JUPITER - (3000K, 6000K, 9000K) - H1 Smart Transformer Station Acceptance Test Guide

The document is an Acceptance Test Guide for Smart Transformer Stations (STS) by Huawei Technologies, detailing the acceptance criteria, testing procedures, and precautions for the JUPITER-3000K, 6000K, and 9000K models. It includes sections on tests before STS operation, such as appearance inspections and performance tests, as well as operational tests after powering on the STS. The guide emphasizes the importance of compliance with safety standards and proper installation procedures to ensure reliability and safety during operation.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
506 views37 pages

JUPITER - (3000K, 6000K, 9000K) - H1 Smart Transformer Station Acceptance Test Guide

The document is an Acceptance Test Guide for Smart Transformer Stations (STS) by Huawei Technologies, detailing the acceptance criteria, testing procedures, and precautions for the JUPITER-3000K, 6000K, and 9000K models. It includes sections on tests before STS operation, such as appearance inspections and performance tests, as well as operational tests after powering on the STS. The guide emphasizes the importance of compliance with safety standards and proper installation procedures to ensure reliability and safety during operation.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 37

Smart Transformer Station

JUPITER-(3000K, 6000K, 9000K)-H1

Acceptance Test Guide

Issue 01
Date 2023-02-10

HUAWEI TECHNOLOGIES CO., LTD.


Copyright © Huawei Technologies Co., Ltd. 2023. All rights reserved.
No part of this document may be reproduced or transmitted in any form or by any means without prior
written consent of Huawei Technologies Co., Ltd.

Trademarks and Permissions

and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd.
All other trademarks and trade names mentioned in this document are the property of their respective
holders.

Notice
The purchased products, services and features are stipulated by the contract made between Huawei and
the customer. All or part of the products, services and features described in this document may not be
within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements,
information, and recommendations in this document are provided "AS IS" without warranties, guarantees
or representations of any kind, either express or implied.

The information in this document is subject to change without notice. Every effort has been made in the
preparation of this document to ensure accuracy of the contents, but all statements, information, and
recommendations in this document do not constitute a warranty of any kind, express or implied.

Huawei Technologies Co., Ltd.


Address: Huawei Industrial Base
Bantian, Longgang
Shenzhen 518129
People's Republic of China

Website: https://e.huawei.com

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. i


Smart Transformer Station
Acceptance Test Guide Contents

Contents

1 Part I Overview........................................................................................................................ 1
1.1 Acceptance Criteria................................................................................................................................................................. 1
1.2 Introduction............................................................................................................................................................................... 1
1.3 Numbering Specifications for Acceptance Items.......................................................................................................... 1
1.4 Precautions................................................................................................................................................................................ 2

2 Part II Tests Before STS Operation...................................................................................... 4


2.1 Appearance and Structure Inspection.............................................................................................................................. 4
2.1.1 Overall STS............................................................................................................................................................................. 4
2.1.2 LV Panel................................................................................................................................................................................... 8
2.1.3 Transformer......................................................................................................................................................................... 10
2.1.4 MV Room............................................................................................................................................................................. 12
2.1.5 Structure and Appearance Inspection Result........................................................................................................... 14
2.2 Function and Performance Tests..................................................................................................................................... 15
2.2.1 Auxiliary Loop..................................................................................................................................................................... 15
2.2.2 LV Panel................................................................................................................................................................................ 17
2.2.3 Transformer Signal............................................................................................................................................................ 20
2.2.4 Ring Main Unit................................................................................................................................................................... 27
2.2.5 Completion of Function and Performance Tests.................................................................................................... 30

3 Part III STS Operation Tests................................................................................................ 32


3.1 STS Operation........................................................................................................................................................................ 32
3.2 Completion of STS Operation Tests................................................................................................................................ 33

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. ii


Smart Transformer Station
Acceptance Test Guide 1 Part I Overview

1 Part I Overview

1.1 Acceptance Criteria


1.2 Introduction
1.3 Numbering Specifications for Acceptance Items
1.4 Precautions

1.1 Acceptance Criteria


This guide is written based on the actual conditions of Huawei equipment.

1.2 Introduction
This document provides guidance for onsite acceptance tests of smart transformer
stations (STSs).
This document applies to JUPITER-3000K-H1, JUPITER-6000K-H1, and
JUPITER-9000K-H1.
This document consists of three parts:
Part I Overview: describes the acceptance criteria, introduction, and precautions.
Part II Tests Before STS Operation: describes the acceptance items, test methods,
and criteria for tests performed before the STS main loop is powered on.
Part III STS Operation Tests: describes the STS test items performed after the STS
main loop is powered on.

1.3 Numbering Specifications for Acceptance Items


Numbering specifications for acceptance items
Four-digit numeration
An acceptance item is numbered in the format of TXX-XX.
The meaning of the acceptance item number is as follows.

