Problem Set U.1
Problem Set U.1
Subject
Operations Research
Unit I:
Introduction to Operations Research
students
Miss Xolio Miguel Alejandro
Morales Saucedo Luis Angel
Rodríguez Juárez Gustavo
City Quantity
Morelia 2,500
Sonora 2,750
Veracruz 1,750
The delivery area engineer estimates the transportation costs per unit of each of the
Plants for each of the destinations are as follows:
With this information, we want to find the combination that minimizes the
transportation costs. Formulate the linear programming problem
Problem 3
WYNDOR GLASS CO. produces high-quality glass items, including windows and doors.
made of glass. It has three floors. Two products are manufactured whose potential sales are very
promising:
an 8-foot glass door with frame of
aluminum Product 2: a sliding window with frame of
wood of 4 by 6 feet The IO team also identified
the data I needed to gather:
1. Number of available production hours per week in each plant to manufacture these
products.
2. Number of manufacturing hours used to produce each batch of each item each time.
of the plants.
3. The profit per batch of each new product. (The profit was chosen
for
lot
Determine what production rates the two products should have in order to maximize the
total utilities, subject to the restrictions imposed by limited production capacities
available on all three floors.
(Each product will be manufactured in batches so that the production rate is defined as the
number of batches produced per week.
Formulate the linear programming problem
Problem 4
A workshop has 2 types of machines A and B, they can manufacture 2 products 1 and 2, all the
Products must go to each machine and each one goes in the same order, first to the
machine A, then to B. The following table shows the hours required on each machine,
per product unit, the total hours available for each machine per week and the
profit per unit sold of each product.
Hours
Type of Machine Product 1 Product 2
available
per week
8 hours of
A 1 hour 4 hours
the
Machine A
4 hours of
B 1 hour 2 hours
the
machine B
Profits
$3 $9
for
Unit
City Quantity
Morelia 2,500
Sonora 2,750
Veracruz 1,750
The delivery area engineer estimates that the transportation costs per unit of each one
from the plants to each of the destinations is as follows:
With this information, we want to find the combination that minimizes transportation costs.
that is, we must decide how many computers from each of the plants should be
transported to each of the destinations, in such a way that the total transportation cost is
minimum. Pose the linear programming problem.
Problem 7
If you want to know the lowest cost allocation for the company. Formulate the problem of
linear programming