Bill 01
Bill 01
1.0 PRELMINARIES:
1.1 P(01) Mobilization and demobilization L.S. item
1.2 119(1) Provide all necessary Insurancee L.S. item
1.3 119(2) Provide all necessary Bonds L.S. item
1.4 103(1) Traffic safety and control Months 6.00
Surveying, levelling and submission of CS and LS
1.5 103(1) drawings as per Engineer's instruction. Km 4.00
1.6 Allow for quality control special tests PS item
EARTH WORKS AND CORRECTIONS TO EXISTING
2.0 SURFACE
2.1 Scarifging Road Surface 50mm Depth Sq.m 12,700.00
2.2 Excavation of soil for road widening Cu.m 840.00
3.0 CONSTRUCTION OF BASE:
Trimming, levelling and compaction of Dense
3.1 ground to 100% standard density Sq.m 5,600.00
200,000.00
300,000.00
650,000.00
200,000.00 1,200,000.00
150,000.00 600,000.00
300,000.00
3,250,000.00
28.00 355,600.00
495.00 415,800.00
771,400.00
83.00 464,800.00
4,895.00 17,548,575.00
-
-
18,013,375.00
-
143.00 2,616,900.00
83.00 1,518,900.00
16,000.00 35,872,000.00
40,007,800.00
1,815.00 65,340.00
1,815.00 1,426,590.00
1,491,930.00
27,500.00
110,000.00
27,500.00
27,500.00
715.00 117,975.00
13,530.00 172,507.50
1,100.00 156,200.00
17,050.00 1,364,000.00
1,430.00 1,072,500.00
13,530.00 3,247,200.00
1,650.00 293,700.00
2,200.00 69,696.00
4,400.00 660,000.00
17,050.00 426,250.00
176.00 501,600.00
176.00 264,000.00
110.00 71,500.00
1,430.00 214,500.00
8,824,128.50
3,250,000.00
771,400.00
18,013,375.00
40,007,800.00
1,491,930.00
8,824,128.50
72,358,633.50
82,488,842.19
ISURU ENGINEERING (PTE) LTD.
CIVIL, ELECTRICAL, MECHANICAL ENGINEERS & CONTRACTORS
No. 983, Pannipitiya Rd, Tel : +94-11-2787739/40/41/42/44
Fax : +94-11-2787747
RU ENGINEERING Battaramulla. (PTE) LTD.
INTERIM
, ELECTRICAL, MECHANICAL ENGINEERS & CONTRACTORS. PAYMENT APPLICATION
Place, Colombo - 7. Tel : +94-11-2676311 Fax : +94 – 11 - 2687706.
WIDENING AND IMPROVEMENTS TO ALUTHGAMA-
Project VEGODAROAD (5+000-8+050)KM
Bill No. : 03
- #REF! #REF!
Site QS (IEL)
Date : …...………………...……………
Date : …...………………...……………
5
PEAK ENGINEERING (PVT) LTD.
No. 9 4/2, Station Rd, Tel : +1112 553323
Bambalapitiya INTERIM PAYMENT APPLICATION
D).
- ### ###
Date : …...………………...……………
Date : …...………………...……………
6
WIDENING AND IMPROVEMENTS TO DANOWITA- MEERIGAMA (4+000-8+610)KM
-
Bill no 01
01 - ### ###
02
03
04
05
06
7
SUMMARY OF VARIATION
TOTAL 210,959.96 -
Thambi Residencies at No 40, [Link] Road, Col -06
IPC NO:01
Amount Remarks
ITEM DESCRIPTION
UNIT QTY. RATE Previous Current Cumulative
Transporting and mobilization of equipment and personnel to
1 Item 1 2,000,000.00 - 2,000,000.00 2,000,000.00
the site for pilling work
Bore throught any material met with , except hard rpck- Avg
2
depth 25m
…………………………………..
CONTRACTOR REPRESENTATIVE
0
-
IPC NO:01
BILL N
2.0 WIDENING & RECTICATION OF CARRIAGEWAY
AS PER ORIGINAL BOQ Previous Current Cumulative
ITEM DESCRIPTION
UNIT QTY. RATE Amount QTY Amount QTY Amount QTY Amount
Supplying,spreading &
2.1 Compacting approve soil m3 1,500.00 1,417.00 2,125,500.00 - - - -
including transport
………………………………….. …………………………………….
CONTRACTOR REPRESENTATIVE CONSULTANT ENGINEER
0
-
IPC NO:01
3.0 OVERLAYING WEARING COURSE
BILL No
AS PER ORIGINAL BOQ Previous Current Cumulative Excee
ITEM DESCRIPTION d
UNIT QTY. RATE Amount QTY Amount QTY Amount QTY Amount QTY
Tack coat using emulsion
3.1 CSS - 1 @ of 0.5 ltr./sq.m m2 23,050.00 82.00 1,890,100.00 - - - -
including transport
………………………………….. …………………………………….
………………………………….. …………………………………….
5.2 Coffer damming using sand bags item 654,000.00 0.25 163,500.00 - 0.25 163,500.00
5.3 Dewartering using water pump 2" item 163,500.00 0.25 40,875.00 - 0.25 40,875.00
5.4 Testing soil and concrete item 109,000.00 0.25 27,250.00 - 0.25 27,250.00
5.5 Excavation in medium soil m3 330.00 709.00 233,970.00 4.37 3,098.33 - 4.37 3,098.33
5.17 Curing of deck slab of culvert m2/days 1,590.40 109.00 173,353.60 6.45 703.05 - 6.45 703.05
………………………………….. ……………………………………. -
CONTRACTOR REPRESENTATIVE CONSULTANT ENGINEER -
0
-
IPC NO:01
BILL No.6.0 ROAD MARKING
………………………………….. …………………………………….
CONTRACTOR REPRESENTATIVE CONSULTANT ENGINEER
IMPROVEMENT TO APPROACH ROAD TO THE 5th RECONNAISANCE REGIMENT OF SRI LANKA ARMY AT PANGOLLA (0+000-4+600 Km)
ITEM DESCRIPTION QTY UNIT RATE AMOUNT Qty PRIVIOUS Qty THIS Qty CUMILATIVE REMARKS
Labour Cost
Work Item : Fabricate and Fixing Handrail for sides in Culvert (17.3 m)
Assumed Quantity 1 nos
2
Tack coat with emulsion CSS-1 at
the rate of 0.5ltr/sq.m including
brushing,cleaning road surface
384.00 4.60 1,766.40
360.00 2.75 990.00 2,756.40 m2
Name…………………………………………….. Name………………………………...…..………….
Designation………………...……...………… Designation………….…………….……...………
Page 20 of 90
Date………………………………….………...…. Date………………………………….……………….