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. 1


Smart Transformer Station
Acceptance Test Guide 1 Part I Overview

1.4 Precautions

NOTICE

● Personnel who will operate the equipment, including operators, trained


personnel, and professionals, should possess the required local national
qualifications in special operations such as high-voltage operations, working at
heights, and operations of special equipment.
● If there is a likelihood of personal injury or equipment damage during
operations, stop immediately, report the case to the supervisor, and take
feasible protective measures.
● Use tools correctly to prevent personal injury and equipment damage.
● When operating the equipment, wear high-voltage insulation gloves, a safety
helmet, insulation shoes, and insulation clothing. When commissioning and
operating the ring main unit, operate the secondary compartment using an
insulated stool.

After arriving at the site, the installation personnel should follow the instructions
and precautions in the user manual and installation guide of the corresponding
Huawei product and pay attention to the following points:

1. Huawei personnel need to discuss with the customer to specify the owner of
each party. The owners are responsible for coordination during the project
installation.
2. Before the kickoff, the two parties need to formulate the project schedule. For
all events that may affect the project schedule, both parties need to specify
reasons and provide solutions in written form.
3. The engineering personnel should check the site environment according to
the requirements specified in the product preparation guide. If the site
environment meets the requirements for project kickoff, the personnel will
start accepting the products and filling in the acceptance list. If there are
missing, incorrect, or damaged parts, contact Huawei in a timely manner to
deliver those parts as soon as possible.
4. The personnel must install the hardware with caution according to the user
manual. After the installation is complete, assign relevant personnel in a
timely manner to perform the equipment acceptance inspection.
5. Both parties need to perform the equipment acceptance and preliminary
acceptance test in strict accordance with relevant standards. Some indicators

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. 2


Smart Transformer Station
Acceptance Test Guide 1 Part I Overview

and parameters have already been tested before delivery. Such items can be
omitted or spot-checked.
6. After the acceptance tests are passed, the system can be commissioned for
operation.
7. The test tools mentioned in this guide are for reference only.

NOTE

Acceptance tests should be performed in compliance with the contract and conventions
agreed by both parties. This guide only serves as a reference.

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. 3


Smart Transformer Station
Acceptance Test Guide 2 Part II Tests Before STS Operation

2 Part II Tests Before STS Operation

2.1 Appearance and Structure Inspection


2.2 Function and Performance Tests

2.1 Appearance and Structure Inspection


Prerequisites:
AC power supply is OFF.
DC power supply is OFF.
Purpose:
To ensure that the delivered STS is intact and to prevent faults caused by
transportation and installation from affecting the reliability and safety of the STS
during subsequent operation.
Test tools:
Torque wrench, ground resistance tester, and multimeter

2.1.1 Overall STS


No. Item Test Method Acceptance Criteria Test Test
Data Result
(If
Any)

T01- Produc Visual The model and quantity □


01 t inspection of the STSs received by Passed
deliver the customer are □ Failed
y consistent with those in
the contract. □ N/A

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. 4


Smart Transformer Station
Acceptance Test Guide 2 Part II Tests Before STS Operation

T01- Consist Visual The packing list is □


02 ency inspection consistent with the Passed
betwee delivered products. □ Failed
n the The spare parts and
packin □ N/A
accessories are complete
g list and delivered with the
and STS.
deliver
ed
produc
ts

T01- STS Visual 1. The enclosure of the □


03 appear inspection STS is free of damage, Passed
ance dents, and cracks. □ Failed
2. If there is a small area □ N/A
of rust, paint the area
according to the user
manual. A large area (0.5
m2 or above) of rust is not
allowed.

T01- STS Visual The sealing rubber strips □


04 sealing inspection are intact and do not fall Passed
off. There is no crack in □ Failed
the sealing areas.
□ N/A

T01- Screen Visual The screen doors of the □


05 doors inspection transformer room are Passed
of the intact without □ Failed
transfo deformation.
rmer □ N/A
room

T01- Doors Visual The doors are closed □


06 of low- inspection tightly. No water or Passed
voltage foreign matter is found in □ Failed
(LV) the LV or MV room.
and □ N/A
mediu
m-
voltage
(MV)
rooms

T01- STS Visual The STS is installed at the □


07 installa inspection specified position. Passed
tion □ Failed
□ N/A

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. 5


Smart Transformer Station
Acceptance Test Guide 2 Part II Tests Before STS Operation

T01- STS Visual The STS is securely □


08 stabilit inspection installed in the right Passed
y position without tilt or □ Failed
force around.
□ N/A
The onsite foundation
meets the requirements in
the STS user manual.

T01- STS Visual The screws on the ground □


09 ground inspection point of the enclosure are Passed
ing tightened and aligned □ Failed
with the marked lines.
□ N/A
The ground label at the
ground point is intact.

