Boiler Gauge Glass Setup Guide

The document describes the procedure for lining up and flushing a boiler gauge glass. Key steps include ensuring valves are in proper working order, slowly opening valves to check for leaks and allow stabilization, observing the water level, and closing/opening valves while flushing to check for blockages. Maintaining a proper water level indicates the gauge glass line up is successful.

Uploaded by

Lakshmi Narayan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (4 votes)
286 views6 pages

Boiler Gauge Glass Setup Guide

The document describes the procedure for lining up and flushing a boiler gauge glass. Key steps include ensuring valves are in proper working order, slowly opening valves to check for leaks and allow stabilization, observing the water level, and closing/opening valves while flushing to check for blockages. Maintaining a proper water level indicates the gauge glass line up is successful.

Uploaded by

Lakshmi Narayan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

3/23/23, 11:15 AM Power plant and calculations: Procedure for Boiler Gauge glass line up & Flushing

More Create Blog Sign In

CLOSE ADS CLOSE ADS

Power plant and calculations


Power plant and calculation site basically includes the detailed study of power plant operation and maintenance, its related all calculations and thumb rules. It also
troubleshooting guides for operation and maintenance of power plant processes and equipments.

Danfoss
High
Pressure
Pumps

We offer fast
service and
competitive prices
for Danfoss
pumps and spare
parts.

Procedure for Boiler Gauge glass line up & Flushing


Boiler Gauge glass: is a transparent glass of shape tubular, flat or square blocks fitted to the boiler
steam drum to facilitate a visual indication of the water level of a steam drum. These types of glasses
are manufactured by borosilicate glass which is robust, temperature & chemical resistant.

TOP-6 BEST POWER PLANT O&M BOOKS

Boiler calculations for Boiler operation engineer (BOE) exam

Line up of Gauge glass:

[Link] 1/6
3/23/23, 11:15 AM Power plant and calculations: Procedure for Boiler Gauge glass line up & Flushing
Ensure all tools & required PPEs are taken to operate the valves (Hand gloves, Safety
goggles, “F” rods etc)

CLOSE ADS Ensure steam & water side valve of gauge glass are healthy & operating properly CLOSE ADS

Ensure there are no any leakages

Ensure steam side & water side valves are closed

Ensure gauge glass drain valve is open & drain is connected/extended to safe location

Now crack open the steam valve & check for any leakages in gauge glass. Wait for some
times until system heats uniformly.

Then crack open the water side valve, wait for some time for stabilization

Then close the drain valve

Open the steam valve & water valve fully

Observe water collected in glass & showing the level

Cross check the level glass with other side level glass or control room transmitter reading
or with Hydra step

Factors considered for Boiler Engineering


Flushing of gauge glass

Ensure all tools & required PPEs are taken to operate the valves (Hand gloves, Safety goggles, “F”
rods etc)

Step-I

Close the water side valve & open the drain valve for flushing, wait for some time

Then close the drain valve & open the water side valve

Note: After opening the water side valve, water level should retain its normal operating level, if not
then there might be blockages in valve or line

Step-II

Close the steam side valve & open the drain valve for flushing, wait for some time

Then close the drain valve & open the steam side valve

Note: After opening the steam side valve, water level should retain its normal operating level, if not
then there might be blockages in valve or line

Questions & Answers on AFBC Boiler

Power plant maintenance calculations

Questions & Answers of Boiler safety valves

Challenging situations & troubleshooting during boiler light up &


start up

Viva QnA on Boiler Safety Valves

Boiler safety valves overhauling steps

at December 24, 2020

Labels: Boiler

1 comment:

Alvin Evans 21 April 2021 at 05:06


You have done a good job by publishing this article about Gauge Glass. I appreciate your
efforts which you have put into this article, It is a beneficial article for us. Thanks for sharing
such informative thoughts.
Klinger Gauge Glass

Reply

Enter comment

Hi all,
This article is written based on practical experience..If liked, share with others, or any suggestions
leave in comment box.

[Link] 2/6
3/23/23, 11:15 AM Power plant and calculations: Procedure for Boiler Gauge glass line up & Flushing

CLOSE ADS CLOSE ADS

Newer Post Home Older Post

Subscribe to: Post Comments (Atom)

11-differences between star connection and delta connections

  11-differences between start connection and delta connections Sl No. Star connection Delta
connection 1 Two types of star connections are ...

Frequently visited posts

Calculation of heat rate & efficiency of the power plant


Heat rate  is the amount of energy used by an electrical generator/power plant to generate one kilo
Watt-hour (kWh) of electricity Hea...

Boiler feed pumps (BFP) questions & answers for interview


Boiler feed pumps (BFP) questions & answers for interview: 1-What is the function of
Boiler feed pumps (BFP) in power plant? ...

STEAM CONDENSER,VACUUM AND CALCULATIONS


A steam condenser is device or an appliance in which steam condenses and heat
released by steam is absorbed by water. Heat is basi...

Objective & Viva Questions & Answers for preparation of Boiler operation Engineer (BOE) exam &
Boiler Interview
1-Why Boiler is considered as explosive equipment / system? Boiler involves the generation of steam
at higher pressure & temperature u...

Basic things you must know about nut bolts & spanners
A Bolt is a mechanical device which has head on one end of a body and a thread on
the other end designed for fastening of two parts. Bo...

50-Interview questions & answers on centrifugal pumps


  1. What are the centrifugal pumps? Centrifugal pumps are the mechanical devices
which pump or transport various fluids by converting their...

Boiler calculations for Boiler operation Engineer Exam (BOE)


  1-Oxygen percentage in Boiler outlet flue gas is 4.9%, then what will be the percentage of excess
air? We have excess air EA = O2 X 100 / ...

[Link] 3/6
3/23/23, 11:15 AM Power plant and calculations: Procedure for Boiler Gauge glass line up & Flushing

CLOSE ADS CLOSE ADS

About Me

Powerplant and calculations


View my complete profile

►  2023 (1)

►  2022 (20)
►  2021 (45)
▼  2020 (58)
December (2)
November (2)
October (4)
September (3)
August (5)
July (11)
June (8)
May (23)

[Link] 4/6
3/23/23, 11:15 AM Power plant and calculations: Procedure for Boiler Gauge glass line up & Flushing

Labels

AVR
CLOSE ADS CLOSE ADS

Boiler

Efficiency & performance

Electrical & Instrumentation

energy conservation & thumb rules in


power plant

ESP

fuel handling

Mechanical Engineering

pmg

power generation

power plant

Power plant best operation &


maintenance books

power plant maintenance

power plants

pumps/compressors/fans

safety and energy

steam turbine

Water treatment plant

Report Abuse

Home

Boiler

Turbine

Maintenance

Fuel handling

Efficiency&Performance

WTP

E&I

Pumps/compressors/fans

Home Search This


Blog
Boiler
Search
Turbine

Maintenance

Fuel handling

Efficiency&Perf
ormance

WTP

E&I

Pumps/compre
ssors/fans

Disclaimer

Privacy policy

About us

Contact us

[Link] 5/6
3/23/23, 11:15 AM Power plant and calculations: Procedure for Boiler Gauge glass line up & Flushing

CLOSE ADS CLOSE ADS


Awesome Inc. theme. Theme images by molotovcoketail. Powered by Blogger.

[Link] 6/6

You might also like