Page 21 of 90
MEASURMENT SHEET
IMPROVEMENT TO APPROACH ROAD TO THE 5th RECONNAISANCE REGIMENT OF SRI LANKA ARMY
AT PANGOLLA (0+000-4+600 Km)
3
Asphalt concrete surfacing with
wearing course (40mm compacted
thickness)
384.00 4.60 0.04 70.66
360.00 2.75 0.04 39.60 110.26 m3
Asphalt Density= 2.35 ton/m3
ASPHALT QTY 259.102 Ton
Name…………………………………………….. Name………………………………...…..………….
Designation………………...……...………… Designation………….…………….……...………
Page 22 of 90
Date………………………………….………...…. Date………………………………….……………….
Page 23 of 90
IMPROVEMENT TO APPROACH ROAD TO THE 5th RECONNAISANCE REGIMENT OF SRI LANKA ARMY AT PANGOLLA
(0+000-4+600 Km)
Road Contract Package - DEYATA KIRULA 2014 Annex -16
Contract No RDA/DW/NWP/GOSL/2013/170
Rate Analysis for Construction pipe culvert
Work Item : Removing ByPass Road & Water Bypass and Disposal unsuitable material from site
Assumed Quantity 1 item
Labour Cost
IPC NO:3
Measurement Sheet
Contract No : RDA/DW/WP/GOSL/2013/180 No : /MS/
Date : 5/8/2014
Bill Item : 2.2 Distribution (COPIES)
Description:-Excavation of soil for road widening 1. File
2. Engineer
3. Contractor
Avg :
Side Description T width Width H Qty Total Unit
LHS
5+015 5+740 Prervious Claim 54.230
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : RDA/DW/WP/GOSL/2013/180 No : /MS/
Date : 5/8/2014
Bill Item : 2.2 Distribution (COPIES)
Description:-Excavation of soil for road widening 1. File
2. Engineer
3. Contractor
Avg :
Side Description T width Width H Qty Total Unit
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : RDA/DW/WP/GOSL/2013/180 No : /MS/
Date : 5/8/2014
Bill Item : 2.2 Distribution (COPIES)
Description:-Excavation of soil for road widening 1. File
2. Engineer
3. Contractor
Avg :
Side Description T width Width H Qty Total Unit
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : RDA/DW/WP/GOSL/2013/180 No : /MS/
Date : 5/8/2014
Bill Item : 2.2 Distribution (COPIES)
Description:-Excavation of soil for road widening 1. File
2. Engineer
3. Contractor
Avg :
Side Description T width Width H Qty Total Unit
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : RDA/DW/WP/GOSL/2013/180 No : /MS/
Date : 5/8/2014
Bill Item : 2.2 Distribution (COPIES)
Description:-Excavation of soil for road widening 1. File
2. Engineer
3. Contractor
Avg :
Side Description T width Width H Qty Total Unit
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : RDA/DW/WP/GOSL/2013/180 No : /MS/
Date : 5/8/2014
Bill Item : 2.2 Distribution (COPIES)
Description:-Excavation of soil for road widening 1. File
2. Engineer
3. Contractor
Avg :
Side Description T width Width H Qty Total Unit
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : RDA/DW/WP/GOSL/2013/180 No : /MS/
Date : 5/8/2014
Bill Item : 2.2 Distribution (COPIES)
Description:-Excavation of soil for road widening 1. File
2. Engineer
3. Contractor
Avg :
Side Description T width Width H Qty Total Unit
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : RDA/DW/WP/GOSL/2013/180 No : /MS/
Date : 5/8/2014
Bill Item : 2.2 Distribution (COPIES)
Description:-Excavation of soil for road widening 1. File
2. Engineer
3. Contractor
Avg :
Side Description T width Width H Qty Total Unit
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : RDA/DW/WP/GOSL/2013/180 No : /MS/
Date : 5/8/2014
Bill Item : 2.2 Distribution (COPIES)
Description:-Excavation of soil for road widening 1. File
2. Engineer
3. Contractor
Avg :
Side Description T width Width H Qty Total Unit
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : RDA/DW/WP/GOSL/2013/180 No : /MS/
Date : 5/8/2014
Bill Item : 2.2 Distribution (COPIES)
Description:-Excavation of soil for road widening 1. File
2. Engineer
3. Contractor
Avg :
Side Description T width Width H Qty Total Unit
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : RDA/DW/WP/GOSL/2013/180 No : /MS/
Date : 5/8/2014
Bill Item : 2.2 Distribution (COPIES)
Description:-Excavation of soil for road widening 1. File
2. Engineer
3. Contractor
Avg :
Side Description T width Width H Qty Total Unit
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : RDA/DW/WP/GOSL/2013/180 No : /MS/
Date : 5/8/2014
Bill Item : 2.2 Distribution (COPIES)
Description:-Excavation of soil for road widening 1. File
2. Engineer
3. Contractor
Avg :
Side Description T width Width H Qty Total Unit
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : - No : /MS/
Date : 7/4/2025
Bill Item : 2.1 Distribution (COPIES)
Description:-Scarifging Road Surface 50mm Depth 1. File
2. Engineer
3. Contractor
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : - No : /MS/
Date : 7/4/2025
Bill Item : 2.1 Distribution (COPIES)
Description:-Scarifging Road Surface 50mm Depth 1. File
2. Engineer
3. Contractor
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : - No : /MS/
Date : 7/4/2025
Bill Item : 1.2 Distribution (COPIES)
Description:-Provide all necessary Insurance 1. File
2. Engineer
3. Contractor
POLICY NO KH0014C0000145
Detail Of Charges
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : - No : /MS/
Date : 7/4/2025
Bill Item : 1.3 Distribution (COPIES)
Description:-Provide all necessary Bonds 1. File
2. Engineer
3. Contractor
Charge Detail
Commission 260,904.91
NBT 5,325.00
A Total Charges 266,229.91 See Detail Annex 01
Charge Detail
Commission 235,520.83
NBT 4,807.00
B Total Charges 240,327.83 See Detail Annex 02
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : - No : /MS/
Date : 7/4/2025
Bill Item : 2.2 Distribution (COPIES)
Description:-Roadway Excavation for widening 1. File
carriageway 2. Engineer
3. Contractor
Avg :
Side Description T width Width H Qty Total Unit
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : - No : /MS/
