MN 043001 en
MN 043001 en
XT and XT FlashGard
motor control center installation
and maintenance manual
Contents
Part Description Page
1 General information. . . . . . . . . . . . . . . . . . 2
2 Receiving, handling, and storage . . . . . . . 5
3 Installing control center sections . . . . . . . 6
4 Installing conduit and wiring. . . . . . . . . . 10
5 Incoming line connections . . . . . . . . . . . 12
6 Inspection prior to energizing. . . . . . . . . 16
7 XT MCC unit installation
and adjustment. . . . . . . . . . . . . . . . . . . . 17
8 XT FlashGard® MCC unit installation
and adjustment. . . . . . . . . . . . . . . . . . . . 19
9 Maintenance. . . . . . . . . . . . . . . . . . . . . . 23
10 Plan views. . . . . . . . . . . . . . . . . . . . . . . . 29
11 Related instruction leaflets. . . . . . . . . . . 31
(11) Top
Wireway Door
24 Vdc Power
Supply Unit
Vertical
Wireway Door
(9) (10)
Top Horizontal Horizontal Bus (11)
Wireway Barriers Top Wireway
(7) Door
Top and Side Cover
(3)
Large Operating
Handle
(6)
Vertical Bus Barrier—Labyrinth
(20)
Ground Bus
(4)
1/4 Turn Latch
(2)
Drawout Unit
(1)
Unit Door
(5)
(3) Device Panel
Small Operating Handle
(21)
Defeater Mechanism Screw
(16)
Vertical Wireway
(15)
Door
Vertical Wireway
(17)
Structural Members
Before and after unloading the motor control center, inspect each The height of the lift Don’t pass ropes
Max.
section and unit exterior for evidence of damage that may have been point above the
45º
or cables
spreader should be through lift holes.
incurred during shipment. If there is any indication that the control at least 1/2 of “A” Use slings with
center has been mishandled or shipped on its back or side, remove (the distance between
eye bolts). This
safety hooks
or shackles.
the drawout units and make a complete inspection of the internal ensures a maximum A
structure, busbars, insulators, and unit components for possible angle of 45º as shown.
hidden damage. Report any damage found to the carrier at once. Lift Hole
MOTOR CONTROL CENTER Lift Angle
Handling
The following guidelines are provided to help avoid personal injury
Figure 5. Correct Use of Lifting Angle
and equipment damage during handling, and to facilitate moving
the motor control center at the job site.
4. After removing the lifting angles, replace the mounting hardware
General hints to prevent the entrance of dirt, etc.
1. Handle the motor control center with care to avoid damage to Forklift truck
components and to the enclosure or its paint finish.
Motor control centers are normally top and front heavy. Balance the
2. Keep the motor control center in an upright position. load carefully, and steady, as necessary, while moving. Always use
3. Ensure that the moving means has the capacity to handle the a safety strap when handling with a forklift.
weight of the motor control center.
Rollers
4. The control center should remain secured to the shipping skid
until the motor control center is in its final location. Rod or pipe rollers, with the aid of pinch bars, provide a simple
method of moving the motor control center on one floor level, if
5. Exercise care during any movement and placement operations
there is no significant incline. Roll the motor control center slowly,
to prevent falling or unintentional rolling or tipping.
and steady the load to prevent tipping.
6. Lifting angles for handling by overhead crane are bolted to the
top of each shipping section. Handling by overhead crane is Storage
preferable, but when crane facilities are not available, the motor
When a motor control center cannot be installed and placed into
control center can be positioned with a forklift truck or by using
operation immediately upon receipt, take steps to prevent damage
rollers under the shipping skid.
by condensation or harsh environmental conditions. If the motor
control center cannot be installed in its final location, store it in a
clean, dry, ventilated building, heated to prevent condensation, and
protected from dirt, dust, water, and mechanical damage. When
storage conditions are less than ideal, install temporary electrical
heating, typically in the form of light bulbs, totaling 150 watts per
section, hung in the vertical wireway, or by applying power to self-
contained space heaters that the motor control center may be
equipped with. Remove all loose packing and flammable materials
before energizing any of the heating elements.
