Operations Management Review

The document is a review of a test submission for a project management class assignment. It contains 3 multiple choice questions testing the student's understanding of calculating earliest start times and latest finish times for activities in a network diagram and project schedule. The student answered all 3 questions correctly, identifying the earliest start time for activities G and E, and determining the latest finish time for activity G based on the given critical path duration of 15 weeks.

Uploaded by

Neerav Sareen
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
106 views2 pages

Operations Management Review

The document is a review of a test submission for a project management class assignment. It contains 3 multiple choice questions testing the student's understanding of calculating earliest start times and latest finish times for activities in a network diagram and project schedule. The student answered all 3 questions correctly, identifying the earliest start time for activities G and E, and determining the latest finish time for activity G based on the given critical path duration of 15 weeks.

Uploaded by

Neerav Sareen
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Neerav Sareen

My Blackboard Courses Content Collection

H
Assignments
Class Assignments
Review Test Submission: Project Mgt - Class Assignment #2

Review Test Submission: Project Mgt - Class


Assignment #2

User Neerav Sareen


Course MGTS-352-CC51(1) - 2021 Fall - Operations Management
Test Project Mgt - Class Assignment #2
Started 10/8/21 9:27 PM
Submitted 10/8/21 9:47 PM
Due Date 10/8/21 11:00 PM
Status Completed
Attempt Score 3 out of 3 points
 
Time Elapsed 19 minutes out of 1 hour
Results All Answers, Submitted Answers, Correct Answers, Feedback, Incorrectly
Displayed Answered Questions

Question 1 1 out of 1 points

If C-F-H is the critical path at 15 weeks. Using the network diagram and project schedule that
you created.

Identify what the Earliest Start Time (ES) would be for Activity "G"

Selected Answer:
10
Correct Answer:
10
Answer range +/- 0 (10 - 10)
Response The earliest start time for Activity "G" would be equal to the earliest finish
Feedback: time of Activity "A".

Question 2 1 out of 1 points

Using the network diagram and project schedule that you created. 

Identify what the Earliest Start Time (ES) would be for Activity "E"

Selected Answer:
8
Correct Answer:
8
Answer range +/- 0 (8 - 8)
Response The earliest start time for Activity "E" would be equal to the earliest finish time
Feedback: of Activity "D"

In this case we have two activities - Activity "D" (EF= 8) and Activity "C" (EF =
6) that immediately precede Activity "E". To find the ES for Activity "E" - we
would take the longer EF of the two activities, which would be Activity "D".

Question 3 1 out of 1 points

Using the network diagram and project schedule that you created. 

Determine what is the latest finish time for Activity - "G"?


Selected Answer: d.
15

Answers: a.
10

b.
11

c.
14

d.
15

Response The latest finish time for Activity "G" would be 15 days. 
Feedback:
The current project duration is 15 days. Given that Activity G does not have
any succeeding activities, the latest it can be completed is 15 days without
delaying the project's completion time.

Friday, October 8, 2021 [Link] PM MDT


OK