KE Distribution Network Protection
KE Distribution Network Protection
11KV SUB-STATION
MCCB
4th : CT Ratio : 400/5
LT Panel
1250A O/C , E/F , Broken Conductor
LT (0.8xIn) TRANSFORMER
HRC
750KVA
Fuse
CK T1 CKT2 CKT3 CKT4
11KV S/S VCB with
Over curren t and
Earth Fault
Protection (or)
Isolator
HT
LINK Fuse
3rd : HT Link Rating :
UG Cable 15A 3A/6A/10A/15A/30A
TRANSFORMER O/C , S/C
11KV OH 250KVA
nd
LT HRC Fuse
SC – 6.8KA
MCCB 400A
2 : MCCB Rating : 200A/
(0.8xIn) 400A/800A/1250A
HT HRC Fuse O/C , S/C
Transformer
HRC Fuse
200A 1st : HRC Fuse Rating :
100A/200A/315A/400A
LT Circuit
O/C , S/C
Breaker
HT Circuit CKT2
Breaker KWH
LT ABC
CKT1 Energy
Meter
1
9/16/2024
2
9/16/2024
and EHT
6th Stage Protection
– 4 Stages fall under Distribution domain,
11KV side of Power Trafo
comprises of HT and LT
5th Stage Protection Upstream
Upto 5th stage of protection, there are majorly 2 Side Grid Protection GSP
protection zones Domain
4th Stage Protection
Downstream Side SS/RMU
Protection
3
9/16/2024
Grid Station
11KV Busbar
5Th Stage Protection
(Upstream Grid Protection)`
CT Ratio : 800/5
O/C , E/F , Broken Conductor
HT
OverHead
11KV S/S VCB with
HT Over current and
OverHead Earth Fault
Protection (or)
Isolator
• Equipment's Grounding
Double Earth With Guard Wire
• Broken Conductor Relay
4
9/16/2024
HT Protection Schemes
Protection Activated x
Protection Failed
x x
P-1A
Protection Failed
P-1
ABC S/S
750
Fault Point
10
5
9/16/2024
LT PROTECTION ZONE
Works effectively when OL current stays Works much effectively than HRC fuse against
for a long while OL and SC faults
HRC Fuse won't be able to detect Currently used CBs won't be able to detect
leakage or High resistive faults leakage or High resistive faults
11
LT PROTECTION ZONE
11KV Overhead
TRANSFORMER
2nd Stage Protection
(LT Protection)
Breaker Rating : 80A/100A/200A/
MCCB
400A/800A/1250A
O/C , S/C Protection
HT HRC Fuse
200A 1st Stage Protection
( LT Protection)
Fuse Rating : 100A/200A/315A/400A
O/C , S/C Protection
Most Critical Zone
BARE
CKT2 KW
LT ABC H
CKT1 Energy
Meter
12
6
9/16/2024
HRC Fuses and Circuit Breakers work perfectly when current reaches up to its threshold value.
But there are conditions when fault current doesn’t reach up to certain threshold value. Some
of the conditions are:
13
RCD:
14
7
9/16/2024
• Relay settings • Testing of all types of • Annual preventive • Tripping trend analysis
relays maintenance
• Protection Scheme • Root cause analysis
designing • Instrument • Periodic corrective
• Load Estimation
transformer tests. maintenance
• Design review
• SOP formulations and
• Breaker Testing • Breakdown
• Feasibility analysis review
maintenance
• Scheme modifications • System data
management
• Short Circuit Analysis
15
Relays
16
8
9/16/2024
Protection Equipment
Relays
17
Relay Setting
A. Pickup Current
⁻ Minimum current in the relay coil at which the relay starts to operate.
⁻ Until the current in the relay is less than the pickup value, the relay does not operate, and the
breaker controlled by it remains in the closed position.
⁻ However, when the relay coil current is equal to or greater than the pickup value, the relay operates
to energize the trip coil which opens the circuit breaker.
B. Current Setting
18
9
9/16/2024
Relay Setting
⁻ The plug bridge permits to alter the number of turns on the relay coil. This changes the torque on the disc
and hence the time of operation of the relay.
