0% found this document useful (0 votes)
752 views41 pages

BoQ and Take-Off Sheet For Semster Project

Uploaded by

Abudi Kasahun
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
752 views41 pages

BoQ and Take-Off Sheet For Semster Project

Uploaded by

Abudi Kasahun
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

SUMMARY OF BOQ

A) SUB STRUCTURE

1- EXCAVATION AND EARTH WORK----------------------BIRR

2- CONCRETE WORK---------------------------------------- BIRR

3- MASONRY WORK----------------------------------------- BIRR

TOTAL SUM OF A -------------- BIRR

B) SUPER STRUCTURE

1- CONCRETE WORK----------------------------------------- BIRR

2- BLOCK WORK---------------------------------------------- BIRR

3- ROOFING WORK------------------------------------------- BIRR

4- CARPENTRY AND JOINERY-------------------------------BIRR

5- METAL WORK--------------------------------------------- BIRR

6- FINISHING WORK---------------------------------------- BIRR

7- GLAZING--------------------------------------------------- BIRR

8- PAINTING-------------------------------------------------- BIRR

9- SANITARY WORK----------------------------------------- BIRR

10- ELECTRICAL WORK--------------------------------------- BIRR

TOTAL SUM OF B ------------- BIRR 0.00

TOTAL SUM (A+B) ------------- BIRR 0.00

10% CONTINGENCY------------- BIRR 0.00

GRAND TOTAL----------------- BIRR 0.00


Semester Project on- BOQ and Specifications Prepared by- Group 1 Members

ITEM DESCRIPTION UNIT QTY RATE AMOUNT

A. SUB-STRUCTURE
1.0. Excavation & Earth work
1.1 Site clearing to an average depth of 200mm
from natural ground level. m2 650.02 44.50 28,925.81
1.2 Bulk excavation to reduce level to an average
depth of 500mm from reduced ground level. m3 325.01 140.00 45,501.27
1.3 Excavation for isolated footing to a depth of
1500-3000mm from reduced level. Price shall
be include 250mm working space in all sides. m3 285.86 180.00 51,454.80
1.4 Back fill around foundation footings with non
expansive granular selected material and well
compacted to an average layers of 200mm m3 239.33 80.00 19,146.43
thick.
1.5 Fill selected granular material under hard core
with granular selected borrowed material and
well compacted to an average layer of 200mm. m3 137.66 120.00 16,518.80
1.6 Cart away surplus excavated material to a
distance not exceeding 5km from the site. m3 363.89 60.00 21,833.14
1.7 250 mm thick basaltic stone hardcore well
rolled, consolidated and blinded with crushed m2 344.14 260.00 89,476.82
stone . Total Carried to Summary
([Link]).......................... ###
2.0. Concrete work
2.1 50mm thick lean concrete in concrete class C-
5, 150kgs of cement /m3 of concrete

a) Under isolated footings m2 86.28 120.00 10,353.60


b) Under grade beam m2 61.51 120.00 7,381.44
c) Under ground floor m2 344.14 120.00 41,296.99
2.2 Reinforced Concrete class C-25, 360kgs of
cement /m3 of concrete filled into form work
and vibrated around steel reinforcement (Form
work and Rebar measured separately)
a) In isolated footing pads m3 42.91 2800.00 120,136.80
b) In foundation columns m3 3.53 2800.00 9,871.05
c) In grade beam m3 2800.00 -
d) In 100mm thick ground floor slab m2 260.00 -
2.3 Provide, cut and fix in position 2.5cm thick
sawn zigba wood or steel formwork to:
a) Isolated foundation footing m2 210.00 -
b) Foundation columns m2 210.00 -
c) Grade beam m2 210.00 -

Page 2 of 41
Semester Project on- BOQ and Specifications Prepared by- Group 1 Members

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


2.4 Mild steel reinforcement according to
structural drawings. Price includes cutting,
bending, placing in position and tying wire..
a) ф 6mm plain bar kg 92.02 70.00 6,441.14
b) ф 8mm deformed bar kg 1705.71 70.00 119,400.03
c) ф10mm deformed bar kg 30.22 70.00 2,115.61
d) ф12mm deformed bar kg 1317.54 70.00 92,227.61
e) ф 14mm deformed bar kg 1765.87 70.00 123,611.05
f) ф 16mm deformed bar kg 397.28 70.00 27,809.35
g) ф 20mm deformed bar kg 602.49 70.00 42,174.10
Total Carried to Summary
([Link]).......................... ###
3.0. Masonry Work
3.1 Supply and construct 400mm thick Stone
masonry foundation wall bedded in cement
m3 70.39 1200.00 84,462.00
sand mortar (1:3) below
Total NGL.
Carried to Summary
84,462.00
[Link]…………..…….
B. SUPER STRUCTURE
1.0. Concrete Work
1.1 Reinforced concrete class C-25, 360kgs of
cement /m3 of concrete filled into form work
and vibrated around steel reinforcement (form
work and Reinforcement measured separately)
First, Second, Third and Fourth Floors
a) In elevation columns m3 43.31 ### 121,269.12
b) In floor beams m3 45.35 ### 126,972.16
c) In 150 mm thick RC floor slab m2 810.26 280.00 226,871.57
d) In 150 mm thick Terrace and Stair Roof Slab m2 84.86 280.00 23,761.95
e) In top tie beams and stair roof beams m3 13.01 ### 36,420.16
f) In stair case & landing m3 13.65 ### 38,223.76
1.2 Provide, cut and fix in position 2.5cm thick
sawn zigba wood or steel formwork to:
First, Second, Third and Fourth Floors
a) Elevation columns m2 464.04 210.00 97,448.40
b) Floor beams m2 566.84 210.00 119,036.40
c) 150mm thick floor slabs m2 810.26 160.00 129,640.90
d) Terrace and Stair Roof Slab m2 84.86 160.00 13,578.26
e) Top tie beams and stair roof beams m2 162.59 210.00 34,143.90
f) Stair case & landing m2 89.73 210.00 18,842.54

Page 3 of 41
Semester Project on- BOQ and Specifications Prepared by- Group 1 Members

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


1.3 Mild steel reinforcement according to
structural drawings. Price includes cutting,
bending, placing in position and tying wire..
a) ф 6mm plain bar kg 338.86 70.00 23,720.26
b) ф8mm deformed bar kg 1705.71 70.00 119,400.03
b) ф10mm deformed bar kg 917.87 70.00 64,250.74
c) ф12mm deformed bar kg 0.00 70.00 -
d) ф 14mm deformed bar kg 2649.04 70.00 185,432.79
e) ф 16mm deformed bar kg 2203.02 70.00 154,211.46
f) ф 20mm deformed bar kg 3040.33 70.00 212,823.16
Total Carried to Summary
###
[Link]…………..…….
2.0. Block Work
2.1 20cm thick HCB wall, embedded in cement-
sand mortar of 1:3 mix ratio. Both sides shall m2 755.34 320.00 241,709.92
be left for plastering.
2.2 Ditto item 2.1, but 15cm thick HCB walls. m2 563.01 310.00 174,533.53
2.3 Ditto item 2.1, but 10cm thick HCB walls. m2 70.84 310.00 21,961.89
Total Carried to Summary
###
[Link]…………..…….
3.0. Roofing & Water Proofing
3.1 Roof cover in G-28 C.I.S sheet Roof covers
including Ridge covers fixed to purlin at
c/c90cm. (roof cover measured in horizontal m2 153.26 360.00 55,175.04
projection)
3.2 0.5mm thick flat metal sheet copping fixed as
shown n the drawing. Development length ml 12.40 200.00 2,480.00
3.3 33mm. and fix G-28 galvanized flat metal sheet
Supply
gutter spliced and welded at joints with two
coats of rust resisting paint. ml 24.80 200.00 4,960.00
3.4 Average 12cm thick light weight concrete
spread and leveled over R.C. roof (cement
pumice and sand mix in the proportion of
([Link]) slopes to wards concrete gutter and
down pipe to be 2%. m2 64.31 350.00 22,507.28
3.5 Supply and lay xypex type water proofing
membrane or equivalent as approved by the
engineer .Price shall include light weight
concrete and cement screed bedding and all
the necessary material and work. m2 64.31 350.00 22,507.28
3.6 Supply and lay Average 3 cm thick smoothly
finished cement-sand
mix ratio of 1:3 and 1 : 1 screed by attaining
the givengutter
concrete slope to
to the
easily accept water-proofing m2 64.31 350.00 22,507.28
tile. Total Carried to Summary
###
[Link]…………..…….
4.0. Carpentery & Joinery

Page 4 of 41
Semester Project on- BOQ and Specifications Prepared by- Group 1 Members

ITEM DESCRIPTION UNIT QTY RATE AMOUNT

Flush Doors
Supply and fix partial Glazing 40mm thick flush
4.1 wood door that shall be produced from wanza,
kerero or hard wood. Work & cost includes all
pre-wood oil paint work & adequate wood-oil
paint, 3 coats of approved clear finish, that
match to the color of the wood, paint. Assa or
approved quality door locks & all other
necessaries work as per the detail
[Link] (Glass measured else were )

a) D1 size: 100 X 320cm No. 1.00 3000.00 3,000.00

b) D2 size: 90 X 290cm (bed rooms) No. 18.00 2800.00 50,400.00

c) D3 size: 90 X 220cm No. 5.00 2800.00 14,000.00

d) D4 size: 80X220cm No. 12.00 2800.00 33,600.00

e) D5 size: 70X220mm No. 18.00 2500.00 45,000.00


4.2 Supply,asemble & mount dia.8-10cm
eucalyptus wooden truss as per the detail
[Link] shall include anti -termite ml 480.70 40.00 19,228.00
treatment and all other necessary acessories
4.3 Supply and fix 50x70 mm zigba wood purlin as
per the detail drawing . ml 173.60 70.00 12,152.00
4.4 Supply & fix paneled 8mm thick gypsum board
ceiling material. Work & cost includes:-
suspended supportive materials & molded &
decorative gypsum corner list at wall & ceiling
connection . m2 153.26 350.00 53,642.40
4.5 Supply and fix kitchen cabinet with shelves
and drawers consisting of a solid 2.5cm thick
timber structure and covered with 4mm thick
veneered white [Link] according to
drawings and engineer's [Link] shall
include best quality hinges, locks
Cabinet size:-3600x900x600 mm No. 1.00 5,000.00 5,000.00
Total Carried to Summary
###
[Link]…………..…….
5.0. Metal Works
5.1 Every Door and window frame is
manufactured
Aluminum fromframe, EURO profile or
tubular
equivalent, 2mm
average weight that thick,shall
withbeanapproved by the
engineer. All works
done according to shall be
the window, door schedule.
Complete
the workIron
necessary includes
mongerall and approved type
of cylindrical
Joints shall belock
waterhandles.
tight. Fixed and opening
panels exposed to weather
shall be provided with weather strips, insuring
that
fixedthe strips areenough to be water tight. All
continuous
aluminum
& windows
doors type shall be approved by the
engineer.
5.1.1 Window-door
WD1 of size (size: 350x340)cm No. 1.00 5000.00 5,000.00

Page 5 of 41
Semester Project on- BOQ and Specifications Prepared by- Group 1 Members

