G.P.-S.33967—4968-69—1,000.
- X
In the Supreme Court of South Africa.
In die Hooggeregshof van Suid-Afrika.
( A11ELLATE &&&£& Division.)
(—__ _______________ __ __________ _ —.... JProviiisiale Afdeling.)
Appeal in Civil Case.
Appel in Siviele Saak.
GLSNTIRUCO ... Appellant,
versus
____ _________......................................................................................... ........... Respondent
Appellant's Attorney Respondent's Attorney j /
Prokureur vir AppellanL^J^ ..... Prokureur vir Respondent
Appellant's Advocate ^Respondent's Advocate Í *3- i
Advokaat vir Appellant.......^....^..^^^^.^.\^)Mvokaat vir Respondents^
Set down for hearing on F
Op die rol geplaas vir verhoor op. •Xi— --------- -- --- —
Z£xjlJLjJL__ _________ LÝ
3
Ji
___ _ í 1
*
5.3c r
------ - 1L 0 O V LO' {p _ *í i'
. f; -
4
nr
IA. <j
J? 4 4~ |
h Bills Taxed—Kosterekenings Getak?efe/t * |°
aj 15K?e. Amount Initials.
3' 'Datum. Bedrag. Paraaf.
Writ-issued 'ï L
Lasbnef-uitgeceik—n. U-p-vx.
?•
/yh)
DsÏU&íbMÍi/ fí M
IN THE__ SUPREME COURT OF SOUTH AFRICA.
(APPELLATE division)
I
In the matter between:- I
GENTIRUCO A.G................... APPELLANT
I
I
AND |
FIRESTONE SOUTH AFRICA (PROPRIETARY) LIMITED .. RESPONDENT
i
Coram: Ogilvie Thompson, C.J., Trollip, Rabie, 1*
I
Muller, JJ.A. et Corbett, A.J.A, |
Heard: 19 November 1971« Delivered: /G February 1972.
JUDGMENT. 1
- i
Trollip, J. A. : - i
I
The provisional orders for costs made by
Í
this Court in this litigation and the reasons for them
I
are set out at the end of the judgment delivered on 22 1
Í
September 1971 (not yet reported) and need not be re- i
i
peated here. In pursuance of paragraph D of those J
i
orders Firestone applied, and Gentiruco counter-applied,
I
I
for them to be varied in certain respects. This judge
ment deals with those applications, and it should be I
i
read with our previous judgment. (The references to .
x i
the latter are to the typed pages thereof.)
i
I
This .... /2
2
i
This Court provisionally ordered Gentiruco
to pay 40$ of Firestone's taxed party and party costs |
in all three courts (excluding certain costs separately )
dealt with). Firestone in its application for a varia-|
tion claimed that it should be awarded all its costs, |
or, alternatively, that the proportion of 40$ should be •
substantially increased; Gentiruco resisted that appliH
i
cation and counterclaimed for an order that Firestone j
should pay a substantial proportion of its costs, or, I
I
alternatively, for a substantial reduction of the pro
portion of 40$, and for certain other relief. |
As appears from this Courtf s previous j
judgment, Firestone, although the successful party, '
I
I
was provisionally not awarded all its costs of the
I
litigation because it had raised and failed on the |
objections of lack of novelty (anticipation) and I
subject-matter (inventiveness)» The first broad
F
submission made on its behalf was that the claims (
of the specification in suit were so vague and in- |
sufficient that it had acted reasonably and properly 1
I
j
in .... /3
3
in raising and persisting in those objections. In
support thereof it invoked Nel v. Nel 19^-3 A0D. 280 j
at p. 288/9» The defect in the claims mainly relied )
upon was the uncertainty of the meaning of "computed |
Mooney”. That defect, it was pointed out, also affected
certain other integers in the claims and, indeed, per- |
meated all the claims, thereby vitiating them, as this |
Court has held. The expression "computed Mooney”, I
it was also emphasized, was hitherto unknown in the I
art; it had been coined by the inventors and used '
i
for the first time in the specification. Conse-
i
quently, so the argument proceeded, Firestone, when
i
sued by G-entiruco, was faced with the uncertainty of
i
the meaning of the claims created by the use of that
expression; hence, with its back to the wall in the j
litigation (cf. Nel v. Nel, ibid.).Firestone had ■
acted reasonably and properly, not only in raising j
those objections, but also in relying on an extensive .