T01- Ground Visual The transformer and □


10 ing of inspection doors of the container, LV Passed
the panel, and MV room, as □ Failed
transfo well as other accessible
rmer places are grounded, □ N/A
and grounding labels are in
doors place, and ground cables
of the are securely connected.
contain
er, LV
panel,
and
MV
room

T01- STS Measure the The screws on the ground □


11 ground resistance point of the enclosure are Passed
ing between two tightened and aligned □ Failed
ground with the marked lines.
points by □ N/A
The ground label at the
using a ground point is intact.
ground
resistance Measure the ground
tester. resistance of the ground
points, and ensure that
the resistance is less than
or equal to 0.1 ohm.

T01- Damag Visual All components in the STS □


12 e or inspection are free of damage, Passed
shifts deformation, and visible □ Failed
of the shifts.
compo □ N/A
nents
in the
STS

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. 6


Smart Transformer Station
Acceptance Test Guide 2 Part II Tests Before STS Operation

T01- Cables Visual Cables in the STS are □


13 in the inspection securely installed. Passed
STS □ Failed
□ N/A

T01- Total Visual The total capacity of the □


14 capacit inspection connected inverters does Passed
y of not exceed the rated □ Failed
the capacity of the STS.
connec □ N/A
ted
inverte
rs

T01- Cross- Visual The cross-sectional areas □


15 section inspection of the input and output Passed
al power cables are within □ Failed
areas the ranges specified in the
of user manual. □ N/A
input
and
output
power
cables

T01- Connec Visual All cables are secured to □


16 tions inspection prevent disconnection or Passed
of safety incidents. □ Failed
input
and □ N/A
output
power
cables
as well
as
comm
unicati
ons
cables

T01- Bend Visual The cable bend radius is □


17 radius inspection at least 15 times the cable Passed
of AC cross-sectional area. A □ Failed
power small bend radius will
cables result in excessive stress □ N/A
on the power cable,
exerting negative impact
on the device.

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. 7


Smart Transformer Station
Acceptance Test Guide 2 Part II Tests Before STS Operation

T01- AC Visual 1. The AC power cables □


18 power inspection and communications Passed
cables cables reserved in the STS □ Failed
and for the SACU are correctly
comm connected to the SACU. □ N/A
unicati The PG connectors at the
ons holes for cables between
cables the SACU and the STS are
reserve sealed.
d in 2. Both ends of the
the reserved AC power cables
STS for and communications
the cables (if unused) are not
Smart energized (the switches in
Array the LV panel are turned
Control off or the cables are
ler removed). The cables are
(SACU) properly protected and
the PG connectors at the
holes for cables between
the SACU and the STS are
intact.

2.1.2 LV Panel
No. Item Test Method Acceptance Criteria Test Test
Data Result
(If
Any)

T01- LV Visual The panel and internal □ Passed


19 panel inspection components are secured □ Failed
— reliably and securely.
stabilit □ N/A
y

T01- LV Visual The internal cables are □ Passed


20 panel inspection securely connected and □ Failed
— aligned with the marked
reliabil lines. □ N/A
ity of
cable
connec
tions

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. 8


Smart Transformer Station
Acceptance Test Guide 2 Part II Tests Before STS Operation

T01- LV Visual The panel is well □ Passed


21 panel inspection grounded inside. The □ Failed
— screws on the ground
groun point are tightened and □ N/A
ding aligned with the marked
reliabil lines.
ity The ground label at the
ground point is intact.

T01- LV Visual There is no foreign matter □ Passed


22 panel inspection such as tools and cable □ Failed
— residue in the panel.
foreign □ N/A
matter

T01- LV Visual The cable holes at the □ Passed


23 panel inspection bottom of the LV panel □ Failed
— have been sealed using
botto firestop putty. □ N/A
m
sealing

T01- LV Visual The copper bars in the LV □ Passed


24 panel inspection room of the STS are not □ Failed
— loose, disconnected, or
copper deformed. □ N/A
bars

T01- Cable Visual Labels on incoming AC □ Passed


25 labels inspection power cables of the LV □ Failed
panel are intact and
legible. □ N/A

T01- Conne Adjust the Screws are not loose. □ Passed


26 ction torque Screws for the incoming □ Failed
of AC wrench to a cables of the LV panel are
cables proper torque tightened to the standard □ N/A
and rotate torque. Do not impose
the handle to large stress on the screws.
ensure that For details, see the user
the screws manual.
are tightened.

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. 9


Smart Transformer Station
Acceptance Test Guide 2 Part II Tests Before STS Operation

T01- LV Turn on and The disconnectors, MCBs, □ Passed


27 panel off the and MCCBs in the LV □ Failed
— disconnectors panel can be turned on
switch , miniature and off. □ N/A
es circuit
breakers
(MCBs), and
molded case
circuit
breakers
(MCCBs) in
the LV panel.