ITEM DESCRIPTION UNIT QTY RATE AMOUNT

WD2 of size (size: 246x340)cm No. 6.00 4000.00 24,000.00


WD3 of size (size: 539x340)cm No. 2.00 8000.00 16,000.00
WD4 of size (size: 542x340)cm No. 4.00 8000.00 32,000.00
WD5 of size (size: 539x290)cm No. 5.00 7000.00 35,000.00
WD6 of size (size: 542x290)cm No. 8.00 7000.00 56,000.00
WD7 of size (size: 350x260)cm No. 3.00 4000.00 12,000.00
WD8 of size (size: 215x260)cm No. 7.00 3500.00 24,500.00
5.1.2 Windows
W1 (size:570X256)cm No. 1.00 5000.00 5,000.00
W2 (size:570X187)cm No. 1.00 7000.00 7,000.00
W4 (size:480x60)cm No. 5.00 6000.00 30,000.00
W5 (size:475x186)cm No. 2.00 6000.00 12,000.00
W6 (size: 476x60)cm No. 2.00 6000.00 12,000.00
W7 (size: 475x86)cm No. 1.00 3000.00 3,000.00
W8 (size:482X186)cm No. 8.00 4000.00 32,000.00
W9 (size: 295X186)cm No. 1.00 5000.00 5,000.00
W10 (size:285X1760)cm No. 2.00 5000.00 10,000.00
W11 (size:280x276)cm No. 1.00 5000.00 5,000.00
W12 (size:275x60)cm No. 1.00 5000.00 5,000.00
W13 ( size:220x186)cm No. 8.00 5000.00 40,000.00
W14 (size:167X176)cm No. 5.00 5000.00 25,000.00
W15 (size:140x2660)cm No. 1.00 5000.00 5,000.00
5.1.3 Doors
D1 (size: 195x340)cm No. 1.00 5000.00 5,000.00
D2 (size:100x340)cm No. 1.00 3500 3,500.00
5.1.4 Curtain Walls
Supply & fix curtain wall, framed with high
quality, anodized
profile frames, aluminum
with clear 8mm thick security
glass, open able
and sealant, windows
all as per the engineers approval
and detail drawings.
Unit price shall include glass, anchorage,
sealant and all other necessary works needed m2 63.91 350.00 22,368.68
5.2 to complete
Supply the90cm
and fix [Link] rail to the staircase
made from Ø30mm extruded aluminum pipe
baluster ,Ø40mm aluminum handrail & 2rows
of Ø20mm aluminum guard rails. Price shall
include metal plates and all other necessary
works and materials needed for anchorage.
Price shall also include synthetic enamel paint
to metal parts & all other necessary
accessories needed to the work with the final ml 79.45 200.00 15,890.00
approval complete of engineer.
Page 6 of 41
Semester Project on- BOQ and Specifications Prepared by- Group 1 Members

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


5.3 Ditto item 5.2 but for Corridors and verandah ml 146.70 200.00 29,340.00
rail
5.4 Ditto item 5.2 but for Terrace rail 70 cm height ml 106.80 200.00 21,360.00
Total Carried to Summary
###
[Link]…………..…….
6. Plastering, Floor, Wall and Other
Finishing Works
Plastering
6.1 Supply and Apply two coats of plaster in
cement-sand mortar to the prepared wall
surface, columns and beams. Mix ratio shall be
1:3. Price shall include preparing the
background for plastering by hacking, nicking
out joints chiseling smooth surfaces to roughen
6.1 To the internal HCB wall surfaces. m2 ### 160.00 253,382.85
6.2 Ditto item 6.1 but to the external HCB wall m2 428.50 160.00 68,559.28
6.3 surface
Ditto item 6.1 but to the Concrete surface m 2
### 160.00 160,222.67
6.4 Ditto item 6.1 but to the stair soffit. m 2
52.52 160.00 8,403.20
6.5 Supply & Apply 1 coat of fine plastering to
internall wall surface the location shall provide
& taken from the engineers, mix ratio shall be m2 ### 130.00 139,581.34
1:1 of cement & sand.
6.6 Ditto item 6.5 but fine coat on concrete m 2
### 130.00 130,180.92
6.7 surface.
Ditto item 6.5 but fine coat on stair soffit. m 2
52.52 130.00 6,827.60
6.8 Supply & Apply 1 coat of fine &/or render
plastering
to external wall the pattern mix ratio shall be
1:1 of & sand.
cement m2 428.50 130.00 55,704.42
6.9 Supply & Apply approved gypsum plaster with
a min. thickness of 3mm over the 2 nd coat
plastered surface of internal wall .Work & cost
includes:-
preparing the surfaces, preparing every
working materials etc. Application shall be
done after well cured the plastered surface and m2 ### 110.00 118,107.29
as per the instruction of engineers.
6.10 Ditto item 6.9 but on plastered stair soffit . m2 52.52 110.00 5,777.20
6.11 Ditto item 6.9 but on plastered concrete m2 ### 110.00 110,153.09
surface.

Floor & Wall Finishes

6.12 Supply and lay polished, chamfered &


calibrated sylivia
or equivalent typeepoxy treated
marble tile, of size
60x60x2cms. The
diagonally with tile shall
4 mm be installed
spacers. The price shall
include Mapei, Cercol,
Keracol or equivalent type fillers and adhesive.
a) For thread
size ( 30 x 3)cm. ml 123.50 400.00 49,400.00

Page 7 of 41
Semester Project on- BOQ and Specifications Prepared by- Group 1 Members

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


b) For riser.
size ( 14 x 2)cm. ml 124.80 400.00 49,920.00
c) For landing floor 2 cm thick. m 2
17.23 480.00 8,268.00
d) For skirting for the stair
size (10×2)cm ml 42.90 400.00 17,160.00
6.13 600x600x8mm non slippery ceramic floor tiles
bedded on cement mortar(1:3) price shall
include 3cm thick cement mortar bed, m2 504.25 500.00 252,125.00
grouting.
6.14 300x300x20mm thick terrazzo tile flooring ;
type quality and pattern of terrazzo to be
approved by the engineer. Price shall include
cement mortar (1:3) bed. m2 34.20 500.00 17,100.00

6.15 Supply and lay 2 cm thick wooden praque floor


finish. Price shall include 3 cm thick cement
mortar (1:3) bed, grinding and polishing of the
floor. Color has to be approved by the m2 529.22 700.00 370,450.50
engineer.
6.16 Supply and fix 150 x 150 x 6 mm white glazed
ceramic wall tiles with cement mortar backing
with 2 mm joints to be grouted with white m2 509.94 500.00 254,970.10
cement .
Total Carried to Summary
###
[Link]…………..…….

7.0. Glazing

7.1 Supply and fix 4 mm thick clear sheet glass to


metal beads and puttied with approved quality
of putty to Doors, Windows and Window doors
as shown on the drawing. m2 563.00 500.00 281,500.00

Total Carried to Summary ###

8.0. Painting

Provide & paints by means of roller or


equivalent approved material on the over all
prepared & inspected wall & ceiling area as
8.1 needed.
To the internal wall surfaces m2 ### 50.00 53,685.13

8.2 Ditto item 8.1 but on External wall. m2 428.50 50.00 21,424.78

Page 8 of 41
Semester Project on- BOQ and Specifications Prepared by- Group 1 Members

ITEM DESCRIPTION UNIT QTY RATE AMOUNT

8.3 Ditto item 8.1 but on Concrete Surface. m2 ### 60.00 60,083.50

8.4 Ditto item 8.1 but on suffix of the stair case. m2 52.52 60.00 3,151.20

Total Carried to Summary


###
[Link]…………..…….

All fixtures 9. Sanitary


which Installation
specified below is subjected
to the
consultant approval, based on
samples ,catalogues
and brochures presented by the contractor.
All the sanitary appliances shall be best quality
heavy duty.

9.1 SANITARY EQUIPMENT (FIXTURES)


Hand Wash Basin
9.1.1 Supply and fix wall mounted hand wash basins made of
viterous china with chrome plated cold and hot water
mixer & pedstal stand in bed room and ground-fourth
floor toilets. Price shall include all necessary connecting
pieces.
Approximate size: 500 x 400 mm No 29 3500.00 101,500.00
Water closet
Supply and fix water closet, of wash down
9.1.2 action,
floor mounted , vertical outlet (floor drainage),
close coupled ,made
(BS3402).The fixtureof white
shall vitreous
conform to China
BS5503-
2
or
Theequivalent institution.
waste fittings, connecting pieces, fixing
and
supporting element and other accessories
which
completes the set shall comply with the
relevant
clauses of BS standards or equivalent
institution. No 28 4000.00 112,000.00

Shower Facilities
9.1.3 Supply and fix pressed steel enameled cast
iron shower tray, including shower head,
mixingfaucet, smell trap,(s or p) etc.. Complete
with all the necessary accessories.
Size:- 700 mm X 700mm No 18 2500.00 45,000.00

Page 9 of 41
Semester Project on- BOQ and Specifications Prepared by- Group 1 Members

ITEM DESCRIPTION UNIT QTY RATE AMOUNT

Toilet
Supply paper
and fixholder
toilet paper holder , made
9.1.4 from
white vitreous china(BS3402)
,concealed/surface
mounted of approved quality complete with all
the
necessary accessories. No 28 450.00 12,600.00

Crystal glass
Supply and mirror quality frameless
fix approved
9.1.5 crystal
glass mirror ,back-silvered ,minimum 6mm
thick
Size 500mm x 400mm .Complete with theft
resistant
concealed wall fastening fittings and other
accessories. No 29 850.00 24,650.00

Floor Drain
9.1.6 Supply and fix floor drains made of polished steel
of approved quality, complete with P-smell trap
and all other necessary fittings and accessories.
Size:- Dia. 50 mm No 38 400.00 15,200.00

Soap
SupplyHolder
and fix soap holder , approved quality
9.1.7 made
of white vitreous china (BS3402),for shower
rooms.
Complete with all the necessary accessories. No 18 350.00 6,300.00

Towel
Supply Hanger
and fix towel hanger of cast iron china
9.1.8 enameled with chrome plated. 760mm X
25mm No 18 500.00 9,000.00

Janitor
ConstructSink
Janitor Sink out of 250mm thick,
9.1.9 smooth
finished with ceramic wall tiles, double brick
walls
and complete with water tap, drain hole, waste
drain
pipe, smell trap,etc as per the detail drawing.
Size - 320 x750mm (internal) No 4 2000.00 8,000.00

Kitchen Sink
Supply and fix Double Bowl Kitchen Sink made
9.1.10 of stainless steel. Complete with mixing faucet
waste water trap, plug, chain, [Link]
with all the necessary accessories.

