Schedule Comparison

This document provides a status update of various construction activities for a power project. It lists activities scheduled and actual start/finish dates. For most activities, it indicates the percentage of work planned, completed in previous months, and in the current month. Most activities are progressing close to or on schedule, though some have yet to begin. Engineering drawings have been approved or released for information for various components.

Uploaded by

ASIF WAZIR
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
113 views7 pages

Schedule Comparison

This document provides a status update of various construction activities for a power project. It lists activities scheduled and actual start/finish dates. For most activities, it indicates the percentage of work planned, completed in previous months, and in the current month. Most activities are progressing close to or on schedule, though some have yet to begin. Engineering drawings have been approved or released for information for various components.

Uploaded by

ASIF WAZIR
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd

PVT LTD.

MW DISTRICT
Status of Construction Activities

Actual Achieved DRAWING STATUS


Scheduled Dates Actual Schedule

Sr. Planned (for the


Activity Remarks
No. M/O Aug) Up-to Current
APPROVED/IFC/JUST
Previous Month
Start Finish Start Finish FOR INFORMATION
Month (Aug)

1 Zone 1
22-6-2015 JUST FOR
A Access Roads to power house 31-Dec-14 30-Jul-15 1-Jan-15 1-Jul-15
INFORMATION
1 Excavation (Pilot Cut) 31-Dec-14 29-Jan-15 1-Jan-15 1-Feb-15 7% 93% 7% 100%
2 Filling (Pilot cut) 31-Dec-14 29-Jan-15 1-Jan-15 1-Feb-15 7% 93% 7% 100%
3 Sub Base 30-Jan-15 28-Feb-15 1-Jan-15 1-Feb-15 7% 93% 7% 100%
4 Aggregate Base 1-Jul-15 30-Jul-16 - - Not in Progress
5 TST 1-Jul-16 30-Jul-16 - - Not in Progress
B Access Bridge to power house 23-Feb-15 5-Jul-15 23-Mar-15 5-Jul-15 19-5-2015 IFC
1 Pilling 23-Feb-15 9-Apr-15 1-Mar-15 27-Aug-15 10% 80% 10% 90%
2 Pile Caps 31-Mar-15 3-Apr-15 1-Jun-15 3-Jun-15 5% 60% 5% 65%
3 Pier 10-Apr-15 4-May-15 24-Jun-15 24-Jul-15 5% 95% 5% 100%
4 Transom 29-Apr-15 18-May-15 20-Aug-15 19-Sep-15 2% 10% 5% 15%
5 Girder & Deck slab Pre cast 31-Mar-15 24-May-15 20-Jun-15 10-Aug-15 0% 50% 0% 50%
6 Abutment . 10-Apr-15 9-May-15 10-Jul-15 9-Aug-15 5% 50% 5% 55%
7 Girder & Deck launching 25-May-15 13-Jun-15 24-Aug-15 12-Sep-15 0% 0% 0% 0%
Deck Remaining cast insitue
8 16-Jun-15 25-Jun-15 - - Not in Progress
concrete
9 Parapet walls 21-Jun-15 5-Jul-15 - - Not in Progress
10 Steel Reinforcement 23-Feb-15 5-Jul-15 23-Mar-15 5-Apr-15
Access Road to weir & inlet 22-6-2015 JUST FOR
C 14-Feb-15 3-May-16 14-Jan-15 8-Feb-16
Tunnel Portal INFORMATION
