• Check that the contingency exists if solids might settle on the plug top.
• Check that the plug is holding pressure after setting.
Tubing Plugs
1. Blanking Plugs (wire line plugs): run on wire line & set in a
nipple. They seal off in a nipple & hold pressure from both
directions (positive plug). Either one trip or two trips.
2. Pump Open Plug: The inside of the plug shears when pre-
determined pressure is applied from top of the plug (positive plugs
with a limited pressure rating.)
3. Pump Out Plug: Similar in principle to pump open plugs but
shears off & drops down hole
4. Pressure cycle plug: Require pressure above the plug to be
cycled a fixed no. of times before the plug opens.
5. Ice Plug: Wrapping the equipment to be frozen in a coil through
which chemicals like glycol are passed after being cooled to a
predetermined temperature by liquid nitrogen.
6. Bridge Plug: Used to shut-off water producing zones by setting in
casing and capping it with cement (expandable plug).
7. Pump-through Plugs: Hold pressure from below but allow
pumping if the need arises.
8. Back Pressure Valves (one-way or two-way valve): It is a check
valve where fluid can pass through it with 1 psi ∆P and it is set in
tubing hanger threaded profile.
• Barriers
Principles of Fluid barriers
For a fluid to be suitable for use as a barrier, the following conditions
must be satisfied:
• Correct specification
• Testing
• Observation.
Correct specification means that the fluid has the correct specific
gravity.
Testing refers to monitoring the specifications when the fluid is being
weighed and pumped.
Observation means that the well should be monitored for a period in
order to satisfy ourselves that the pumped fluid is stabilizing it.
Simply, we should select the correct kill fluid (weight and
specifications) to minimize formation overpressure & ensure
formation fluid compatibility
Completion Operations
Outlines
I. Overview
II. Introduction to Well Control
III. Introduction to Barriers
IV. Risk Management
V. Circulating System
VI. Testing
VII. Influx Characteristics & Behavior
VIII.Shut In Procedures
IX. Well Control Methods
X. Contingency Planning
• Risk Assessment (All involved parties)
RA process involves:
• Identifying and ranking risk events, developing mitigation options to
minimize probability and severity of outcome, and providing contingency
procedures that can be implemented if the events occur.
• The risk events are then re-ranked assuming that mitigations and
contingencies (M &C) have been applied, which will show whether the
M&C have changed these risks to an acceptable level.
Hydrostatic Barrier
Required to be monitored and maintainable to qualify as a barrier.
Some stable fluids may qualify as a barrier without maintenance ( e.g.
Water)
• Testing Barriers
Documentation of leak and function testing of well barriers
• All well integrity tests shall be documented and accepted by an
authorized person.
• The chart and the test documentation should contain
o type of test,
o test pressure,
o test fluid,
o system or components tested,
o estimated volume of system pressurized,
o volume pumped and bled back,
o time and date.
• A low pressure and high pressure leak test are normally performed for
component that is to be or may be exposed to well pressure. Which one of
the following statement is correct?
a. If no leaks are visible on the equipment, the test is OK.
b. The acceptance criteria should be found in relevant documentation (well program,
API, NORSOK, or manufacturer recommendations).
c. 10% pressure drop is inside the acceptance criteria.
d. 25% pressure drop is inside the acceptance criteria.
e. 5% pressure drop is inside the acceptance criteria.
Completion Operations
Outlines
I. Overview
II. Introduction to Well Control
III. Introduction to Barriers
IV. Risk Management
V. Circulating System
VI. Testing
VII. Influx Characteristics & Behavior
VIII.Shut In Procedures
IX. Well Control Methods
X. Contingency Planning
• Well influx can consist of gas, water, oil, or any combination of these media.
• When shutting in a producing well, there will be rapid increase in pressure displayed
on X/T gauge. Which one of the following is correct?
a. The increase is mainly caused by gas migration.
b. The increase is mainly caused by temperature increase.
c. The increase is mainly caused by cross flow in the reservoir.
d. The increase is mainly caused by temperature decrease.
e. The increase is mainly caused by pressure build-up from the reservoir.
Completion Operations
Outlines
I. Overview
II. Introduction to Well Control
III. Introduction to Barriers
IV. Risk Management
V. Circulating System
VI. Testing
VII. Influx Characteristics & Behavior
VIII.Shut In Procedures
IX. Well Control Methods
X. Contingency Planning
• Shutting-in Xmas Trees
Correct shutting in
During well operations, the local hydraulic pump is connected to
the DHSV and the hydraulically actuated master valve. This
pump must be monitored continuously during the operation.
When valves in the Xmas tree are being opened, we must first
make sure that the pressure across the valves has been equalized.
If we forget to do so, the valve may become “pressure locked”.
When the well is to be shut in, this is done by first closing the
valves on the line in the direction of the X/T; wing, UMV, and
finally the DHSV.
• Shutting-in Xmas Trees
When we open a valve that is pressurized on only one side;
The valve may suffer damage
The valve will suffer a strong hydraulic shock
There will be high probability of pressure lock
The mechanical force required to turn handle can damage or break the stem
The high differential pressure disables the gate movement when opening
The sudden pressure surge on opening can damage piping equipment downstream.
DISADVANTAGES:
• Gas may slip up the tubing if the pump rate is not sufficient for
larger tubing sizes
Method involves pumping kill fluid directly into tubing to force tubing
contents back into formation.
Preferred when reverse circulation is not possible (stuck closed sliding
sleeve or insufficient information is available to calculate a reverse-
circulation kill).