Page 10 of 41
Semester Project on- BOQ and Specifications Prepared by- Group 1 Members

ITEM DESCRIPTION UNIT QTY RATE AMOUNT

Size, 1000mm x 500mm No 4 3000.00 12,000.00


Water Heater
Supply and fix 50 liters capacity Water Heater,
9.1.11
complete all water proofing, mounting and
fastening material ,heat fastening
material ,heat insulation, safety and non-
return valves complete with all the necessary
accessories. No 19 7500.00 142,500.00

Fire
SupplyExtinguisher
and fix 6kg CO2 Powder fire
9.1.12 extinguisher
for ABCE class of fire besides fire cabinet.
The material shall comply with TUV or,BSI
or ,NFPA orinstitution certification and
equivalent
approval.
Complete with approved standard hanging and
fixing materials . No 8 5000.00 40,000.00

Water Tank
9.1.13 Suply,mount and properly place fiber glass
water tank
on roof top where shown on roof plan and
ground floor
for storage,Complete with all the necessary
accessories
and connections such as inlet pipes, outlet
pipes,
drain pipes, over flow pipes all with gate
valves,
vent pipes with mesh cover,80mm uPVCvent
caps,
manhole,etc,The manhole shall have a strong,
lockable and easily operable cover just above
the inlet pipe.
The tank shall have:-
diameter 40mm outlet pipe,
diameter 40mm inlet pipe,
diameter 40mm approved quality float valve
diameter 25mm drainage pipe with horizontal
bronze gate valve( 16 BAR )
diameter 32mm over flow pipe
Size:-9m³ No 1 ### 40,000.00

9.2 WATER SUPPLY


Supply, lay PIPESPolypropelene
and connect AND VALVESpipe
(PPR)
pressure pipes with metallic insert,ClassE
(PN10),
for cold water supply system to sanitary
fixtures
Complete with all the necessary connecting
pieces

Page 11 of 41
Semester Project on- BOQ and Specifications Prepared by- Group 1 Members

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


such as bends, Ys, Ts, reducers, nipples,
unions,
galvanized clips, the interval shall be as per
manufacturer's
(if recommendation
any) etc... Unit price shall & supports
include ,disinfection of
the pipes with Chlorine and all the necessary
assistance to the installation works .
9.2.1 Supply and install Polypropelene pipe (PPR) pipes to
internal hot and cold water distribution system as
shown on the sanitary drawing. Complete with all the
necessary fittings and accessories.
Outer Diameter 15mm ml 436.8 100 43,680.00
Outer Diameter 20mm ml 380.4 100 38,040.00
Outer Diameter 25mm ml 204 100 20,400.00

9.2.2 Ditto Item No 9.2.1 but outer diameter 40mm


from water tanker. ml 80 200 16,000.00

9.2.3 Ditto Item No 9.2.1 but outer diameter 50mm


from water meter to water tanker. ml 40 200 8,000.00

Gate
SupplyValve Before
and fix bronzeFixtures
gate valves (PN 10 ) ,of
9.2.4 approved
standards compatible with PPR pipe before
Hand
basin,wash
water closets, kitchen sink,and all other
fixtures
complete with all the necessary accessories .
Diameter 15 mm No 98 150.00 14,700.00

Gate
SupplyValve Before
and fix bronzeBranch Pipes(PN 10 ) ,of
gate valves
9.2.5 approved
standards compatible with PPR pipe on internal
&
external branch water pipes,pipe inlet
tobuildings,
and water tank where shown on the drawing
complete with all the necessary accessories .
Diameter 20 mm No 64 150.00 9,600.00

9.2.6 Ditto Item No 9.2.5 but 25mm diameter No 40 150.00 6,000.00

9.2.7 Ditto Item No 9.2.5 but 40mm diameter No 20 150.00 3,000.00

Page 12 of 41
Semester Project on- BOQ and Specifications Prepared by- Group 1 Members

ITEM DESCRIPTION UNIT QTY RATE AMOUNT

9.2.8 Ditto Item No 9.2.5 but 50mm diameter No 10 150.00 1,500.00

9.3 WASTE, VENT AND RAIN WATER PIPES


AND ACCESSORIES
All domestic waste, vent and storm water pipe lines
shall be PVC pipes and shall be provided with a
minimum slope of 2% towards the outlet. All PVC
pipes and necessary fittings shall be standard quality
and be free from damage during storage, construction
and etc. Unit price shall include all the necessary
assistance civil works, such as excavation
cartaway, fixing or hanging to walls, beams or slabs.
etc., necessary fittings such as bends, Y, T, etc.
Storm water PVC pipes shall resist the external
temperature and the quality shall meet the purpose.

9.3.1 Supply and lay internal & external PVC waste and
vent pipes according to where shown on the drawings.
Complete with all the necessary fittings.
Diameter 50 mm ml 140 200 28,000.00
Diameter 110 mm ml 200 200 40,000.00
9.3.2 Supply and install vent caps made of rigid PVC to be
connected to the roof terminal of vent pipe as shown
on the riser diagram,complete with all the necessary
sealing gaskets and accessories.
Diameter 110mm No 6 200 1,200.00

9.3.3 Supply and lay approved quality storm water PVC


down pipes according to where shown on the
drawing. Price shall include all the necessary
connecting pieces.
Diameter 80 mm ml 102 200 20,400.00

9.4 SITE WORK

9.4.1 Supply & install G.S.P. water supply pipes for cold
water distribution in open ground to an average depth
of 500 mm from ground level. Price shall include

Page 13 of 41
Semester Project on- BOQ and Specifications Prepared by- Group 1 Members

ITEM DESCRIPTION UNIT QTY RATE AMOUNT

excavation, cartaway,asphalt paper or equivalent cover


and 100 mm thick gravel around the pipe. Price
shall also include all necessary connecting pieces
such as elbows, Tees & etc. and reconstruction of
asphalt layer on the excavated pipe route.
Diameter 50mm ml 50 200 10,000.00
" 32 " ml - -

9.4.2 Supply and lay PVC sewage pipes to B9 4660: 1989


and B9 5481: 1977 or equivalent according to the
drawing shown with a minimum slope of 1% or
natural ground slope which ever is greater on a firm bed
sand 100 mm thick below and 200 mm thick above
the crown of pipe in open ground.
The joints shall be made tight and installation
shall make possible the best condition for
cleaning & maintenance. Unit price shal include
excavation of the trench and cartaway. (Installation
shall also follow manufactuers' instruction .)
Dia.160 mm ml 60 200 12,000.00
MANHOLES
9.4.3 Supply and lay mortar jointed concrete storm water
drainage pipe according to the drawing shown on the
site work with a minimum slope of 1% or natural ground
slope which ever is greater on a firm bed of sand 100mm
thick below and 200 mm thick above the crown of pipe
in open ground. The joints shall be made tight and
installation shall make possible the best condition for
cleaning and maintenance. Unit price shall include
excavation of the trench and cart away.
Dia. 150 mm ml 70 200 14,000.00
MANHOLES
9.4.4 Construct manholes on a sanitary sewer as where
shown on the drawing in precast concrete round pipes
on 150mm thick reinforced concrete bottom slab in
dia.10c.c150mm both ways and 120 mm thick reinforced
cover slab in dia.10c.c150 mm both [Link] shall
include all assistance civil works and handle.

Page 14 of 41
Semester Project on- BOQ and Specifications Prepared by- Group 1 Members

ITEM DESCRIPTION UNIT QTY RATE AMOUNT

Dia. 600 mm, average dpeth 800 mm No 7 2000 14,000.00

9.5 Septic tank.


Construct septic tanks out of stone masonry walls, and
reinforced concrete bottom and top slabs, reinforced and
concrete manhole covers. The work shall be carried
out in accordance with the structural and sanitary
drawings. Price shall include excavation of pit cartaway
and backfilling.
Size: 3000x2000 x [Link] approximate 3500 No 1 80000 80,000.00

Total Carried to Summary


###
[Link]…………..…….

Electrical 10. Electrical


wiring should beInstallation
color coded and
labeled.

10.1 DISTRIBUTION BOARDS


The name of the board should be fixed over
the external door of the board with metal
plate, All ciruit breakers shall have label on
10.1.1 them and in each board graphically show the
location in which each breaker is dedicated
[Link] shall include atleast 30% reserve
space to be provided with fixing rail in all the
boards and Tumbler switch boxes.
Supply and install Floor Mounted Main
Distribution Board (MDB), IP 44, made of
approved quality standard steel sheet metal
with lockable door and separate earthing ,
nuetral,and phase bus bars of 400A/15KA and
consisting of :
26pcs MCB of 16A (1-ph)
2pcs MCB of 20A (1-ph)
1pc MCB of 32A (1-ph)
2pcs MCB of 25A (3-ph)
1pc MCB of 50A (3-ph)
1pc MCCB of 200A (3-ph)
3pcs ammeter of (0-710A) with current
transformer
1pc volt meter (0-500 V), with selector switch
3 pcs pilot lamps.
complete with all the necessary accessories
and atleast 30% reserve space. No 1 10000 10,000.00

Page 15 of 41
Semester Project on- BOQ and Specifications Prepared by- Group 1 Members

ITEM DESCRIPTION UNIT QTY RATE AMOUNT

Supply and install Floor Mounted Sub Main


Distribution Board (SMDB-SER), IP 44, made
10.1.2 of approved quality standard steel sheet metal
with lockable door and separate earthing ,
nuetral,and phase bus bars of 100A/10kA and
consisting of :
4pcs MCB of 16A (1-ph)
1pc MCB of 25A (1-ph)
1pc MCB of 40A (3-ph)
1pc MCB of 50A (3-ph)
complete with accessories and 30% reserve No 1 5000 5,000.00
space.
Supply and install Floor Mounted Sub Main
Distribution Board (SDB-GSER), IP 44, made of
10.1.3 approved quality standard steel sheet metal
with lockable door and separate earthing ,
nuetral,and phase bus bars of 50A/10kA and
consisting of :
8pcs MCB of 10A (1-ph)
1pc MCB of 16A (1-ph)
1pc MCB of 25A (3-ph)
complete with accessories and 30% reserve No 1 5000 5,000.00
space.

Supply and install Flush Mounted Sub


Distribution Board (SDB-GS1, SDB-GS2,
10.1.4 SDB-GS3, & SDB-GS4) IP 44, made of
approved quality standard steel sheet metal
with lockable door and separate earthing ,
nuetral,and phase bus bars of and consisting of
1pc MCB of 10A (1-ph)
2pcs MCB of 16A (1-ph)
complete with accessories and 25% reserve No 4 5000 20,000.00
space.
10.2 Light Points

10.2.1 Light points fed through PVC insulated copper


conductors of 3x2.5mm2 inside PVC conduits of
16mm diameter for recessed installation,
including junction boxes with covers and
insulating type screw cap connectors for
complete installation. No 149 300 44,700.00

10.3 Extra over light points :-


(TYPE LEGRAND DÉCOR OR EQUIVALENT)
10.3.1 Extra over light points flush mounted Legrand
Galea cover plates and frames with
mechanism :
Page 16 of 41
Semester Project on- BOQ and Specifications Prepared by- Group 1 Members

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


single pole switches No 53 300 15,900.00
two gang switches No 4 300 1,200.00
triple switches No 5 300 1,500.00
two way switches No 18 300 5,400.00
four gang switches No 4 300 1,200.00

10.4 Socket Outlet (Siemens shucko type)

Legrand Galea cover plates and frame with


mechnism or equivalent
Flush Mounted
Flush mounted socket outlets of 10/16A(1-ph)
with earthing contact terminal and fed
through PVC insulated copper conductors of
10.4.1 3x2.5mm2 inside PVC conduit of 16mm
diameter for recessed installation including
junction boxes with covers and insulating
screw cap connectors No 4 300 1,200.00

Ditto as item "a" above but with 16A/1ph water


10.4.2
proof cover. No 4 300 1,200.00

10.4.3 Ditto as item "a" above but twin socket out let. No 4 300 1,200.00

Ditto as item "a" above but 20A/1ph wall outlet


10.4.4 with inbuilt switch socket out let for hand drier
and water heater. No 4 300 1,200.00

Ditto as item above but with 25A (1-ph) socket


outlet and in built swich for Stove and "Injera
10.4.5 mitad" fed through PVC insulated copper
conductor of 3x4mm2 inside PVC conduit of
19mm diameter for recessed installation. No 2 300 600.00

Telephone/Data System

Price shall include related works and


accessories
a) RJ45 twin outlets type legrand (74213)
category 5e
with 8contacts complete with clip on support
frame
and labeling accessories No 2 300 600.00

b) Data/ telecommunication point fed through


2(4_pair category 6e UTP cable) inside
recessed
PVC conduit of 25mm diameter complete
with all
accessories No 2 300 600.00
c) Telephone line floor distribution box No 2 300 600.00
d) conduit of diameter 25mm No 2 300 600.00

Page 17 of 41
Semester Project on- BOQ and Specifications Prepared by- Group 1 Members

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


e)conduit of diameter 50mm No 2 300 600.00
Bell System

Bell points fed through PVC insulated


conductor of 2x1mm2 in conduit of 13.5mm for
recessed installation including Legrand
Diplomatic push button ,cover with
mechanism, junction box with cover and screw
type connectors.