2.1.3 Transformer
No. Item Test Method Acceptance Criteria Test Test
Data Result
(If
Any)

T01- Transf Visual The transformer □ Passed


28 ormer inspection enclosure is free of □ Failed
— defects and paint peeling.
enclos □ N/A
ure

T01- Transf Visual The screws on the ground □ Passed


29 ormer inspection point of the enclosure are □ Failed
— tightened and aligned
enclos with the marked lines. □ N/A
ure The ground label at the
groun ground point is intact.
ding

T01- Transf Check all All components are □ Passed


30 ormer sealing rings sealed properly and no oil □ Failed
— of the leakage occurs around
transfo transformer, the sealing rings. □ N/A
rmer including the
sealin seal of the
g transformer
box, oil level
meter, oil
temperature
meter, heat
sink, oil drain
valve,
butterfly
valve, and tap
changer.

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. 10


Smart Transformer Station
Acceptance Test Guide 2 Part II Tests Before STS Operation

T01- Transf Visual The clamping plate for □ Passed


31 ormer inspection the pressure release valve □ Failed
— is removed, and the
pressu actuating strut of the □ N/A
re pressure release valve is
release in the normal position.
valve

T01- Transf Visual There is no gas in the □ Passed


32 ormer inspection transformer gas relay □ Failed
— gas (gas needs to be released
relay if any). □ N/A

T01- Transf Visual The butterfly valves on □ Passed


33 ormer inspection both sides of the gas □ Failed
— relay are open.
butterf □ N/A
ly
valve

T01- Transf Visual The appearance of the □ Passed


34 ormer inspection OTI and WTI (if any) is □ Failed
— oil normal, the pointer
tempe indication is normal, and □ N/A
rature there is no foreign matter
indicat in the watch face.
or
(OTI)
and
windin
g
tempe
rature
indicat
or
(WTI,
if any)

T01- Transf Visual 1. The oil level meter can □ Passed


35 ormer inspection be observed without □ Failed
— oil obstacles.
level □ N/A
2. The indicated oil level
meter is in accordance with the
oil level-oil temperature
curve of the transformer.

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. 11


Smart Transformer Station
Acceptance Test Guide 2 Part II Tests Before STS Operation

T01- Transf Visual The STS is properly □ Passed


36 ormer inspection installed. Before the STS □ Failed
— is put into operation, the
dehydr dehydrating breather is □ N/A
ating properly installed. The
breath dehydrating breather
er (common model)
appearance is normal and
intact and the color of
silicon gel is normal. If
the color of more than
half of the silicon gel is
abnormal, replace the
silicon gel in the
dehydrating breather.

T01- Transf Visual The transformer tap □ Passed


37 ormer inspection changer is set to position □ Failed
— tap 3 before delivery. Adjust
chang the tap changer position □ N/A
er based on site
setting requirements and tighten
the protective cover.

2.1.4 MV Room
No. Item Test Acceptance Criteria Test Test
Method Data Result
(If
Any)

T01- MV Visual All internal components □


38 room inspection are securely installed Passed
— without shifting or □ Failed
stabilit loosening.
y □ N/A

T01- MV Visual The internal cables are □


39 room inspection securely connected and Passed
— aligned with the marked □ Failed
reliabil lines.
ity of □ N/A
cable
connec
tions

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. 12


Smart Transformer Station
Acceptance Test Guide 2 Part II Tests Before STS Operation

T01- MV Visual The screws on the indoor □


40 room inspection ground point of the Passed
— enclosure are tightened □ Failed
ground and aligned with the
ing marked lines. □ N/A
reliabil The ground label at the
ity ground point is intact.

T01- MV Visual There is no foreign matter □


41 room inspection such as tools and cable Passed
— residue in the MV room. □ Failed
foreign
matter □ N/A

T01- MV Check and The gas pressure indicator □


42 room record the pointer is in the green Passed
— gas value of the area. □ Failed
pressur gas pressure
e indicator of □ N/A
indicat the ring
or of main unit. If
the a Siemens
ring ring main
main unit
unit indicator is
used, record
the color of
the pointed
area.

T01- Conne Adjust the For the torque used to □


43 ction torque securing MV outgoing Passed
of wrench to a cables, see the □ Failed
incomi proper specifications of the cable
ng and torque and connector purchased by □ N/A
outgoi rotate the the customer. Do not
ng AC handle to impose large stress on the
cables ensure that screws. For details, see the
the screws user manual.
are
tightened.

T01- MV Turn on and The switches of the ring □


44 room off the main unit can be turned on Passed
— switches of and off normally. □ Failed
switch the ring
es of main unit. □ N/A
the
ring
main
unit

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. 13


Smart Transformer Station
Acceptance Test Guide 2 Part II Tests Before STS Operation

T01- MV Turn on and The fuses and circuit □


45 room off the fuses breakers can be turned on Passed
— and circuit and off normally. □ Failed
switch breakers in
es in the auxiliary □ N/A
the power
auxilia distribution
ry box.
power
distrib
ution
box

2.1.5 Structure and Appearance Inspection Result


Result of the o Passed
Tests
o Failed (Known issues can be described in the
following remarks)

Remarks

Huawei representative

Name: ___________________________

Role: ___________________________

Date: ___________________________

Signature: ________________________

Customer representative

Name: __________________________

Role: ___________________________

Date: ___________________________

Signature: _______________________

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. 14


Smart Transformer Station
Acceptance Test Guide 2 Part II Tests Before STS Operation

2.2 Function and Performance Tests


Prerequisites:

An auxiliary device (generator) is available to supply power to the auxiliary loop


of the STS.

