Activity Labor
1-5 tone
Excavator 6-10 tone
10-50 tone
Bar Bending
1 Fitter + 1.5 Helpers
(Reinforcement)
Form Work 1 Carpenter + 1.5
(Shuttering) Helpers
Concreting 1 Mason + 1 Helper
Block Works 1 Mason + 1.5 Helpers
Plastering 1 Mason + 1.5 Helpers
1 Applicator + 1-2
Water Proofing
Helpers
1 Plumber + 1-1.5
Plumbing
Helpers
Tiling 1 Tiler + 1 Helper
Painting 1 Painter + 1 Helper
Woodwork 1 Carpenter + 1 Helper
Granite & Marble 1 Mason/Polisher + 1
Works Helper
Glass & Aluminum
1 Fitter + 1 Helper
Works
Carpentry 1 Carpenter + 1 Helper
Kota Flooring 1 Mason + 1 Helper
Granite Flooring 1 Mason + 1 Helper
Brickwork 1 Mason + 1 Helper
False Ceiling 1 Fitter + 1 Helper
Productivity Rate
10-20 cum/hr
20-40 cum/hr
40-100 cum/hr
170-200 kg/day
5-7 sqm/day
20 cum/day
6-8 sqm/day
10-12 sqm/day
50-150 sqm/day
3 Toilets/day / 7 Rmt/day
10-15 sqm/day
20-25 sqm/day
2-3 Nos/day
2-5 sqm/day
5-10 sqm/day
2-5 sqm/day
2-3 sqm/day
2-3 sqm/day
1.27 cum/day
10-12 sqm/day