range and variety of documents to prove them, i.e., to |
prove that, whatever the Court ultimately found the |
claims .... /4 |
I
4
claims meant, they had been anticipated or were not
inventive. Indeed, it was even maintained that, by
framing the specification in such an ambiguous and
insufficient manner and by refraining throughout from
amending the claims to remove such defects, G-entiruco,
and not Firestone, was "responsible" for Firestone’s
having raised those ob jections and for the manner in
which they were canvassed. (For the origin of the
use of "responsible11 in this context, see the die turn
of Gardiner, J., in the Union Share Agency case, 1$26
CoP.D. 129 at p. 141, quoted on p. 272 of our previous
judgment,)
Those arguments, in my view, cannot
prevail,
Firstly, despite the novelty of the
concept and the uncertainty of the meaning of "compu
ted Mooney", it must have been quite clear to Firestone
that the invention, as described and claimed in the
specification, related fundamentally to the use of
tough or high (measured) Mooney rubbers with a minimum
degree /5
5
degree of toughness, i.e., those rubbers hitherto re
garded as practically unprocessable (see pages 96, 172,
and 241 of this Court * s previous judgment), and that
the phrase ”a ’computed Mooney' plasticity of at least
90” was used in the relevant claims to express that
minimum degree of plasticity. (On this aspect I
think that any difficulty created by the rubber, Diene
55r can be disregarded, for it was an unusual rubber
and probably unknown at the effective date of the
specification - see p. 144 - and that must have been
known to Firestone at all material times.) Conse
quently Firestone, being in doubt about the precise
meaning of the phrase, should nevertheless have assumed
at the outset that that integer of the claims involved
the use of tough rubbers with a measured minimum Mooney
of about 90, Accordingly, it could and should have
J
I
made and prepared for its objections of anticipation
and obviousness on that basis• That would have been
a safe, practical, and fair assumption to have made. ■
For it is clear from the explanation of "computed
Mooney" in the body of the specification (and this |
was ... /6
6
was common cause) that, whatever its true meaning,
the computed Mooney of a rubber is sometimes the same
as, but it is never less than, its measured Mooney;
so, if tough rubber with a measured Mooney of a least
90 is assumed, it would mean that its computed Mooney
would also not be less than 90; and that is what
claim 1 (the broade s t claim) and mo st of the o ther
claims prescribed.
It was, however, submitted that, since
the meaning of ”computed Mooney” was so uncertain as
to be meaningless, Firestone was entitled to assume,
and this Court ought to have assumed, that rubbers
of any toughness or softness were useable in the in
vented process. But that would have been quite un
realistic . For this Court did not hold that the ex
pression ”a ’computed Mooney
* plasticity of at least
90" was meaningless; it merely held that it was
uncertain which of four different possible meanings
or methods of computation it conveyed; and, in any
event, such an assumption would have been a travesty
7
of the invention as described in the specification.
It was for those reasons that this Court itself, having
held that the meaning of "computed Mooney” was ambiguous
assumed that that integer of the claims involved the
use of tough rubbers having a measured Mooney of at
least 90 in order to determine those objections (see
pages 180 and 243). And despite Firestone's criti
cism of it, I think that that assumption was correctly
made. Firestone should also have made and acted on
the same assumption at all relevant times. !
Indeed, it is clear, I think, that
Firestone, from an early stage, did approach the sit-
1
uation on that basis. Thus, Dr• Bull, who was mainly
responsible for collecting possible anticipatory docu
ments for Firestone, explained under cross-examination
that, by 11 tough” rubber ”in the context of the anti
cipations”, he meant generally rubber with a measured I
Mooney of more that 90, and that it was reasonable to
adopt that figure for the purpose of discussing anti-
i
cipation. And when Firestone 1s counsel opened its j
case .... /8
8
case at the trial, he stated in regard to the ob
jection of anticipation that, notwithstanding the no
velty of the concept of computed Mooney,
11 the Court will accept, where necessary, a
conversion from the recognised standards of measure-
I
I
ment of viscosity, or plasticity, .... to this new
scale of 'computed Mooney1 .... (and) will be entitled
to use the inventors’ own definition, viz. that the
'computed Mooney' must be equal to, or greater than,
the actual measured Mooney, So that accepting for j
the purposes of this aspect of our case, that compu
ted Mooney is a valid concept .... then it is sufficient
I
i
for us to show that rubbers had a measured Mooney of
at least 90 to bring those anticipated uses within the
scope of the claim".