1 Excavation (Pilot Cut) 14-Feb-15 14-Apr-15 14-Jan-15 14-Feb-15 20% 80% 20% 100%
2 Filling (Pilot cut) 16-Mar-15 14-Apr-15 14-Jan-15 14-Feb-15 20% 80% 20% 100%
3 Sub base 4-Apr-16 3-May-16 4-Mar-16 4-Apr-16 35% 65% 35% 100%
22-6-2015 JUST FOR
D Access Road to outlet portal 14-Feb-15 14-Apr-15 4-Mar-15 5-May-15
INFORMATION
1 Excavation (Pilot Cut) 14-Feb-15 14-Apr-15 4-Mar-15 5-May-15 14% 86% 14% 100%
2 Filling (Pilot cut) 14-Feb-15 14-Apr-15 4-Mar-15 5-May-15 14% 86% 14% 100%
22-6-2015 JUST FOR
E Access Road to surge tank 1-Mar-15 14-Apr-15 1-Jun-15 14-Jul-15
INFORMATION
1 Excavation (Pilot Cut) 1-Mar-15 14-Apr-15 1-Jun-15 14-Jul-15 5% 55% 5% 60%
2 Filling (Pilot cut) 1-Mar-15 14-Apr-15 1-Jun-15 14-Jul-15 5% 55% 5% 60%
22-6-2015 JUST FOR
F Colony Roads 1-Mar-15 27-Sep-15 1-Jan-15 1-Jul-15
INFORMATION
1 Excavation (Pilot Cut) 1-Mar-15 28-Jun-15 1-Jan-15 28-Apr-15 2% 98% 2% 100%
2 Filling (Pilot cut) 1-Mar-15 28-Jun-15 1-Jan-15 28-Apr-15 10% 90% 10% 100%
3 Sub Base 29-Jun-15 12-Aug-15 29-Apr-15 28-Jun-15 6% 94% 6% 100%
4 TST 29-Aug-15 27-Sep-15 - - 24-7-2015 IFC Not in Progress
G Buildings 16-Mar-15 9-Jul-16 1-Jun-15 1-Oct-16
Type I,II,III,IV Residential Buildings 16-Mar-15 14-Mar-16 1-Jun-15 14-Jun-16 5% 5% 5% 10%
Office Buildings 11-Apr-15 5-Jan-16 - - Not in Progress
Mosque 11-Apr-15 5-Jan-16 - - Not in Progress
Guest House 11-May-15 9-May-16 - - Not in Progress
Hospital 10-Jun-15 8-Jan-16 - - Not in Progress
Bechelor Hostel 20-Jun-15 18-Jun-16 - - Not in Progress
Shoaps,Despencery and an other 11-Jul-15 9-Jul-16 - - Not in Progress
2 Zone 2
Work has been
11-5-2015 IFC & 19-
A Causeway 21-Feb-15 1-Apr-15 13-May-15 23-Jul-15 5% 70% 5% 75% stopped due to Local
8-2015 REV.2 IFC
issues
1 Excavation for River Diversion 21-Feb-15 3-Mar-15 13-May-15 24-May-15 - 100% 0% 100%
2 Filling for River Diversion 21-Feb-15 2-Mar-15 13-May-15 24-May-15 - 100% 0% 100%
3 Excavation for Causeway 3-Mar-15 12-Mar-15 24-May-15 3-Jun-15 100% 0% 100%
4 Steel Reinforcement 9-Mar-15 28-Mar-15 2-Jun-15 21-Jun-15 75% 0% 75%
5 Concrete 13-Mar-15 1-Apr-15 1-Jun-15 18-Jun-15 75% 0% 75%
22-6-2015 JUST FOR
B Tyrolene Weir intake Right side 1-Sep-15 14-Dec-15 - - Not in progress
INFORMATION
1 Excavation for River Diversion 1-Sep-15 15-Sep-15 - - Not in progress
2 Filling for River Diversion 1-Sep-15 15-Sep-15 - - Not in progress
3 Excavation for weir 16-Sep-15 30-Sep-15 - - Not in progress
4 Steel Reinforcement 1-Oct-15 30-Oct-15 - - Not in progress
5 Concrete 16-Oct-15 4-Nov-15 - - Not in progress
6 Grouting (if Needed) 15-Nov-15 14-Dec-15 - - Not in progress
22-6-2015 JUST FOR
7 u/s & d/s Rip Rap 15-Nov-15 14-Dec-15 - - Not in progress
INFORMATION
C Tyrolene Weir intake Left side 15-Dec-15 28-Mar-16
1 Excavation for River Diversion 15-Dec-15 29-Dec-15 - - Not in progress