Date : 7/4/2025
Bill Item : 2.3 Distribution (COPIES)
Description:-Trimming, levelling and compacting 1. File
original ground 2. Engineer
3. Contractor
Avg :
Side Description T width Width H Qty Total Unit
BOTH
5+530 7+900 AS PER IPC NO 02 3857.30 3857.30 m2
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : -
No : /MS/
Date : 7/4/2025
Bill Item : 2.4 Distribution (COPIES)
Description:-Dense graded aggregate base course 1. File
spreading,watering & compacting in strips not 2. Engineer
exceeding 1.2m including transport
3. Contractor
Avg :
Side Description T width Width H Qty Total Unit
EDGE WIDNING
BOTH 5+530 7+900
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : RDA/DW/WP/GOSL/2013/180 No : /MS/
Date : 7/4/2025
Bill Item : 3.1 Distribution (COPIES)
Description:-Trimming, Levelling and compacting 1. File
original ground 2. Engineer
3. Contractor
Avg :
Side Description T width Width H Qty Total Unit
LHS &
RHS 5+015 7+150 Total Qty 2960.850
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : RDA/DW/WP/GOSL/2013/180 No : /MS/
Date : 7/4/2025
Bill Item : 3.1 Distribution (COPIES)
Description:-Trimming, Levelling and compacting 1. File
original ground 2. Engineer
3. Contractor
Avg :
Side Description T width Width H Qty Total Unit
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : RDA/DW/WP/GOSL/2013/180 No : /MS/
Date : 7/4/2025
Bill Item : 3.1 Distribution (COPIES)
Description:-Trimming, Levelling and compacting 1. File
original ground 2. Engineer
3. Contractor
Avg :
Side Description T width Width H Qty Total Unit
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : RDA/DW/WP/GOSL/2013/180 No : /MS/
Date : 7/4/2025
Bill Item : 3.1 Distribution (COPIES)
Description:-Trimming, Levelling and compacting 1. File
original ground 2. Engineer
3. Contractor
Avg :
Side Description T width Width H Qty Total Unit
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : RDA/DW/WP/GOSL/2013/180 No : /MS/
Date : 7/4/2025
Bill Item : 3.1 Distribution (COPIES)
Description:-Trimming, Levelling and compacting 1. File
original ground 2. Engineer
3. Contractor
Avg :
Side Description T width Width H Qty Total Unit
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : RDA/DW/WP/GOSL/2013/180 No : /MS/
Date : 7/4/2025
Bill Item : 3.1 Distribution (COPIES)
Description:-Trimming, Levelling and compacting 1. File
original ground 2. Engineer
3. Contractor
Avg :
Side Description T width Width H Qty Total Unit
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
WIDENING AND IMPROVEMENTS TO NALLA - MEERIGAMA ROAD (0+000-4+000)KM
Measurement Sheet
Contract No : RDA/DW/WP/GOSL/2013/178 No : /MS/
Date : 5/8/2014
Bill Item : 3.1 Distribution (COPIES)
Description:-Trimming, Levelling and compacting 1. File
original ground 2. Engineer
3. Contractor
Avg :
Side Description T width Width H Qty Total Unit
LHS
5+015 5+020 5.00 0.400 0.350 1.750
5+020 5+030 10.00 0.300 0.150 1.500
5+030 5+040 10.00 0.000 0.150 1.500
5+040 5+050 10.00 0.300 0.375 3.750
5+050 5+060 10.00 0.450 0.575 5.750
5+060 5+070 10.00 0.700 0.700 7.000
5+070 5+080 10.00 0.700 0.510 5.100
5+080 5+090 10.00 0.320 0.445 4.450
5+090 5+100 10.00 0.570 0.625 6.250
5+100 5+110 10.00 0.680 0.595 5.950
5+110 5+120 10.00 0.510 0.675 6.750
5+120 5+130 10.00 0.840 0.800 8.000
5+130 5+140 10.00 0.760 0.720 7.200
5+140 5+150 10.00 0.680 0.645 6.450
5+150 5+160 10.00 0.610 0.555 5.550
5+160 5+170 10.00 0.500 0.410 4.100
5+170 5+180 10.00 0.320 0.490 4.900
5+180 5+190 10.00 0.660 0.570 5.700
5+190 5+200 10.00 0.480 0.455 4.550
5+200 5+210 10.00 0.430 0.440 4.400
5+210 5+220 10.00 0.450 0.475 4.750
5+220 5+230 10.00 0.500 0.500 5.000
5+230 5+240 10.00 0.500 0.450 4.500
5+240 5+250 10.00 0.400 0.405 4.050
5+250 5+260 10.00 0.410 0.485 4.850
5+260 5+270 10.00 0.560 0.525 5.250
5+270 5+280 10.00 0.490 0.420 4.200
5+280 5+290 10.00 0.350 0.475 4.750
5+290 5+300 10.00 0.600 0.530 5.300
5+300 5+310 10.00 0.460 0.445 4.450
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
WIDENING AND IMPROVEMENTS TO NALLA - MEERIGAMA ROAD (0+000-4+000)KM
Measurement Sheet
Contract No : RDA/DW/WP/GOSL/2013/178 No : /MS/
Date : 5/8/2014
Bill Item : 3.1 Distribution (COPIES)
Description:-Trimming, Levelling and compacting 1. File
original ground 2. Engineer
3. Contractor
Avg :
Side Description T width Width H Qty Total Unit
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
WIDENING AND IMPROVEMENTS TO NALLA - MEERIGAMA ROAD (0+000-4+000)KM
Measurement Sheet
Contract No : RDA/DW/WP/GOSL/2013/178 No : /MS/
Date : 5/8/2014
Bill Item : 3.1 Distribution (COPIES)
Description:-Trimming, Levelling and compacting 1. File
original ground 2. Engineer
3. Contractor
Avg :
Side Description T width Width H Qty Total Unit
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
WIDENING AND IMPROVEMENTS TO NALLA - MEERIGAMA ROAD (0+000-4+000)KM
Measurement Sheet
Contract No : RDA/DW/WP/GOSL/2013/178 No : /MS/
Date : 5/8/2014
Bill Item : 3.1 Distribution (COPIES)
Description:-Trimming, Levelling and compacting 1. File
original ground 2. Engineer
3. Contractor
Avg :
Side Description T width Width H Qty Total Unit
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : - No : /MS/
Date : 7/4/2025
Bill Item : 2.5 Distribution (COPIES)
Description:-Supplying spreading and 1. File
compaction of Dense graded aggregate base 2. Engineer
course of nominal maximum size of 37.5 mm
(ABC) including transport of 35Km distance
3. Contractor
Measurement Sheet
Contract No : - No : /MS/
Date : 7/4/2025
Bill Item : 2.6 Distribution (COPIES)
Prime coat with emulsion CSS - 1 using 1 ltr,/sqm 1. File
including blinding with sand and transport. 2. Engineer
3. Contractor
AVG.