The other ambiguities or insufficiencies
in the claims relied on by Firestone do not take its j
argument on this aspect any further.
Consequently, in my view, the ambiguity
I
I
or uncertainty of the meaning of "computed Mooney",
and /9
9
and other defects in the claims, did not necessitate
or justify the production and use by Firestone of the
mass and variety of documents relating to anticipation
and obviousness (said by Gentiruco to be about 120
documents) and the protraction of the litigation caused
by them and the evidence concerning them. In that
regard it is also relevant to bear in mind that an
appreciable number of those documents were relied on
to prove obviousness; but, as Firestone did not prove
that they or any part of them constituted common know
ledge at the relevant time, they did not even qualify
for consideration in the determination of that issue
(see pages 233 to 236); and the incurrence and wastage
of those costs were not in any way due to any defects
in the claims.
Secondly, I must confess to some diffi
culty in understanding how, because of the defects
in the claims, Gentiruco was "responsible” for Fire
stone T s having raised anticipation and obviousness as
objections, let alone for the somewhat extravagant
manner in which they were canvassed. However, in
order . /10
10
order to dispose of this part of Firestone’s argument,
it suffices merely to say that we entertain no doubt
that, even if the claims had been reasonably certain
in meaning and not insufficient in any respect t Fire
stone would still have raised those objections and
canvassed them in the manner that it did. Or to put ■
I
it in another way: we are satisfied that it was not |
I
the defects in the claims that induced Firestone to
raise those objections and to canvass them as it did,
but its determination to attack the patent on the
grounds of lack of novelty and subject-matter
*
In support of its argument under this
head Firestone also relied on sections 43 (6) and 54
(1) (a) of the Patents Act, No. 37 of 1952. Both
provisions say in effect that the Commissioner may,
in the exercise of his discretion as to costs, take
into consideration the conduct of the patentee in fra
ming defective claims and permitting them to remain
defective. The situation postulated by those sections:
I
for the exercise of that discretionary power against 1
the .... /11
11
the patentee, is, of course, not present here. It
only arises where the specification or claims are de
fective but the Commissioner nevertheless decides in
the patentee's favour to uphold the specification, sub
ject to its being suitably amended, instead of revo
king the patent, or to grant relief in respec t of any
valid claim that has been infringed. Nevertheless,
Firestone contended that those provisions embody a
principle of general application, namely, that a
patentee can and ought to be penalised by an adverse
order of costs for framing defective claims and allow
ing them to remain defective. Assuming, without de
termining, the existence and content of such a princi
ple , I do not think that it ought to be applied here,
since, for reasons already given, there was no causal
connection between the defects in the claims and the
raising of and the manner of canvassing the objections
In other words, sections 43 (6) and 54 (1) (a) do not
advanc e Fires tone 1s c aus e.
Thirdly, even if it could be assumed
to .... /12
12
to have been reasonable, proper, or prudent for Fire
stone to raise those objections and to canvass them
in the manner that it did, I do not think that that
assists it. In our previous judgment we held that
it was reasonable and proper for Firestone to have
denied infringement, and, applying Nel v. Nel, supra,
we awarded the costs of that issue to Firestone (see
pages 282/3). But we provisionally differentiated
between the issues of infringement and of anticipation
and obviousness. In consequence, we provisionally
declined to apply Nel v. Nel, supra, to the latter
issues and preferred to adopt in respect of them the
dieta of Gardiner, J., in the Union Share Agency case,
supra, and of Bowen, L.J., in the Badische Anilin case,
2 R.P.C, 73 at p- 118. The reasons for doing so are
fully set out at pages 272 to 284, and need not be
repeated here. It suffices to say that I have not
been persuaded by Firestone's argument that our pro
visional decision was wrong in any respect.
Consequently, Firestone * s first
submission .... /13
13
submission fails.