2 Filling for River Diversion 15-Dec-15 29-Dec-15 - - Not in progress
3 Excavation for weir 30-Dec-15 13-Jan-16 - - Not in progress
4 Steel Reinforcement 14-Jan-16 12-Feb-16 - - Not in progress
5 Concrete 29-Jan-16 17-Feb-16 - - Not in progress
6 Grouting (if Needed) 28-Feb-16 28-Mar-16 - - Not in progress
7 u/s & d/s Rip Rap 28-Feb-16 28-Mar-16 - - Not in progress
22-6-2015 JUST FOR
D Connecting Channel 17-Mar-15 24-Jul-16 27-Jul-15 27-Nov-16
INFORMATION
Excavation 17-Mar-15 30-Apr-15 27-Jul-15 10-Sep-16 25% 10% 25% 35%
Filling 1-Apr-15 30-Apr-15 Not in progress
Steel Reinforcement 1-May-15 24-Jul-15 Not in progress
Concrete 1-May-15 24-Jul-15 Not in progress
26-08-2015 FOR
E Sand Trap & Spill channel 25-Mar-15 22-Sep-15 27-Jul-15 27-Jan-16
APPROVAL
Excavation 25-Mar-15 22-Jun-15 27-Jul-15 27-Oct-15 5% 15% 5% 20%
Filling 25-Mar-15 22-Jun-15 27-Jul-15 27-Oct-15 2% 3% 2% 5%
Steel Reinforcement 25-Jun-15 22-Sep-15 - - Not in progress
Concrete 25-Jun-15 22-Sep-15 - - Not in progress
22-6-2015 JUST FOR
F Headrace channel 26-Oct-15 22-Apr-16 - - Not in progress
INFORMATION
Excavation 26-Oct-15 23-Jan-16 - - Not in progress
Filling 26-Oct-15 23-Jan-16 - - Not in progress
Steel Reinforcement 24-Jan-16 22-Apr-16 - - Not in progress
22-6-2015 JUST FOR
Concrete 24-Jan-16 22-Apr-16 - - Not in progress
INFORMATION
G Protection wall 1-Sep-15 17-Feb-16 - - Not in progress
Stone wire crates wall 1-Sep-15 17-Feb-16 - - Not in progress
H Syphon 1-Jan-17 16-Mar-17 - - Not in progress
Excavation 1-Jan-17 30-Jan-17 - - Not in progress
Filling 1-Jan-17 30-Jan-17 - - Not in progress
Steel Reinforcement 31-Jan-17 16-Mar-17 - - Not in progress
Concrete 31-Jan-17 16-Mar-17 - - Not in progress
Concrete 31-Jan-17 16-Mar-17 - - Not in progress
DRAWINGS IN
I Hydrmechanical works 1-Nov-16 31-Mar-17 - - Not in progress
PROGRESS
Hydrmechanical works on weir 1-Nov-16 29-Jan-17 - - Not in progress
Hydrmechanical works on sand trap 1-Nov-16 29-Jan-17 - - Not in progress
Hydrmechanical works on inlet 1-Jan-17 31-Mar-17 - - Not in progress
Zone 3(Power house civil &
3 18-Mar-15 11-May-17 15-Aug-15 15-Oct-17
E&M)
22-6-2015 JUST FOR
A Power house civil 18-Mar-15 10-May-17 15-Aug-15 15-Oct-17
INFORMATION
Excavation 18-Mar-15 30-Jul-15 15-Aug-15 15-Dec-15 15% 0% 15% 15%
Lean concrete 31-Jul-15 29-Aug-15 Not in progress
Steel Reinforcement (Foundation or
31-Jul-15 28-Sep-15 Not in progress
floor) 1st stage
Structural concrete Foundation or
10-Sep-15 8-Nov-15 Not in progress
floor 1st stage
Steel Reinforcement walls 9-Nov-15 6-Feb-16 Not in progress
Structural Concrete walls 19-Nov-15 16-Feb-16 Not in progress
Steel Reinforcement top slab 17-Feb-16 16-Apr-16 Not in progress
Structural Concrete Top slab 27-Feb-16 26-Apr-16 Not in progress