B. Persons working on exposed parts that are or may be energized 1. Run a grounding electrode conductor (ground wire)
should, in addition, be qualified persons who have been trained having a size in accordance with NEC 250.94 from the
to work on energized circuits. grounding electrode to the MCC ground bus or ground
terminal provided. See also NEC 250.92(A) and 92(B).
Installation 2. If the system is grounded at any point ahead of the
MCC, the grounded conductor must be run to the MCC
1. Before any installation work begins, consult all drawings in accordance with NEC 250, and connected to the
furnished by Eaton, as well as all applicable contract drawings ground bus terminal.
for the installation. Give particular attention to the physical
location of units in the control center and their relation to existing 3. Do not make any connections to ground on the load side
or planned conduit, busways, etc. Provide for future conduit of any neutral disconnecting line or any sensor used
entrance prior to control center installation. for ground-fault protection. Do not connect outgoing
grounding conductors to the neutral.
2. Locate the control center in the area shown on the building floor
plans. If in a wet location or outside of the building, protect the b. MCCs used as service equipment for an ungrounded
control center from water entering or accumulation within the system or as an incoming line section for a separately
enclosure. Recommended clearances or working spaces are derived, previously ungrounded system:
as follows: 1. Run a grounding electrode conductor (ground wire)
a. Clearance from walls (where not rear accessible)— having a size in accordance with NEC 250.94 from the
a minimum of 1/2-inch for indoor and 6 inches for outdoor grounding electrode to the MCC ground bus terminal.
or wet locations. See NEC 250.92(A) and 92(B).
b. Clearance from front of MCC (working space)—minimum c. MCCs not used as service equipment nor as an incoming line
of 3 feet for control centers without exposed live parts. section for a separately derived system, and used on either a
See NEC 110.13. grounded or ungrounded system:
NNote: This working space should not be used for storage and should 1. Ground the MCC ground bus by means of equipment
have adequate lighting. grounding conductors having a size in accordance with
NEC 250.95 or by bonding to the raceway enclosing
3. Since MCCs are assembled at the factory on smooth and level the main supply conductors in accordance with
surfaces to ensure correct alignment of all parts, MCCs should NEC 250.92(B).
be securely mounted on a level surface. The foundation furnished
8. When all wiring and adjustments are complete, close all unit and
by the purchaser must be true and level, or the bottom frames
wireway doors.
must be shimmed to support the entire base in a true plane. It is
recommended that leveled channel sills under both the front and 9. In damp indoor locations, shield the MCC to prevent moisture
rear of the control center be used to provide this level base. Drill and water from entering and accumulating.
and tap the channel sills for mounting bolts in accordance with 10. Unless the MCC has been designed for unusual service
the applicable floor plan drawing and then either install the MCC conditions, it should not be located where it will be exposed
level with, or on top of, the finished floor. If sills are grouted in to ambient temperatures above 40°C (104°F), corrosive or
concrete, the mounting bolts should be screwed in place and explosive fumes, dust, vapors, dripping or standing water,
remain until the concrete has hardened. abnormal vibration, shock, or tilting.
m Caution
Do not use emery cloth or any abrasive containing metal.
Carriage Splice
Bolt Plate
21" Deep
Nut
Plate
16" Deep
16" Deep
Flat Lock
Hex–Head Bolt Washer Washer Figure 11. Quadruple-Bar Splice Kits
21" Deep
16" Deep
Front Face
Eight Bars per Phase—21" Deep
m WARNING
Specific safety note for installing and removing MCC units—
recommend the use of new accessory.
Wiring
Install the line and load conductors sized in accordance with the NEC.
