𝐓𝐇𝐔𝐌𝐁 𝐑𝐔𝐋𝐄𝐒 𝐅𝐎𝐑 𝐂𝐈𝐕𝐈𝐋 𝐖𝐎𝐑𝐊𝐒 𝐋𝐀𝐁𝐎𝐔𝐑 𝐏𝐑𝐎𝐃𝐔𝐂𝐓𝐈𝐕𝐈𝐓𝐘
𝐁𝐚𝐫 𝐁𝐞𝐧𝐝𝐢𝐧𝐠 𝐖𝐨𝐫𝐤𝐬 ( 𝐑𝐞𝐢𝐧𝐟𝐨𝐫𝐜𝐞𝐦𝐞𝐧𝐭 )
Slab & Beams -
1 Fitter +1.5 Helper - 170 Kg/day
Footing -
𝐅𝐨𝐫𝐦 𝐖𝐨𝐫𝐤 ( 𝐒𝐡𝐮𝐭𝐭𝐞𝐫𝐢𝐧𝐠 )
1 Fitter +1.5 Helper - 200 Kg/day
- Fixing & Removal Slab & Beams -
1 Carpenter +1.5 Helper - 5 Sqm/day
Footing
1 Carpenter +1.5 Helper - 7 Sqm/day
Column Box Fixing
1 Carpenter + 2 Helpers- 20 Sqm/day
Column Starter Fixing -
𝐅𝐨𝐫𝐦 𝐖𝐨𝐫𝐤 𝐌𝐚𝐤𝐢𝐧𝐠
1 carpenter + 2 Helpers - 6 Nos/day
Beam sides
1 Carpenter +1 Helper - 6 Sqm/day
Column Boxes -
1 Carpenter +1 Helper - 3 Sqm/day
Starter
𝐂𝐨𝐧𝐜𝐫𝐞𝐭𝐢𝐧𝐠
1 Carpenter + 1Helpers - 5 Nos/day
Slab & Beams
𝐁𝐥𝐨𝐜𝐤 𝐖𝐨𝐫𝐤𝐬
1Mason+1Helper- 20 Cum/day
𝐏𝐥𝐚𝐬𝐭𝐞𝐫𝐢𝐧𝐠 𝐖𝐨𝐫𝐤𝐬
Block Work -1 Mason +1.5 Helper- 6-8Sqm/day
Internal Plastering
1Mason +1.5Helper- 10Sqm/day.
External Plastering
1Mason +1.5Helper- 12Sqm/day (Per Coat)
Ceiling Plastering
1Mason +1.5Helper- (10-12)Sqm/day
Corner beading Fixing
1Mason +1Helper- 7Nos/day
Mesh Fixing & Packing
𝐄𝐚𝐫𝐭𝐡 𝐖𝐨𝐫𝐤 𝐄𝐱𝐜𝐚𝐯𝐚𝐭𝐢𝐨𝐧
2Mason+1Helper - 60Running Feet/day
Manual Excavation
2 Labours - 100Cft/day
Machine Operated (Poclain)-60Cum/Hr
𝐌𝐒 𝐖𝐨𝐫𝐤𝐬
Window Grill Fixing
1Mason +1.5Helper- 3 Nos/day (Size -1800X1400)
Balcony Handrail Fixing -
𝐖𝐚𝐭𝐞𝐫 𝐏𝐫𝐨𝐨𝐟𝐢𝐧𝐠 𝐖𝐨𝐫𝐤𝐬
1 Mason +1.5Helper-5Nos/day(2400X900 mm)
Horizontal Membrane Application
1 Applicator + 1 Helper- 150 Sqm/day
Vertical Membrane Application
1 Applicator+2Helper- 50 Sqm/day
Brush On Application-1Applicator+1Helper- 20Sqm/day (1Coat)
𝐏𝐥𝐮𝐦𝐛𝐢𝐧𝐠 𝐖𝐨𝐫𝐤𝐬
Bore Packing -1Applicator +1Helper - 3Nos/day
Toilet Chasing -1Chipper -7Rmt/day
Waterline Fixing -1Plumber +1.5Helper - 3 Toilets/day
Sanitary Line Fixing-1Plumber+2 Helper- 3 Toilets/day
𝐄𝐥𝐞𝐜𝐭𝐫𝐢𝐜𝐚𝐥 𝐖𝐨𝐫𝐤𝐬
Sanitary & CP Fittings-1.5Plumber +3Helper - 3 Toilets & 1kitchen/day
Box Fixing (Marking+Chasing+Fixing + Leveling) -1 Skilled Eletrician+2Semi Skilled
Electrician -1 Flat/3 days
𝐓𝐢𝐥𝐢𝐧𝐠 𝐖𝐨𝐫𝐤𝐬
Note- 3 bedroom flat with around 50 Boxes
Toilet Dado -80 Sft/mason/day
Door Jambs - 30 Rft/mason/day
Toilet Skirting -45 Rft/mason/day
Toilet Flooring -90 Sft/mason/day
Balcony Skirting - 50 Rft/mason/day
Vitrified Flooring ( Straight Joints ) -100 Sft/mason/day
Vitrified Flooring ( Diagonal Joints ) - 90 Sft/mason/day
Vitrified Skirting -70 Rft/mason/day
Joint Filling -100 Sft/mason/day
𝐆𝐫𝐚𝐧𝐢𝐭𝐞 & 𝐌𝐚𝐫𝐛𝐥𝐞 𝐖𝐨𝐫𝐤𝐬
Roof Tiling -150 Sft/mason/day
Hand Cutting -150 Rft/mason/day
Machine Cutting - 450 Rft/mason/day
Groove Cutting -200 Rft/mason/day
Indian & Italian Marble , Granite Flooring - 60 Sft/mason/day
Staircase 50 Sft/mason/day
Lift Cladding -50 Sft/mason/day
Joint Filling -100 Sft/mason/day
Floor Polishing -100 Sft/mason/day
Half & Full Nosing Making -60 Rft/mason/day
Nosing ( Champhering ) Making -200 Rft/mason/day
Half & Full Nosing Polishing - 35 Rft/ mason/day