Steel Reinforcement(Foundation or
2-Nov-16 30-Jan-17 Not in progress
Floor) 2nd stage
Structural Concrete foundation or
12-Nov-16 9-Feb-17 Not in progress
floor 2nd stage
Finishing works 10-Feb-17 10-May-17 Not in progress
22-6-2015 JUST FOR
B Tailrace 1-Jan-16 8-Jun-16 Not in progress
INFORMATION
Excavation 1-Jan-16 29-Feb-16 Not in progress
Lean concrete 1-Mar-16 30-Mar-16 Not in progress
Steel Reinforcement 31-Mar-16 29-May-16 Not in progress
Structural Concrete 10-Apr-16 8-Jun-16 Not in progress
22-6-2015 JUST FOR
4 Zone 4 (Tunnel & Penstock) 1-Mar-15 13-May-17 15-Jun-15 15-Aug-17
INFORMATION
A Inlet Portal 1-Mar-15 13-Jul-15 15-Jun-15 15-Oct-15
Excavation & Preparatory works 1-Mar-15 3-Jun-15 15-Jun-15 3-Aug-15 2% 20% 2% 22%
Rock Bolts 25-May-15 3-Jul-15 - - Not in progress
22-6-2015 JUST FOR
Shotcreteing 4-Jun-15 3-Jul-15 - - Not in progress
INFORMATION
B Outlet Portal 6-Mar-15 3-Jul-15 15-Jun-15 15-Oct-15
Excavation & Preparatory works 6-Mar-15 24-May-15 15-Jun-15 15-Aug-15 10% 90% 10% 100%
Rock Bolts 25-May-15 23-Jun-15 - - Not in progress
Shotcreteing 4-Jun-15 3-Jul-15 - - Not in progress
22-6-2015 JUST FOR
C Tunnel inlet side 5-Apr-15 13-May-17 Not in progress
INFORMATION
Tunnel Excavation 4-Jun-15 3-Jul-15 - - Not in progress
Rock Bolts & wire Mesh 5-Apr-15 13-Jan-17 - - Not in progress
Shotcreteing 5-Apr-15 13-Jan-17 - - Not in progress
Concrete Linig 14-Jan-17 13-May-17 - - Not in progress
22-6-2015 JUST FOR
D Tunnel outlet side 25-May-15 13-May-17 15-Jun-15 15-Jun-17
INFORMATION
Tunnel Excavation 25-May-15 13-Jan-17 15-Jun-15 15-Jun-17 Not in progress
Rock Bolts 25-May-15 13-Jan-17 - - Not in progress
Shotcreteing 25-May-15 13-Jan-17 - - Not in progress
22-6-2015 JUST FOR
Concrete Linig 14-Jan-17 13-May-17 - - Not in progress
INFORMATION
E surge Tank 11-Jun-15 22-Dec-15 - - Not in progress
Excavation 11-Jun-15 7-Nov-15 - - Not in progress
Rock Bolts 21-Jun-15 17-Nov-15 - - Not in progress
Shotcreteing 21-Jun-15 17-Nov-15 - - Not in progress
Concrete Linig 13-Nov-15 22-Dec-15 - - Not in progress
22-6-2015 JUST FOR
F Penstock (CIVIL) 1-Oct-15 3-Apr-17 Not in progress
INFORMATION
Excavation 1-Oct-15 28-Jan-17 Not in progress
Steel Reinforcement 31-Oct-16 28-Jan-17 Not in progress
Concrete Anchor Blocks 5-Nov-16 2-Feb-17 Not in progress
Back Filling 23-Feb-17 3-Apr-17 Not in progress
G Switch yard 7-Feb-16 4-Aug-16 Not in progress
22-6-2015 JUST FOR
Excavation 7-Feb-16 5-Jun-16 Not in progress
INFORMATION
Land Leveling 7-Feb-16 5-Jun-16 Not in progress
Foundation Concrete 7-Feb-16 5-Jun-16 Not in progress
Foundation Steel 7-Feb-16 5-Jun-16 Not in progress
Not in progress
10.2 MW Jabori Hydropower Project Monthly Progress Report (Aug 2015)
Status of Interim Payment Certificates