Use copper wire only for control terminations. Use copper wire
only for power terminations unless they are marked “CU/AL.”
Use conductors with a temperature rating of 167ºF (75ºC) or higher,
but regardless of the insulation temperature rating, select the wire
size on the basis of 167ºF (75ºC) wire ampacity. Using a higher
temperature wire ampacity table often results in a smaller cross-
section of copper available for carrying heat away from terminals.
Install insulated wire and cable at a temperature sufficiently warm to
prevent the insulation from cracking or splitting.
When more than one conduit is run from a common source or to a
common load, be sure to have each conduit carry conductors from
each phase and the same number of conductors per phase. If the
phase conductors are not distributed uniformly, eddy currents will
be generated in the steel between the conduits.
Locate conductors within the MCC to avoid physical damage and
to avoid overheating. Secure incoming power lines in a manner
adequate to withstand the forces that will act to separate the
conductors under short-circuit conditions. Use the cable ties
furnished in both horizontal and vertical wireways to support the
load and interconnection wire. Use a shielded communications cable Figure 17. Unit Terminal Blocks
inside of flexible metal conduit to protect very low voltage signals
transmitted to or from a computer or programmable controller.
Lugs furnished with the MCC and its components are for Class B
and Class C stranding. Verify the compatibility of wire size, type, and
stranding with the lugs furnished. Where they are not compatible,
change the wire or lugs accordingly. If crimp lugs are used, crimp
with the tools recommended by the manufacturer.
Use care in stripping insulation to avoid nicking or ringing the metal.
All field wiring to control units should be made in accordance with
the wiring drawings that are furnished with the control center. Load
and control wiring can be brought in through the upper and/or lower
horizontal wireways. Determine the type of wiring installed in the
control center (NEMA Type B or C) and proceed per the following
appropriate paragraph.
The phase sequence of the power circuit load terminals (top-to-
bottom: T1, T2, T3) in units mounted on the rear side of the MCC is
opposite to that of the load terminals in units mounted on the front
side of a back-to-back MCC. To obtain the same direction of rotation
for a motor connected to a rear-mounted unit as for one connected
to a front-mounted unit, re-label the terminals in the rear-mounted
unit: T3, T2, T1, and wire accordingly. Refer to the warning sticker
supplied with rear-side units. When making power connections
to the starter terminals, be sure to leave sufficient slack in the
wires so that the unit can be withdrawn to the detent position Figure 17a. Pull-Apart Terminal Blocks
for maintenance. See Table 2 on page 16.
Vertical
Wireway
Stab
Connections
Figure 19. Main Disconnect with Stab Load Connections Figure 21. Main Circuit Breaker
Overcurrent Protection to be Located in the MCC, Provided
the Feeder Taps from the Transformer are Sufficiently Short
and Other Requirements are Met
Rope Requirements:
3/8" diameter
Nylon, twisted
Size = #12
3 strand
Tensile strength = 3340 lbs (1515 kg)
Working load = 278 lbs (126 kg)
Cable
Rope
Note 1
Cable
Lugs
(Note 2)
Note 1
Instructions:
1. Route cable as close together as possible.
2. Wrap rope around the cable 6 in (152.4 mm) from lugs (see Note 1).
3. The second wrap is to be applied 6 in (152.4 mm) from the first wrap.
4. After the second wrap, the cables should be wrapped at 12 in (304.8 mm) increments to the entry or exit point of the switchgear.
5. Verify that each set contains 5 loops and that all ropes are pulled as tight as possible.
Note 1: The goal is to bundle all cables together in one bundle, but near the lug landings, so the bundles may need to separate.
In this case, the rope between cables should be wrapped to provide support.
Note 2: The center pole cable lugs are shown in-line with outer poles; Figure 21 shows lugs with center pole offset either leading
or lagging outer poles, depending on top or bottom feed cables. The six-inch dimension shown in these arrangements is from the closed lug,
which is the center pole for top entry and outer poles for bottom entry as shown in Figure 21.