⁻ The values assigned to each tap are expressed in terms of percentage full-load rating of C.T with which the
relay is associated and represents the value above which the disc commences to rotate and finally closes
the trip circuit.
⁻ The current plug settings usually range from 50% to 200% in steps of 25% for over current relays and 10%
to 70% in steps of 10% for earth leakage relays. The desired current setting is obtained by inserting a plug
between the jaws of a bridge type socket at the tap value required.
19
Relay Setting
C. Plug Setting Multiplier
⁻ It is the ratio of fault current in the relay coil to the pickup current i.e.
Example
If Fault current = 4800 A, CS= 150% & CT Ratio = 400/5 A., the PSM value can be calculated as:
Pickup Current = 150% x 5 = 7.5 A
Fault Current in relay sec. coil = 4800 x 5/400 = 60 A
PSM = 60/7.5 = 8
20
10
9/16/2024
Relay Setting
21
Relay Setting
E. Time PSM Curve
Time PSM curve shows the relationship between PSM value and
the relay operating time (𝑇 ).
Example:
If fault current = 4800 A, CS=150% & CT ratio = 400/5 A., the
actual time of operation of relay if TMS =0.6 can be calculated
as:
Solution:
Pickup Current = 150% x 5 =7.5 A
Fault current in relay sec. coil = 2400 x 5/400 = 30 A
PSM = 30/7.5 = 8
Tactual = TSM x Top = 0.6 x 3.5 = 2.1 sec
22
11
9/16/2024
23
24
12
9/16/2024
25
26
13
9/16/2024
27
Overcurrent Settings:
a) Inverse Time Phase O/C (51P) settings: 0.8 x In 0.8 x 5A = 4A OR 0.8 x 400A = 320 A
b) Instantaneous Phase O/C (50P) settings: 2.4 x In 2.4 x 5A = 12A OR 2.4 x 400A = 960A
c) Time Multiplier Settings (using below formula): 0.05
28
14
9/16/2024
Overcurrent Settings:
a) Inverse Time Phase O/C (51P) settings: 0.8 x In 0.8 x 5A = 4A OR 0.8 x 400A = 320 A
b) Instantaneous Phase O/C (50P) settings: 2.4 x In 2.4 x 5A = 12A OR 2.4 x 400A = 960A
c) Time Multiplier Settings (using below formula): 0.05
29
30
15
9/16/2024
31
Safety Procedure
⁻ AM Protection / AE Protection will obtain PTW as per SOP KE-HSED-006/2017.
⁻ AM Protection / AE Protection will deliver on-site Toolbox Talk to communicate relevant SOP to staff
and maintain a record.
⁻ AM Protection / AE Protection shall ensure proper usage of PPEs/SPEs during execution.
⁻ AM Protection / AE Protection will assess all equipment and tools to ensure working condition as per
clause.
Testing Procedure
⁻ AM/AE Protection shall check and ensure in presence of CM team that
32
16
9/16/2024
33
34
17
9/16/2024
35
36
18
9/16/2024
For relay connection in various type of VCBs/RMU installed in KE Distribution Network, please refer annexures as
stated in below table in Distribution protection Manual:
37
38
19
9/16/2024
39
Relay Installation Diagram Fanox SIAC Connection Diagram for Schneider MICOM P-116 Relay
40
20
9/16/2024
Following steps shall be followed in order to discriminate the relays installed in distribution
SS/RMU with Grid:
⁻ Relay coordination activity shall be performed before the energization of VCB/RMU.
⁻ Relay complete wiring verification shall be performed with VCB/RMU.
⁻ Relay testing shall be performed as per procedure.
⁻ Earthing of substation/RMU shall be ensured before energization.
⁻ Standard relay settings as mentioned in section shall be done on VCB/RMU. Please ensure that
TMS values of both phase and neutral shall be less than the available grid relay TMS settings.
⁻ After completing above mentioned procedures, request shall be forwarded to GSP analysis
team for the induction of time delay on Instantaneous Phase O/C (msec), Instantaneous
Neutral O/C (msec) or activation of BC feature at Grid feeder relay.
⁻ After fulfillment of requirements and confirmation from GSP analysis team, feeder tripping
response shall be monitored as per procedure.
41
⁻ All the distribution feeders that are aligned with Grid shall be
monitored to ensure the effectiveness of protection.