Used only if there is no sand or scale (perforations open)
Used only if it does not causes any appreciable damage to formation (it is
likely to have formation damage)
Cannot be used if there is blockage (stuck plug in tail pipe or severely
collapsed casing above perforations) or tight formation preventing bull
heading.
Note: DHSV with serious leak in control line is not a blockage
Calculation must be made for Max allowable surface pressure and tubing
burst pressure.
Pump rates must be restricted to keep pressure below fracture point.
A live well is to be killed by bull heading. Which of these factors limit
the maximum allowable surface pressure?
a. Completion size.
b. Maximum pump speed.
c. SIWHP.
d. Maximum safe working pressure of the surface equipment.
e. Completion burst limits.
f. DHSV operating pressure.
g. Possible formation fracture.
DISADVANTAGES :
• Gas and oil will mix with the packer fluid due to gravitation
requiring special handling equipment
INITIAL STAGE GAS OUT OIL OUT ANN FULL OF KILL FL KILL FL AT SURFACE
GAS
It is important to install a wire line set plug
OIL
below packer to isolate formation from
PACKER
completion & kill fluid.
KILL
In case plug is not installed, maintain 200 psi
extra pressure from surface through choke.
Q. NO. 1
Find SITHP and SICP at different stages of reverse circulation.
Draw Tubing and Casing pressure graphs.
Tubing Capacity = 0.01458 bbl/ft Annulus Capacity = 0.0252 bbl/ft
Gas = 2000 ft, 0.04 psi/ft Oil = 4000 ft, 0.38 psi/ft
SSD = 6000 ft Pump output = 0.0157 bbl/stroke
Packer fluid = 0.6 psi/ft Kill fluid = 0.5 psi/ft
IN
Formation Pressure = BHP
= 6000x0.6 = 3600 psi
STAGE-4
ANN FULL OF KILL FLUID
Q. NO. 2
The well in the schematic is vertical and has a constant ID/OD. Friction
pressure losses and any fluid losses to the formation are ignored. An
overbalance of 200 psi is held over formation pressure at all times during the
well kill.
Using the following data and reverse circulation kill graph, answer the
questions below. THP = 1965 psi
• Tubing Data :
CHP = 0 psi
Size 3 ½” in KILL = 0.52 psi/ft
Weight 10.3 lbs/ft.
IN
Capacity = 0.0083 bbl/ft BRINE = 0.49 psi/ft
DHSV @ 1800 ft
• Casing Data:
Size 7 in GAS = 0.12 psi/ft
Gas/Oil Contact
Weight 29 lbs/ft
@ 4000 ft
Annulus Capacity = 0.0252 bbl/ft OIL = 0.35 psi/ft
• Gradients
Brine in annulus = 0.49 psi/ft Form Grad = 0.48 psi/ft SSD @ 7450 ft
Kill fluid = 0.52 psi/ft GAS
Gas in tubing = 0.12 psi/ft PACKER @ 7500 ft
OIL
Oil in tubing/casing = 0.35 psi/ft Top of Perf @ 7700 ft BRINE
Formation Gradient = 0.48 psi/ft KILL
Pump out put = 0.0899 bbl/stroke
SITHP = 1965 psi SICHP = 0 psi
Transition from gas to oil = 4000 ft Packer depth = 7500 ft
Sliding Side Door depth = 7450 ft Top of perforation = 7700 ft
FIGURE (A) FIGURE (B) FIGURE (C) FIGURE (D) FIGURE (E)
INITIAL STAGE GAS OUT OIL OUT KILL FLUID HEAVIER ANNULUS FULL
THP = 1965 psi THAN BRINE BY 200 psi OF KILL FLUID
CHP = 0 (Casing pr down from 200 to 0)
KILL = 0.52 psi/ft IN
BRINE = 0.49 psi/ft DHSV @ 1800 ft
GAS = 0.12 psi/ft 200 psi overbalance is held
Gas/Oil Contact
OIL = 0.35 psi/ft @ 4000 ft Kill fluid is heavier than brine
Form Grad = 0.48 psi/ft SSD @ 7450 ft
GAS
PACKER @ 7500 ft
OIL
Top of Perf @ 7700 ft BRINE
KILL
2165 psi (A) TUBING PRESSURE
CASING PRESSURE
Position A B C D E F
Volume pumped (bbls) 0 33 62 170 188 250
GAS
OIL
PACKER
KILL
INITIAL GAS GOING OUT OIL OUT KILL ENTERS TBG KILL AT SURFACE
(A) (B) (D) (E) (F)
DISADVANTAGES:
• Very slow
LUBRICATE & BLEED
ALTERNATE CYCLING
KILL FLUID PUMPED IN
GAS BLED OUT
Circulating device
(closed)
GAS
OIL
PACKER
KILL
• Bleed-off/lubrication
Bleed-off/lubrication is a method that can be used when:
• circulation is impossible (we cannot enter the well as a
result of a restriction)
• Bullheading cannot be employed as it would result in
excessive topside pressures.
Lubrication & Bleeding involves pumping kill fluid into
tubing, allowing it to lubricate down and bleeding gas out
through choke.
The process is repeated several times till gas is out and tubing
pressure becomes 0
Tubing hydrostatic pressure is increased due to pumping kill
fluid and then BHP is maintained by reducing the tubing
pressure through choke.
Since the gas necessarily has to migrate through each injection
of kill fluid sufficient time must be allowed for this to happen
before we bleed off again and inject a new “pill” of kill fluid.
Killing a well by the lubrication method may take several days.