Description lb-in
1. Before energizing the motor control center (MCC), conduct a
thorough inspection to make certain that all foreign materials, Control Wiring
such as tools, scraps of wire, and other debris, are removed Coil leads 8 lb-in
from all units and the structure. Remove any accumulation of Relays 8 lb-in
dust and dirt with a vacuum cleaner.
Pushbuttons 8 lb-in
2. All circuit connections are tightened at time of assembly Control fuse blocks 8 lb-in
by power-driven tools with controlled torque. However, the
vibrations experienced in transit may loosen some of these Auxiliary contacts 8 lb-in
connections. Check at least 10% of the total connections for a Control Wiring Terminal Blocks
tight connection. Should this spot-check reveal some loose Side-mounted lug/compression 4.5 lb-in
connections, it will be necessary to check all connection Rail-mounted lug type 12 lb-in
points. The connections to be checked include bus hardware,
Rail-mounted compression type 18 lb-in
circuit breaker and switch terminals, contactor and relay
terminals, and terminal blocks. Always check the incoming line Unit Load Terminal Block
connections. Tighten to the torque values shown in Table 1. 100A load block 110 lb-in
3. Remove all blocks or other temporary holding means used for 180A load block 150 lb-in
shipment from all component devices in the MCC interior.
4. Check the enclosure to see that it has not been damaged so as
to reduce electrical spacings. Table 2. Power Wiring—Starters
5. Compare all circuits for agreement with the wiring diagrams that Tightening Torque Load Side
XT Contactor
accompany the MCC. Be sure that each motor is connected to Catalog Number Slotted Torque (lb-in) Conductors
its intended starter.
Power wire (AWG) Use 75°C
6. Make certain that field wiring is clear of live busses and NEMA size 1 14–6 25 copper
physically secured to withstand the effects of fault current. conductors
NEMA size 2 12–2 35
7. Check to determine that all grounding connections are NEMA size 3 8–250 kcmil 120
made properly.
NEMA size 4 9–250 kcmil 120
8. Check all devices for damage. Make all necessary repairs or NEMA size 5 1/0–250 200
replacements, prior to energizing.
XT contactor/starter Control wire (AWG)
9. Manually exercise all switches, circuit breakers, and other
#16–14 10
operating mechanisms to make certain that they are properly
aligned and operate freely.
10. Test any ground-fault protection systems that were furnished.
11. Set any adjustable current and voltage trip mechanisms to the Table 3. C440 Solid-State Overload Relay
proper values. Terminal Wire Size (AWG) Torque lb-in
12. Ensure that overload relay heater elements are installed and Control 2 x (18–12) 9
selected to the full-load current shown on the nameplate of
NEMA size 1 and 2 1 x (12–100) 23
each motor.
1 x (8–6) 28
13. Install power circuit fuses in the fusible switches in accordance
NEMA size 3 1 x (6–1) 28
with NEC application requirements. Make sure that fuses are
completely inserted in the clips provided. Do not attempt to
defeat the rejection feature on the fuse clip, when provided.
Breakers—Refer to torque values on breaker case.
14. Do not operate a current transformer with its secondary circuit
open. Ensure current transformer is connected to a load, or a
secondary shorting bar is installed. Table 4. Incoming Line Lugs
Description lb-in
15. To prevent possible damage to equipment or injury to personnel,
check to ensure that all parts and barriers that may have #2/0–350 kcmil 360 lb-in
been removed during wiring and installation have been #2/0–650 kcmil 360 lb-in
properly reinstalled. #2/0–750 kcmil 500 lb-in
16. Conduct an electrical insulation resistance test to make sure 500–1000 kcmil 600 lb-in
that the MCC and field wiring are free from short circuits and
grounds. Do this test phase-to-phase, phase-to-ground, and
phase-to-neutral, with the switches or circuit breakers opened.