Side Description L width Width
Qty Total Unit
BOTH
7+250 7+900 AS PER IPC NO 02 3250.000 3300.00 m2
LHS
5+530 5+540 10.00 0.700 0.750 7.500
5+540 5+550 10.00 0.800 0.850 8.500
5+550 5+560 10.00 0.900 0.800 8.000
5+560 5+570 10.00 0.700 0.675 6.750
5+570 5+580 10.00 0.650 0.925 9.250
5+580 5+590 10.00 1.200 1.300 13.000
5+590 5+600 10.00 1.400 1.350 13.500
5+600 5+610 10.00 1.300 1.200 12.000
5+610 5+620 10.00 1.100 1.100 11.000
5+620 5+630 10.00 1.100 1.050 10.500
5+630 5+640 10.00 1.000 1.000 10.000
5+640 5+650 10.00 1.000 0.900 9.000
5+650 5+660 10.00 0.800 0.750 7.500
5+660 5+670 10.00 0.700 0.980 9.800
5+670 5+680 10.00 1.260 1.280 12.800
5+680 5+690 10.00 1.300 1.250 12.500
5+690 5+700 10.00 1.200 1.100 11.000
5+700 5+710 10.00 1.000 1.025 10.250
5+710 5+720 10.00 1.050 0.975 9.750
5+720 5+730 10.00 0.900 0.975 9.750
5+730 5+740 10.00 1.050 1.100 11.000
5+740 5+750 10.00 1.150 1.025 10.250
5+750 5+760 10.00 0.900 1.000 10.000
5+760 5+770 10.00 1.100 0.975 9.750
5+770 5+780 10.00 0.850 0.925 9.250
5+780 5+790 10.00 1.000 0.900 9.000
5+790 5+800 10.00 0.800 0.800 8.000
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : - No : /MS/
Date : 7/4/2025
Bill Item : 2.6 Distribution (COPIES)
Prime coat with emulsion CSS - 1 using 1 ltr,/sqm 1. File
including blinding with sand and transport. 2. Engineer
3. Contractor
5+800 5+810 10.00 0.800 0.750 7.500
5+810 5+820 10.00 0.700 0.750 7.500
5+820 5+830 10.00 0.800 0.850 8.500
5+830 5+840 10.00 0.900 0.950 9.500
5+840 5+850 10.00 1.000 0.925 9.250
5+850 5+860 10.00 0.850 0.975 9.750
5+860 5+870 10.00 1.100 0.875 8.750
5+870 5+880 10.00 0.650 0.675 6.750
5+880 5+890 10.00 0.700 0.650 6.500
5+890 5+900 10.00 0.600 0.800 8.000
5+900 5+910 10.00 1.000 1.000 10.000
5+910 5+920 10.00 1.000 1.000 10.000
5+920 5+930 10.00 1.000 1.050 10.500
5+930 5+940 10.00 1.100 1.150 11.500
5+940 5+950 10.00 1.200 1.100 11.000
5+950 5+960 10.00 1.000 1.050 10.500
5+960 5+970 10.00 1.100 1.075 10.750
5+970 5+980 10.00 1.050 1.075 10.750
5+980 5+990 10.00 1.100 1.150 11.500
5+990 6+000 10.00 1.200 0.850 8.500
6+000 6+010 10.00 0.500 0.900 9.000
6+010 6+020 10.00 1.300 1.200 12.000
6+020 6+030 10.00 1.100 1.200 12.000
6+030 6+040 10.00 1.300 1.250 12.500
6+040 6+050 10.00 1.200 1.150 11.500
6+050 6+060 10.00 1.100 1.100 11.000
6+060 6+070 10.00 1.100 1.050 10.500
6+070 6+080 10.00 1.000 1.075 10.750
6+080 6+090 10.00 1.150 1.175 11.750
6+090 6+100 10.00 1.200 1.315 13.150
6+100 6+110 10.00 1.430 1.315 13.150
6+110 6+120 10.00 1.200 1.100 11.000
6+120 6+130 10.00 1.000 0.900 9.000
6+130 6+140 10.00 0.800 0.850 8.500
6+140 6+150 10.00 0.900 0.800 8.000
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : - No : /MS/
Date : 7/4/2025
Bill Item : 2.6 Distribution (COPIES)
Prime coat with emulsion CSS - 1 using 1 ltr,/sqm 1. File
including blinding with sand and transport. 2. Engineer
3. Contractor
6+150 6+160 10.00 0.700 0.700 7.000
6+160 6+170 10.00 0.700 0.800 8.000
6+170 6+180 10.00 0.900 0.850 8.500
6+180 6+190 10.00 0.800 0.900 9.000
6+190 6+200 10.00 1.000 1.000 10.000
6+200 6+210 10.00 1.000 1.100 11.000
6+210 6+220 10.00 1.200 1.100 11.000
6+220 6+230 10.00 1.000 0.950 9.500
6+230 6+240 10.00 0.900 0.800 8.000
6+240 6+250 10.00 0.700 0.700 7.000
6+250 6+260 10.00 0.700 0.750 7.500
6+260 6+270 10.00 0.800 0.900 9.000
6+270 6+280 10.00 1.000 0.850 8.500
6+280 6+290 10.00 0.700 0.700 7.000
6+290 6+300 10.00 0.700 0.700 7.000
6+300 6+310 10.00 0.700 0.950 9.500
6+310 6+320 10.00 1.200 1.100 11.000
6+320 6+330 10.00 1.000 0.900 9.000
6+330 6+340 10.00 0.800 0.750 7.500
6+340 6+350 10.00 0.700 0.650 6.500
6+350 6+360 10.00 0.600 0.600 6.000
6+360 6+370 10.00 0.600 0.700 7.000
6+370 6+380 10.00 0.800 0.750 7.500
6+380 6+390 10.00 0.700 0.725 7.250
6+390 6+400 10.00 0.750 0.875 8.750
6+400 6+410 10.00 1.000 0.900 9.000
6+410 6+420 10.00 0.800 0.650 6.500
6+420 6+430 10.00 0.500 0.600 6.000
6+430 6+440 10.00 0.700 0.700 7.000
6+440 6+450 10.00 0.700 0.650 6.500
6+450 6+460 10.00 0.600 0.750 7.500
6+460 6+470 10.00 0.900 1.050 10.500
6+470 6+480 10.00 1.200 1.250 12.500
6+480 6+490 10.00 1.300 1.000 10.000
6+490 6+500 10.00 0.700 0.950 9.500
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : - No : /MS/
Date : 7/4/2025
Bill Item : 2.6 Distribution (COPIES)
Prime coat with emulsion CSS - 1 using 1 ltr,/sqm 1. File
including blinding with sand and transport. 2. Engineer
3. Contractor
6+500 6+510 10.00 1.200 1.200 12.000
6+510 6+520 10.00 1.200 0.950 9.500
6+520 6+530 10.00 0.700 0.450 4.500
6+530 6+540 10.00 0.200 0.300 3.000
6+540 6+550 10.00 0.400 0.450 4.500
6+550 6+560 10.00 0.500 0.600 6.000
6+560 6+570 10.00 0.700 0.625 6.250
6+570 6+580 10.00 0.550 0.675 6.750
6+580 6+590 10.00 0.800 0.900 9.000