Bell buzzer with 220/8 V , 25VA transformer


with Melody sound type approved by the
Engineer Residences, Library & Cafeteria.

TV System

Price shall include cost of socket


outlet ,cable,conduit and accessories
Flush mounted through wiring TV-FM_SAT
socket outlet
,Legrand Galea cover with mechanism type or
equivalent,
fed through coaxial broad band TV cable in
conduit of
diameter 25mm for recessed installation
including all for complete installation
accessories No 37 1500 55,500.00

TV Floor Distribution Boxes No 4 1000 4,000.00

Conduit of diameter 50mm ml 40 60 2,400.00

Supply and fix TV splitter circuit board. Price


shall include lockable board and all the
necessary accessories for complete No 1 40000 40,000.00
insatallation.
Light Fittings and Lamps
(Specified or Equivalent)
(for unit estimation purpose average price is
taken)fitting as specified in the drawings or
Light
equivalent approved by the Engineer and the
Owner. Lamps should be equivalent energy
saving types as manufactured by OSRAM or
equivalent. Flourescent lamps in class rooms,
reading and office areas should be 840. No 149 1000 149,000.00
Power Outlet

Page 18 of 41
Semester Project on- BOQ and Specifications Prepared by- Group 1 Members

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


Power outlet for Elevator fed through PVC
sheathed cable of 5x10mm2 in conduit of
diameter 50mm with 40A/3ph circuit breacker
complete with junction boxes with cover and
insulating screw cap connecters.
No 0 1,500.00 0.00
Ditto as item above but to Water pump fed
through cable of 5x4mm2 in conduit of
diameter 29mm with 25A/3ph.
No 1 1,000.00 0.00
Ditto as item above but to Coffee Machine,
Refrigerator and Kitchen hood fed through
cable of 3x4mm2 in conduit of diameter 19mm
No 3 800.00 0.00
with 25A/1ph.
Supply power to mercury switches in ground
and overhead water tanks through PVC
insulated copper cables of 3x2.5 [Link] in
thermoplastic conduit of minimum diameter No 2 4,000.00 0.00
25mm.
Supply and install mercury switch of approved
quality in ground and overhead water tanks.
Cable Ducts
Supply and recess rigid conduit ( Price shall
include related works) of diameter :
19mm ml 693.00 15.00 10,395.00
25mm ml 27.00 20.00 540.00
29mm ml 78.00 25.00 1,950.00
50mm ml 68.00 50.00 3,400.00
110mm ml 20.00 120.00 2,400.00
Concrete Pipe 200mm ml 12 200.00 2,400.00
PVC Sheathed Cable
(Siemens NYY 0.6/1.0KV)
(price shall include related works)
3x2.5mm2 ml 646.00 26.25 16,957.50
3x4mm2 ml 47.00 33.13 1,556.88
3x6mm 2
ml 27.00 47.50 1,282.50
5x4mm 2
ml 78.00 52.50 4,095.00
5x10mm 2
ml 68.00 160.00 10,880.00
3x120/70mm2 ml 20.00 975.00 19,500.00
Manhole
a) Double brick man hole internally plastered
with
10cm mass concrete base and 8cm thick
reinforced concrete top cover with handler.
of size: 150x150x100cm. No 1 4000 4,000.00
Earthing System

Page 19 of 41
Semester Project on- BOQ and Specifications Prepared by- Group 1 Members

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


a) Earthing rod of diameter 16mm (4pcs,
complete with driving stud, coupler, spike and
rod to cable clamp, all connected with
eachother using earthing cable) driven to
depth of 240cm (minimum) so as to attain
efficient earthing system (price shall include No 1 4000 4,000.00
b) Earthing cable of 1x70mm2 No 1 1000 1,000.00
Total Carried to Summary
###
[Link]…………..…….

Page 20 of 41
TAKE OFF SHEET
PROJECT:-
LOCATION:-
CLIENT:-
PREPARED BY:- GROUP 1 Page No. 1

T D S Unit Description T D S Unit Description

A-SUB STRUCTURE

[Link] & EARTH WORK -14 0.40 Deduct concrete in foundation column
1.1 Site clearing to a depth of 200mm 0.20
Adding 1.50m working space on both sides 1.50 -1.68 m3 (-)
1 36.87 ∑L1=33.87+1.5*2= 36.87m 6 2.50 c) Footing- F3=6pcs
17.63 ∑L2=14.63+1.5*2=17.63m 2.50
650.02 m2 Total site clearing 2.00 75.00 m3 (+)
-6 2.00 Deduct concrete in footing pads
1.2 Bulk Excavation to an avg. depth of 500mm 2.00
1 36.87 ∑L1=33.87+1.5*2= 36.87m 0.60 -14.40 m3 (-)
17.63 ∑L2=14.63+1.5*2=17.63m -6 0.40 Deduct concrete in foundation column
0.50 Avg. depth=0.50m 0.20
325.01 m3 Total bulk excavation 1.40 -0.67 m3 (-)
1.3) Pit Excavation to a depth of 1500mm 1 2.10 d) Footing- F4=1pcs
but not exceeding 3000mm 2.10
Depth Avg.=2.0m & 25cm working space all side 2.00 8.82 m3 (+)
a) Footing- F1=7pcs (1400x1400mm) -1 1.60 Deduct concrete in footing pads
7 1.90 L= 1.40+0.25*2=1.90m 1.60
1.90 W= 1.40+0.25*2=1.90m 0.35 -0.90 m3 (-)
2.00 50.54 m 3
(+) -1 0.40 Deduct concrete in foundation column
b) Footing- F2=14pcs (1800mmx1800mm) 0.20 (C1)
14 2.30 L= 1.80+0.25*2=2.30m 1.65 -0.13 m3 (-)
2.30 W= 1.80+0.25*2=2.30m -1 0.25 Deduct concrete in foundation column
2.00 148.12 m 3
(+) 0.25 (C4)
c) Footing- F3=6pcs (2000mmx2000mm) 1.65 -0.10 m3 (-)
6 2.50 L= 2.0+0.25*2=2.50m 1 1.30 e) Footing- F5=1pcs
2.50 W= 2.0+0.25*2=2.50m 1.30
2.00 75.00 m3 (+) 2.00 3.38 m3 (+)
d) Footing- F4=1pcs (1600mmx1600mm) -1 0.80 Deduct concrete in footing pads
1 2.10 L= 1.60+0.25*2=2.10m 0.80
2.10 W= 1.60+0.25*2=2.10m 0.20 -0.13 m3 (-)
2.00 8.82 m3
(+) -1 0.25 Deduct concrete in foundation column
e) Footing- F5=1pcs (800mmx800mm) 0.25
1 1.30 L= 0.8+0.25*2=1.30m 1.80 -0.11 m3 (-)
1.30 W= 0.8+0.25*2=1.30m 239.33 m3 Total fill around foundation
2.00 3.38 m3 (+) 1.5) Fill under hardcore
285.86 m 3
Total Pit Excavation (ref. item 1.7, page 2)
1.4) Fill around foundation 1 344.14 40cm thick
7 1.90 a) Footing- F1=7pcs 0.40
1.90 137.66 m3 Total fill under hardcore
2.00 50.54 m3 (+) 1.6) Cart away surplus excavated
-7 1.40 Deduct concrete in footing pads material
1.40 1 650.02 i) from site clearance (ref. item 1.1 total)
0.35 -4.80 m3 (-) 0.20 130.00 m3 (+)
-7 0.40 Deduct concrete in foundation column ii) from bulk excavation (ref. item 1.2)
0.20 1 325.01 325.01 m3 (+)
1.65 -0.92 m3 (-) iii) from pit excavation (ref. item 1.3)
14 2.30 b) Footing- F2=14pcs 1 285.86 285.86 m3 (+)
2.30 iv) fill around foundation (ref. item 1.4)
2.00 148.12 m 3
(+) -1 239.33 -239.33 m 3
(-)
-14 1.80 Deduct concrete in footing pads v) fill under hardcore
1.80 -1 137.66 -137.66 m3 (-)
0.50 -22.68 m 3
(-) 363.89 m3 Total Cartaway

TAKE OFF SHEET


Page No. 2

T D S Unit Description T D S Unit Description

1.7) 250mm thick hard core


a) B/n Axis 1-2 and A-B (under stair case) v) GB-5 on axis 2 & 3
1 4.51 L1=4.81-0.15-0.15 =4.51m 2 13.75 L= 0.82+5.91+4.21+4.31-0.4*3-0.3=13.75m
4.16 L2=4.31-0.15 =4.16m 0.30 W=0.3m
18.76 m2 (+) 8.25 m2 (+)
b) GFS-1 (4 Pcs) vi) GB-6 on axis 8
4 4.35 L1=4.35m 1 9.12 L=5.91+4.21-0.4-0.3*2=9.12m
3.80 L2=3.80m 0.30 W=0.3m
66.12 m 2
(+) 2.74 m2
(+)
b) GFS-2 (7 Pcs) vii) GB-7 on axis 4, 5 & 6
7 4.35 L1=4.35m 3 14.47 L= 0.82*2+5.91+4.21+4.31-0.4*4=14.47m
3.80 L2=3.80m 0.30 W=0.3m
115.71 m2 (+) 13.02 m2 (+)
c) GFS-3 (6 Pcs) viii) GB-8 on axis 7
6 5.50 L1=5.50m 1 10.56 L= 0.82*2+5.91+4.21-0.4*3=10.56m
4.35 L2=4.35m 0.30 W=0.3m
143.55 m2 (+) 3.17 m2 (+)
344.14 m2 Total area of hard core 61.51 m2 Total lean conc. under grade beams

2. CONCRETE WORK c) Under ground floor slab


2.1) 50 mm thick Lean Concrete (ref. item 1.7, on this page )
a) Under footing pads 1 344.14
7 1.40 i) F-1 (7pcs) 344.14 m2 Total lean conc. under ground floor slab
1.40
13.72 m2 (+) 2.2) Reinforced Concrete, C-25