Purpose:

To verify the reliability and effectiveness of devices and components; to ensure


safe and reliable operation of the STS by rectifying non-compliant items.

Test tools:

Insulation tester, diesel generator (DG), multimeter, laptop, network cable (30 m),
insulation cap, insulation pad, insulation rod, and insulation gloves

2.2.1 Auxiliary Loop


No. Item Test Method Acceptance Test Test
Criteria Data Result
(If
Any)

T02 Insulation Disconnect the The insulation □


-01 of the fuse of the surge resistance is Passed
auxiliary protective device higher than 10 □ Failed
loop (SPD) in the megohms.
auxiliary loop, turn □ N/A
off the main power
switch 3FB of the
auxiliary loop,
switch on other
MCBs of the
auxiliary loop, and
measure the
insulation
resistance between
the 3XDY2 terminal
and the ground.
Adjust the test
voltage of the
insulation tester to
1000 V and
maintain the
voltage for 1
minute, and record
the insulation
resistance values at
the 10th second,
30th second, and
60th seconds.

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. 15


Smart Transformer Station
Acceptance Test Guide 2 Part II Tests Before STS Operation

T02 Power-on In the auxiliary The auxiliary □


-02 of the power distribution equipment runs Passed
auxiliary box in the MV properly. □ Failed
loop room, apply
voltage to the □ N/A
main power supply
of the UPS and
low-power
auxiliary
equipment.

T02 UPS power Charge the UPS for After the external □
-03 supply a period of time (1 auxiliary power Passed
hour) and supply is □ Failed
disconnect the disconnected, the
external auxiliary auxiliary loop □ N/A
power supply. In keeps working
this case, the UPS without power
supplies power to interruption.
the auxiliary loop.

T02 Communic Connect the The SmartLogger □


-04 ation with SmartLogger to the can search for and Passed
the STS properly, set add the STS. The □ Failed
SmartLogg parameters teleindication and
er according to the telemetry signals □ N/A
installation guide, of the STS are
check whether the displayed properly
STS is connected to on the device
the SmartLogger monitoring page.
and whether the No alarm signal is
teleindication and displayed in the
telemetry signals alarm list.
of the STS on the
device monitoring
page are normal,
and check the
alarm list.

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. 16


Smart Transformer Station
Acceptance Test Guide 2 Part II Tests Before STS Operation

T02 Temperatu On the WebUI of All temperature □


-05 re/ the SmartLogger, and humidity Passed
Humidity view the top oil signals are □ Failed
monitorin temperature, displayed properly.
g winding □ N/A
temperature,
temperature in LV
panels A and B,
humidity in LV
panel B, humidity
of the
maintenance-free
dehydrating
breather (if any),
and temperature
and humidity in
the MV room.

T02 Fans On the STS The rotation □


-06 parameter setting speeds of all fans Passed
page of the are displayed □ Failed
SmartLogger properly. After the
WebUI, start fan fan self-check is □ N/A
self-check, check complete, no fan
the rotational fault alarm or
speeds of the fans cooling system
in the LV panel and fault alarm is
MV room. After the generated.
fan self-check is
complete (3
minutes later),
check the alarm
information on the
SmartLogger.

2.2.2 LV Panel
No. Item Test Method Acceptance Test Test
Criteria Data Result
(If
Any)

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. 17


Smart Transformer Station
Acceptance Test Guide 2 Part II Tests Before STS Operation

T02 Insulation Use a temporary The resistance is □


-07 of the LV ground cable to greater than 10 Passed
bus ground two busbars megohms. □
in the LV panel, Failed
connect the positive
pole of the □ N/A
insulation tester to
the third busbar,
and connect the
negative pole to the
ground. Apply 2.5
kV voltage for 1
minute, and record
the resistance at
the 10th, 30th, and
60th seconds.
For details about
the test method,
see the user
manual.

T02 Mechanica Perform the 1. MCCBs can be □


-08 l operation following steps on turned on and off Passed
of MCCBs all MCCBs in the LV twice smoothly. □
in the LV panel: 2. The MCCBs Failed
panel 1. Manually turn on trips after the Trip □ N/A
and off the MCCBs button is pressed.
twice. 3. The MCCBs
2. Press the Trip cannot be turned
button on the on after tripping.
MCCBs. 4. The MCCBs can
3. Attempt to turn be turned on
on the MCCBs after after being
tripping. turned off.
4. Turn off the
MCCBs and then
turn them on.