6+590 6+600 10.00 1.000 0.900 9.000
6+600 6+610 10.00 0.800 0.525 5.250
6+610 6+620 10.00 0.250 0.375 3.750
6+620 6+630 10.00 0.500 0.550 5.500
6+630 0.600 0.300 0.000
0.000
6+770 6+780 10.00 0.700 0.700 7.000
6+780 6+790 10.00 0.700 0.450 4.500
6+790 6+800 10.00 0.200 0.500 5.000
6+800 6+810 10.00 0.800 0.775 7.750
6+810 6+820 10.00 0.750 0.675 6.750
6+820 6+830 10.00 0.600 0.750 7.500
6+830 6+840 10.00 0.900 0.825 8.250
6+840 6+850 10.00 0.750 0.675 6.750
6+850 6+860 10.00 0.600 0.550 5.500
6+860 6+870 10.00 0.500 0.500 5.000
6+870 6+880 10.00 0.500 0.450 4.500
6+880 6+890 10.00 0.400 0.500 5.000
6+890 6+900 10.00 0.600 0.600 6.000
6+900 6+910 10.00 0.600 0.650 6.500
6+910 6+920 10.00 0.700 0.650 6.500
6+920 6+930 10.00 0.600 0.625 6.250
6+930 6+940 10.00 0.650 0.575 5.750
6+940 6+950 10.00 0.500 0.600 6.000
6+950 6+960 10.00 0.700 0.850 8.500
6+960 6+970 10.00 1.000 1.000 10.000
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : - No : /MS/
Date : 7/4/2025
Bill Item : 2.6 Distribution (COPIES)
Prime coat with emulsion CSS - 1 using 1 ltr,/sqm 1. File
including blinding with sand and transport. 2. Engineer
3. Contractor
6+970 6+980 10.00 1.000 1.050 10.500
6+980 6+990 10.00 1.100 1.150 11.500
6+990 7+000 10.00 1.200 1.200 12.000
7+000 7+010 10.00 1.200 0.750 7.500
7+010 7+020 10.00 0.300 0.350 3.500
7+020 7+030 10.00 0.400 0.450 4.500
7+030 7+040 10.00 0.500 0.600 6.000
7+040 7+050 10.00 0.700 0.750 7.500
7+050 7+060 10.00 0.800 0.750 7.500
7+060 7+070 10.00 0.700 0.700 7.000
7+070 7+080 10.00 0.700 0.600 6.000
7+080 7+090 10.00 0.500 0.500 5.000
7+090 7+100 10.00 0.500 0.500 5.000
7+100 7+110 10.00 0.500 0.600 6.000
7+110 7+120 10.00 0.700 1.000 10.000
7+120 7+130 10.00 1.300 0.850 8.500
7+130 7+140 10.00 0.400 0.450 4.500
7+140 7+150 10.00 0.500 0.500 5.000
7+150 7+160 10.00 0.500 0.600 6.000
7+160 7+170 10.00 0.700 0.550 5.500
7+170 7+180 10.00 0.400 0.500 5.000
7+180 7+190 10.00 0.600 0.550 5.500
7+190 7+200 10.00 0.500 0.750 7.500
7+200 7+210 10.00 1.000 0.900 9.000
7+210 7+220 10.00 0.800 0.750 7.500
7+220 7+230 10.00 0.700 0.750 7.500
7+230 7+240 10.00 0.800 0.850 8.500
7+240 7+250 10.00 0.900 0.900 9.000
7+250 7+260 10.00 0.900 0.900 9.000
7+260 7+270 10.00 0.900 0.900 9.000
7+270 7+280 10.00 0.900 0.850 8.500
7+280 7+290 10.00 0.800 0.850 8.500
7+290 7+300 10.00 0.900 0.900 9.000
7+300 7+310 10.00 0.900 0.750 7.500
7+310 7+320 10.00 0.600 0.850 8.500
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : - No : /MS/
Date : 7/4/2025
Bill Item : 2.6 Distribution (COPIES)
Prime coat with emulsion CSS - 1 using 1 ltr,/sqm 1. File
including blinding with sand and transport. 2. Engineer
3. Contractor
7+320 7+330 10.00 1.100 1.000 10.000
7+330 7+340 10.00 0.900 0.950 9.500
7+340 7+350 10.00 1.000 0.950 9.500
7+350 7+360 10.00 0.900 0.800 8.000
7+360 7+370 10.00 0.700 0.900 9.000
7+370 7+380 10.00 1.100 1.050 10.500
7+380 7+390 10.00 1.000 1.050 10.500
7+390 7+400 10.00 1.100 1.050 10.500
7+400 7+410 10.00 1.000 0.800 8.000
7+410 7+420 10.00 0.600 0.850 8.500
7+420 7+430 10.00 1.100 1.100 11.000
7+430 7+440 10.00 1.100 1.000 10.000
7+440 7+450 10.00 0.900 0.900 9.000
7+450 7+460 10.00 0.900 0.950 9.500
7+460 7+470 10.00 1.000 0.850 8.500
7+470 7+480 10.00 0.700 0.825 8.250
7+480 7+490 10.00 0.950 1.150 11.500
7+490 7+500 10.00 1.350 1.125 11.250
7+500 7+510 10.00 0.900 0.900 9.000
7+510 7+520 10.00 0.900 0.800 8.000
7+520 7+530 10.00 0.700 0.675 6.750
7+530 7+540 10.00 0.650 0.475 4.750
7+540 7+550 10.00 0.300 0.300 3.000
7+550 7+560 10.00 0.300 0.350 3.500
7+560 7+570 10.00 0.400 0.450 4.500
7+570 7+580 10.00 0.500 0.700 7.000
7+580 7+590 10.00 0.900 0.850 8.500
7+590 7+600 10.00 0.800 0.850 8.500
7+600 7+610 10.00 0.900 0.800 8.000
7+610 7+620 10.00 0.700 0.850 8.500
7+620 7+630 10.00 1.000 0.900 9.000
7+630 7+640 10.00 0.800 0.700 7.000
7+640 7+650 10.00 0.600 0.550 5.500
7+650 7+660 10.00 0.500 0.500 5.000
7+660 7+670 10.00 0.500 0.625 6.250
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : - No : /MS/
Date : 7/4/2025
Bill Item : 2.6 Distribution (COPIES)
Prime coat with emulsion CSS - 1 using 1 ltr,/sqm 1. File
including blinding with sand and transport. 2. Engineer
3. Contractor
7+670 7+680 10.00 0.750 0.675 6.750
7+680 7+690 10.00 0.600 0.600 6.000
7+690 7+700 10.00 0.600 0.725 7.250
7+700 7+710 10.00 0.850 0.750 7.500
7+710 7+720 10.00 0.650 0.675 6.750
7+720 7+730 10.00 0.700 0.675 6.750
7+730 7+740 10.00 0.650 0.750 7.500
7+740 7+750 10.00 0.850 0.875 8.750
7+750 7+760 10.00 0.900 0.925 9.250
7+760 7+770 10.00 0.950 1.125 11.250
7+770 7+780 10.00 1.300 1.150 11.500
7+780 7+790 10.00 1.000 0.950 9.500
7+790 7+800 10.00 0.900 0.825 8.250
7+800 7+810 10.00 0.750 0.875 8.750