Completion Operations
Outlines
I. Overview
II. Introduction to Well Control
III. Introduction to Barriers
IV. Risk Management
V. Circulating System
VI. Testing
VII. Influx Characteristics & Behavior
VIII.Shut In Procedures
IX. Well Control Methods
X. Contingency Planning
• Surface Problems
1. Bleeding off gas (Joule-Thomson Effect)
When we have flow through a pipe or a valve we may find that the
temperature of the flowing medium is lower than the ambient
temperature. The difference between the ambient temperature and the
temperature of the flow is known as the Joule-Thomson Effect.
When gas pressure falls (through a pipeline or across a valve) the gas
expands and loses energy. If the expansion of the gas takes place with
constant enthalpy (H) where;
H = U (internal energy) + PV (pressure x volume) = constant
some of the energy will manifest itself as a reduction in temperature due
to the lower pressure.
Normally, temperature falls by about half a degree Celsius per bar of
pressure drop, i.e. 100 bar pressure drop will produce a 50 degree fall
in temperature (23 F/ 10 psi)
Bleeding off gas at low temperature, with a large pressure drop and
low outlet pressure may result in brittle fracture in pipelines and other
equipment. Stainless steel may suffer from brittle fracture at
temperatures as “high” as -20 C.
• Surface Problems
2. Blockages in the well
2.1 Blockage mechanisms in wells
• Formation sand (from sand-producing wells)
• Scale
• Mechanical blockages (collapsed casing, jammed valves & downhole strings)
2.2 Removing blockages
• There are normally two ways of doing this: By mechanical methods or By
means of chemicals
• Mechanical methods require the use of intervention equipment such as
wireline, coiled tubing (jarring or milling).
• Chemical methods involve pumping chemicals down to the region of the
restriction. We allow the chemicals to react for a while, and produce them by
the same route up again. In order to prevent the process from becoming
unstable, it may be necessary to add more chemicals at the surface before the
original chemicals enter the process.
The flow rate from a naturally flowing production well has been slowly and steadily
reducing. It has been checked that the tree valves and the DHSV are all fully open. It is
though that there may be a blockage forming in the well bore. What is the first correct
action to take?
• Hydrate Formation
• Hydrate Formation
Conditions under which hydrates form
1. Presence of free water
2. Presence of light gas molecules
3. Relatively high pressure
4. Relatively low temperature.
• True or False?
1. Hydrates are likely to form at emergency blow-down lines.
2. Hydrates are likely to form at pressure relief valves.
3. Hydrates can only form in the presence of free (liquid) water.
4. Hydrates can damage well bore and intervention equipment.
5. Hydrates may cause damage if they become free with a high differential pressure.
6. Injecting brine into the flow stream can reduce the formation of hydrates.
7. Temperature below freezing point of water (0 ◦C) is necessary for hydrates
formation?
8. Hydrates are less likely to form if injecting Glycol
9. For the same pressure, hydrates melt at the same temperature as they formed
10. Hydrates are common downstream of chokes
11. Hydrates will form at low rather than high pressures
• Which of the following measures can prevent or remove hydrates?
a. Rapid bleed-off of gas from the topside system
b. Use of water/glycol mixture during pressure testing
c. Pressure testing up to close-in pressure
d. Raising the temperature of the equipment used
e. Injecting methanol into the equipment.
f. Pull out of the well and fill the topside equipment with diesel oil
g. Check for the presence of external ice in order to locate the hydrates
h. Close BOP, bleed pressure above it, open connection above BOP and remove the hydrates
i. Try to warm up the hydrates using a high-pressure steamer
j. Work the string up and down while you bleed off the surface pressure.
Day 1
Completion Equipment
Outlines
I. Blowout Preventers
II. Completion Equipment
Day 1
• Blowout Preventers
General Blowout Preventer Stack Specifications
New API metal rings are to be used each time a flange is assembled
or a connection is broken. Flange grooves should be well cleaned and
dry.
API RX or BX rings are required. Use of API R rings will not be
permitted.
All preventer packing elements and gaskets are visually inspected at
the time of installation and rejected if they aren't satisfactory
In operating side valves, the inside valves are considered master
valves and would normally never be opened or closed when there is
pressure unless the outside valve is closed.
Preventer assemblies will be dismantled periodically between wells to
inspect for internal erosion or corrosion and to check flange bolts.
All testing shall be done with clear water.
Day 1
Flanges type API 6B Use Sealing Rings API type R or API type RX
Flanges type API 6BX Use Sealing Rings API type BX
• Type RX and BX gaskets provide a pressure energized seal but are not
interchangeable.
• It is recommended that a new gasket be used each time the joint is made up.
Day 1
Type R and RX
6B Flanges Are of The Ring Joint Type and Are Not Designed for Face-to-Face
Makeup. The Connection Makeup Bolting Force Reacts on The Ring Gasket.
6B Flange
Type BX Rings
6BX Flanges Are Designed for Face-to-Face Makeup. The Connection
Makeup Bolting Force Reacts Primarily on the Raised Face of The Flange.
6BX Flange
Day 1
Well Completion
Outlines
I. Blowout Preventers
II. Completion Equipment
Day 1
Choke Tee
Master valve
Casing valve
To production
equipment Tubing head
Casing head
Tubing
Casing
Packer
Perforations
Day 1
• Completion Equipment
Xmas tree
The Xmas tree is an item of safety equipment placed on top of wellhead.
The purpose of the X/T is to control the flow of hydrocarbons from the
well and to allow access to the well during the operational phase. We
call the Xmas tree a safety barrier.