14 1.80 ii) F-2 (14pcs) a) In Footing Pads


1.80 i) Footing F-1 (7pcs)
45.36 m2 (+) 7 1.40
6 2.00 iii) F-3 (6pcs) 1.40
2.00 0.35
24.00 m 2
(+) 4.80 m3 (+)
1 1.60 iv) F-4 (1pcs) ii) Footing F-2 (14pcs)
1.60 14 1.80
2.56 m2 (+) 1.80
1 0.80 v) F-5 (1pcs) 0.50
0.80 22.68 m3 (+)
0.64 m2
(+) iii) Footing F-3 (6pcs)
86.28 m2 Total lean conc. under footing pads 6 2.00
b) Under grade beam 2.00
i) GB-1 on axis D 0.60
1 27.66 L= 4.81*6-0.1-0.2*5-0.1=27.66m 14.40 m3 (+)
0.30 W=0.3m iv) Footing F-4 (1pcs)
8.30 m2 (+) 1 1.60
ii) GB-2 on axis B & C 1.60
2 32.27 L= 4.81*7-0.1-0.2*6-0.1=32.27m 0.35
0.30 W=0.3m 0.90 m3 (+)
19.36 m 2
(+) v) Footing F-5 (1pcs)
iii) GB-3 on axis A 1 0.80
1 18.44 L= 4.81*4-0.1-0.2*3-0.1=18.44m 0.80
0.30 W=0.3m 0.20
5.53 m2
(+) 0.13 m3 (+)
iv) GB-4 on axis 1 42.91 m3 Total conc. in footing pads
1 3.81 L= 4.21-0.2*2=3.81m
0.30 W=0.3m
1.14 m2 (+)

TAKE OFF SHEET


Page No. 3

T D S Unit Description T D S Unit Description

2.2) Reinforced Concrete, C-25


b) In Foundation Column
i) Column C-1 on F-1 & F-4= 8pcs
x-section =400x200mm
8 0.40 depth= 2.0-0.35-0.05=1.60m
0.20
1.60 1.02 m3 (+)
ii) Column C-1 on F-2 = 9pcs
x-section =400x200mm
9 0.40 depth= 2.0-0.5-0.05=1.45m
0.20
1.45 1.04 m3 (+)
iii) Column C-2 on F-2 = 5pcs
x-section =400x200mm
5 0.40 depth= 2.0-0.5-0.05=1.45m
0.20
1.50 0.60 m3 (+)
iv) Column C-2 on F-3 = 5pcs
x-section =400x200mm
5 0.40 depth= 2.0-0.6-0.05=1.35m
0.20
1.35 0.54 m3 (+)
v) Column C-3 on F-3 = 1pcs
x-section =400x200mm
1 0.40 depth= 2.0-0.6-0.05=1.35m
0.20
1.35 0.11 m3 (+)
vi) Column C-4 on F-4 = 1pcs
x-section =250x250mm
1 0.25 depth= 2.0-0.35-0.05=1.60m
0.25
1.60 0.10 m3 (+)
vii) Column C-4 on F-5 = 1pcs
x-section =250x250mm
1 0.25 depth= 2.0-0.2-0.05=1.75m
0.25
1.75 0.11 m3 (+)
3.53 m 2
Total concrete in foundation column
c) In Grade Beams
i) GB-1 on axis D
1 27.66 L=27.66m (ref. item 2.1b-I, page 2)
0.30 x-section =300x500mm
0.50 4.15 m3 (+)
ii) GB-2 on axis B & C
2 32.27 L=32.27m (ref. item 2.1b-ii, page 2)
0.30 x-section =300x500mm
0.50 9.68 m3 (+)
TAKE OFF SHEET
Page No. 4

T D S Unit Description T D S Unit Description


1.7) 250mm thick hard core under
Ground Floor slab c) B/n Axis 3-4 and C-D
a) B/n Axis 1-2 and C-D 1 5.39 L1=5.59-0.1*2 =5.39m
1 5.44 L1=5.59-0.05-0.10 =5.44m 4.04 L2=4.14-0.10 =4.04m
4.04 L2=4.14-0.10 =4.04m 21.78 m2 (+)
1 5.39 L1=5.59-0.1*2 =5.39m
0.00 m2 (+) 2.71 L2=2.91-0.10*2 =2.71m
b) B/n Axis 2-3 and C-D 14.61 m 2
(+)
1 5.42 L1=5.62-0.2 =5.42m 1 2.70 h) B/n Axis 4-5 and B-C
4.04 L2=4.14-0.10 =4.04m 2.71 L1=2.85-0.05-0.1 =2.70m
21.90 m2 (+) 7.32 m2 (+) L2=2.91-0.10*2 =2.71m

TAKE OFF NO. 2


T D S Unit Description T D S Unit Description

i) B/n Axis 1-2 and A-B


1 5.44 L1=5.59-0.05-0.10 =5.44m 2.2) C-25 Concrete in

3.74 L2=3.94-0.10*2 =3.74m a) Isolated Foundation Footing


20.35 m2 (+) 12 2.40 F-1 (12pcs)
j) B/n Axis 2-3 and A-B 2.40
1 5.42 L1=5.62-0.2 =5.42m 0.60
3.74 L2=3.94-0.10*2 =3.74m 41.47 m3 (+)
20.27 m 2
(+) 8 2.55 F-2 (8pcs)
j) B/n Axis 3-4 and A-B 2.55
1 5.39 L1=5.59-0.1*2 =5.39m 0.60
3.74 L2=3.94-0.10*2 =3.74m 31.21 m3 (+)
20.16 m2 (+) 72.68 m3 Total footing pad concrete
k) B/n Axis 4-5 and A-B b) Foundation Column
1 2.70 L1=2.85-0.05-0.1 =2.70m i) Column C-1, C-3 & C-5 (10pcs)
3.74 L2=3.94-0.10*2 =3.74m X-section =400x300mm
10.10 m2 (+) 10 1.90 depth= 2.55-0.05--0.60 =1.90m
l) Suspend beam 0.40
1 10.80 L1 =11.40-0.2*3=10.80m 0.30
1.24 L2=1.54-0.10+0.20 =1.24m 2.28 m3 (+)
13.39 m 2
(+) ii) Column C-2, C-4 & C-6 (10pcs)
470.07 m2 Total area of hardcore 10 1.90 X-section =400x400mm
0.40 depth= 2.55-0.05--0.60 =1.90m
2. CONCRETE WORK
0.40

2.1) 50 mm thick Lean Concrete 3.04 m3 (+)


a) Under footing pads 5.32 m3 Total Foundation Coln. Concrete
12 2.40 i) F-1 (12pcs) c) Grade Beam
2.40 GB on Axis- A & D
69.12 m2 (+) 2 18.45 L=19.95m
8 2.55 ii) F-2 (8pcs) 0.20 X-section =200x400mm
2.55 0.40
52.02 m2 (+) 2.95 m3 (+)

121.14 m2 Total lean concrete under footing pads GB on Axis- B & C

b) Under stone masonry wall 2 20.05 L=20.05m


computed by+10cm width addition 0.20 X-section =200x400mm
3 11.13 i) on Axis 1, 2 & 3 0.40
0.60 L= 12.73-0.4*4=11.13m, W=0.5+0.1=0.6m 3.21 m3 (+)
20.03 m2
(+) GB on Axis- 1,2 & 3
2 9.79 b) on Axis 4 & 5 3 12.73 L=12.73m
0.60 L=11.39-0.4*4=9.79m 0.20 X-section =200x400mm
11.75 m2 (+) 0.40
2 18.45 c) on Axis A & D 3.06 m3 (+)
0.60 L=19.95-0.3*5=18.45m GB on Axis- 4 & 5
22.14 m2 (+) 2 11.39 L=11.39m
2 18.05 c) on Axis B & C 0.20 X-section =200x400mm
0.60 L=20.05-0.4*5=18.05m 0.40 1.82 m3 (+)

21.66 m2 (+) 11.04 m3 Total GB Concrete

75.58 m 2
Total lean concrete under masonry wall

TAKE OFF NO. 3


T D S Unit Description T D S Unit Description

d) 100mm thick ground floor slab 2.3) Form work


(ref. item no. 1.17 page 1 & 2)
a) B/n Axis 1-2 and C-D a) To isolated foundation footing
1 5.44 12/4 2.40 i) footing F1- 12pcs
4.04 0.60
21.98 m2 (+) 69.12 m2 (+)
b) B/n Axis 2-3 and C-D 8/4 2.55 ii) footing F2- 8pcs
1 5.42 0.60
4.04 46.08 m2 (+)
21.90 m2
(+) 115.20 m2 Total formwork to footing pads
c) B/n Axis 3-4 and C-D b) To foundation column
1 5.39 i) Column C-1, C-3 & C-5 (10pcs)
4.04 X-section =400x300mm
21.78 m2 (+) depth=1.90m
d) B/n Axis 4-5 and C-D (Stair case) 10 1.90 dev.L=2(0.4+0.3)=1.40m
1 2.70 1.40
4.04 26.60 m2 (+)
10.91 m2 (+) ii) Column C-2, C-4 & C-6 (10pcs)
e) B/n Axis 1-2 and B-C X-section =400x400mm
1 5.44 depth=1.90m
2.71 10 1.90 dev.L=2(0.4+0.4)=1.60m
14.74 m2 (+) 1.60
f) B/n Axis 2-3 and B-C 30.40 m2 (+)
1 5.42 57.00 m2 Total formwork to foundation coln.
2.71 c) To grade beam (200x400mm)
14.69 m2 (+) Axis 1,2 & 3 (ref. item no.1.4/a page-1)
g) B/n Axis 3-4 and B-C SL total==12.73*3=38.19m
1 5.39 1 38.19 dev.L= 2*0.40=0.80m
2.71 0.80
14.61 m2 (+) 30.55 m2 (+)
1 2.70 h) B/n Axis 4-5 and B-C Axis 4 & 5 (ref. item no.1.4/b page-1)
2.71 SL total==11.39*2=22.78m
7.32 m2 (+) 1 22.78 dev.L= 2*0.40=0.80m
i) B/n Axis 1-2 and A-B 0.80
1 5.44 18.22 m2 (+)
3.74 Axis A,B,C & D (ref. item no.1.4/a page-1)
20.35 m2 (+) SL total==19.95*4=79.80m
j) B/n Axis 2-3 and A-B 1 79.80 dev.L= 2*0.40=0.80m
1 5.42 0.80
3.74 63.84 m2 (+)
20.27 m 2
(+) 112.62 m2 Total formwork to GB
j) B/n Axis 3-4 and A-B
1 5.39 2.4) Steel reinforcement bar

3.74 (refer bar bending schedule for Sub-Str.)


