0% found this document useful (0 votes)
59 views3 pages

Modular Buildings Project RFQ Breakdown

The document outlines the Bill of Quantities (BOQ) and price breakdown for Project No. 20-1001, which involves the construction of modular buildings. It details various construction and development works, including site preparation, utility connections, modular facility units, and landscaping, with a total project cost of $424,489. The project is expected to be completed in 148 days, with additional costs for equipment, labor, and overhead.

Uploaded by

adnan.lazem
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
59 views3 pages

Modular Buildings Project RFQ Breakdown

The document outlines the Bill of Quantities (BOQ) and price breakdown for Project No. 20-1001, which involves the construction of modular buildings. It details various construction and development works, including site preparation, utility connections, modular facility units, and landscaping, with a total project cost of $424,489. The project is expected to be completed in 148 days, with additional costs for equipment, labor, and overhead.

Uploaded by

adnan.lazem
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

PROJECT NO; 20-1001- Modular Buildings

RFQ Number: FA5710-20-Q-0008


BILL OF QUANTITIES (BOQ) & PRICE BREAKDOWN

BID ITEM TOTAL


ITEM UNIT COST
NO.
COST
ITEM DESCRIPTION QTY UNIT (USD)
(USD)
1.0 CONSTRUCTION WORKS

Site Clearing, scraping off the top weak soil (depth according to USAF Engineers) and preparation of the site
1.1 including removal of existing damaged scrap/rocks and disposed-off as directed to predefined municipal LS Cu. Yd 15 4200
dumping site
1.2 Underground And Aboveground Utilities Survey Works 1000 Sq. Ft 9 9,000
Foundation Earthworks Excavations; Unless otherwise stated, Rate shall include for
▪ back filling with selected excavated material & consolidating. Surface treatment; compaction
before filling / foundation.
1.3 ▪ disposal of surplus soil as directed & keeping all excavations free from water unless otherwise 300 Cu. Yd 18 5,400
measured separately.
▪ any additional excavation for working space.

1.4 Sewer Lines Piping Connect – Plumbing works 315 LFT 8.5 2678

1.5 Storm Water Piping Connect – Drainage works 175 LFT 6.4 1120

1.6 Potable water Piping Connect – Plumbing works 285 LFT 8.8 2508

1.7 Electrical Power Lines Connect – Electrical works 257 LFT 12.8 3290
Foundation Concrete Works – Concrete works, Pour of fresh concrete in concrete floor slab. Concrete
1.8 footing will sit approximately 2” above grade and be sloped from the post toward the edges. Concrete Grade 26.19 Cu. Yd 65.6 1716
4000 PSI, 1:1.5:3 design mix concrete
Surface Concrete Floor And Pedestal – Concrete works, Pour of fresh concrete in concrete floor slab.
1.9 Concrete footing will sit approximately 2” above grade and be sloped from the post toward the edges. Concrete 6.55 Cu. Yd 65.6 430
Grade 4000 PSI, 1:1.5:3 design mix concrete
2.0 DEVELOPMENT WORKS

2.1 Installation Process Using Heavy Equipments & Machinery 7 unit 800 5600

2.2 CHU Transport, Landing And Storage 7 unit 1000 7000


MODULAR FACILITIES UNITS;
2.3 1 unit 50,000 50,000
Design, manufacture, and delivery of RLB #1 Jolly Operations.

Page 1 of 3
PROJECT NO; 20-1001- Modular Buildings
RFQ Number: FA5710-20-Q-0008
BILL OF QUANTITIES (BOQ) & PRICE BREAKDOWN

MODULAR FACILITIES UNITS;


2.4 1 unit 50,000 50,000
Design, manufacture, and delivery of RLB #2 King Operations.
MODULAR FACILITIES UNITS;
2.5 1 unit 50,000 50,000
Design, manufacture, and delivery of RLB #3 GA Operations.
MODULAR FACILITIES UNITS;
2.6 1 unit 50,000 50,000
Design, manufacture, and delivery of RLB #4 Jolly/King AFE.
MODULAR FACILITIES UNITS;
2.7 1 unit 50,000 50,000
Design, manufacture, and delivery of RLB #5 GA AFE.
MODULAR FACILITIES UNITS;
2.8 1 unit 30,000 30,000
Design, manufacture, and delivery of RLB #7 Medical Facility.
MODULAR FACILITIES UNITS;
2.9 1 unit 25,000 25,000
Design, manufacture, and delivery of RLB #6 GYM LOCKER Facility.

2.10 Landscaping 1000 Sq. Ft --- ---

2.11 Final Testing;


LS LS --- ---
(Multiple works to include final testing cleaning and demounting works …etc.)
2.12 Site Cleanup 441.48 Sq. Ft --- ---

3.0 HANDOVER WORKS

3.1 Handover Of CHU Building Units, Infrastructure, Documentation And Building System LS LS --- ---

4.0 DOCUMENTATION WORKS

4.1 --- ---


As Built Drawings SET Doc.

4.2 --- ---


Warranties SET Doc.

4.3 --- ---


Test Log SET Doc.
OTHER REQUIREMENTS (OPTIONAL)
5.0 Other items of the SOW obligation not in the technical specification or elsewhere. Please state and describe all LS LS Not Applied Not Applied
items forming part of the above works.
4.0 SUBTOTAL 347,942.00

Page 2 of 3
PROJECT NO; 20-1001- Modular Buildings
RFQ Number: FA5710-20-Q-0008
BILL OF QUANTITIES (BOQ) & PRICE BREAKDOWN

5.0 Equipments 27,835

6.0 Labor 13,918

7.0 Overhead & Profit 34,794

8.0 SUBTOTAL 76,547.00

9.0 TOTAL 424,489.00

10.0 REQUIRED TIME (Days) 148

X
NAEM JABER JAAFAR
COMPANY MANAGER

1st MARCH 2020

Page 3 of 3