The following valves are normally installed on the Xmas tree:
Manual operated master valve
• This is located closest to the wellhead and is the backup valve for
the Hydraulic master valve (NOT working valve)
• It is normally impossible to cut wire lines with manually operated
valves. The torque required would be so high that parts of the valve
would be destroyed before the wireline was cut.
Hydraulic operated master valve
• This is located above the Manual master valve. It is hydraulically
actuated (from the platform control room) and is “fail-safe closed”. In
the case of a hydraulic leak, the valve will revert to its closed
condition
Choke Valve
• Restrict, control or regulate flow of well fluids.
Day 1
• Completion Equipment
Xmas tree
The following valves are normally installed on the Xmas tree:
Hydraulic operated wing valve
• This is the “last” valve in the Xmas tree before the well-flow enters
the flow line to the choke valve/process system. This valve is
normally “fail-safe closed”.
Swab valve/ Crown Valve
• This is a manual valve that stands at the top of the Xmas tree
under the “tree cap” (also known as the “lubricator adaptor”).
• This valve must be opened in the case of well intervention.
• On the outside of the swab valve we often find a cup that should
be fitted with a needle valve so that any pressure on the other
side can be checked using a pressure gauge and bled off trapped
pressure before it is opened.
Kill valve
• This valve is located next to the wing valve and is used during
pumping and production or injection via neighboring wells. This
valve is normally also fitted with a cup and “needle valve”.
Day 1
• This counts as a
barrier in most
operations
(production, pumping,
wire line).
• Completion Equipment
Wellheads
The wellhead provides the following functions:
• Anchoring/connections for each individual casing
• Pressure isolation of individual casings
• Connections for Xmas tree
• Connections for completion string
• Isolation of production annulus
• Access to annulus for pressure monitoring and/or pumping.
Conventional
Day 1 Wellhead Features:
1. Starter Spool (Conductor Pipe)
2. Surface Casing Head
3. Surface Casing Hanger
4. Production Casing Head
5. Production Casing Hanger
6. Tubing Head
7. Tubing Hanger
Day 1
• Completion Equipment
Tubing Hanger
Functions
• It is set in Tubing Head Spool to transfers (support) the weight of
the top completion string to the wellhead
• It prevents annulus pressure from leaking past the tubing hanger
to X/T or out to atmosphere or sea, or vice-versa).
• It is BPV receptacle as it allows an internal plug to be installed
• It provides a seal around hydraulic and electrical control lines.
Day 1
Day 1
Day 1
Day 1
Well Completion
Well Completion design is dictated by the type of well to be
completed.
1. Producer
2. Injector
Flow Coupling
1. Anchoring Device SCSSV Landing Nipple
• Landing Nipples
2. Circulation Device Top No-Go Nipple
• SSD
• SPM SPM
3. Isolation Device
Top No-Go Nipple
• Packer (between top & bottom completion)
• Tubing Seal Assembly, PBR SSD
Top Packer
4. Anti-Erosion Device
• Blast Joint SSD
• Flow Coupling
Producing Zone 2 Blast Joint
5. Others
• WLEG Btm Packer
• Perforated Joint Bottom No-Go Nipple
• Control Line Perforated Joint
• Tubing Hanger WL Entry Guide
Producing Zone 1
• Completion Equipment
Down Hole Safety Valve
Close the well in an emergency
Downhole safety valves (DHSVs) are installed in the well in order to
prevent blowouts if:
• the topside Xmas tree becomes damaged (e.g. by collision with a crane lift)
• surface equipment is sabotaged
• a neighboring well suffers a blow-out (in order to prevent a domino effect)
• drilling collision from neighboring well.
They are set below the depth where they can be damaged by surface
impact explosion
Such valves are of the “Fail-safe Closed” type. If hydraulic pressure to
the valve is lost, it will immediately close.
These valves can also be pumped through from the surface even when
they are closed.
Such valves open and close by effect of pressure. There exist two
closure mechanisms:
1. Flapper valves
2. Ball-valves.
Day 1
• Completion Equipment
Down Hole Safety Valve
Internationally, the DHSV is not regarded as a well control barrier. This is
because API permits a certain amount of leakage through the DHSV 3.6 BPD
liquid . Some countries regard DHSV as a barrier after an approved inflow test
which verifies that leakage rates are not exceeding 3.6 BPD.
They can be divided into two categories :
1. SSCSSSV (Sub-Surface Controlled Sub-Surface Safety Valve)
2. SCSSSV (Surface Controlled Sub-Surface Safety Valve)
SVLN Lock-Out
Lock
Mandrel Mechanism
Packing
Profile
Packing
Piston
CL Port
Piston
Flow Tube
Seal Bore
Spring
Spring
Flow Tube
Flapper Flapper
Day 1
SSSV
• Pressure Theory
Surface • Flapper & Ball Sub-surface
controlled Mechanisms controlled
Tubing Wireline
Differential Ambient
Retrievable Retrievable
SCSSSV
Day 1
Day 1
Day 1
• When a Tubing retrievable DHSV is run into the well we need to
lock it open
a. False
b. True
• Completion Equipment
Down Hole Safety Valves
Annulus safety valve
• Some countries require annulus safety valves to be installed in
gas-lift wells on fixed installations.
• The idea is the same as for DHSVs, i.e. to prevent an
uncontrolled reverse backflow of gas from the annulus, if any of
the wellhead and/or Xmas tree equipment should be damaged.
Day 1
Landing Nipples
• Used to receive flow control devices
• Short tubular with 3 main features; Shoulder, Seal Bores,
and Profiles. It can accommodate and secure a locking
device called a lock mandrel run usually using wireline
well intervention equipment.