20.16 m2 (+) 1316.63 kg a) Dia. 8mm deformed bar
k) B/n Axis 4-5 and A-B 0.00 kg b) Dia. 10mm deformed bar
1 2.70 0.00 kg c) Dia. 12mm deformed bar
3.74 348.70 kg d) Dia. 14mm deformed bar
10.10 m2 (+) 6660.54 kg e) Dia. 16mm deformed bar
l) Suspend slab 3. Masonry Work

1 10.80 1 140.77 3.1) 500 mm thick stone masonry


1.24 0.50 1.0m below GL

13.39 m 2
(+) 1.00 SL total=38.19+22.78+79.80=140.77m

212.18 m2 Total ground floor slab concrete 70.39 m3 Total vol. of stone masonry

TAKE OFF NO. 4


T D S Unit Description T D S Unit Description
B-SUPER STRUCTURE
1. CONCRETE WORK v) Fourth Floor Elevation Column
1.1 Reinforced Concrete C-25 C1,C3 & C5 (10 PC )
a) Elevation Columns 10 2.79 Heght=3.19-0.4= 2.79m
i) Ground Floor Elevation Column 0.40 (400X300mm)
C1,C3 & C5 (10 PC ) 0.30
10 3.75 Heght =4.15-0.4= 3.75m 3.35 m3 (+)
0.40 (400X300mm) C2,C4 & C6 (10 PC )
0.30 10 2.79 Heght=3.19-0.4= 2.79m
4.50 m3 (+) 0.40 (400X400mm)
C2,C4 & C6 (10 PC ) 0.40
10 3.75 Heght=4.15-0.4= 3.75m 4.46 m3 (+)
0.40 (400X400mm) 7.81 m3 Total- v
0.40 vi) For Elevated Water Tank Column
6.00 m3 (+) C3 (2 PC )
10.50 m 3
Total- i 2 2.79 Heght=3.19-0.4= 2.79m
ii) First Floor Elevation Column 0.40 (400X300mm)
C1,C3 & C5 (10 PC ) 0.30
10 2.79 Heght=3.19-0.4= 2.79m 0.67 m3 (+)
0.40 (400X300mm) C4 (2 PC )
0.30 2 2.79 Heght=3.19-0.4= 2.79m
3.35 m3 (+) 0.40 (400X400mm)
C2,C4 & C6 (10 PC ) 0.40
10 2.79 Heght=3.19-0.4= 2.79m 0.89 m3 (+)
0.40 (400X400mm) 1.56 m3 Total- vi
0.40 43.31 m 3
Total Elev. Column Concrete
4.46 m3 (+)
7.81 m3 Total- ii b) Floor Beams
iii) Second Floor Elevation Column per floor

C1,C3 & C5 (10 PC ) FB on Axis- A,B,C & D


10 2.79 Heght=3.19-0.4= 2.79m 4 19.95 L=19.95 M
0.40 (400X300mm) 0.20
0.30 0.40
3.35 m3 (+) 6.38 m3 (+)
C2,C4 & C6 (10 PC ) FB on Axis- 1,2 & 3
10 2.79 Heght=3.19-0.4= 2.79m 3 12.73 L=12.73 M
0.40 (400X400mm) 0.20
0.40 0.40
4.46 m3 (+) 3.06 m3 (+)
7.81 m3 Total- iii FB on Axis- 4 & 5
iv) Third Floor Elevation Column 2 11.86 L=11.86 M
C1,C3 & C5 (10 PC ) 0.20
10 2.79 Heght=3.19-0.4= 2.79m 0.40
0.40 (400X300mm) 1.90 m3 (+)
0.30 11.34 m3 Total per floor
3.35 m3 (+) 4 11.34
C2,C4 & C6 (10 PC ) 45.35 m3 Total for four story FB concrete
10 2.79 Heght=3.19-0.4= 2.79m
0.40 (400X400mm)
0.40
4.46 m3 (+)
7.81 m3 Total- iv

TAKE OFF NO. 5


T D S Unit Description T D S Unit Description

c) In 150mm thick floor slab d) Terrace and Stair Roof Slab


per floor 150mm thick
B/n Axis 1-2 and C-D Terrace Slab
1 5.44 B/n Axis 3-4 and C-D
4.04 1 5.39
21.98 m2 (+) 4.04
B/n Axis 2-3 and C-D 21.78 m2 (+)
1 5.42 B/n Axis 3-4 and B-C
4.04 1 5.39
21.90 m2 (+) 2.71
B/n Axis 3-4 and C-D 14.61 m2 (+)
1 5.39 B/n Axis 3-4 and A-B
4.04 1 5.39
21.78 m2 (+) 3.74
B/n Axis 4-5 and C-D 20.16 m2 (+)
1 0.00 Void for Stair case 1 2.70 B/n Axis 4-5 and B-C
0.00 2.71
0.00 m2 (+) 7.32 m2 (+)
B/n Axis 1-2 and B-C B/n Axis 4-5 and A-B
1 5.44 1 2.70
2.71 3.74
14.74 m2 (+) 10.10 m2 (+)
B/n Axis 2-3 and B-C Stair roof slab/Water tank slab
1 5.42 B/n Axis 4-5 and C-D
2.71 1 2.70
14.69 m2 (+) 4.04
B/n Axis 3-4 and B-C 10.91 m2 (+)
1 5.39 84.86 m2 Total for terrace & stair roof slab
2.71
14.61 m2 (+) e) Top beam & Stair Roof beam
1 2.70 B/n Axis 4-5 and B-C TTB on Axis- A,B,C & D and
2.71 1 86.10 SRB on Axis- C & D b/n 4&5
7.32 m2 (+) 0.20 L=19.95*4+3.15*2=86.10 M
B/n Axis 1-2 and A-B 0.40
1 5.44 6.89 m3 (+)
3.74 TTB on Axis- 1,2 & 3
20.35 m2 (+) 3 12.73 L=12.73 M
B/n Axis 2-3 and A-B 0.20
1 5.42 0.40 32.60
3.74 3.06 m3 (+)
20.27 m2 (+) TTB on Axis- 4 & 5 and
B/n Axis 3-4 and A-B 1 38.30 SRB on Axis- 4 & 5 b/n C&D
1 5.39 0.20 L=11.86*2+4.44*2+2.85*2=38.30 M
3.74 0.40
20.16 m2 (+) 3.06 m3 (+)
B/n Axis 4-5 and A-B 13.01 m3 Total concrte for TTB & SRB
1 2.70
3.74 f) Stair Case and Landing
10.10 m2 (+) 1 4.200 Section 1-1
Cantilevers 1.330 From 0.00 to +2.45
1 10.96 L=5.54+5.42=10.96M 0.160 Soffit
1.34 0.89 m3 (+)
14.69 m2 (+) 7 1.330 Riser (14 Risers & 1 flights)
202.56 m 2
Total 0.172 14*0.5=7
4 202.56 0.300
810.26 m2 Total for four story floor slab 0.48 m3 (+)

TAKE OFF NO. 6


T D S Unit Description T D S Unit Description

Stair Case……… C-2, C-4 & C-6 (10pcs)


Section 2-2 10 2.79 (400X400mm)
1 4.140 From +2.45 to +4.15 1.60
1.330 Soffit 44.64 m2 (+)
0.160 Second Floor Elevation Coulmn
0.88 m3 (+) 10 2.79 C-1, C-3 & C-5 (10pcs)
Riser (10 Risers & 1 flights) 1.40 (400X300mm)
5 1.330 10*0.5=5 39.06 m2 (+)
0.172 C-2, C-4 & C-6 (10pcs)
0.300 10 2.79 (400X400mm)
0.34 m3 (+) 1.60
Section 3-3 44.64 m2 (+)
from +4.15 to +5.75, +7.34 to +8.94, Third Floor Elevation Coulmn
4 4.140 + 10.53 to +12.13, & +13.72 to +15.32 10 2.79 C-1, C-3 & C-5 (10pcs)
1.330 Soffit 1.40 (400X300mm)
0.160 39.06 m2 (+)
3.52 m3 (+) C-2, C-4 & C-6 (10pcs)
Riser (10 Risers & 4 flights) 10 2.79 (400X400mm)
20 1.330 1.60
0.172 44.64 m2 (+)
0.300 Fourth Floor Elevation Coulmn
1.37 m3 (+) 10 2.79 C-1, C-3 & C-5 (10pcs)
Section 4-4 1.40 (400X300mm)
from +5.75 to +7.34 , +8.94 to+10.53 39.06 m2 (+)
4 4.140 +12.13 to +13.72 & +15.32 to +16.91 C-2, C-4 & C-6 (10pcs)
1.330 Soffit 10 2.79 (400X400mm)
0.160 1.60
3.52 m3 (+) 44.64 m2 (+)
Riser (10 Risers & 4 flights) For Elevated Water Tank Column
20 1.330 C3 (2 PC )
0.172 2 2.79 (400X300mm)
0.300 1.40
1.37 m3 (+) 7.81 m2 (+)
Landing Beam C4 (2 PC )
5 3.150 +2.45,+5.75, +8.94, +12.13 & 15.32 2 2.79 (400X400mm)
0.200 L=3.15 M 1.60
0.400 8.93 m2 (+)
1.26 m3 (+) 464.04 m2 Total formwork to Elev. Column
13.65 m 3
Total conc. for staircase & landing beam b) Floor Beam
to Floor Beam per Floor
1.2) Form work 4 19.95 on Axis- A,B,C & D
a) Elevation Coulmn 1.00 dev.L=2(0.4)+0.2=1.0m
Ground Floor Elevation Coulmn 79.80 m2
10 3.75 C-1, C-3 & C-5 (10pcs) on Axis- 1,2 & 3
1.40 (400X300mm) 3 12.73 dev.L=2(0.4)+0.2=1.0m
52.50 m2 (+) 1.00
C-2, C-4 & C-6 (10pcs) 38.19 m2
10 3.75 (400X400mm) on Axis- 4 & 5
1.60 2 11.86 dev.L=2(0.4)+0.2=1.0m
60.00 m2 (+) 1.00
First Floor Elevation Coulmn 23.72 m2
10 2.79 C-1, C-3 & C-5 (10pcs) 141.71 m2 Total per floor
1.40 (400X300mm) 4 141.71
39.06 m2 566.84 m2 Total formwork to four story FB

TAKE OFF NO. 7


T D S Unit Description T D S Unit Description

c) In 150mm thick floor slab d) Terrace and Stair Roof Slab


per floor 150mm thick
B/n Axis 1-2 and C-D Terrace Slab
1 5.44 B/n Axis 3-4 and C-D
4.04 1 5.39
21.98 m2 (+) 4.04
B/n Axis 2-3 and C-D 21.78 m2 (+)
1 5.42 B/n Axis 3-4 and B-C
4.04 1 5.39
21.90 m2 (+) 2.71
B/n Axis 3-4 and C-D 14.61 m2 (+)
1 5.39 B/n Axis 3-4 and A-B
4.04 1 5.39
21.78 m2 (+) 3.74
B/n Axis 4-5 and C-D 20.16 m2 (+)
1 0.00 Void for Stair case 1 2.70 B/n Axis 4-5 and B-C
0.00 2.71
0.00 m2 (+) 7.32 m2 (+)
B/n Axis 1-2 and B-C B/n Axis 4-5 and A-B
1 5.44 1 2.70
2.71 3.74
14.74 m2 (+) 10.10 m2 (+)
B/n Axis 2-3 and B-C Stair roof slab/Water tank slab
1 5.42 B/n Axis 4-5 and C-D
2.71 1 2.70
14.69 m2 (+) 4.04
B/n Axis 3-4 and B-C 10.91 m2 (+)
1 5.39 84.86 m2 Total formwork for terrace slab
2.71
14.61 m2 (+) e) Top Tie & Stair Roof beam
1 2.70 B/n Axis 4-5 and B-C on Axis- A,B,C & D
2.71 1 86.10 L=19.95*4+3.15*2=86.10 M
7.32 m2 (+) 1.00 dev.L=2(0.4)+0.2=1.0m
B/n Axis 1-2 and A-B 86.10 m2 (+)
1 5.44 on Axis- 1,2 & 3
3.74 3 12.73 dev.L=2(0.4)+0.2=1.0m
20.35 m2 (+) 1.00
B/n Axis 2-3 and A-B 38.19 m2 (+)
1 5.42 on Axis- 4 & 5
3.74 1 38.30 L=11.86*2+4.44*2+2.85*2=38.30 M
20.27 m2 (+) 1.00 dev.L=2(0.4)+0.2=1.0m
B/n Axis 3-4 and A-B 38.30 m2 (+)
1 5.39 162.59 m2 Total formwork for TT &SR beam
3.74
20.16 m2 (+) f) Stair Case and Landing
B/n Axis 4-5 and A-B Section 1-1
1 2.70 1 4.20 From 0.00 to +2.45
3.74 1.33
10.10 m2 (+) 5.59 m2 (+)
Cantilevers Sides (right & left)
1 10.96 L=5.54+5.42=10.96M 2 4.20
1.34 0.16
14.69 m2 (+) 1.34 m2 (+)
202.56 m 2
Total 14 1.33 Front of Riser (14 Risers)
4 202.56 0.17

