Following quiz provides Multiple Choice Questions (MCQs) related to SAP PM. You will have to read all the given answers and click over the correct answer. If you are not sure about the answer then you can check the answer using Show Answer button. You can use Next Quiz button to check new set of questions in the quiz.

Questions and Answers

Answer : E

Explanation

Key functions as part of Plant Maintenance −

  • Inspection and Notifications
  • Corrective and Preventive Maintenance
  • Breakdown Maintenance
  • Repair
  • Other measures - charactertics and Key Figures

Answer : C

Explanation

In SAP PM, when there is a malfunction occurs for any of the equipment which requires a response from Maintenance team. The process of correcting this situation is known as Breakdown maintenance.

Q 3 - Which of the following plan can be created without a maintenance strategy and is used for performance based maintenance?

A - Single Cycle Plan

B - Strategy Plan

C - Multiple Counter plan

D - Maintenance plan for service procurement

Answer : C

Explanation

A multiple counter plan can be created without a maintenance strategy and is used for performance based maintenance. In the multiple counter plan you create maintenance cycles and allocate counters of equipment or functional locations with different dimensions to them.

Q 4 - Which process of SAP Plant Maintenance is used to repair spare parts and to return the spare parts to warehouse or to the equipment?

A - Refurbishment Process

B - Project-Oriented Maintenance

C - Breakdown Maintenance

D - Preventive Maintenance

E - Work Clearance Maintenance

Answer : A

Explanation

Refurbishment is defined as process to repair spare parts and to return the spare parts to warehouse or to the equipment. You can define a Refurbishment order as Maintenance order by which you can execute the process of refurbishing damaged equipment and to perform this you need a material and Serial # combination.

Q 6 - In Refurbishment process, to move the material to Warehouse which of the following movement type is created?

A - Movement type 101

B - Movement type 102

C - Movement type 103

D - Movement type 104

Answer : A

Q 7 - Which of the following location is used to define maintenance task lists and material planning is carried out?

A - Maintenance Plant

B - Maintenance Planning Plant

C - Warehouse

D -All of the above

Answer : B

Q 8 - Which of the following shows an invalid warranty and negative checks are shown for Warranty claim results?

A - 00

B - 03

C - 01

D - 02

Answer : B

Explanation

  • 00 shows a valid warranty and positive check result are shown.
  • 03 shows an invalid warranty and negative check result are shown.
  • 01 shows no warranty check possible since required measuring point is missing in the warranty claim.
  • 02 shows no warranty check possible since required measurement document is missing in the system.

Q 9 - When you create a maintenance strategy plan for a Printer to be performed after 1 million copies, it is example of?

A - Time based

B - Performance Based

C - Both of these

Answer : B

Q 10 - Which of the following are the technical objects?

A - None

B - Equipment & Functional location

C - Material

D - BOM

Answer : B