Firestone’s second broad submission
for variation of the 40$ proportion related to the
particular order made by the Court a quo in paragraph
7 (e) of its orders, namely, that all the costs of the
trial and appeal to it occasioned by the calling of
certain overseas witnesses (Deutsch, Meishner, Hain-
bach, and Zutrauen) had to be paid by Firestone (see
p. 268). Firestone’s cross-appeal against that order
was struck off, so that the order in par. 7 (e) has
to stand (see p. 269)- In addition, this Court, in
provisionally ordering Gentiruco to pay 40$ of Fire
stone 1s costs in each of the two lower Courts, excluded
the abovementioned costs therefrom (see paragraph C,
pages 289 and 290). The result is that Firestone
will therefore have to pay Gentiruco
s
* costs in the
lower Courts relating to the calling of those wit
nesses, whilst Firestone's costs in those Courts re
lating thereto are provisionally excluded from the 40$>
apportionment. (if the evidence of those witnesses
occasioned .... /14
14
occasioned any costs to Firestone in the appeal to this;
I
Court they would be subject to the 40% proportion, for •
we made no order excluding them.) It should also be
explained here that those witnesses were called by
Firestone on the issues of anticipation and obvious
ness . Firestone therefore submitted that, since the
Court a quo1s order in par. 7 (e) in Gentiruco's fa
vour has to stand, "the overall picture of costs’* was
substantially altered, and that the effect of also
excluding those particular costs from the 40$ apportion
ment was "to penalise Firestone twice for the same
error of judgment", which was inequitable.
In considering this argument I find it
convenient to deal also with Gentiruco's counter
application that the proportion of 40$ ought to be sub
stantially altered in its favour. This Court, in
fixing that proportion, did take into account, as a
broad but not precise factor, the still extant, special
orders of the Court a quo obliging Firestone to pay
certain costs of Gentiruco’s, including those relating
to .... /15
15
to the abovementioned witnesses. That is indicated
by the wording of the relevant orders. In Gentiruco’s
counter-application facts were furnished purporting
to show the amount of time taken up at the trial by the
evidence of those witnesses and by canvassing the
issues of anticipation and obviousness. Thus, the
evidence of those witnesses occupied 511 pages, or
about 10$, of the record of the viva voce proceedings.
That represents an appreciable amount of time at the
hearing. But as against that, the other data, and
especially the information on the documentary evidence,
concerning the issues of anticipation and obviousness
tend to show that the proportion of 40$ was somewhat
too favourable to Firestone. But the latter factor
must not be pushed too far in Gentiruco1s favour.
For it seems probable that Gentiruco* s data and informa
tion do not take sufficient account of the fact that
a not insubstantial portion of that evidence and those
documents related to the issues on which Firestone
succeeded, such as the state of the art at the relevant
time .... /16
16
time and the technical background to the invention.
Those factors therefore tend to cancel each other out.
As explained in our previous judgment, the proportion
of 40% was a practical estimate of the appropriate
apportionment of the costs between the parties, and
it was only arrived at after long, careful, and
anxious consideration. In the result I have not been
persuaded by the arguments of either party that it was
wrong or ought to be altered•
Consequently, Firestonefs second sub
mission and Gentiruco’s counter-application in regard
to the 40$ proportion both fail.
Gentiruco also submitted that Firestone
ought to be ordered to pay the costs relating to the
issue of infringement on grounds that can be summarised
thus: Firestone unnecessarily denied the relevant
facts relied on by Gentiruco, it adopted a tardy and
less than candid attitude towards its obligation to
discover documents relating to infringement, and the
costs thereby unnecessarily incurred by Gentiruco were
not
17
not insubstantial. The reasons for provisionally
awarding those costs to Firestone appear from our
previous judgment (pages 282/3)» Counsel for Gen-
tiruco conceded that ordinarily, for those reasons,
Gentiruco should pay those costs, but he contended
that the aforementioned grounds constituted exceptional
circumstances justifying a different order. I do
not agree. Despite the argument to the contrary,
I still do not think that Firestone acted unreasonably
or improperly in completely denying infringement.
After all, the onus was on Gentiruco to prove it, and
in our previous judgment we merely assumed, without
deciding, in Gentiruco"s favour that it had discharged
that onus. Moreover, the evidence on the issue, which
was given by three witnesses, only took up about two
days of the trial, the argument in each Court less than
one day, and the relevant documents filled less than
one volume of the record. Hence, as our previous
judgment stated (p. 283)> the investigation of the
issue in each Court did not, relatively speaking,
unduly . /18
18
unduly protract or materially add to the costs of the
litigation. Lastly, even if there were substance
in Gentiruco’s complaint about Firestonefs conduct
concerning discovery, I do not think that, by itself,
it justifies a variation of the order of costs at pre
sent under inquiry. That order must therefore remain
undisturbed•
Gentiruco also raised the question of the
costs of the massive record of the trial that took
place in Baltimore, U.S.A,, concerning the American
patent, be tween the parent companies of the parties.