Contract Price (Rs.)= 2,786,254,005.00

Contractor's Interim Payment Status


Amount Remarks
IPC No. Dated
Pak Rs.
01 26-Dec-14 176,700,000 I.P.C -01 (Advance Payment)
02 Jan-15 36,737,716 Approved - Paid

03 Feb-15 40,027,679 Approved - Paid

04 Mar-15 41,681,894 Approved - Paid

05 May-15 47,941,713 Approved - Paid

06 Aug-15 30,708,517 Approved - Paid

07

08

09

Total Amount= 373,797,519

Note: 7 % Withholding Tax is deductible from Certified amount


STATUS OF CONTRACTOR'S STAFF AND LABOUR MOBILIZED TO SITE

Status of Mobilization (Nos.) Deployment Source

Sr. Ending Addition/


Description Total To Sub- Remarks
No. July Deletion in Contractor
Date Contractor
2015 Aug 2015

A SITE BASED STAFF

Project Manager 1 1

Site Manager 1 1

Site Engineers 7 7

Quantity Surveyor 4 4

Surveyor 10 10

Site Civil Works Supervisor 9 9

Surveyor Helper 8 8

Store Manager 1 1

Equipment & Plant Manager 1 1

Accounts Officer 1 1

Accountant 3 3

Procurement Officer 1 1

Material Engineer 2 2

Lab. technicians 6 6

Camp Administrator 1 1

56 56 56 0

B HEAD OFFICE BASED STAFF

Manager Planning 1 1

Assistant Manager Planning 1 1

Planning Engineer 2 2

Accounts Officer 1 1

Mechanical Engineer 1 1 Main Workshop Multan


Procurement and Logistic
1 1
Officer
Accountant 1 1

Quantity Surveyor 1 1

Draftsman 1 1

Mechanical Works Supervisor 1 1 Main Workshop Multan

Mechanics 4 4 Main Workshop Multan

15 15 15 0

C Labour

Operator/Mechanics 8 8

Skilled Labor 39 39

Un-skilled Labor 100 100

Sub-Total C 147 147 147 0

Total (A+B+C) 218 218 218 0

Proportion of local population (%) 31 31

Note: Source of the above information is the EPC Contractor's Monthly Progress Report for Aug, 2015
STATUS OF CONTRACTOR'S PLANT AND EQUIPMENT AT SITE

Deployment at Site ( Nos.) Mobilization Source


Sr. Ending Addition/
Description Total To Remarks
No. July Deletion in Owned Rental
Date
2015 Aug 2015

1 Excavator 4 1 5 - R
2 Mixture Machine 3 1 4 O -
3 Dumper 0 2 2 O -
4 Compactor 0 1 1 O -
5 Shotcrete Pump 1 0 1 O -
6 Concrete Vibrator 3 1 4 O -
7 Dewatering Pump 5 0 5 O -
8 Dumper Trollies 3 0 3 O -
9 Tunnel Liner 1 0 1 O -
10 Stone Driller Machine 8 6 14 O -
11 Hand drill Machine 0 1 1 O -
12 Diesel Tanker 1 0 1 O -
13 Air Compressor 2 2 4 O -
14 Pick Hammer 4 0 4 O - TOKU TCA-7

15 Rock Drilling Machine 4 0 4 O -


16 Peter Engine with Denimo 0 1 1 O -
17 Compactor small 0 1 1 -
18 Welding Plant 400 WT 1 1 O -
19 Batching Plant 0 1 1 O

20 Gass welding plant 0 1 1 O -


21 Motor Cycle 3 3 O -
22 Tractor Trollies 8 8 - R
23 Water Tanks 2 2 O -
24 Generator 4 4 O - Petrol light generator

25 Generator 1 1 2 O - 15 kVA

26 Concrete Batching Plant 0 1 1 O - To be installed when required

27 Welding Plant 1 1 O - 350 Watts

28 Double Door ( Dalla ) 1 1 O -


29 Double Door ( Surf ) 2 2 O -
30 Other Vehicles 7 7 O -

Total 69 21 90 90
Note: Source of the above information is the EPC Contractor's Monthly Progress Report for Aug , 2015
Sr. # Attendees Location Date Agenda
MEETINGS
1.       Assistant Director
(PEDO) Stoppage of work at weir and Power
1 Site Office 16/08/2015
house site
2.       M/s Representatives

Stoppage of work at weir and Power


2 1.Project Manager Consultants Site Office 17/08/2015
house site

SITE VISITS

Progress review and discussion on


1.       GM -JV HPP-
1 MASEHRA
HPP Site 19/08/2015 various issues related to execution of
construction works

1.       PEDO Representatives


Stoppage of work at weir and Power
2 HPP Site 18/08/2015
house site
2.       M/s Representatives