• Types
Selective
Non-selective or no-go
Day 1
Day 1
Day 1
Selective Nipples
Main advantage is that all seal bores
are the same size.
No tapering of tubing size.
• Completion Equipment
Circulation Equipment
The term “circulation equipment” refers to the following items:
• Side Pocket Mandrels (SPM)
• Sliding sleeves
• Nipples with port(s)/sleeves
Circulation equipment is employed to:
• Provide gas-lift (SPM with gas-lift valves)
• Create an under-balance in the well in advance of perforation
(SPM, sliding sleeve and nipple)
• Kill the well (SPM, sliding sleeve and nipple).
Day 1
• Completion Equipment
Circulation Equipment
Side Pocket Mandrels
• SPMs are used either for gas-lift purposes or for temporary
communication between the annulus and the completion string (to
create an under-balance in the well, to kill the well, etc.).
• An important point to remember before plugs or valves in the
SPM can be pulled is to equalize the pressure across the GLV.
• Equipment that can be located in side pockets:
o Circulation or orifice valve
o Injection valve
o Pressure and temperature sensors
o Plug (dummy valve)
o Gas-lift valve.
Day 1
Side Pocket Mandrel
• Gas Lift Valves (Nitrogen charged or spring loaded)
− Different designs are available. They may be orifice valves or pressure operated type
valves.
− They all contain a check valve to prevent tubing to Annulus flow These check valves
may leak with time and should not be considered as well control barriers.
• Dummy Valves
− These valves can be installed in SPM for the purpose of tubing & casing isolation.
They also facilitate pressure testing from both tubing & annulus.
− It is also possible to leave the valve in the side pocket mandrel for continued
circulation. This is accomplished by shearing down on the inner core with a special
tool.
• Completion Equipment
Circulation Equipment
Sliding sleeves
• Sliding sleeves can also be used for gas lift purposes.
• A sliding sleeve consists of a movable inner sleeve with ports and
a fixed outer part. We can move the inner sleeve up and down
with the aid of a shifting tool which is run on a wireline or CT.
• SSD is normally positioned
1. Immediately above the top production packer
2. Between 2 packers
• You should
1. Check that the SSD is fully open before starting circulation
2. Check that the pressures across the SSD are equalized before
opening
SSD
Day 1
• Completion Equipment
Production Packers (Isolation Device)
packer is used to provide a seal between the casing and the tubing
in a well.
Packers are installed just above the top perforation
The purpose of using a packer in a well completion is:
• To isolate the casing from reservoir fluids (provide seal between the
tubing & completion annulus)
• To protect the casing from the effects of flowing pressures by
isolating the annulus above the packer from casing below packer &
tubing
• To isolate various producing zones.
• Packers can be used as service tools to perform acid/fracture jobs
In general, packers are constructed of hardened slips, which are
forced to bite into the casing wall to prevent upward or downward
movement while a system of rubberized elements contact the
casing wall to effect a seal.
Day 1
• Completion Equipment
Production Packers
Retrievable Production Packers
• Are run on the tubing string and may be set mechanically or
hydraulically.
• Can be retrieved with completion string or with special pulling tool on
drill pipe
Permanent Production Packers
• These may be run in a variety of ways and become an integral part of
the casing once set but can only be retrieved by milling
• A permanent packer may be run as follows:
o on electric wireline
o on pipe and set hydraulically by application of pipe pressure.
o latched onto the completion tubing and hydraulically set by the
application of tubing pressure.
Day 1
Day 1
• Completion Equipment
Re-entry Guide
A re-entry guide generally takes one of two forms:
• Bell guide
• Mule shoe.
The bell guide has a 45° lead in taper to allow easy re-entry
into the tubing of well intervention tool strings (i.e., wireline or
coiled tubing).
The mule shoe guide is essentially the same as the bell guide
with the exception of a large 45° shoulder.
Day 1
Perforated Joint
Anti-Erosion Device
Blast Joint
• Heavy-walled tubular.
• Installed opposite perforations
where abrasive action &
external cutting occurs caused
by formation fluids or sand.
Flow Coupling
• Heavy-walled tubular.
• Installed down stream FCD
which caused turbulence e.g.
Nipple, SSD, SCSSV.
• High velocity & high pressures
wells installed both up-stream &
down-stream.
Day 1
Wire Line
Outlines
I. Introduction to Wireline
II. Typical Slickline Rig up
III. Typical Braided Line Rig up
IV. Managing A Leak or Malfunction on Surface
V. Operational Considerations
Day 1
• SLICKLINE
Single strand wire with wire OD range from 0.105”, 0.108”,
0.125” & 0.190 (0.092”, 0.082”, 0.072” & 0.066”).
• BRAIDEDLINE
Multi-strands wire cable OD range from 3⁄16”, 7⁄32”, ¼” & 5 ⁄16”.
Application:
– Retrieval of downhole tools with slick line failure.
– Fishing job
• ELECTRICLINE
Multi-strands wire cable range from 3⁄16”, 7⁄32”, ¼” & 5 ⁄16”,
7⁄16” & ¾” OD with single (mono) or multiple conductors.
Application;
– SRO Pressure & Temperature Recorder
– SRO Electronic Logging Instrument for open hole & cased hole.
– Packer setting
– Perforations etc.