Analytics
⁻ Each cluster shall maintain the monthly analysis sheet comprising of
all aligned feeders protection performance.
Identification of
⁻ The protection performance of each feeder shall be monitored based Troubleshooting non-responding
on below parameters: feeders
⁻ Plan shall also be developed for feeders that are responding accurately in order to maintain the required
results
42
21
9/16/2024
⁻ Monthly performance analysis of feeders (excluding Main cable faults) shall be maintained as per below
template by each cluster.
43
⁻ Comparison of performance against the previous month shall be maintained against below summarized table:
44
22
9/16/2024
HT Fuse Link
45
HT Fuse link
11kV fuse links are used in drop out cutout to protect distribution transformers from
damage caused by overcurrent and short circuit.
A fuse link must act quickly to isolate equipment from lines when the equipment suffers
internal or external failure.
46
23
9/16/2024
1 3
2 6
3 10
4 15
5 30
6 40
47
Circuit Breaker
48
24
9/16/2024
Protection Equipment
Circuit Breakers
• Circuit breakers are interrupting and switching devices that provide time-
overcurrent protection.
• It is capable of making, with standing and interrupting overload currents as well as
short-circuit currents.
• In medium-voltage (1–72.5 kV) circuit breakers, the sensing devices are separate
current transformers (CTs) and protective relays.
• For low-voltage (under 1000 V) circuit breakers, the sensing elements are an
integral part of the circuit breaker.
• These trip units may be thermal or magnetic series devices; or they may be
electronic devices used with CTs mounted in the circuit breaker.
49
50
25
9/16/2024
- MCCBs shall be installed on PMTs, inside LT panels and feeder pillar boxes to protect
transformer and LT circuits from overloading/faults.
- Based on tripping mechanism thermo-magnetic and electronic trip circuit breakers are being
used in KE network.
51
52
26
9/16/2024
Time current characteristic curves of LS make circuit breakers are as given below:
53
Time current characteristic curves of LS make circuit breakers are as given below:
54
27
9/16/2024
Time current characteristic curves of LS make circuit breakers are as given below:
55
Time current characteristic curves of LS make circuit breakers are as given below:
56
28
9/16/2024
Time current characteristic curves of LS make circuit breakers are as given below:
57
Time current characteristic curves of LS make circuit breakers are as given below:
58
29
9/16/2024
Time current characteristic curves of LS make circuit breakers are as given below:
59
MCCBs rating shall depend upon transformer secondary current. Selection and setting of low voltage circuit
breakers shall be as per Table below in LT network Guidelines as shown below.
60
30
9/16/2024
HRC Fuse
61
Protection Equipment
Fuses
62
31
9/16/2024
HRC FUSE
⁻ HRC = High Rupturing Capacity
⁻ Time of operation depends upon nature of
fault
⁻ Works on overload and short circuit faults
⁻ HRC fuse operation is defined by the curve in
standard IEC-60269-2
⁻ Curve is gG type (General purpose use)
⁻ HRC fuses shall be installed on secondary side
of transformer in DBs, LT panels and pillar
boxes to protect LT cables and conductors
from overloading and short circuit.
63
HRC FUSE
⁻ HRC = High Rupturing Capacity
⁻ Time of operation depends upon nature of
fault
⁻ Works on overload and short circuit faults
⁻ HRC fuse operation is defined by the curve in
standard IEC-60269-2
⁻ Curve is gG type (General purpose use)
⁻ HRC fuses shall be installed on secondary side
of transformer in DBs, LT panels and pillar
boxes to protect LT cables and conductors
from overloading and short circuit.
0.2 s
64
32
9/16/2024
Time current characteristic curves of gG type fuse links as per IEC 60269-2 (latest applicable)
65
66
33
9/16/2024
TOOLS &
EQUIPMENT
Terminal Screw
Air Blower Allen Key Set Extension Board
Driver set
RS-232 to USB
Plier Crocodile clamps Drill Machine
Converter
67
Working
Gloves
Safety
Uniform
Shoes
Face
First Aid Box
Shield Goggles
68
34
9/16/2024
THANK YOU
Lorem ipsum dolor sit ame t
69
35