810.26 m2 Total formwork for four story floor slab 3.17 m2 (+)

TAKE OFF NO. 8


T D S Unit Description T D S Unit Description

Sides of Riser (14Risers) 1.3) Steel reinforcement bar


7 0.17 Refer bar bending schedule for
0.30 Super-Structure(B)
0.36 m2 (+) a) Dia. 8mm deformed bar
Section 2-2 3,164.00 kg Total
From +2.45 to +4.15 b) Dia. 10mm deformed bar
1 4.14 13,716.18 kg Total
1.33 c) Dia. 12mm deformed bar
5.51 m2
(+) 1,095.95 kg Total
d) Dia. 14mm deformed bar
Sides (right & left) 2,271.55 kg Total
2 4.14 e) Dia. 16mm deformed bar
0.16 10,818.46 kg Total
1.32 m2 (+) f) Dia. 20mm deformed bar
Sides of Riser (10Risers) 3,425.68 kg Total
5 0.17
0.30
0.26 m2 (+)
Section 3-3
from +4.15 to +5.75, +7.34 to +8.94,
+ 10.53 to +12.13, & +13.72 to +15.32
4 4.14
1.33
22.02 m2 (+)
Sides (right & left)
8 4.14
0.16
5.30 m2 (+)
Sides of Riser (10Risers & 4 flights)
20 0.17
0.30
1.02 m2 (+)
Section 4-4
from +5.75 to +7.34 , +8.94 to+10.53
+12.13 to +13.72 & +15.32 to +16.91
4 4.14
1.33
22.02 m2 (+)
Sides (right & left)
8 4.14
0.16
5.30 m2 (+)
Sides of Riser (10Risers & 4 flights)
20 0.17
0.30
1.02 m2 (+)
Landing Beam
@level +2.45,+5.75, +8.94, +12.13 & 15.32
5 3.10 dev.L=2(0.4)+0.2=1.0m
1.00
15.50 m2 (+)

89.73 m 2
Total formwork for staircase & landing
TAKE OFF NO. 9
T D S Unit Description T D S Unit Description

Ground floor
2. Block Work Internal /partition / wall
2.1) 200mm thick HCB wall on Axis A-B b/n 1 - 2
Ground floor (External wall) 1 16.47 L=16.47m, h=3.68m
On Axis D from 1 to 5 3.68
1 18.65 L=18.65m, h=3.68m 60.61 m2 (+)
3.68 on Axis 4 b/n C & D
68.63 m2 (+) 1 3.69 L=3.69m, h=3.68m
Ddt for W1 3.68
-1 3.55 L=3.55m, h=1.23m 13.58 m2 (+)
1.23 74.19 m2 Subtotal
-4.37 m 2
(-) First floor (External wall)
Ddt for W2 On Axis D from 1-2
-1 5.42 L=5.42m, h=2.90m 1 5.39 L=5.39m, h=2.94m
2.90 2.94
-15.72 m2 (-) 15.85 m2 (+)
Ddt for W3 Ddt for W1
-1 5.39 L=5.39m, h=2.90m -1 3.55 L=3.55m, h=1.23m
2.90 1.23
-15.63 m2 (-) -4.37 m2 (-)
On axis 1 from A' to D On Axis D from 4-5
L=11.15m, h=3.68m 1 3.05 L=3.05m, h=2.94m
1 11.15 2.94
3.68 8.97 m2 (+)
41.03 m2 (+) On axis A' b/n 1-2
Ddt for W4 1 5.39 L=5.39m, h=2.94m
-1 1.88 L=1.88m, h=1.95m 2.94
1.92 15.85 m2 (+)
-3.61 m 2
(-) Ddt for W7
Ddt for W5 -1 5.39 L=5.39m, h=0.93m
-1 2.45 L=2.45m, h=1.95m 0.93
1.95 -5.01 m2 (-)
-4.78 m2 (-) On axis 1&3 from A' to D
Ddt for W6 L=12.46m, h=2.94m
-1 3.49 L=3.49m, h=1.95m 1 12.46
1.90 2.94
-6.63 m2 (-) 36.63 m2 (+)
On axis A' b/n 1-2 Ddt for W8
1 5.39 L=5.39m, h=3.68m -1 1.00 L=1.0m, h=2.10m
3.68 2.10
19.84 m2 (+) -2.10 m2 (-)
Ddt for W7 Ddt for W9
-1 5.39 L=5.39m, h=0.93m -1 1.40 L=1.40m, h=1.28m
0.93 1.28
-5.01 m2 (-) -1.79 m2 (-)
On axis 3 b/n A'-A Ddt for W10
1 1.31 L=1.31m, h=3.68m -1 3.49 L=3.49m, h=1.03m
3.68 1.03
4.82 m2 (+) -3.59 m2 (-)
78.57 m2 Sub total 60.43 m2 Sub total

TAKE OFF NO. 10


T D S Unit Description T D S Unit Description
First floor Second, Third & Fourth Floor
200mm thick HCB wall Internal /partition / wall
Internal /partition / wall 3 18.40 on Axis 2 and 3 b/n A' & D

on Axis 2 b/n C - D 2.79 L=9.2*2=18.4m, h=2.79m


1 8.85 L=8.85m, h=2.94m 154.01 m 2
(+)
2.94 on Axis 4 & B
26.02 m2
(+) 3 8.20 L=5.55+2.65=8.20m, h=2.79m
on Axis B b/n 1 - 2 2.79
1 4.59 L=4.59m, h=2.94m 68.63 m2 (+)
2.94 222.64 m2 Subtotal
13.49 m2
(+) (Sum of all sub total)

on Axis 4 b/n A & D 755.34 m2 Total 200mm thick HCB


1 7.18 L=7.18m, h=2.94m
2.94 2.2) 150mm thick HCB
21.11 m2
(+) First floor
60.62 m2 Subtotal 1 5.15 Partition in,kitchen, store & toilet
2.94 L=5.15m, h=2.94m
Second, Third & Fourth Floor 15.14 m 2
(+)
(External wall) Second, Third & Fourth Floor
200mm thick HCB wall 150mm thick HCB wall
On axis 1 from A' to D on Axis B b/n 1 - 4
3 11.15 L=11.15m, h=2.79m 3 13.50 L=13.50m, h=2.79m
2.79 2.79
93.33 m2 (+) 113.00 m2 (+)
Ddt for W11 on wall b/n B & C
-3 1.20 L=1.20m, h=2.70m 3 13.90 L=13.90m, h=2.79m
2.70 2.79
-9.72 m2 (-) 116.34 m2 (+)
On Axis D from 1 to 5 Partition in toilet b/n C & D
3 18.65 L=18.65m, h=2.79m 3 9.60 L=3.20*3=9.60m, h=2.79m
2.79 2.79
156.10 m2 (+) 80.35 m2 (+)
Ddt for W12 Partition in toilet b/n A & B
-9 2.87 L=2.87m, h=2.57m 3 7.50 L=2.50*3=7.50m, h=2.79m
2.57 2.79
-66.38 m2 (-) 62.78 m2 (+)
Ddt for W13 3 4.23 L=1.41*3=4.23m, h=2.79m
-9 1.75 L=1.75m, h=1.23m 2.79
1.23 35.41 m2 (+)
-19.37 m2
(-) Ddt for W13
On axis A' b/n 1-5 -9 0.99 L=0.99m, h=1.23m
3 9.43 L=9.43m, h=2.79m 1.23
2.79 -10.96 m2
78.93 m2
(+) For parapet wall & Stair roof
on balcony part 1 39.15 14.83*3.16 L1=12.95*2+13.25=39.15m, & L2=14.83

9 2.89 L=2.89m, h=1.0m 1.20 46.86 m2 h1=1.20m h2=3.16m


1.00 93.84 m 2
(+)
26.01 m2 (+) 1 17.09 L=6.88+4.03+6.18=17.09m,

258.89 m2 Sub total 0.60 h=0.60m


10.25 m2
(+)

563.01 m 2
Total 150mm thick HCB

TAKE OFF NO. 11


T D S Unit Description T D S Unit Description

2.3) 100mm thick HCB wall 3.5) Water proofing


Ground floor 1 5.99 B/n Axis 3' & 4 and from Axis B' to D
Partition for Ladies & Gents Toilet 4.00
1 4.19 L=4.19m, h=3.68m 23.96 m2 (+)
3.68 1 6.85 B/n Axis 3' & 4 and from Axis A' to B'
15.42 m2 (+) 5.89
40.35 m2 (+)
2 1.81 L=1.81m, h=3.68m 64.31 m2 Total area of water proofing
3.68
13.32 m2 (+) 3.6) 3 cm thick smoothly finished
First floor cement
Partition for Toilet 1 5.99 B/n Axis 3' & 4 and from Axis B' to D
1 5.06 L1=5.06m, h=3.04m 4.00
3.04 23.96 m2 (+)
15.38 m2
(+) 1 6.85 B/n Axis 3' & 4 and from Axis A' to B'
5.89
1 3.66 L2=3.66m, h=3.04m 40.35 m2 (+)
3.04 64.31 m2 Total area of finished cemen
11.13 m2
(+)
4. Carpentery & Joinery
L3=1.71m, h=3.04m
3 1.71 4.2) Dia. 8-10cm eucalyptus truss
3.04 a) Dia. 10cm upper & lower chord
15.60 m2 (+) placed c/c 120cm

70.84 m2 Total 100mm thick HCB L=12.36m, No. =12.4/1.2=11pcs


2x11 12.36

3.0. Roofing & Water Proofing 271.92 ml (+)


3.1) G-28 C.I.S Roof Cover a) Dia. 8cm diag. & vertical member
From section A' to D on axis 1 to 3' Ldiag.=5.53*2=11.06m
1 12.40 Lvert..=3.96*2=7.92m
12.36 Ltotal=18.98 and 11pcs
153.26 m 2
Tota projeccted area of G-28 roof cover 11 18.98
208.78 ml (+)
3.2) Flat metal sheet copping 480.70 ml Total Length of eucalyptus truss
1 12.40
12.40 ml Total Length of Copping 4.3) 50x70 mm zigba wood purlin
placed c/c 90cm
3.3) Gutter for G28 L=12.40m, No. =12.36/0.9=14pcs
On axis A' & D 14 12.40
2 12.40 173.60 ml (+)