Day 1
• WIRELINE EQUIPMENT
1 Surface Equipment
1.1 WL Unit
1.2 Power Pack
1.3 Hoisting Unit
Optional PCE
2 PCE
2.6 Tool Trap
2.1 Quick Union
2.7 Tool Catcher
2.2 Stuffing Box / GIH
2.8 Injection Sub
2.3 Lubricator
2.8 SCU SAFETY CHECK UNION
2.4 BOP
2.9 Pumping Tee
2.5 Tree Adapter
3 Subsurface Equipment (SSE)
3.6 Shifting Tool
3.1 Toolstring
3.7 Kick Over Tool
3.2 Service Tools
3.8 Overshot
3.3 Tubing Conditioning Tools
3.9 Spear
3.4 Running Tools
3.10 Flow Control
3.5 Pulling Tools Device
Day 1
Wire Line
Outlines
I. Introduction to Wireline
II. Typical Slickline Rig up
III. Typical Braided Line Rig up
IV. Managing A Leak or Malfunction on Surface
V. Operational Considerations
Day 1
Day 1
Day 1
Day 1
Day 1
PCE - LUBRICATOR
Manual BOP
Day 1
Day 1
Slickline PCE
Stuffing Box
Stuffing Box
Lubricator
Lubricator
SLICKLINE FISHING
SLICKLINE OPERATION OPERATION
Blind Ram
Blind Ram Blind Ram
Dual Drum
Day 1
Wire Line
Outlines
I. Introduction to Wireline
II. Typical Slickline Rig up
III. Typical Braided Line Rig up
IV. Managing A Leak or Malfunction on Surface
V. Operational Considerations
Day 1
Day 1
Day 1
S
Z
Day 1
Day 1
Day 1
SCU
Grease Pump
BOP
Flow Tube
Flow Tube, Flow Tube
Cable & & Cable
Grease GIH GREASE SYSTEM
Day 1
Day 1
Day 1
BRAIDEDLINE PCE
GIH
PRIMARY BARRIER
SCU
Lubricator
SECONDARY BARRIER
1 1 Braidedline Ram
2 2 Braidedline Inverted Ram
3
4 3 Blind Ram
4 Shear Ram
Wire Line
Outlines
I. Introduction to Wireline
II. Typical Slickline Rig up
III. Typical Braided Line Rig up
IV. Managing A Leak or Malfunction on Surface
V. Operational Considerations
Day 1
Wire Line
Outlines
I. Introduction to Wireline
II. Typical Slickline Rig up
III. Typical Braided Line Rig up
IV. Operation Planning
V. Managing A Leak or Malfunction on Surface
VI. Operational Considerations
Day 1
• Operational Considerations
Lubricator
When conducting wire line operations on gas wells or high
GOR oil wells it is important that the fluid used to pressure test
the lubricator is inhibited, to prevent the formation of hydrate
plugs around the wellhead. Typically, a mixture of glycol and
water is used.
Prior to opening X/T valves it is important that lubricator is
approximately equal to or slightly above, the SIWHP. This is to:
• Reduce the chance of damaging the valve seals when opening.
• Reduce the chance of differential surges damaging the tool or
wire.
When RIH the tree valve opening sequence should be
1. Hydraulic master valve (HMV)
2. Swab valve
So that the HMV does not have a differential pressure across it when
opening, when pulling out the shut-in sequence should be:
1. Swab valve (Check the correct number of turns )
2. HMV
Day 1
• Operational Considerations
The Stuffing Box
During slick line operations, the stuffing box needs to provide a
leak tight seal around the wire while still allowing the wire to
move.
However the stuffing box should not be over tightened, since:
• This causes excessive packing wear
• More weight needs to be used to overcome the extra friction
• The extra weight brings line tensions closer to limits
• The tool string is lengthened, requiring a longer lubricator.
On high wellhead pressure wells, note that extra stem is
required not only to overcome the extra upwards force on the
cable, but to overcome the extra stuffing box friction.
Day 1
• Operational Considerations
DHSV And Tree Valve Control
During wire line operations, the normal tree valve control
system is overridden and operation of the valves is achieved
through a separate bypass control unit.
This ensures that valves are not accidentally closed by the
process control ESDs, etc. while wire line is in the hole.
This unit should not be placed in the well bay area, unless it is
permanently manned by someone in adequate communication
with the wire line operator/supervisor.
When conducting W/L operations below the DHSV, the control
line can be closed in at the X/T, to lock in pressure, ensuring
that the valve can’t be accidentally closed on the cable.
Removing a DHSV can permit the well fluids access to the CL.
In the case of unexpected pressure in the well, a build-up can
escape via this line. This can cause:
• External leaks
• Pressurization of components & hydraulic oil reservoirs beyond
their rating.
Day 1
• Operational Considerations
DHSV Protection
If the well contains a wire line retrievable DHSV, the valve may
have to be pulled in order to provide access for the tool string.
Protection sleeves are available for setting in the DHSV landing
nipple that prevent damage of the seal bore by wire line cutting.
When wire line is in the well in the hole below the DHSV, it is
not normally considered to be a barrier, whether or not it is
capable of cutting the wire.
Day 1
• Operational Considerations
Tool String Weight
The weight of the tool string should be increased to:
• Overcome sealing assembly friction and well pressure on the
cross-sectional area of the wire line
• Ensure sufficient weight to provide required jarring force.
• Ensure sufficient weight to keep tool string stationary if flowing the
well for logging purposes.
Adjusting the tool string weight is simply achieved by adding or
removing lengths of stem. However there are limits to the
amount of weight that can be added because of:
• Tool length limit
• Lubricator length limit.
• Down hole pick-up weight constraints (cable strength limit).
