Construction of High Voltage Transmission
lines, type of towers, type of insulators
M.SELVARAJ
Engineering Officer
Central Power Research Institute, Bangalore
E-mail : [email protected]
10-Jan-20 1
TOWER DESIGN
1. TOWER TYPES
2. CLASSIFICATION OF TOWER
3. TOWER CONFIGURATION
4. LOADING OF TOWER
5. ANALYSIS AND DESIGN
10-Jan-20 2
COST COMPARISION OF TRANSMISSION LINE
10% Tow ers
10% Conductors
40%
Foundations
15%
Insulators& Fittings
Land Rentals &
20% Compensations
10-Jan-20 3
Type of Towers
a). Tangent towers with suspension string (0° to 2 °)
b). Small angle towers with tension strings (2° to 15 °)
c). Medium angle towers with tension strings (15 ° to 30 °)
d). Large angle (30 ° to 60 °) and dead end towers with
tension strings.
10-Jan-20 4
CLASSIFICATION OF TOWERS
ACCORDING TO CONSTRUCTIONAL FEATURE:
- Self Supporting Towers.
- Conventional Guyed Towers.
ACCORDING TO NO OF CIRCUITS THEY
CARRY:
- Single Circuit Towers.
- Double Circuit Towers.
- Multi Circuit Towers.
ACCORDING TO TOWER SHAPES:
- Horizontal Towers.
- Vertical towers.
10-Jan-20 5
WIND LOADS
Conductors and insulators
) AD
OR LO
UCT R
ND TO
(CO UC
S O ND
O AD ENC
ITYL OK
AV BR
GR T)
EIGH
/W
IND
(W
AN
SP
Towers
Foundations
Transmission line system
10-Jan-20 6
DESIGN OF MECHANICAL SUPPORTS
i) POLE - SINGLE MAIN MEMBER
STEEL, R.C.C, P.S.C, WOOD
ii) TOWER - LATTICE STRUCTURE
Mild Steel, H.T.S
ROLLED STEEL ANGLES
10-Jan-20 7
SELF SUPPORTING TOWER
HORIZONTAL CONFIGURATION VERTICAL CONFIGURATION
10-Jan-20 8
COMPACT TRANSMISSION LINE STRUCTURES
GUY TOWER 132 kV D/C 132 kV S/C -POLE 132 kV D/C - POLE
10-Jan-20 9
TOWER CONFIGURATION
A TOWER IS CONSTITUTED OF FOLLOWING:
- PEAK
- CROSS ARM
- BOOM
- CAGE
- TOWER BODY
- BODY EXTENSION
- LEG EXTENSION
- STUB/ANCHOR BOLT & BASE PLATE
ASSEMBLY.
10-Jan-20 10
DESIGN PARAMETERS
- VOLTAGE LEVEL
- SPAN
- CONDUCTOR DETAILS ( ACSR/AAAC)
- EARTHWIRE DETAILS ( GSS/OPGW)
- WIND SPEED
- MAX & MIN TEMPERATURE ( Climatic condition )
- INSULATOR DETAILS ( Porcelain / Polymeric )
- MIN. GROUND CLEARANCE
- PHASE TO PHASE CLEARANCE ( horizontal & vertical)
10-Jan-20 11
Right of Way ( ROW) Requirement
Conventional Lattice Towers
Occupy large space, acute
right of way ( ROW)
problems, tower members
theft etc.