Table 5. Bus Bolts
17. If the MCC contains a labyrinth vertical bus barrier system,
verify the operation of the automatic shutters. See Part 7 for Description lb-in
adjustments of this mechanism. All 360 lb-in
18. Install covers, close doors, and make certain that no wires
are pinched and that all enclosure parts are properly aligned
and tightened.
19. Turn all circuit breakers and fusible switches to the OFF position
before energizing the bus.
m caution
Units 18” or more high have a retaining brace at the lower edge
of each side of the unit frame to add stability in shipping. The
shipping braces may be retained or removed after installation;
unscrew prior to unit withdrawal.
m caution
Units 18 inches or more high have a retaining screw at the
lower edge of each side of the unit frame to add stability in
shipping. The shipping screws may be retained and reused or
removed after installation; unscrew prior to unit withdrawal.
Removing a unit
1. Turn unit operator OFF and keep unit door closed. At this point,
the Stab Position Indicator should show RED, indicating that the
stabs are fully extended and connected to the vertical bus. The
Shutter Position Indicator should show RED, also indicating that
the shutters are open.
2. To disconnect the stabs from the vertical bus, a 3/8-inch square
drive should be inserted into the Racking Receiver. The 3/8-inch
square drive can either be a manual tool or a remote racking
device. Please see IL04300001E for instructions on proper Figure 30. Disengaging Pull-Apart Terminal Blocks
installation of the remote racking device. Rotate the square drive
counterclockwise to begin to remove the stabs. If you happen
to rotate clockwise, the unit should spin freely and prevent the
stabs from being forced any further on the vertical bus. The Stab
Position Indicator flag and the Shutter Position Indicator flag
should begin to rotate to show the position of the stabs and
internal shutter. It takes approximately 30 full rotations to move
the stabs from the CONNECTED to the DISCONNECT position,
at the end of the transition a CLICKING sound is audible. The
DISCONNECT position will be illustrated when the Stab Position
Indicator and the Shutter Indicator are both showing GREEN.
Open the vertical wireway door to remove any plug-in terminal
blocks that might be connected to the unit (Figure 30). Please
look for any additional wiring that might be terminated inside
the unit. These connections will need to be removed prior to
removal of the unit from the structure.
3. Turn the Unit Latch, which is located left of the unit operator
(Figure 31), counterclockwise approximately 1/4-turn.
4. Open unit door and remove any interconnection wiring between
units, master terminal block, or external point of the motor
control center (MCC). For units that contain a motor load stab,
disconnection of the motor leads is not required in order to
remove the unit from the structure. Figure 31. Defeater Mechanism
5. Inspect the unit for any other material, accessories, or cable that
might interfere with the removal of the unit.
6. Pull the unit toward you. Guide rails that assist in the removal of
the bucket will support the bucket. Visually verify that the shutter
in the structure for the bucket has closed over the opening to
the vertical bus. If the shutter did not close, please shut down
power to the MCC prior to replacement or repair of the shutter.
7. Close unit door by securing the door 1/4-turn latches on the right
side of the door to reduce access to the unit.
Starter
Device Island/Panel
Breaker Start, Stop,
Auto, Manual
1. Prior to installation of the unit, verify that the unit stabs are fully
withdrawn and the internal shutters are closed (Figure 33). The
unit latch at the top of the bucket needs to be flush with the top
of the bucket to prevent interference with the divider pan when
installing the bucket. The unit operator needs to be in the OFF
position and the unit latch should be turned down so the metal
tab on the left side of the unit is inside the unit. This will prevent
any interference with the structure frame when installing in
the structure.
2. Open the unit door and slide the bucket into the structure.
The unit uses two guide rails that are located on the left and
right side bottom of the divider pan. The top wrapper of the
unit has grooves on the left and right side that sit into the
guide rail (Figure 36).