Day 1
• Operational Considerations
Flowing Wells
Flowing the well with tools in the hole is carried out when
• Production logging (braided line)
• Pressure / temperature gradient / MPLT surveys (slick line).
To prevent the tools from being carried up the hole by the force of
the wellbore fluid, with the potential for the tools stuck;
• Ensure sufficient tool string weight
• Open well slowly, after positioning tool string below the fluid level
When conducting slick line logging it is sometimes difficult to
detect a loss in weight. With braided line the tool position can be
monitored by means of the CCL.
When pulling plugs, etc. it is important to ensure that the device
is equalized, i.e. has the same pressure above and below.
If the pressure above is too high, it may be impossible to pull the
prong/device, perhaps eventually leading to a broken wire.
If the pressure below is too high, the surge may cause the
prong/device to be blown up the well, also leading to tangling and
possibly broken wire.
Day 1
Day 1
Coiled Tubing
Outlines
I. Coiled Tubing Description
II. Description of Fatigue
III. Pressure Control Equipment
IV. BOP Test Procedures
V. General Rig Up Procedures
VI. Contingencies
Day 1
CT EQUIPMENT
Day 1
Day 1
Tubing Injector Head
The injector head is mounted above
the BOPs and stripper and drives the
tubing to be run into and out of the well
under pressure.
Profile Gripper Blocks: hydraulic
adjustable friction grips CT without
slippage & crimp CT.
Hydraulic Drive Chains: 2 hydraulic
unison motors drive chains & disk
brakes to hold CT weight in stationary
position.
Face-to-face Gripper Block backed by
hydraulic force Skate Profile grip CT in
motion or stationary position.
Accumulator compensate CT OD
abnormalities.
Day 1
Day 1
Day 1
Tubing Guide Arch (Gooseneck)
Coiled Tubing
Outlines
I. Coiled Tubing Description
II. Description of Fatigue
III. Pressure Control Equipment
IV. BOP Test Procedures
V. General Rig Up Procedures
VI. Contingencies
Day 1
Day 1
Day 1
Day 1
• Beyond this minimum bending radius the steel will be stressed beyond
its elastic strain limit.
• When coiled tubing is initially spooled plastic deformation will take place.
Day 1
• Description of Fatigue
The Coiled Tubing is subjected to repeated bending and
straightening events, commonly referred to as bend-cycling.
Bend cycling Coiled Tubing with internal pressure loading
dramatically reduces the fatigue life of the pipe.
A given bend-cycle load applied later in the tube working life
causes greater fatigue damage than the equivalent bend-cycle
load applied earlier in the tube working life.
For predicting the fatigue condition of the coiled tubing, use;
• Running Feet Method
• Trip or empirical method
• Theoretical method
The working life of the Coiled Tubing can be extended by
• increasing the bend radii of the tubing guide arch and reel core.
• selecting a tube with a thicker wall.
• increasing the material yield strength of the tube.
• Decrease OD size of the Coiled Tubing.
• Apply lower pumping pressures
Day 1
Coiled Tubing
Outlines
I. Coiled Tubing Description
II. Description of Fatigue
III. Pressure Control Equipment
IV. BOP Test Procedures
V. General Rig Up Procedures
VI. Contingencies
Day 1
Stripper CT EQUIPMENT
Pressure containment device – Primary Barrier in well
control system.
Installed above BOP & below IH.
Dual assembly used for extreme well conditions.
Hydraulic activation from Control Cabin.
Can be redressed during operation with pressure
isolated
1. Conventional Stripper
2. Tandem Stripper
3. Side Door Stripper
4. Radial Stripper
Day 1
Conventional Stripper
Day 1
ANNULAR
BOP SHEAR/SEAL BOP
Day 1
CT ANNULAR PREVENTER
Piston indicator hole
Wear Plate
Element Segment
Packing Element
Latching head
Opening chamber
piston
Closing Chamber
Piston Seals
Wear sleeve
• Seal
Day 1
with tubing or without tubing.
• When there is a need to seal around tools which have
a different outside diameter than the CT
• Essential precautions should be taken when
stripping through an annular BOP
Head
1. Closely monitor annular operating pressure and
weight indicator reading
2. Consult fishing (dimensional) diagram of BHA
Element
Piston
Body
Day 1
Coiled Tubing
Outlines
I. Coiled Tubing Description
II. Description of Fatigue
III. Pressure Control Equipment
IV. BOP Test Procedures
V. General Rig Up Procedures
VI. Contingencies
Day 1
Fill up the riser and BOP via the test line to the tree valve. Close the blind
rams. Increase pressure in 500 psi increments to maximum and hold for
the prescribed time. Record on a chart.
Day 1
• Fill the coiled tubing reel with test water from the cement unit. Displace at least
twice the tubing volume. During this circulation a pig and stainless steel ball can
be used
• Attach the coiled tubing tools & close the test cap and pressure up in 500 psi
increments.
• Hold stabilized pressure for the prescribed time. Record on a chart.
• The end of the string should be as close to deck as possible.
Day 1
Coiled Tubing
Outlines
I. Coiled Tubing Description
II. Description of Fatigue
III. Pressure Control Equipment
IV. BOP Test Procedures
V. General Rig Up Procedures
VI. Contingencies
Day 1
• Rings should be used one time
only, then discarded. Install rings
in clean, dry grooves only.
• The rig up to the Xmas tree should
be a flange to flange, or flange to
Bowen type connection. Do not
use threaded connections
between the BOPs and tree.