Voltage level ROW
33 kV 15 m
66 kV 18 m
110 kV 22 m
132 kV 27 m
220 kV 35 m
400 kV 50 m
800 kV 85 m
10-Jan-20 12
WIND LOADS
Basic wind speed (Vb)
10 m above ground level
averaged over 3 seconds
Reference wind speed (VR)
averaged over 10 minutes
VR = Vb / 1.375
10-Jan-20 13
SAG-TENSION
Conductor and Ground wire
As per IS:5613 (Part 2/Sec 1) : 1985 for the following
combinations
- 100 % design wind pressure at every day
temperature
- 36 % design wind pressure at minimum
temperature
PSTI-CPRI
10-Jan-20 14
TEMPERATURE EFFECTS
Temperature variations
Maximum temperature
ACSR conductor - 75° C
AAAC conductor - 85° C
Ground wire - 53° C
Average temperature - 32° C 15° C
Minimum temperature - -5° C
10-Jan-20 15
CONDUCTOR TYPES
ACSR
AAAC
ACAR
AAC
New Technology Conductors
- Trapezoidal
- ACSS
- INVAR
- Self Damping
- Vibration Resistant
10-Jan-20 16
10-Jan-20 17
10-Jan-20 18
10-Jan-20 19
10-Jan-20 20
DESIGN OF TOWERS
- DESIGN PARAMETERS
- SAG-TENSION CALCULATION
- TOWER GEOMETRY
- ESTIMATION OF EXTERNAL LOADS
- COMPUTER MODELLING
- TOWER ANALYSIS/DESIGN
10-Jan-20
PSTI-CPRI 21
SAG - TENSION CALCULATION
- CONDUCTOR
- GROUNDWIRE (90 % of Conductor Sag )
- SHIELDING ANGLE
ADEQUATE LIVE METAL CLEARANCE TO BE ALLOWED
FOR GIVEN SWING OF JUMPER / INSULATOR STRINGS
- DEPENDS ON LINE VOLTAGE
10-Jan-20
PSTI-CPRI 22
TOWER GEOMETRY
- DEPENDS ON LINE VOLTAGE
- ELECTRICAL CLEARANCE
- SELECTION OF CONDUCTOR
- MAX. SAG + CREEP
- MIN GROUND CLEARANCE
- LOCATION
10-Jan-20
PSTI-CPRI 23
TOWER OUTLINE
h4
h1 = Max.Sag + Creep
+ Ground clearance
h3
h2
h1
B
10-Jan-20 24
CLEARANCE DIAGRAM
= shielding angle
for lines up to 220 kV
= 30
for lines 400 kV and above
= 20
10-Jan-20 25
CLEARANCE DIAGRAM
220 kV TOWER
SPAN : 350 m
VERTICAL SPACING (v)
V : 5.0 m
H : 8.5 m
Min. Ground
Clearance : 7.0 m
x2 Mid span
Clearance : 8.5 m
Swing angle : 15 deg
x1 60 deg
X1 : 2.1 m
X2 : 1.7 m
ACSR/AAAC – ZEBRA
HORIZONTAL SPACING ( H)
10-Jan-20 26
10-Jan-20 27
10-Jan-20 28
Minimum Electrical clearances
10-Jan-20 29
Minimum clearances for any conductor of an overhead line from
ground and buildings at different places shall be as given below:
Low & Medium High voltage
lines Voltage lines
(m) (m)
a)Minimum height of any conductor 5.80 6.10
of an overhead line across any street
b)Minimum height of any conductor
of an overhead line along any street 5.50 5.80
c)Minimum height of any conductor (bare)
of an overhead line erected elsewhere 4.60 4.60
d)Minimum height of any conductor
(insulated) of an overhead line erected 4.00 4.00
elsewhere
e)Minimum clearance of overhead line 2.50 3.70
conductor from building (vertical) (vertical)
10-Jan-20
1.20 1.20 30
(horizontal) ( horizontal)
Basic wind speeds IS:875 ( Part-3 )
Wind Zone Basic wind speed
m/s km/hr
1 33 119
2 39 130
3 44 158
4 47 169
5 50 180
6 55 198
10-Jan-20 31
Design wind speed (Vd)
Vd = VR * K1 * K2
where
K1 = Risk coefficient
function of Reliability level and
wind zone
K2 = Terrain coefficient
10-Jan-20 32
Design wind pressure (Pd)
Pd = 0.6 Vd 2
Wind load on tower (Fwt)
Fwt = Pd * Cdt * Ae * GT
Cdt = drag coefficient
Ae = total net surface area
GT = gust response factor
10-Jan-20 33
FLOW CHART FOR TOWER DESIGN
NAME, VOLTAGE, GEOLOGICAL DESIGN PHILOSPHY
CLASS, WIND ZONE & CONSTRAINTS (FROM IS / IEC/
BASIC DESIGN DETAILS OF ROUTE & STANDARDISATION
PARAMETERS ( FROM BILL OF QUANTITIES COMMITTEE
APPROVED FR OR SEF (FROM SITE) REPORTS)
GROUP)
INPUTS
REVIEW
CONFOIGURATION & TYPE OF TOWERS
REVIEW
TOWER LOADINGS & CONDITIONS
REVIEW DESIGN
STURUCTIRAL ANALYSIS STAGES
-BY COMPUTER
-BY MANUAL VERIFICATION
REVIEW
FINAL DESIGN (THEORITICAL)
STRUCTURAL DRAWINGS
PROTO MANUFACTURE/ FABRICATION TESTING &
MODIFY DESIGN FINALISATION
SUCCESSFUL
FAILED
PROTO TESTING (FULL SCALE) DESIGN FINALISED
10-Jan-20 34
LOAD ESTIMATION
10-Jan-20 35
LOADING DIAGRAM
10-Jan-20 36
TOWER DESIGN – CTADS SOFTWARE
10-Jan-20 37
3-D MODELLING OF 132 kV TOWER
10-Jan-20 38
CTADS- POST PROCESSOR
10-Jan-20 39
10-Jan-20 40
10-Jan-20 41
10-Jan-20 42
10-Jan-20 43