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. 18


Smart Transformer Station
Acceptance Test Guide 2 Part II Tests Before STS Operation

T02 Operation 1. Turn on and off 1. After the ON □


-09 of ACB in the ACBs twice. and OFF buttons Passed
the LV 2. Rotate the are pressed, the □
panel remote/local switch ACB can be Failed
on the panel of the normally turned
on and off. □ N/A
LV panel to the
local position, press 2. After the
the ON button and remote/local
then OFF button on switch on the
the panel of the LV panel of the LV
panel, and remotely panel is set to the
turn on and off the local position and
ACB in the LV panel the ON button
on the SmartLogger and then OFF
WebUI. button on the
3. Rotate the panel of the LV
remote/local switch panel are pressed,
on the panel of the the ACB can be
LV panel to the normally turned
remote position, on and off. After
press the ON the ACB turn-on
button and then and turn-off
OFF button on the operations are
panel of the LV performed on the
panel, and remotely SmartLogger
turn on and off the WebUI, the ACB
ACB in the LV panel does not respond.
on the SmartLogger 3. After the
WebUI. remote/local
switch on the
panel of the LV
panel is set to the
remote position
and the ON
button and then
OFF button on
the panel of the
LV panel are
pressed, the ACB
does not respond.
After the ACB
turn-on and turn-
off operations are
performed on the
SmartLogger
WebUI, the ACB
can be normally
turned on and
off.
4. The ACB turn-
on and turn-off

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. 19


Smart Transformer Station
Acceptance Test Guide 2 Part II Tests Before STS Operation

signal values on
the SmartLogger
WebUI are
consistent with
the actual ACB
operations.

2.2.3 Transformer Signal


No. Item Test Method Acceptance Test Test
Criteria Data Result
(If
Any)

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. 20


Smart Transformer Station
Acceptance Test Guide 2 Part II Tests Before STS Operation

T02 Transform Before the test, 1. When micro □


-10 er gas turn on the ACB in switch K1 of the Passed
relay the LV panel and gas relay is short- □ Failed
signal the circuit breaker circuited, the value
monitorin in the ring main of the light □ N/A
g unit. transformer gas
1. Short-circuit signal is 1 on the
micro switch K1 of SmartLogger
the gas relay and WebUI, and the
check the STS light transformer
teleindication gas alarm is
signal on the generated.
SmartLogger 2. When the short-
WebUI. circuit cable is
2. Remove the removed from
short-circuit cable micro switch K1 of
from micro switch the gas relay, the
K1 of the gas relay value of the light
and check the STS transformer gas
teleindication signal is 0 on the
signal on the SmartLogger
SmartLogger WebUI, and the
WebUI. light transformer
gas alarm is
3. Press the probe cleared.
of the gas relay
and view the status 3. After the probe
of the ACB in the of the gas relay is
LV panel and the pressed, the ACB
circuit breaker in in the LV panel
the ring main unit, and the circuit
and the breaker in the ring
teleindication main unit trip. The
signals and alarm value of the heavy
list on the transformer gas
SmartLogger signal is 1 on the
WebUI. SmartLogger
WebUI, and the
4. After step 3 is heavy transformer
complete, release gas alarm and
the gas relay transformer non-
probe. electrical
protection action
alarm are
generated.
4. After the probe
of the gas relay is
released, the value
of the heavy
transformer gas
signal becomes 0
on the

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. 21


Smart Transformer Station
Acceptance Test Guide 2 Part II Tests Before STS Operation

SmartLogger
WebUI, and the
heavy transformer
gas alarm and
transformer non-
electrical
protection action
alarm are cleared.

T02 Transform Before the test, 1. After the □


-11 er pressure turn on the ACB in actuating strut of Passed
release the LV panel and the pressure □ Failed
valve the circuit breaker release valve is
signal in the ring main manually pulled □ N/A
monitorin unit. up, the ACB in the
g 1. Manually pull up LV panel and the
the actuating strut circuit breaker in
of the pressure the ring main unit
release valve, check trip. The value of
the status of the the transformer
ACB in the LV pressure relief
panel and the valve action is 1
circuit breaker in on the
the ring main unit, SmartLogger
and check the WebUI, and the
teleindication transformer
signals and alarm pressure relief
list on the valve action alarm
SmartLogger and transformer
WebUI. non-electrical
protection action
2. Restore the alarm are
actuating strut of generated.
the pressure
release valve. 2. After the
actuating strut of
the pressure
release valve is
restored, the value
of heavy
transformer gas
changes to 0 on
the SmartLogger
WebUI, and the
transformer
pressure relief
valve action alarm
and transformer
non-electrical
protection action
alarm are cleared.