Its counsel submitted that the record was mainly, if
not wholly, irrelevant to any issue on which Firestone
had succeeded. It became common cause, however, that
the only order that could be made by this Court is
that the Taxing Master of the Court concerned should
determine in the ordinary way all questions arising
in regard to those costs. Such an order will be made.
That leaves for consideration the
question of the costs of the expensive U.S.A. Commission.
The .... /19
19
The order for that commission was granted by consent
on Firestone's application. However, at the in
stance of Gentiruco, the costs of the application and
commission were reserved for the decision of the trial
court; the order also expressly noted that Gentiruco
did not at any time concede that the commission was
necessary. The Court a quo, reversing the order made
by the Commissioner at the trial, ordered Gentiruco
to pay those costs, but allowed the costs of only one
counsel at the commission (see pages 266 to 270 of our
previous judgment). Gentiruco appealed, inter alia,
against that order. This Court, whilst not overlooking
that the commission dealt mainly with the issue of
inventiveness, nevertheless provisionally ordered those
costs to be costs in the cause. In doing so, it was
influenced by the view of the Court a quo that Gentiruco
had itself largely brought about the need for the com
mission by unnecessarily refusing Firestone’s reasonable
requests to make certain admissions. That provisional
order means that if it stands, Gentiruco would have to
pay /20
20
pay U0$> of Firestone’s costs of the commission. Gen
tiruco contended that that would be inequitable, since,
for various reasons urged by it, Firestone ought to
be made to pay all the costs thereof.
We have been furnished with a copy of
the somewhat elaborate and complicated proceedings
for the issue of the commission. The answering affi
davit filed on behalf of Gentiruco made its attitude
to Firestone * s application quite clear: it did not
concede that any of the evidence sought to be taken
was relevant to any of the issues to be canvassed at
the trial, but it appreciated that the Commissioner
could not at that stage determine its relevance or
admissibility; moreover, Gentiruco was not desirous
of holding up the trial, the commencement of which
had already been delayed; consequently, it agreed to
the granting of the commission, subject to the costs
being reserved and not being made costs in the cause
(as Firestone prayed), for, it submitted, if such evi
dence turned out to be inadmissible on any ground,
Firestone /21
21
Firestone should be ordered at the trial to pay the
costs.
In the result, the Commissioner, with
the parties’ consent, reserved the question of the
costs. Consequently, I think that the appropriate
order to make now must depend upon the nature of the
evidence actually taken on commission, its relevance
and probative value to the issues raised and de termined
in the litigation, and this Court’s decision on those
issues and on the costs relating thereto.
According to Firestone’s application
the evidence sought to be adduced on commission related
to (a) facts concerning anticipations, (b) facts con
cerning certain documents which Firestone intended
using at the trial in connection with common knowledge,
(c) facts for the purpose of identifying and proving
the records of the trials in Baltimore and Canada,
(d) facts concerning criticisms of the specification
in suit, and (e) facts relevant to the allegation
i
I
that the specification and claims in suit were not
framed .... /22
22
framed in good faith, and with reasonable skill and
knowledge.
The evidence adduced on commission re
lating to (a) and (b) was directed mainly at proving
the publication, circulation, or accessibility in the
U.S.A, of certain documents, including some of the
tire test reports dealt with in our previous judgment
(see pages 239 and 24o), and at showing that some of
them were in the possession of General Tire and Rubber
Company or were known or available to certain of its
employees, including the inventors of the patent in
suit. Its relevance and probative value to the issues
of anticipation and common knowledge or inventiveness
are most obscure and its contribution to proving the
state of the art at the relevant time or the technical
background to the invention in suit was negligible, if
not nil. Firestone should therefore bear the costs
of such evidence, since we have held that it failed
on those issues and is liable for most of Gentiruco1s
costs relating thereto.
No .... /23
23
No evidence was adduced on (c), presumabl
because the parties came to some arrangement about the
records of the Baltimore and Canadian trials.