7+810 7+820 10.00 1.000 0.850 8.500
7+820 7+830 10.00 0.700 0.975 9.750
7+830 7+840 10.00 1.250 1.225 12.250
7+840 7+850 10.00 1.200 1.200 12.000
7+850 7+860 10.00 1.200 1.150 11.500
7+860 7+870 10.00 1.100 0.900 9.000
7+870 7+880 10.00 0.700 0.750 7.500
7+880 7+890 10.00 0.800 0.650 6.500
7+890 7+900 10.00 0.500 0.500 5.000
7+900 0.500 0.250 0.000
0.000
RHS 5+530 5+540 10.00 1.600 1.450 14.500
5+540 5+550 10.00 1.300 1.350 13.500
5+550 5+560 10.00 1.400 1.400 14.000
5+560 5+570 10.00 1.400 1.370 13.700
5+570 5+580 10.00 1.340 1.220 12.200
5+580 5+590 10.00 1.100 0.950 9.500
5+590 5+600 10.00 0.800 0.715 7.150
5+600 5+610 10.00 0.630 0.815 8.150
5+610 5+620 10.00 1.000 1.000 10.000
5+620 5+630 10.00 1.000 0.950 9.500
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : - No : /MS/
Date : 7/4/2025
Bill Item : 2.6 Distribution (COPIES)
Prime coat with emulsion CSS - 1 using 1 ltr,/sqm 1. File
including blinding with sand and transport. 2. Engineer
3. Contractor
5+630 5+640 10.00 0.900 0.850 8.500
5+640 5+650 10.00 0.800 0.975 9.750
5+650 5+660 10.00 1.150 1.375 13.750
5+660 5+670 10.00 1.600 1.500 15.000
5+670 5+680 10.00 1.400 1.250 12.500
5+680 5+690 10.00 1.100 0.900 9.000
5+690 5+700 10.00 0.700 0.850 8.500
5+700 5+710 10.00 1.000 1.150 11.500
5+710 5+720 10.00 1.300 1.200 12.000
5+720 5+730 10.00 1.100 1.125 11.250
5+730 5+740 10.00 1.150 1.025 10.250
5+740 5+750 10.00 0.900 0.900 9.000
5+750 5+760 10.00 0.900 0.975 9.750
5+760 5+770 10.00 1.050 0.875 8.750
5+770 5+780 10.00 0.700 0.700 7.000
5+780 5+790 10.00 0.700 0.625 6.250
5+790 5+800 10.00 0.550 0.665 6.650
5+800 5+810 10.00 0.780 0.765 7.650
5+810 5+820 10.00 0.750 0.775 7.750
5+820 5+830 10.00 0.800 0.900 9.000
5+830 5+840 10.00 1.000 0.950 9.500
5+840 5+850 10.00 0.900 0.750 7.500
5+850 5+860 10.00 0.600 0.700 7.000
5+860 5+870 10.00 0.800 0.875 8.750
5+870 5+880 10.00 0.950 0.975 9.750
5+880 5+890 10.00 1.000 1.000 10.000
5+890 5+900 10.00 1.000 0.950 9.500
5+900 5+910 10.00 0.900 0.850 8.500
5+910 5+920 10.00 0.800 0.925 9.250
5+920 5+930 10.00 1.050 0.975 9.750
5+930 5+940 10.00 0.900 0.925 9.250
5+940 5+950 10.00 0.950 0.900 9.000
5+950 5+960 10.00 0.850 0.800 8.000
5+960 5+970 10.00 0.750 0.625 6.250
5+970 5+980 10.00 0.500 0.525 5.250
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : - No : /MS/
Date : 7/4/2025
Bill Item : 2.6 Distribution (COPIES)
Prime coat with emulsion CSS - 1 using 1 ltr,/sqm 1. File
including blinding with sand and transport. 2. Engineer
3. Contractor
5+980 5+990 10.00 0.550 0.775 7.750
5+990 6+000 10.00 1.000 1.050 10.500
6+000 6+010 10.00 1.100 1.050 10.500
6+010 6+020 10.00 1.000 1.000 10.000
6+020 6+030 10.00 1.000 0.950 9.500
6+030 6+040 10.00 0.900 0.450 4.500
6+040 6+050 10.00 0.000 0.000 0.000
6+050 6+060 10.00 0.000 0.000 0.000
6+060 6+070 10.00 0.000 0.000 0.000
6+070 6+080 10.00 0.000 0.600 6.000
6+080 6+090 10.00 1.200 1.050 10.500
6+090 6+100 10.00 0.900 0.850 8.500
6+100 6+110 10.00 0.800 0.950 9.500
6+110 6+120 10.00 1.100 0.975 9.750
6+120 6+130 10.00 0.850 0.850 8.500
6+130 6+140 10.00 0.850 0.775 7.750
6+140 6+150 10.00 0.700 0.750 7.500
6+150 6+160 10.00 0.800 0.850 8.500
6+160 6+170 10.00 0.900 0.900 9.000
6+170 6+180 10.00 0.900 1.000 10.000
6+180 6+190 10.00 1.100 1.150 11.500
6+190 6+200 10.00 1.200 1.150 11.500
6+200 6+210 10.00 1.100 1.000 10.000
6+210 6+220 10.00 0.900 0.950 9.500
6+220 6+230 10.00 1.000 0.900 9.000
6+230 6+240 10.00 0.800 0.850 8.500
6+240 6+250 10.00 0.900 0.900 9.000
6+250 6+260 10.00 0.900 0.800 8.000
6+260 6+270 10.00 0.700 0.700 7.000
6+270 6+280 10.00 0.700 0.850 8.500
6+280 6+290 10.00 1.000 1.100 11.000
6+290 6+300 10.00 1.200 1.200 12.000
6+300 6+310 10.00 1.200 1.275 12.750
6+310 6+320 10.00 1.350 1.225 12.250
6+320 6+330 10.00 1.100 1.050 10.500
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : - No : /MS/
Date : 7/4/2025
Bill Item : 2.6 Distribution (COPIES)
Prime coat with emulsion CSS - 1 using 1 ltr,/sqm 1. File
including blinding with sand and transport. 2. Engineer
3. Contractor
6+330 6+340 10.00 1.000 0.950 9.500
6+340 6+350 10.00 0.900 0.900 9.000
6+350 6+360 10.00 0.900 0.950 9.500
6+360 6+370 10.00 1.000 1.000 10.000
6+370 6+380 10.00 1.000 0.850 8.500
6+380 6+390 10.00 0.700 0.700 7.000
6+390 6+400 10.00 0.700 0.850 8.500
6+400 6+410 10.00 1.000 1.150 11.500
6+410 6+420 10.00 1.300 1.100 11.000
6+420 6+430 10.00 0.900 1.050 10.500
6+430 6+440 10.00 1.200 1.150 11.500
6+440 6+450 10.00 1.100 1.100 11.000
6+450 6+460 10.00 1.100 1.100 11.000
6+460 6+470 10.00 1.100 0.950 9.500
6+470 6+480 10.00 0.800 1.020 10.200
6+480 6+490 10.00 1.240 0.970 9.700
6+490 6+500 10.00 0.700 0.850 8.500
6+500 6+510 10.00 1.000 1.150 11.500
6+510 6+520 10.00 1.300 1.050 10.500
