Power System Planning| 2024-2025
[Link] KHALED
Introduction
Section.1
COURSE CONTENTS
Load Forecasting
Planning Economics
Maintenance Schedule
Introduction to power system planning
Agenda
Distribution Planning Distribution Planning
Attributes Requirements Planning stages
Time Horizon for Distribution Planning Distribution Planning Load C’CS
power system studies Problems initiation
1-Time-horizon perspective of power system studies
Duration Study Planning Type
Power System Planning
1Year-10Years Power System planning
()مثل بناء المحطات وأضافت وحد جديدة
1Week-1Year Maintenace Scheduling Operational planning
Unit Commitment
Economic Dispatch and Optimal
1Minute-1Week Operational planning
Power Flow
Automatic generation control
Milliseconds-Seconds Power system Dynamics Operational planning
Nanoseconds-Microseconds Power system Transients Operational planning
1-Time-horizon perspective of power system studies
Power System Planning
هي عبارة عن التخطيط الي بعملة علشان أضيف وحدات أو محطات جديدة بحيث أواكب الزيادة على ال Demandالي
بتحصل بشكل مستمر.
طيب أنا أعرف منين أن محتاج وحدات جديدة؟
من دراسة هندرسها بالشبتر ده أسمها ال Load Forecastingهشوف قد أيه الحمل المتوقع مستقبلًا وأقارنه
بال Generationالي عندي بحيث لازم يكون:
Generated +Residual >= Demand )!!WHY (Search
Maintenance Schaudel
هي عبارة عن الجداول الي بتتعمل علشان أشوف أيه الوحدات الي هخرجها من الخدمة للصيانة بحيث أضمن أن طول
فترة صيانة الوحد دي أن الشرط بتاع:
Generated +Residual >= Demandمتحقق.
1-Time-horizon perspective of power system studies
Unit Commitment
هي عبارة عن دراسة بتتعمل علشان أشوف أيه الوحد الي المفروض تشتغل علشان أغطي أحتياجات الحمل مع أقل
تكلفة للتوليد في وجود بعض ال Constrainsمثل (.)Operational Reserve & Start-up & Shut-down time
Economic Dispatch
هي عبارة عن دراسة بتتعمل بعد ال Unit Commitmentعلشان بعد ما حددت الوحد الي هتدخل معايا بالخدمة،
أشوف كل وحدة تولد كام بحيث أحصل على Lowest Generation Costمع مراعات الظروف التشغيلية لكل وحدة
(زي ال minmum & maximum power generationللوحدة ،وال) Reseduial
Optimum Power Flow
هي عبارة عن دراسة بتتعمل علشان أشوف ايه هو أفضل Generation + Power Flowفي الشكبة يديني أفضل
Solutionللظروف التشغيلية في الشبكة (زي ال Voltage Dropفي الخطوط و ال TL capacityو Minimum power
)lossبأقل تكلفة ممكنة.
1-Time-horizon perspective of power system studies
Automatic generation control
ده عبارة عن النظام الي بعوض زيادة الحمل على المولدات .أزاي؟
دلوقتي لما ( [Link]>[Link]بشرط طبعًا يبقى فيه )Reserveبتبدأ سرعة المولد تتباطأ وزي ما حضرتك
عارف أنN=120F/P :
بالتالي لما السرعة أتقل رح يحصل حاجة أسمها Frequency Droopأي حصل تغير بسيط في التردد ()eg. ΔF=3%
بالتالي التغير ده بيدي alarmلل Governerيقولي زودلي ال Input Powerشوية علشان أزود السرعة وأرجع ظروف
التشغيل الطبيعية.
كل ال Processدي أسمها ال AGCو وظيفته أن Automaticallyيحافظ على الأتزان بين التوليد والحمل.
Power System Dynamics Power System Transients
زي مثلا ال Motor startingو ال Load Variation زي مثلا ال Lightningوال Switching
2-Distribution Planning Attributes )(العناصر الأساسية للتخطيط
1. Predict Future demand and requirements accurately.
2. Define the problems and deficiencies of the distribution facilities:
a. to provide adequate capacity.
b. to conform with safety requirements.
c. to meet the performance standards are analytically identified and quantified.
3. To propose projects to solve the problems and deficiencies with least cost:
a. to improve system performance such as reliability.
b. to reduce system losses, have positive net benefits from the point of view of
the customers.
4. The documentation of the proposed projects must show the compliance with
regulatory requirements.
5. The financing plan and the funding sources.
3-Distribution Planning Problems
()المشاكل التي يجب على مهندس التخطيط أيجاد الحل الأمثل لها أثناء عملية التخطيط
1. Electrification of un-energized areas.
2. Locations, sizes and timing of distribution substations.
3. Types, sizes and routing of sub-transmission lines.
4. Types, sizes and routing of distribution lines.
5. Locations and sizes of power conditioning, sectionalizing and switching
equipment.