In regard to (d) and (e), the only wit
ness examined was one TeGrotenhuis, a lawyer, who
assisted in drafting the American and South African
patents. His examination was directed at showing
that he and the inventors possessed certain informa
tion at the time the invention was evolved, and also I
at proving that there were certain discrepancies in
the figures and data between the South African speci-
i
fication and certain disclosed documents. These dis
crepancies were ultimately admitted by Gentiruco at
the hearing before the Commissioner but without its
conceding their relevancy. Again, the relevance and
probative value of that evidence to any issue between
the parties at the trial is not apparent. Certainly, í
i
i
I
the allegation of want of good faith or absence of
reasonable skill and knowledge in framing the specifi
cation and claims was not put to TeGrotenhuis crisply•
And .... /24
24
And if that allegation was relevant, as, for example,
to a possible attempt by G-entiruco to amend the speci
fication, and TeGrotenhuis1s evidence thereon was
necessary, the allegation in Firestone’s application
for the commission - ”from enquiries made by it
Firestone believes that Mr. TeGrotenhuis is unwilling
to come to this country to testify on behalf of Fire
stone” - was not substantiated. For at the commission
he testified, without being challenged thereon, that
he was never asked by anyone whether he was willing
to come here to testify in person.
On the question of Gentiruco’s alleged
unreasonable refusal to admit certain facts, thereby
rendering the commission necessary, the position is
as follows. Gentiruco did make many admissions in
terms of Firestone’s requests. But Firestone alleged
in its application that the commission was nevertheless
essential because Gentirucofs qualifications to those
admissions rendered them inadequate to establish the
facts that Firestone was seeking to prove. In reply
to .... /25
25
to that allegation Gentiruco pointed out that it had ,
previously informed Firestone that, if it reframed
its requests for admission without referring to the
record of the Baltimore trial, Gentiruco might make
further admissions, but, it alleged, that was never
done, in consequence of which, when the trial was set
down for hearing in September 1967, it (Gentiruco)
had then refused to make any further admissions.
But, Gentiruco stated further, once the relevant docu
ments had been properly identified and considered by
it, it would be in a position to make further admission^
i
which might eliminate the need for some of the evid-
dence sought to be taken on commission. (That
apparently did subsequently happen.) Firestone answered
by denying that its requests for admissions were not
thereafter reframed and that the relevant documents
i
had not hitherto been properly identified, and it con
cluded by stigmatising Gentirucofs attitude as being
throughout "obstructive”.
i
In view of that dispute on the affidavits,
I .... /26
26
I cannot say, at any rate without having heard argu
ment thereon, that Gentiruco
s
* refusal to make further
or unqualified admissions was unreasonable at the time
of the application for the commission. And, in any
event, even if it was then unreasonable, I do not think
that it has now any decisive bearing on the issue of
the costs of the commission. For, as stated earlier,
that issue must now be resolved by the nature of the
evidence actually taken on commission, its relevance
and probative value to the issues in the litigation,
and this CourtT s decision on those issues and on the
costs relating thereto.
Section 76 (1) (g) of the Patents Act,
1952, empowers the Commissioner to issue commissions
de bene esse. That discretionary power is exercisable
"where it appears convenient or necessary for the pur
poses of justice” (see Rule of Court 38 (3), rendered
applicable by the concluding part of section 76 (1)
and section 82 (1) of the Patents Act). Despite ;
Gentiruco1s disputing from the outset the relevance
and . /27
27
and admissibility of the proposed testimony, it must
have appeared, prima facie, to the Commissioner that
it was convenient or necessary for the purposes of
justice for the commission to issue, especially as
Gentiruco consented thereto. However, as costs
were reserved and in view of that dispute and Gentiruco’s
present application, I think that the onus is on
Firestone, as the applicant for the commission, to
satisfy us now that the commission was convenient or
necessary for the purposes of justice in order to justi
fy our confirming that the costs should be costs in
the cause. For reasons already given, I do not think
that Firestone has discharged that onus. Moreover,
as also pointed out above, in so far as the commission
related to the issues of anticipation and inventive
ness, the liability for those costs must fall on Fire
stone. It should therefore be ordered to pay all ,
those costs. It follows that it should also pay all
Gentiruco's costs incurred on the appeals to the Court
a quo and this Court in respect of the viva voce and '
documentary
28
documentary evidence taken on the U„S.A, commission.
But the time of the actual hearing on the appeals taken
up by such evidence was negligible, and the same can
be assumed to apply to the trial, since the contrary
was not contended. Hence, for taxation purposes,
such time can be ignored. The provisional orders
previously made by this Court must therefore be
varied accordingly.
