Project: Design of Flood Wall along Morong River
For Tradeoff 1 (Sheet Pile)
BILL OF QUANTITIES
ITEM NO. DESCRIPTION QTY UNIT TOTAL UNIT COST TOTAL COST
I. DESIGN PHASE:
Preliminary Survey/Studies 1.00 lot 187,590.00 187,590.00
TOTAL FOR DESIGN PHASE 187,590.00
II. CONSTRUCTION PHASE
A. GENERAL REQUIREMENTS
1 Temporary Facilities 1.00 lot 533,910.00 533,910.00
2 Safety & Health Standard and Housekeeping 1.00 lot 899,100.01 899,100.01
TOTAL GENERAL REQUIREMENTS 1,433,010.00
B. CONSTRUCTION OF FLOOD WALL .
1 CIVIL WORKS
1.1 FORMWORKS AND EXCAVATION
Cover Walls 288.68 cu.m 3,515.40 1,014,833.20
Hauling & Disposal of debris 1.00 lot 1,065,036.00 1,065,036.00
1.2 INSTALLATION OF SHEET PILES
U- Type Sheet Piles 1067 pcs 27000 28,809,000
Total Civil Works 30,888,869.20
Project: Design of Flood Wall along Morong River
For Trade-offs 2 (Concrete Retaining Wall )
BILL OF QUANTITIES
ITEM NO. DESCRIPTION QTY UNIT TOTAL UNIT COST TOTAL COST
I. DESIGN PHASE:
Preliminary Survey/Studies 1.00 lot 187,590.00 187,590.00
TOTAL FOR DESIGN PHASE 187,590.00
II. CONSTRUCTION PHASE
A. GENERAL REQUIREMENTS
1 Temporary Facilities 1.00 lot 533,910.00 533,910.00
2 Safety & Health Standard and Housekeeping 1.00 lot 899,100.01 899,100.01
TOTAL GENERAL REQUIREMENTS 1,433,010.00
B. CONSTRUCTION OF FLOOD WALL .
1 CIVIL WORKS
1.1 FORMWORKS AND EXCAVATION
Cover Walls 288.68 cu.m 3,515.40 1,014,833.20
Hauling & Disposal of debris 1.00 lot 1,065,036.00 1,065,036.00
1.2 INSTALLATION OF CONCRETE RETAINING WALL
Concrete Retaining wall blocks 14000 pcs 800 13,140,000
Base Gravel 43.3579 m3 784.17 34000
Backfill Gravel 1981.933 m3 784.17 1,555,350
Special Cap blocks 2000 pcs 970 40000
Total Civil Works 14,769,350
Project: Design of Flood Wall along Morong River
For Trade-offs 3 (SeaWall )
BILL OF QUANTITIES
ITEM NO. DESCRIPTION QTY UNIT TOTAL UNIT COST TOTAL COST
I. DESIGN PHASE:
Preliminary Survey/Studies 1.00 lot 187,590.00 187,590.00
TOTAL FOR DESIGN PHASE 187,590.00
II. CONSTRUCTION PHASE
A. GENERAL REQUIREMENTS
1 Temporary Facilities 1.00 lot 533,910.00 533,910.00
2 Safety & Health Standard and Housekeeping 1.00 lot 899,100.01 899,100.01
TOTAL GENERAL REQUIREMENTS 1,433,010.00
B. CONSTRUCTION OF FLOOD WALL .
1 CIVIL WORKS
1.1 FORMWORKS AND EXCAVATION
Cover Walls 288.68 cu.m 3,515.40 1,014,833.20
Hauling & Disposal of debris 1.00 lot 1,065,036.00 1,065,036.00
1.2 INSTALLATION OF CONCRETE SEAWALL
Concrete (cement,sand, gravel) 12000 m3 1000 12000000
Rebars 10000 pcs 40 400000
Carriage Bolts 5000 pcs 250 125000
Total Civil Works 12,525,000