6. Locations and sizes of distribution transformers.
7. Service connection requirements of future customers.
8. Other non-network assets to efficiently operate the distribution facilities
and to attend to the needs of customers.
4-Distribution Planning Requirements متطلبات عمل تخطيط للشبكة الكهربائية
1. Load forecast for the power system under consideration for a period of several years.
2. Energy forecast in the long term.
3. Standardization, availability, exchangeability and compatibility of equipment.
4. Standardized rated parameters of equipment.
5. Restrictions on system operation.
6. Feasibility with regard to technical, financial and time aspects.
7. Political acceptance.
8. Ecological and environmental compatibility.
9. The information database of the existing power system with respect to geographical,
topological and electrical parameters.
10. Information about rights - of - way, right of possession and space requirements for substations
and line routes
11. Information about investment and operational costs of installations
12. Information about the costs of losses
13. Knowledge of norms, standards and regulations.
5-Distribution Planning initiation متى نبادر بعمل تخطيط
1. Demand from customers for supply of higher load, or connection of new
production plants in industry.
2. Demand for higher short - circuit power to cover.
3. requirements of power quality at the connection point (point of common
coupling).
4. Construction of large buildings, such as shopping centers, office buildings
or department stores.
5. Planning of industrial areas or extension of production processes in
industry with requirement of additional power.
6. Planning of new residential areas.
7. General increase in electricity demand.
Planning Stages
P: Project Planning:
S: system development planning
B: basic planning.
S B
P طبعا زي ما انتا شايف من ال
Curvesأن مدة التخطيط بتختلف
على حسب قيمة الجهد.
فمثلا ،أضافة محول على جهد
200KVيحتاج زمن أكبر للتخطيط
من أضافته على جهد .66KV
Planning Stages: 1-Basic Planning:
Standardization of equipment, neutral earthing concepts, nominal voltages
and basics of power system operation.
بدرس فيها الأساسيات الي هنشأ عليها المشروع ،فمثلا ايه الجهد الي هولد عنده وايه الجهد الي
هنقل عليه وأيه نظام التأريض الي همشي عليه وببدأ أبص على أساسيات تشغيل المشروع.
بالأضافة الى القوانين الي هفرضها وهمشي عليها الخ...
بتوصل الى 10سنوات Low-voltage systems :
بتوصل الى 20سنة High-Voltage systems:
Planning Stages: 2-System Development Planning:
1. Detailed planning of the system topology is carried out based on the load
forecast.
2. Alternative concepts are analyzed technically by load - flow calculations, short -
circuit analysis and stability computations.
3. Cost estimates are also carried out.
4. Disturbance and operational statistics are evaluated and locations for
installations are determined.
5. The main parameters of equipment, such as cross – section of overhead lines and
cables, short - circuit impedance of transformers is defined.
The planning horizon is approximately five years in a low - voltage system and
up to 10 years for a high - voltage transmission system
Planning Stages: 2-System Development Planning:
-1ببدأ أشوف ال Topologyالي همشي عليها بناءا على بيانات ال Load Forecasting
-2ببدا أعمل تحليل للشبكة أو المشروع عن طريق عمل Load-Flow, Short-Circuit, Stability
.Analysis
-3ببدأ برده أعمل .Cost Estimation
-4بشوف برده ايه الحجات الأضطرابات الي ممكن تحصل بالشبكة بالأضافه الى دراسة أفضل
الأماكن لوضع المعدات.
-5بحسب برده الحجات الأساسية للمعدات .مثلا مساحة مقطع الكابلات وخطوط النقل و معاوقة
الخطأ للمحولات الخ...
زمن المرحلة دي يصل الى 5سنوات في الجهود المنخفضة ،ويصل الى 10سنوات في الجهود العالية
Planning Stages: 3-Project Planning:
1. The connection types of new customers
2. Connection of new substations to the power system.
3. Restructuring measures.
4. Evaluation of information on system loading.
5. preparation of tender documents and evaluation of offers supervising
construction contracts
6. cost calculation and cost control
7. It covers a time range of one year in the low - voltage system and up to four years
in the high - voltage system
سنوات في الجهود العالية10 ويصل الى، سنوات في الجهود المنخفضة5 زمن المرحلة دي يصل الى
LOAD Characteristics
ودي عبارة عن معادلات بتمثل سلوك الحمل معModels أي حمل في الدنيا بتمثل في حاجة أسمها
:Parameters ومن أهم هذه ال. معينةParameters
Voltage, Temperature, Torque.
Example: Variation on voltage in PU. for equipment
Example: Variation on Temperature for Air-Conditioner Model
Variation on Temperature for Heat-Pump Model
LOAD Characteristics
مش معلوم يتمParameters Variation أيApplication Model أثناء التعويض في ال:معلومة
.Zeroالتعويض به ب
Application Models
1. Static Model
2. Exponential Models
3. Polynomial Models
Press here for Section Quiz