As to the costs of the present pro
ceedings, we were asked by Firestone to order that they
be costs of the appeal on the merits, since, it was
contended, the present proceedings were merely an
extension of the hearing of that appeal. It is true
that, where this Court leaves the question of costs
open for later debate, such an order may be justified.
I
But the present proceedings are distinguishable from
such a situation. We canvassed the question of costs
I
fully in our previous judgment, arriving at certain
provisional conclusions thereon, in an effort to in
duce finality in this lengthy litigation and especially
to .... /29
29
to avoid the expense of a hearing on costs. Hence,
the present proceedings are not merely an extension
of the hearing of the appeal on the merits; they are
in reality fresh proceedings initiated by the parties’
applications to have the provisional orders varied.
Now Firestone has failed entirely in its application,
whereas Gentiruco has succeeded in having the pro
visional orders amended in an important respect, which
was also an issue that it raised by its appeal to this
Court against the relevant orders of the Court a quo•
Consequently I think that Centimeo is entitled to
these costs. To make them costs of the appeal would,
mean condemning Gentiruco to pay 40$ of Firestone’s
costs of proceedings in which Gentiruco has succeeded
and Firestone has failed, which would be most in
equitable .
The following orders are therefore made:
I. The orders made on 22 September 1971 by this Court
are amended in terms of paragraph D thereof as follows I
(i) .... /30
30
(i) . Paragraph B2 thereof is amended to read as
follows:-
"2(a). Firestone is ordered to pay the costs
of the appeal to this Court relating to the
recorded viva voce and documentary evidence
taken on the U.S.A, commission granted on (
Firestone's application. ( I
(b) . For the purpose of the taxation of
costs, the length of time occupied by the
hearing relating to such evidence can be re
garded as nil.
(c) . G-entiruco is ordered to pay of
Firestone1s taxed party and party costs of thé
appeal, including the costs in respect of
three counsel, but excluding those costs
dealt with in this sub-paragraph and para- I
graph A hereof”.
(ii) . Paragraph C thereof is amended to read as
follows:-
”C. The Orders of the Court a quo. i
1. Paragraph (6) of the orders of the Court a
quo, as amended, is amended to read as fallows:
31
1 (6) . Save to the extent set out in.
paragraph (7) hereof, the Respondent (Gen-
tiruco) is ordered to pay -
(a) . 40$ of Appellant’s (Firestone’s) ,
taxed party and party costs of the action
and counterclaim, excluding those particular
costs mentioned in paragraph (7) hereof;
(b) , 40$ of Appellant’s (Firestone’s) j
taxed party and party costs of the appeal,
including the costs of the application to (
amend this Court's order, but excluding those ■
i
particular costs mentioned in paragraph (7)
hereof;
(c) . Appellant’s (Firestone’s) taxed
party and party costs in respect of Responderit1s
(Gentiruco1s) application for leave to take
evidence on commission in the U.S.A.
(d) . Appellant’s (Firestone’s) taxed
party and party costs for its application
for the setting aside of certain notice of
set .... /32
32
set down filed by the Respondent (Gentiruco)
for 16 May 19^6. r I
2. Paragraph (7) of the orders of the
Court a quo, as amended, is amended by adding the follow
ing sub-paragraph thereto -
'(f). Firestone is ordered to pay the
1I
costs of its application to take evidence on commission
in the U.S.A., the costs appertaining to such commission,
and the costs of the trial and appeal relating to the
recorded viva voce and documentary evidence taken on
that commission. For the purpose of the taxation
of costs, the length of time occupied by the hearing |
at the trial and on appeal relating to such evidence
can be regarded as nil.1 |
3- Paragraph (8) of the orders of the I
Court a quo, as amended, is amended by deleting the
words, * save that the costs of only one counsel are to !
be allowed in respect of the proceedings before the ,
U.S.A, commission.’”
III
II The following paragraphs are added to the orders
I
of .... /33 '
33
of this Court made on the 22 September 1971 -
”E. All questions whether, and if so,
to what extent and in what amount or amounts, the costs
of Firestone relating to the record of the trial in
Baltimore, U.S.A., should be allowed and taxed in Fire
stone’s party and party costs in any court, shall be
de termined in the ordinary way by the Taxing Master
concerned.
F. Firestone is ordered to pay the costé
of the parties1 applications and the hearing on 19
November 1971 for the variation of the provisional
orders made on 22 September 1971» such costs to in
clude the costs relating to three counse
W.C. Trollip, J.A
concur.