0% found this document useful (0 votes)
135 views3 pages

Monthly Project Manager's Report

The project manager's report summarizes the following: 1) Progress, issues, risks, and opportunities from the past month. 2) Planned activities for the next period. 3) Resourcing status and any issues. 4) Project control details including time, cost, and variance metrics to track performance against the baseline plan.

Uploaded by

iskandar027
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
135 views3 pages

Monthly Project Manager's Report

The project manager's report summarizes the following: 1) Progress, issues, risks, and opportunities from the past month. 2) Planned activities for the next period. 3) Resourcing status and any issues. 4) Project control details including time, cost, and variance metrics to track performance against the baseline plan.

Uploaded by

iskandar027
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd

Project Manager’s Report to end Month

1. PROGRESS DURING MONTH

2. ISSUES

3. RISKS AND OPPORTUNITIES

4. ACTIVITIES FOR NEXT PERIOD

5. RESOURCING

6. PROJECT CONTROL - Select from the following, as appropriate

6.1 Time

Forecast completion date

Original required Completion Date


Forecast Completion Date
Completion Date Variation
Variation on Program Critical Path (Months)
Notes:

Major Milestones

Milestones Date Notes


Estimated Actual

6.2 Variations/ contingencies management

(This is the project budget, not the funding appropriation or current year allocation)
Forecast cost & budget to complete are as follows:

BUSINESS CASE PROJECT PLAN REVISED REVENUE FORECAST FINAL COST


BUDGET
Budgeted work
Variations
Cost of Work
Contingencies
Total Estimated cost

/conversion/tmp/scratch/[Link] Page 1
Project Manager’s Report to end Month

Variation Log

No Date Variation Source of Funds Amount Time Completion


Extensio Date
n

6.3 Cost
Forecast final expenditure position relative to funding appropriation– all financial years

Overall Project $M Notes


Original Approved Appropriation
CBRC Approved/Revised Appropriation
Forecast Final Cost
Variation on Revised Appropriation
Notes:
Current expenditure position – all financial years

Overall Project Expenditure Revenue Total ($M)


($M) ($M)
Previous financial years
This financial year
Total project to Date
Notes:
Expenditure details – This financial year

Month Original Actual Variation year Original Revenue CBRC Forecast


Expenditure Expenditure to Date /Revised $M Approved/ Final
Estimate year to Date Allocation Revised Project Project
(cumulative) $M $M $M Budget (All years) Cost (All
$M $M years)
$M
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
/conversion/tmp/scratch/[Link] Page 2
Project Manager’s Report to end Month

6.4 Earned value (where appropriate/possible)

Earned value and schedule performance on the project to the end of month relative to latest baseline
budget (project plan + variation nos … to …) are shown below:

Planned Value Earned Value Actual Cost Schedule Schedule Cost Cost Variance
Cost (BCWS) Cost (BCWP) (ACWP) Performance Variance Performance
Index (SPI) Index (CPI)

Note - These figures exclude contingencies


- BCWS = Budgeted Cost of Works Scheduled SV - Schedule Variance = BCWP - BCWS (Target +ve)
- BCWP = Budgeted Cost of Works Perform CPI - Cost Performance index = BCWP/ACWP (- Target > 1)
- ACWP = Actual Cost of Works Performed CV - Cost Variance = BCWP - ACWP (Target +ve)
- SPI - Schedule performance index = BCWP/BCWS (Target >1)
- SV - Schedule Variance = BCWP - BCWS (Target +ve)

Interpretation of figures -

The project is …… ahead/behind schedule on cost because…….


The project is …… ahead/behind schedule on time because……
The revised baseline shows project completion to be …………..
The following corrective action is proposed ……………............

/conversion/tmp/scratch/[Link] Page 3

You might also like