24.80 ml Total Length of Gutter 173.60 ml Total Length of eucalyptus truss

3.4) Roof concrete (for Terrace) 4.4) 8mm thick gypsum board
1 5.99 B/n Axis 3' & 4 and from Axis B' to D Top floor Bed Rooms & Bath
4.00 1 12.40 L=12.4m, W=12.36m
23.96 m 2
(+) 12.36
1 6.85 B/n Axis 3' & 4 and from Axis A' to B' 153.26 m2 Tota area of 8mm thick gypsum board
5.89
40.35 m2 (+)

64.31 m2 Total area of roof concrete

TAKE OFF NO. 12


T D S Unit Description T D S Unit Description

5.0. Metal Works Internal wall plastering


5.1.4 Curtain Walls at front On axis 1 from A' to D
1 9.33 1 11.15 L=11.15m, h=3.68m
4.68 3.68
43.66 m2 (+) 41.03 m2 (+)
1 2.17 -15.02 m 2
Deduction for windows
9.33 26.01 m2 (+) sub total
20.25 m 2
(+) On axis A' b/n 1-2
63.91 m2 Total Curtain Walls 1 5.39 L=5.39m, h=3.68m
3.68
5.2 Guard rails for stair case 19.84 m2 (+)
Inclined Guard rails -5.01 m 2
Deduction for windows
1 4.57 14.82 m2 (+) sub total
4.57 ml (+) On axis 3 b/n A'-A
18 3.46 9x2=18pcs 1 1.31 L=1.31m, h=3.68m
62.28 ml (+) 3.68
Vertical Guard rails 4.82 m2 (+)
14 0.90 4+10=14pcs Internal /partition / wall in Bank & Store
12.60 ml (+) on Axis A-B b/n 1 - 2

79.45 ml Total Length of Guard rails 2 16.47 L=16.47m, h=3.68m


3.68
5.3 Corridors and Verandah rail 121.22 m2 (+)
On axis A from axis 1 to 4 (Horizontal) on Axis 4 b/n C & D
45 2.90 9x5=45pcs 2 3.69 L=3.69m, h=3.68m
130.50 ml (+) 3.68
On axis A from axis 1 to 4 (Vertical) 27.16 m2 (+)
27 0.60 9x3=27pcs Partition for Ladies & Gents Toilet
16.20 ml (+) 2 4.19 L=4.19m, h=3.68m

146.70 ml Total for corridor & verandah rails 3.68


30.84 m2 (+)
5.4 Terrace rail 40 cm height
(Horizontal) , 6pcs 4 1.81 L=1.81m, h=3.68m
6 16.40 Ltotal=16.40 3.68 2 sides & 2ps
98.40 ml (+) 26.64 m 2
(+)
(Vertical) 284.43 m2 Total inter. plastering for ground floor
12 0.70 12pcs
8.40 ml (+) First floor

106.80 ml Total length of Terrace rails Internal wall plastering


1 5.39 On Axis D from 1-2
6. Plastering, Floor, Wall and 2.94 L=5.39m, h=2.94m
Other Finishing Works 15.85 m2
Plastering -4.37 m2 Deduction for windows
6.1 Internal wall plastering 1 3.05 On Axis D from 4-5
Ground floor 2.94 L=3.05m, h=2.94m
1 18.65 Bank ( Axis D b/n 1-5) 8.97 m
2
(+)
3.68 1 5.39 On axis A' b/n 1-2

68.63 m2 2.94 L=5.39m, h=2.94m


-35.72 m2 Deduction for windows 15.85 m2 (+)
32.92 m2 (+) sub total -5.01 m2 Deduction for windows

TAKE OFF NO. 13


T D S Unit Description T D S Unit Description

First floor
Internal wall plastering On axis A' b/n 1-5
On axis 1&3 from A' to D 3 9.43 L=9.43m, h=2.79m
1 12.46 L=12.46m, h=2.94m 2.79
2.94 78.93 m2 (+)
36.63 m2
on balcony part
-7.49 m2 Deduction for windows 9 2.89 L=2.89m, h=1.0m
on Axis 2 b/n C - D 1.00
1 8.85 L=8.85m, h=2.94m 26.01 m2 (+)
2.94 on Axis B b/n 1 - 4
26.02 m2 (+) 6 13.50 L=13.50m, h=2.79m
on Axis B b/n 1 - 2 2.79
1 4.59 L=4.59m, h=2.94m 225.99 m2 (+)
2.94 on wall b/n B & C
13.49 m2 (+) 6 13.90 L=13.90m, h=2.79m
on Axis 4 b/n A & D 2.79
1 7.18 L=7.18m, h=2.94m 232.69 m2 (+)
2.94 Partition in toilet b/n C & D
21.11 m2 (+) 6 9.60 L=3.20*3=9.60m, h=2.79m
Partition in,kitchen, store & toilet 2.79

2 5.15 Ltotal=5.15m, h=2.94m 160.70 m2 (+)


2.94 Partition in toilet b/n A & B
30.28 m2
(+) 6 7.50 L=2.50*3=7.50m, h=2.79m
Partition for Toilet & Lobby 2.79
2 5.06 L1=5.06m, h=3.04m 125.55 m2 (+)
3.04 6 4.23 L=1.41*3=4.23m, h=2.79m
30.76 m2
(+) 2.79
70.81 m2 (+)
2 3.66 L2=3.66m, h=3.04m -10.96 m 2
Deduction for toilet windows
3.04 Total internal plastering for Second,
1063.67 m2
22.25 m2
(+) Third & Fourth Floor
284.43+235.54+1063.67
6 1.71 L3=1.71m, h=3.04m 1583.64 m2 Total area of internal wall plastering
3.04
31.19 m2 6.2 External Wall Plastering

235.54 m 2
Total internal plastering for first floor Right Side on Axis D b/n 1-5
refer item no. 2.1
Second, Third & Fourth Floor 1 130.37
Internal wall plastering 130.37 m2 (+)
On axis 1 from A' to D Left Side on Axis A' b/n 1-5
3 11.15 L=11.15m, h=2.79m refer item no. 2.1 & 2.2
2.79 1 51.67
93.33 m2 (+) 51.67 m2 (+)
-9.72 m2
Deduction for windows Rear Side on Axis A' b/n 1-5
On Axis D from 1 to 5 refer item no. 2.1 & 2.2
3 18.65 L=18.65m, h=2.79m 1 142.36
2.79 142.36 m2 (+)
156.10 m2
(+) 104.10 m2 For parapet wall & Stair roof

-85.76 m2
Deduction for windows 428.50 m2
Total area of external plastering

TAKE OFF NO. 14


T D S Unit Description T D S Unit Description

6.3 Plastering Concrete surface 6.8 Fine Coat/ Rendering to external


Column (400X300mm) wall surface
C1,C3 & C5 (10 PC ) refer item no. 6.2 on page no.13
10 1.20 Permiter=0.4*2+0.3+0.1=1.20m 1 428.50
3.85 428.50 m2 Total
46.20 m2
(+)
Column (400X400mm) 6.9 Apply gypsum plaster over
C2,C4 & C6 (10 PC ) plastered surface of internal wall
10 1.40 Permiter=0.4*3+0.2=1.40m refer item no. 6.5 on this page
3.85 1 1073.70
53.90 m2 (+) 1073.70 m2 Total
Column (400X300mm) 6.10 Apply gypsum plaster over
C1,C3 & C5 (10 PC ) plastered stair soffit .
10x3 1.20 Permiter=0.4*2+0.3+0.1=1.20m refer item no. 6.7 on this page
2.79 1 52.52
100.44 m2 (+) 52.52 m2 Total
Column (400X400mm) 6.11 Apply gypsum plaster over
C2,C4 & C6 (10 PC ) plastered concrete surface.
10x3 1.40 Permiter=0.4*3+0.2=1.40m refer item no. 6.6 on this page
2.79 1 1001.39
117.18 m2 (+) 1001.39 m2 Total
Floor Beam & Top Tie Beam
L=19.95*4+12.73*3+11.86*2=141.71
5 141.71 Permiter=0.4+0.25+0.2=0.85m
0.65 141.71
460.56 m2 (+)
Slab & Terrace Concrete ceilling work
884.21 refer item no. 1.1c & d-page.4
884.21 m2
(+)

1001.39 m2 Total area of concrete plastering

6.4 Plastering to stair soffit

5 2.60 B/n Axis 4-5 and C-D

4.04
52.52 m2 Total

6.5 One Coat of Internal wall

Plastering
1073.70 refer item no. 6.1 -page.12&13

1073.70 m2 Total

6.6 Fine coat plastering on concrete


surface.
1001.39 refer item no. 6.3 -above
1001.39 m2 Total

6.7 Fine coat plastering on stair


soffit

52.52 refer item no. 6.4 -above

52.52 m2 Total

TAKE OFF NO. 15


T D S Unit Description T D S Unit Description

Floor & Wall Finishes Reception & Store


6.12 Marble 1 9.30 refer AR Drawing
a) For thread 9.30 m2 (+)
On staircase threads
95 1.30 Second, Third & Fourth Floor
123.50 ml Total Bathrooms and toilets
b) For riser 3x3 3.50 refer AR Drawing
On staircase riser 31.50 m2 (+)
96 1.30 3x3 4.90 refer AR Drawing
124.80 ml Total 44.10 m 2
(+)
c) For landing 504.25 m2 Total ceramic Tile Flooring
On staircase landing
5 2.65 6.14 Terrazzo tile flooring
1.30 Size 300x300x2mm
17.23 m 2
Total Second, Third & Fourth Floor Balcony
d) For skirting for the stair 3x3 3.80 refer AR Drawing
1 5.64 34.20 m2 (+)
5.64 ml (+) 34.20 m 2
Total Terrazzo Tile Flooring
9 4.14
37.26 ml (+) 6.15) 2 cm thick wooden praque
42.90 ml Total tile flooring for bed rooms
Second, Third & Fourth Floor
6.13 Ceramic floor tiles 3x3 19.55 refer AR Drawing
Size 600x600x8mm 175.95 m2 (+)
Ground Floor 3 24.80
Bank 74.40 m2 (+)
1 147.40 refer AR Drawing 3 30.15
147.40 m2 (+) 90.45 m2 (+)
Store 3 31.60
1 27.70 refer AR Drawing 94.80 m2 (+)
27.70 m 2
(+) For Corridor & Lobby
Toilet Lobby 3 16.80
1 9.25 refer AR Drawing 1.40
9.25 m2 (+) 70.56 m2 (+)
Toilet room 3 2.90
1 12.70 refer AR Drawing 2.65
12.70 m2 (+) 23.05 m2 (+)
Veranda 529.22 m 2
Total wooden praque Tile Flooring
1 21.40 refer AR Drawing
21.40 m 2
(+) 6.16) Glazed Ceramic wall tiles
First Floor For Toilet & Bath room
Restaurant 1 1583.64 m2 refer ittem 6.4 & 6.5
1 136.80 refer AR Drawing -1073.70 m2
136.80 m 2
(+) 509.94 m2 Total Ceramic wall tiles
Kitchen
1 38.20 refer AR Drawing
38.20 m2 (+)
Toilet Lobby
1 6.90 refer AR Drawing
6.90 m
2
(+)
Toilet room
1 19.00 refer AR Drawing
19.00 m 2
(+)

TAKE OFF NO. 16


T D S Unit Description T D S Unit Description

7. Glazing 8. Painting
7.1) 4mm thick clear glass