Figure 34. Stabs in DISCONNECTED Position
6. Close unit door and secure unit latches located on the right side
of the door.
7. To connect the stabs to the vertical bus, a 3/8-inch square
drive should be inserted into the Racking Receiver. The 3/8-inch
square drive can either be a manual tool or a remote racking
device. Please see IL04300001E for instructions on proper
installation of the remote racking device. Rotate the square
drive clockwise to begin to insert the stabs. If you happen to
rotate counterclockwise, the unit should spin freely and prevent
the stabs from being withdrawn any further. The Stab Position
Indicator flag and the Shutter Position Indicator flag should begin
to rotate to show the position of the stabs and internal shutter. It
takes approximately 30 full rotations to move the stabs from the
DISCONNECTED to the CONNECTED position, at the end of
the transition a CLICKING sound is audible. The CONNECT
position will be illustrated when the Stab Position Indicator
and the Shutter Position Indicator are both showing RED.
8. At this point, the operator handle can be turned ON to energize Figure 37. Door Hinge Pin
the unit.
The 1/4-turn unit interlock is used to secure the unit into the 5. Insert unit.
structure. It also serves as the interlock to ensure that a unit is not
removed or inserted while the disconnect is in the ON position. If a
unit disconnect cannot be turned on, verify that the unit interlock is
in the engaged or locked position. This position is when the slot
is parallel to the floor. If a unit cannot be withdrawn, verify that the
unit interlock is fully in the unlocked or disengaged position.
The interlock is fully disengaged when the slot is rotated 1/4-turn
counterclockwise from parallel to the floor.
m caution
Maintenance of the control components requires that all
power to these components be turned OFF by opening the
branch circuit disconnect means and withdrawing the unit to
the DISCONNECTED position in the Freedom FlashGard MCC unit.
m caution
When using multiple padlocks with an adaptor, beware of
locking bars that are an asymmetrical shape. Fully inspect
and check effectiveness of arrangement being applied.
m warning
IF FULLY INSERTED, THE POWER AND CONTROL CIRCUITS WILL BE
ENERGIZED. Padlocking to prevent this handle movement
may be accomplished by the same method as described above.
m caution
All inspections and tests are to be made on controllers and
equipment that are de-energized, disconnected, and isolated
so that accidental contact cannot be made with live parts
Contact Plate
and so that all plant safety procedures will be observed. (Brass or Copper)
Door
Defeater Screw Cable Assemblies
Breaker Operator
Handle
Device Panel
Device Panel
Unit Terminal
Blocks
Figure 47. 20 Inches Wide, 16 Inches Deep, Figure 49. 20 Inches Wide, 21 Inches Deep,
Front-Mounted Only (4710A30) Front-Mounted Only (4710A31)
Figure 48. 24 Inches Wide, 16 Inches Deep, Figure 50. 24 Inches Wide, 21 Inches Deep,
Front-Mounted Only (4710A33) Front-Mounted Only (4710A34)
NNotes:
1. Minimum length of anchor bolt is 2.00 (50.8) (0.38-16 grade 5 torqued at 31 lb-ft).
A. For non-seismic, mount with two center bolts per enclosure.
B. For seismic, mount with minimum four corner bolts per enclosure.
2. Recommended maximum conduit height above floor line is 3.50 inches (88.9 mm).
3. Maximum conduit space with channel sills is 17.50 x 9.73 inches (444.5 x 247.1 mm).
4. For multiple structure assemblies, either one or both of these members is removed to provide
maximum unrestricted conduit space at the bottom of the MCC.
5. This conduit space is not recommended when a neutral bus and/or a space heater is required.
Otherwise this space is available for conduit. See Figure 53 for vertical dimensions.