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. 22


Smart Transformer Station
Acceptance Test Guide 2 Part II Tests Before STS Operation

T02 Transform 1. Short-circuit the 1. After the □


-12 er oil level transformer oil transformer oil Passed
meter level low signal level low signal □ Failed
signal terminal in the terminal in the
monitorin terminal block of terminal block of □ N/A
g the LV panel, and the LV panel is
view the short-circuited, the
teleindication value of the
signals and alarm transformer oil
list on the level low signal
SmartLogger changes to 1 and
WebUI. the transformer oil
2. Short-circuit the level low alarm is
transformer oil displayed on the
level high signal SmartLogger
terminal in the WebUI.
terminal block of 2. After the
the LV panel, and transformer oil
view the level high signal
teleindication terminal in the
signals and alarm terminal block of
list on the the LV panel is
SmartLogger short-circuited, the
WebUI. value of the
3. Remove the transformer oil
short-circuit cable. level high signal
changes to 1 and
the transformer oil
level high alarm is
displayed on the
SmartLogger
WebUI.
3. After the short-
circuit cable is
removed, the
teleindication
signal values
change to 0, and
the preceding
alarms are
cleared.

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. 23


Smart Transformer Station
Acceptance Test Guide 2 Part II Tests Before STS Operation

T02 Transform Before the test, 1. The value of the □


-13 er oil turn on the ACB in transformer top oil Passed
temperatu the LV panel and temperature signal □ Failed
re the circuit breaker on the
monitorin in the ring main SmartLogger □ N/A
g unit. WebUI and the
1. Check the value pointer value of
of the transformer the transformer
top oil temperature OTI are basically
signal on the consistent (the
SmartLogger discrepancy is less
WebUI and the than 2 K).
pointer value of 2. After the
the transformer transformer oil
OTI. temperature high
2. Short-circuit the signal terminal in
transformer oil the terminal block
temperature high of the LV panel is
signal terminal in short-circuited, the
the terminal block value of the
of the LV panel, transformer oil
and view the temperature high
teleindication signal changes to
signals and alarm 1 and the
list on the transformer oil
SmartLogger temperature high
WebUI. alarm is displayed
on the
3. Short-circuit the SmartLogger
transformer oil WebUI.
temperature ultra
high signal 3. After the
terminal on the transformer oil
terminal block of temperature ultra
the LV panel, and high signal
check the status of terminal on the
the ACB of the LV terminal block of
panel and circuit the LV panel is
breaker of the ring short-circuited, the
main unit as well ACB of the LV
as the panel and the
teleindication circuit breaker of
signals and alarm the ring main unit
list on the trip. The value of
SmartLogger the transformer oil
WebUI. temperature ultra
high signal
4. Remove the changes to 1 and
short-circuit cable. the transformer
high oil
temperature–
induced tripping
alarm and

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. 24


Smart Transformer Station
Acceptance Test Guide 2 Part II Tests Before STS Operation

transformer non-
electrical
protection action
alarm are
displayed on the
SmartLogger
WebUI.
4. After the short-
circuit cable is
removed, the
teleindication
signal values
change to 0, and
the preceding
alarms are
cleared.

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. 25


Smart Transformer Station
Acceptance Test Guide 2 Part II Tests Before STS Operation

T02 Transform Before the test, 1. The value of the □


-14 er winding turn on the ACB in transformer Passed
temperatu the LV panel and winding □ Failed
re the circuit breaker temperature signal
monitorin in the ring main on the □ N/A
g unit. SmartLogger
(optional) 1. Check the value WebUI and the
of the transformer pointer value of
winding the transformer
temperature signal WTI are basically
on the consistent (the
SmartLogger discrepancy is less
WebUI and the than 2 K).
pointer value of 2. After the
the transformer transformer
WTI. winding
2. Short-circuit the temperature high
transformer signal terminal in
winding the terminal block
temperature high of the LV panel is
signal terminal in short-circuited, the
the terminal block value of the
of the LV panel, transformer
and view the winding
teleindication temperature high
signals and alarm signal changes to
list on the 1 and the
SmartLogger transformer
WebUI. winding
temperature high
3. Short-circuit the alarm is displayed
transformer on the
winding SmartLogger
temperature ultra WebUI.
high signal
terminal on the 3. After the
terminal block of transformer
the LV panel, and winding
check the status of temperature ultra
the ACB of the LV high signal
panel and circuit terminal on the
breaker of the ring terminal block of
main unit as well the LV panel is
as the short-circuited, the
teleindication ACB of the LV
signals and alarm panel and the
list on the circuit breaker of
SmartLogger the ring main unit
WebUI. trip. The value of
the transformer
4. Remove the winding
short-circuit cable. temperature ultra
high signal

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. 26


Smart Transformer Station
Acceptance Test Guide 2 Part II Tests Before STS Operation

changes to 1 and
the transformer
high winding
temperature–
induced tripping
alarm and
transformer non-
electrical
protection action
alarm are
displayed on the
SmartLogger
WebUI.
4. After the short-
circuit cable is
removed, the
teleindication
signal values
change to 0, and
the preceding
alarms are
cleared.

NOTE

After the preceding tests are complete, switch the remote/local switch of the LV panel and
ring main unit to the local position and maintain the position for more than 1 minute, and
then set the switch to the remote position.