6+520 6+530 10.00 0.800 1.000 10.000
6+530 6+540 10.00 1.200 0.900 9.000
6+540 6+550 10.00 0.600 0.650 6.500
6+550 6+560 10.00 0.700 1.000 10.000
6+560 6+570 10.00 1.300 1.000 10.000
6+570 6+580 10.00 0.700 0.650 6.500
6+580 6+590 10.00 0.600 0.650 6.500
6+590 6+600 10.00 0.700 0.700 7.000
6+600 6+610 10.00 0.700 0.775 7.750
6+610 6+620 10.00 0.850 0.875 8.750
6+620 6+630 10.00 0.900 1.000 10.000
6+630 1.100 0.550 0.000
0.000
0.000
6+770 6+780 10.00 1.100 1.050 10.500
6+780 6+790 10.00 1.000 1.025 10.250
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : - No : /MS/
Date : 7/4/2025
Bill Item : 2.6 Distribution (COPIES)
Prime coat with emulsion CSS - 1 using 1 ltr,/sqm 1. File
including blinding with sand and transport. 2. Engineer
3. Contractor
6+790 6+800 10.00 1.050 0.950 9.500
6+800 6+810 10.00 0.850 0.850 8.500
6+810 6+820 10.00 0.850 0.800 8.000
6+820 6+830 10.00 0.750 0.725 7.250
6+830 6+840 10.00 0.700 0.775 7.750
6+840 6+850 10.00 0.850 0.900 9.000
6+850 6+860 10.00 0.950 0.850 8.500
6+860 6+870 10.00 0.750 0.725 7.250
6+870 6+880 10.00 0.700 0.900 9.000
6+880 6+890 10.00 1.100 0.900 9.000
6+890 6+900 10.00 0.700 0.850 8.500
6+900 6+910 10.00 1.000 0.950 9.500
6+910 6+920 10.00 0.900 0.800 8.000
6+920 6+930 10.00 0.700 0.800 8.000
6+930 6+940 10.00 0.900 0.775 7.750
6+940 6+950 10.00 0.650 0.575 5.750
6+950 6+960 10.00 0.500 0.500 5.000
6+960 6+970 10.00 0.500 0.650 6.500
6+970 6+980 10.00 0.800 0.700 7.000
6+980 6+990 10.00 0.600 0.700 7.000
6+990 7+000 10.00 0.800 0.900 9.000
7+000 7+010 10.00 1.000 1.000 10.000
7+010 7+020 10.00 1.000 1.050 10.500
7+020 7+030 10.00 1.100 0.950 9.500
7+030 7+040 10.00 0.800 0.700 7.000
7+040 7+050 10.00 0.600 0.700 7.000
7+050 7+060 10.00 0.800 0.750 7.500
7+060 7+070 10.00 0.700 0.750 7.500
7+070 7+080 10.00 0.800 0.900 9.000
7+080 7+090 10.00 1.000 1.150 11.500
7+090 7+100 10.00 1.300 1.250 12.500
7+100 7+110 10.00 1.200 1.100 11.000
7+110 7+120 10.00 1.000 1.000 10.000
7+120 7+130 10.00 1.000 0.900 9.000
7+130 7+140 10.00 0.800 0.800 8.000
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : - No : /MS/
Date : 7/4/2025
Bill Item : 2.6 Distribution (COPIES)
Prime coat with emulsion CSS - 1 using 1 ltr,/sqm 1. File
including blinding with sand and transport. 2. Engineer
3. Contractor
7+140 7+150 10.00 0.800 0.750 7.500
7+150 7+160 10.00 0.700 0.750 7.500
7+160 7+170 10.00 0.800 0.750 7.500
7+170 7+180 10.00 0.700 0.850 8.500
7+180 7+190 10.00 1.000 1.000 10.000
7+190 7+200 10.00 1.000 1.000 10.000
7+200 7+210 10.00 1.000 1.100 11.000
7+210 7+220 10.00 1.200 1.100 11.000
7+220 7+230 10.00 1.000 1.100 11.000
7+230 7+240 10.00 1.200 1.100 11.000
7+240 7+250 10.00 1.000 1.050 10.500
7+250 7+260 10.00 1.100 1.050 10.500
7+260 7+270 10.00 1.000 0.850 8.500
7+270 7+280 10.00 0.700 0.650 6.500
7+280 7+290 10.00 0.600 0.750 7.500
7+290 7+300 10.00 0.900 0.950 9.500
7+300 7+310 10.00 1.000 1.000 10.000
7+310 7+320 10.00 1.000 0.900 9.000
7+320 7+330 10.00 0.800 0.900 9.000
7+330 7+340 10.00 1.000 0.950 9.500
7+340 7+350 10.00 0.900 1.000 10.000
7+350 7+360 10.00 1.100 1.000 10.000
7+360 7+370 10.00 0.900 1.050 10.500
7+370 7+380 10.00 1.200 1.150 11.500
7+380 7+390 10.00 1.100 1.250 12.500
7+390 7+400 10.00 1.400 1.350 13.500
7+400 7+410 10.00 1.300 1.250 12.500
7+410 7+420 10.00 1.200 1.200 12.000
7+420 7+430 10.00 1.200 1.200 12.000
7+430 7+440 10.00 1.200 0.950 9.500
7+440 7+450 10.00 0.700 0.675 6.750
7+450 7+460 10.00 0.650 0.750 7.500
7+460 7+470 10.00 0.850 0.900 9.000
7+470 7+480 10.00 0.950 0.950 9.500
7+480 7+490 10.00 0.950 0.825 8.250
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : - No : /MS/
Date : 7/4/2025
Bill Item : 2.6 Distribution (COPIES)
Prime coat with emulsion CSS - 1 using 1 ltr,/sqm 1. File
including blinding with sand and transport. 2. Engineer
3. Contractor
7+490 7+500 10.00 0.700 0.800 8.000
7+500 7+510 10.00 0.900 0.875 8.750
7+510 7+520 10.00 0.850 0.675 6.750
7+520 7+530 10.00 0.500 0.675 6.750
7+530 7+540 10.00 0.850 0.925 9.250
7+540 7+550 10.00 1.000 0.950 9.500
7+550 7+560 10.00 0.900 0.750 7.500
7+560 7+570 10.00 0.600 0.650 6.500
7+570 7+580 10.00 0.700 0.650 6.500
7+580 7+590 10.00 0.600 0.500 5.000
7+590 7+600 10.00 0.400 0.500 5.000
7+600 7+610 10.00 0.600 0.650 6.500
7+610 7+620 10.00 0.700 0.700 7.000
7+620 7+630 10.00 0.700 0.800 8.000
7+630 7+640 10.00 0.900 0.850 8.500
7+640 7+650 10.00 0.800 0.600 6.000
7+650 7+660 10.00 0.400 0.550 5.500
7+660 7+670 10.00 0.700 0.800 8.000
7+670 7+680 10.00 0.900 0.650 6.500
7+680 7+690 10.00 0.400 0.450 4.500
7+690 7+700 10.00 0.500 0.550 5.500
7+700 7+710 10.00 0.600 0.700 7.000
7+710 7+720 10.00 0.800 0.800 8.000
7+720 7+730 10.00 0.800 0.800 8.000