Day 1 Low Pressure High Pressure
Day 1
Coiled Tubing
Outlines
I. Coiled Tubing Description
II. Description of Fatigue
III. Critical Control and Monitoring Equipment
IV. Pressure Control Equipment
V. BOP Test Procedures
VI. General Rig Up Procedures
VII. Contingencies
Day 1
• Contingencies
Holes In Tubing
Possible solutions depend on the severity of the hole, and what
types of fluids are being pumped.
Depending on the length, pressure, integrity of the tubing (i.e. if
a pinhole exists), and whether any hazardous fluids are in use,
the hole in the tubing should be run back into the well between
the stripper and pipe ram and the well killed.
If a circulating spool is provided below the stack, close the slip
and pipe ram and then kill the well. Once killed, the pipe can be
safely pulled from the well.
If the fluid is not hazardous, if the hole is small, and if the hole
in the tubing can be safely spooled onto the reel, this will
effectively stop the leak. The tubing may then be pulled from
the well if the supervisor deems that is it safe to continue.
Day 1
• Contingencies
Tubing Parts
Should the coil parts downhole, the operator should be aware
of a sudden change in pressure and/or a sudden loss of
weight.
By continuing to pump fluid down the pipe to prevent wellbore
fluids from coming up the pipe, by estimating the length of pipe
lost and by careful and regular checking when near the
surface, the pipe can be safely pulled out of the hole.
When near surface, SV can be gently closed (counting turns)
every few ft. to check whether the pipe is still across the valve.
If the pipe parts on surface, there are check valves that stop
wellbore fluids from escaping. If also failed, close the slip and
pipe rams, shear the pipe with the cutter rams, pull pipe from
stack, and close the blind rams. The well must be killed
If the tubing parts downhole, pull tubing in well above the blind
ram, and close the blind ram. The well should be killed using
the proper method (i.e. Bullhead or Volumetric).
After the well has been killed, the tubing can be fished.
Day 1
• Contingencies
Leaks
If a leak develops in a BOP, tool lubricator, crossover, spool, or
any component above the tree, then attempts should be made
to stop the leak. If the leak cannot be stopped, then the well
should be killed.
If the leak starts accelerating, or becomes too critical while
attempting the kill, the decision may be made to cut CT& then
the swab or master valves closed (count turns).
If leaks develop in stripper or stuffing box, close pipe rams and
replace packing element.
If the leak develops in a lubricator or connection, close the pipe
ram and try to stop the leak. If this does not stop the leak, the
well should be killed and the leak repaired, or the tubing
stripped out of the well, the crown or master valves closed and
the leak repaired.
Day 1
• Contingencies
Stuck Coiled Tubing
The pipe is said to be stuck when the pull required is greater than 80%
of pipe yield strength.
Some of the more common ways of sticking are:
• Settled solids around the pipe during washing operations.
• Obstruction in the well.
• Increased friction drag. (Pumping friction reducers around CT outside).
• Differential stuck or Mechanical stuck when it hangs on anything downhole.
If the pipe is stuck and you can circulate, try pumping friction-reducing
fluids, one of the pump cylinders should be crippled. If this doesn’t work,
spot a heavier fluid around the stuck point back to surface to increase
the pipe’s buoyancy. If the pipe remains stuck, work the pipe pulling
minimum tensile.
If the pipe is stuck and you cannot circulate, apply maximum pressure to
tubing to try to hydraulically jack the tubing free or drop the ball and
release the BHA.
If the pipe cannot be freed by any of the above techniques, the free point
must be determined and use a chemical cutter run of wireline.
If the well is under pressure, the well should be killed prior to cutting the
tubing.
Day 1
• Contingencies
Runaway Tubing
This is the condition where the pipe is moving faster than the operator can
control. It can occur when running in or pulling out.
It is usually caused by the drive blocks loosing their grip on the pipe. In
high pressure wells the pipe may be ejected whilst in low pressure wells
the pipe may run in.
The operator should be able to stop the pipe from continuing to be ejected
by increasing the stripper operating pressure to maximum and closing the
slip rams.
The operator should be able to stop the pipe from continuing to be
injected by stopping injection and increasing the inside tension. Increasing
the stripper operating pressure to maximum also creates more friction.
Depending on company policy, applying reel brakes
However, it should be realized that these options may cause sudden
failure of the tubing.
Day 1
• Contingencies
Power Pack Failure
The failure of a power pack during operations should not cause
a well control problem.
All functions on the unit are fail safe or there are manual locks
and brakes that can be applied.
The BOP do not require the power pack running to operate them
because they use, as with any BOP system, stored pressure in
an accumulator.
In the event of a power pack failure:
• Engage injector brake
• Close pipe rams and manually lock
• Close manual stems on pipe and slip rams as back-up
• Apply the reel brake if it is not fail-safe applied
• While maintaining circulation (if possible), repair or replace power
pack
• Equalize pressure across pipe rams and open pipe and slip rams
• Release injector brake
• Re-commence coiled tubing operations.
Day 1
• Contingencies
Coiled Tubing Pinhole
If the pinhole is above the stripper, the leak will be very visible.
There are check valves at the bottom of the pipe that should
stop wellbore fluids from exiting the well via the pinhole.
If the check valves are not holding the individual circumstances
of the problem will determine the steps to be taken. This might
well involve closing the BOPs, cutting the pipe, killing the well
and fishing the pipe.
Check Valve Failure
If the check valves are no longer holding, by continuing to
pump fluid down the pipe it is often possible to POOH to
replace the check valves.
This can depend on the work being performed and the
pressures involved. It may prove necessary to kill the well
before pulling out.