Figure 51. 20 Inches Wide, 21 Inches Deep, Figure 53. Side View A
Front- and Rear-Mounted (4710A32)
Removable
Cover Ground Bus 12.12 (307.8) Horizontal Bus
Location Location 12.12 Horizontal Bus Location See Note 9
Top (307.8)
Conduit 3.12 (79.2) Ground Bus Vertical Bus Location
20.38 2.25 10.50
Space (517.6) 4.62 (117.3) Location (266.7) Removable Bus Barrier
(57.2)
or 4.62 (117.3)
16.00 3.12 (79.2)
5.41 Horizontal
(406.4) Wireway Removable Bus 2.25 A
(137.4) Barrier (57.2) 15.00 4.62 (117.3)
7.16 (181.9) (381.0)
2.20 Deep Flat Cover 4.62 (117.3)
(55.9) Supplied on See Note 9A
1.25 1.25 Rear of Front-
(31.7) (31.7) Vertical View Horizontal Wireway
Mounted-Only 7.16 (181.9) Deep
10.00 Structure C Rear Horizontal Wireway
(254.0) 7.50 See Note 7 4.97 (126.3) Deep
3.00 (76.2)
(190.5) 9.73 Channel
Top View (247.1) Sills Supplied
or Only When See Note 7
Removable Bottom 14.11 Specified
Frame Members (358.4)
See Note 4. (Not to 5.00
be removed for D
Floor Line (127.0)
seismic)
7.50 See Note 7
1.00 (25.4) 3.0 See Note 7
(190.5) (76.2)
1.25 1.25 See Note 9A
(31.7) (31.7) 15.73 (399.5) or
10.50 20.11 (510.8)
See Note 5 B 5.00 E
(266.7) Neutral Bus Location 3.00 (76.2) Channel
When Specified Floor Line (127.0)
5.41 (137.4) Sills Supplied Only
18.35 (466.1) When Specified
5.78 (146.8) Bottom Conduit Space 14.11
1.00 (358.4) 3.00 (76.2)
5.41 (137.4) See Notes 2 and 3 (25.4)
20.11
0.70 (510.8)
1.58 (40.1)
(17.8) 10.50
0.53 (13.5) Bottom View Neutral Bus Location When Specified
5.00 (266.7)
Dia. (2)
See Note 1 (127.0)
Figure 52. 10 Inches Wide, 16 or 21 Inches Deep, Figure 54. Side View B
Transition Structure (4710A35/6)
NNotes: 6. Master Terminal Block (MTB) assembly is furnished for Type C wiring only
1. Minimum length of anchor bolt is 2.00 (50.8) (0.38-16 grade 5 torqued when location not specified. MTB supplied at the bottom.
at 31 lb-ft). 7. Rear horizontal bus barrier not supplied with front-mounted-only structure.
A. For non-seismic, mount with two center bolts per enclosure. 8. Standard structure arrangement:
B. For seismic, mount with minimum four corner bolts per enclosure. A. In front
2. Recommended maximum conduit height above floor line is Without MTB: A and B = 9.00 (228.6 mm)
3.50 inches (88.9 mm). With MTB at bottom: A and B = 9.00 (228.6 mm)
3. Maximum conduit space with channel sills is 17.50 x 9.73 inches With MTB at top: A and B = 3.00 (76.2 mm)
(444.5 x 247.1 mm). B. In rear
4. For multiple structure assemblies, either one or both of these members Without MTB: C = 0, D = 72 (1828.8 mm), E = 3.00 (76.2 mm)
is removed to provide maximum unrestricted conduit space at the bottom With MTB at bottom: C = 0, D = 66.00 (1676.4 mm),
of the MCC. E = 9.00 (228.6 mm)”
5. This conduit space is not recommended when a neutral bus and/or a With MTB at top: C = 12, D = 60 (1524.0 mm), E = 3.00 (76.2 mm)
space heater is required. Otherwise, this space is available for conduit.
See Figure 54 for vertical dimensions.
Eaton Corporation
Electrical Sector
1111 Superior Avenue
Cleveland, OH 44114 USA
[Link]