7+730 7+740 10.00 0.800 0.800 8.000
7+740 7+750 10.00 0.800 0.900 9.000
7+750 7+760 10.00 1.000 0.950 9.500
7+760 7+770 10.00 0.900 0.900 9.000
7+770 7+780 10.00 0.900 0.825 8.250
7+780 7+790 10.00 0.750 0.850 8.500
7+790 7+800 10.00 0.950 1.075 10.750
7+800 7+810 10.00 1.200 1.300 13.000
7+810 7+820 10.00 1.400 1.250 12.500
7+820 7+830 10.00 1.100 0.975 9.750
7+830 7+840 10.00 0.850 0.775 7.750
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : - No : /MS/
Date : 7/4/2025
Bill Item : 2.6 Distribution (COPIES)
Prime coat with emulsion CSS - 1 using 1 ltr,/sqm 1. File
including blinding with sand and transport. 2. Engineer
3. Contractor
7+840 7+850 10.00 0.700 0.650 6.500
7+850 7+860 10.00 0.600 0.550 5.500
7+860 7+870 10.00 0.500 0.650 6.500
7+870 7+880 10.00 0.800 0.800 8.000
7+880 7+890 10.00 0.800 0.800 8.000
7+890 7+900 10.00 0.800 0.900 9.000
7+900 0.00 1.000 0.500 0.000
This Bill QTY 553.00 m2
Measurement Sheet
Contract No : - No : /MS/
Date : 7/4/2025
Bill Item : 5.1 Distribution (COPIES)
Description:-Excavation in medium soil 1. File
2. Engineer
3. Contractor
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : - No : /MS/
Date : 7/4/2025
Bill Item : 5.6 Distribution (COPIES)
Description:-Mixing & Laying cement concrete 1. File
[Link](37.5mm) For Foundation 2. Engineer
3. Contractor
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : - No : /MS/
Date : 7/4/2025
Bill Item : 5.7 Distribution (COPIES)
Description:-Supplyin & fixing 25mm thick class II 1. File
timer as shuttering (rough) 2. Engineer
3. Contractor
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : - No : /MS/
Date : 7/4/2025
Bill Item : 5.7 Distribution (COPIES)
Description:-Supplyin & fixing 25mm thick class II 1. File
timer as shuttering (rough) 2. Engineer
3. Contractor
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : - No : /MS/
Date : 7/4/2025
Bill Item : 5.8 Distribution (COPIES)
Description:-Mixing & laying cement concrete Grade 1. File
25 For Foundation 2. Engineer
3. Contractor
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : -
No : /MS/
Date : 7/4/2025
Bill Item : 5.9 Distribution (COPIES)
Description:-Supply & fixing shuttering smooth finished 1. File
2. Engineer
3. Contractor
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : -
No : /MS/
Date : 7/4/2025
Bill Item : 5.9 Distribution (COPIES)
Description:-Supply & fixing shuttering smooth finished 1. File
2. Engineer
3. Contractor
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : - No : /MS/
Date : 7/4/2025
Bill Item : 5.10 Distribution (COPIES)
Description:-Mixing & Laying cement concrete 1. File
[Link](37.5mm)For Supper Structure 2. Engineer
3. Contractor
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : - No : /MS/
Date : 7/4/2025
Bill Item : 5.10 Distribution (COPIES)
Description:-Mixing & Laying cement concrete 1. File
[Link](37.5mm)For Supper Structure 2. Engineer
3. Contractor
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : RDA/DW/WP/GOSL/2013/178 No : /MS/
Date : 7/4/2025
Bill Item : 6.11 Distribution (COPIES)
Description:-Forming weepholes using PVC pipe 1. File
100mm 2. Engineer
3. Contractor
LHS 4/2Culvert
(A) 1 5.20 2.00 1.20 12.48
(B) 1 5.20 2.00 0.60 6.24
(C) 1 5.20 2.00 1.20 12.48
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : - No : /MS/
Date : 7/4/2025
Bill Item : 5.14 Distribution (COPIES)
Description:-Mixing & laying cement concrete G-25 1. File
2. Engineer
3. Contractor
2.05
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : RDA/DW/WP/GOSL/2013/178 No : /MS/
Date : 7/4/2025
Bill Item : 6.15 Distribution (COPIES)
Description:-Fabricate & lay for tor steel as 1. File
reinforcement 2. Engineer
3. Contractor
LHS 4/2Culvert
(A) 1 5.20 2.00 1.20 12.48
(B) 1 5.20 2.00 0.60 6.24
(C) 1 5.20 2.00 1.20 12.48
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : RDA/DW/WP/GOSL/2013/178 No : /MS/
Date : 7/4/2025
Bill Item : 6.16 Distribution (COPIES)
Description:Fabricate & lay for MS steel as 1. File
reinforcement 2. Engineer
3. Contractor
LHS 4/2Culvert
(A) 1 5.20 2.00 1.20 12.48
(B) 1 5.20 2.00 0.60 6.24
(C) 1 5.20 2.00 1.20 12.48
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
ISURU ENGINEERING(PTE)LTD
0
Measurement Sheet
Contract No : - No : /MS/
Date : 7/4/2025
Bill Item : 5.17 Distribution (COPIES)
Description:Curing of deck slab of culvert 1. File
2. Engineer
3. Contractor
6.45
………………………………………………….. …………………………………………………..
Signature of R.E./O.I.C (RDA05/19/2025B) Signature Of S.E. Contractor (IEL)
Date:- ………………………………………… Date:- …………………………………………
0
RDA/DW/WP/GOSL/2013/180
INTERIM PAYMENT APPLICATION 7/4/2025
Bill No :01
224.501
IPC NO 2 Claim Previous Claim 224.475
Balance Qty 0.026
Cumilative Qty 224.501
11,019,361.00