2.2.4 Ring Main Unit


No. Item Test Method Acceptance Test Test
Criteria Data Result
(If
Any)

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. 27


Smart Transformer Station
Acceptance Test Guide 2 Part II Tests Before STS Operation

T02 Insulation Connect the The resistance is □


-15 of the MV positive pole of the greater than 100 Passed
loop insulation tester to megohms. □ Failed
the MV tube and
the negative pole □ N/A
to the ground.
Apply 2.5 kV
voltage for 1
minute. Record the
resistance at the
10th, 30th, and
60th seconds.
For details about
the test method,
see the user
manual.

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. 28


Smart Transformer Station
Acceptance Test Guide 2 Part II Tests Before STS Operation

T02 Operations 1. Press the turn- 1. The circuit □


-16 of the on and turn-off breaker is Passed
circuit buttons on the correctly turned □ Failed
breaker of circuit breaker on and off.
the ring panel of unit G2 in □ N/A
2. On the STS
main unit the ring main unit. teleindication
2. Set the remote/ page of the
local switch on the SmartLogger
panel of the ring WebUI, the
main unit to the value of remote
remote position. operation of
3. On the STS disconnector
telecontrol page of for transformer
the SmartLogger cabinet G2
WebUI, deliver the changes to 1.
medium-voltage 3. The circuit
circuit breaker on breaker of the
and medium- ring main unit
voltage circuit is turned on
breaker off and off
commands. successfully.
The values of
switch-on of
circuit breaker
for transformer
cabinet G2 and
switch-off of
circuit breaker
for transformer
cabinet G2 on
the STS
teleindication
page of the
SmartLogger
WebUI are
consistent with
the actual
circuit breaker
status.

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. 29


Smart Transformer Station
Acceptance Test Guide 2 Part II Tests Before STS Operation

T02 Operations Operate the G2 When the switch □


-17 of disconnector, G2 interlocking Passed
disconnect earthing switch, G1 requirements are □ Failed
ors, load load switch (if met, each switch
switches, any), G1 earthing can be operated □ N/A
and switch (if any), G3 smoothly. The
earthing load switch, and teleindication
switches G3 earthing switch signal values on
of the ring of the ring main the STS
main unit unit. teleindication
page of the
SmartLogger
WebUI are
consistent with
the actual switch
status.

2.2.5 Completion of Function and Performance Tests


Result of the Tests o Passed

o Failed (Known issues can be described in the


following remarks)

Remarks

Huawei representative

Name: ___________________________

Role: ___________________________

Date: ___________________________

Signature: ________________________

Customer representative

Name: __________________________

Role: ___________________________

Date: ___________________________

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. 30


Smart Transformer Station
Acceptance Test Guide 2 Part II Tests Before STS Operation

Signature: _______________________

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. 31


Smart Transformer Station
Acceptance Test Guide 3 Part III STS Operation Tests

3 Part III STS Operation Tests

3.1 STS Operation


3.2 Completion of STS Operation Tests

3.1 STS Operation


No. Item Test Method Acceptance Test Test
Criteria Data Result
(If
Any)

T03 No-load Turn off the ACB and The power-on □


-01 operation MCCB of the LV panel indicator on the Passed
of the STS; turn off ring main unit is □ Failed
the G1 earthing on, and the STS
switch (if any) and runs normally □ N/A
turn on the G1 load without
switch (if any) in the abnormal noise.
ring main unit; turn
off the G3 earthing
switch (if any) and
turn on the G3 load
switch (if any); turn
off the G2 earthing
switch, and turn on
the G2 disconnector
and circuit breaker.
For the detailed
sequence, see the
yellow label on the
ring main unit panel.

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. 32


Smart Transformer Station
Acceptance Test Guide 3 Part III STS Operation Tests

T03 On-load After the STS runs The power-on □


-02 operation without loads for 24 indicator on the Passed
hours, turn on all the ring main unit is □ Failed
MCCBs and the ACBs on, and the STS
of the 800 V runs normally □ N/A
incoming cables on without
the LV side of the abnormal noise.
STS.

T03 Electric View the voltage and The STS □


-03 energy current of the LV telemetry page Passed
data panels and MV rooms of the □ Failed
monitorin on the telemetering SmartLogger
g page of the WebUI correctly □ N/A
SmartLogger WebUI. displays the
three-phase
current, line
voltage, active
power, reactive
power, power
factor, and
frequency of the
LV panel and
MV room.

3.2 Completion of STS Operation Tests


Result of the Tests o Passed

o Failed (Known issues can be described in the


following remarks)

Remarks

Huawei representative

Name: ___________________________

Role: ___________________________

Date: ___________________________

Signature: ________________________

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. 33


Smart Transformer Station
Acceptance Test Guide 3 Part III STS Operation Tests

Customer representative
Name: __________________________
Role: ___________________________
Date: ___________________________
Signature: _______________________

Issue 01 (2023-02-10) Copyright © Huawei Technologies Co., Ltd. 34