M/S Sabr Infra Developers Private Limited-Patna: Your Bid ID Dated

The document is a Letter of Acceptance from the East Central Railway's Sonpur Division to SABR Infra Developers for a construction project involving a retaining wall and other works at LC No. 5F, with a total contract value of Rs. 81,41,190.32. The contractor is required to submit a Performance Guarantee of Rs. 4,07,059.52 within 21 days and complete the work within 9 months. Failure to comply may result in contract termination and forfeiture of the earnest money deposit.

Uploaded by

sanjithkumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
67 views6 pages

M/S Sabr Infra Developers Private Limited-Patna: Your Bid ID Dated

The document is a Letter of Acceptance from the East Central Railway's Sonpur Division to SABR Infra Developers for a construction project involving a retaining wall and other works at LC No. 5F, with a total contract value of Rs. 81,41,190.32. The contractor is required to submit a Performance Guarantee of Rs. 4,07,059.52 within 21 days and complete the work within 9 months. Failure to comply may result in contract termination and forfeiture of the earnest money deposit.

Uploaded by

sanjithkumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

EAST CENTRAL RLY

SONPUR DIVISION-
ENGINEERING
OFFICE OF DRM
SONPUR, SONPUR,
SARAN
SONPUR, 841101
Bihar, India

Letter No: SONPUR DIVISION-ENGINEERING /


Dated: 07/02/2023
25SEE22-23-04 / 10098880071161

M/s SABR INFRA DEVELOPERS PRIVATE


LIMITED-PATNA
MIG 8M/85, [Link]
Near Balaji Hospital
Patna- 800026
Bihar, India

Sub: Letter Of Acceptance

Ref: 1. Tender No. 25SEE22-23-04 closing date 16-01-2023 13:00


for Construction of retaining wall, Road Cover shed height
gauge and other allied works of LHS at LC No. 5F
including the sump and drainage.
2. Your bid ID 14726673 dated 15/01/2023 12:28

The Competent Authority has accepted your offered rates in


connection with the subject work. The total cost of the work at the
accepted rates works out to Rs. 8141190.32 (Rupees Eighty-One Lakh
Fourty-One Thousand One Hundred And Ninety Rupees And Thirty-Two
Paise Only)

A sum of Rs.0 deposited as Earnest Money vide IREPS reference ID


NIL has been retained towards initial Security Money for due and faithful
fulfillment of the contract, and the balance Security Money will be
recovered from the progressive bills @ 6 % of the bill amount till it
reaches 5 % of the contract value in terms of clause 16 (1) of General
Contract Conditions, April-2022.

You are requested to submit Performance Guarantee in the form as


given in Clause 16 (4) of General Contract Condition, April-2022
equivalent to 5 % of the contract value amounting to Rs. 407059.52
(Rupees Four Lakh Seven Thousand And Fifty-Nine Rupees And Fifty-
Two Paise Only) within 21 days from the date of issue of Letter of
Acceptance, valid up to stipulated date of completion plus 60 days so that
contract agreement can be executed. You are requested to deposit Bank
Guarantee Bond or in any acceptable form issued from SBI any
Nationalized Bank as performance guarantee in the form of as given in
Clause 16 (4) of General Contract Condition, April-2022 equivalent to 5%
of contract value amounting to Rs. 4,07,059.52/- (Four Lakh Seven
Thousand And Fifty-Nine Rupees And Fifty-Two Paise Only) valid up to
Two month beyond the date of completion and you are also requested to
submit Exemption Start Up Earnest Money Rs.1,77,500/- i.e. Total value
Rs. (4,07,060.00 + 1,77,500) i.e. Rs.5,84,560.00/- (Rupees Five lakh
Eighty-Four thousand Five hundred And Sixty only) duly pledge in favour
of FA & CAO/[Link], Hajipur payable at State Bank of India,
Hajipur and attend this office to execute the contract agreement within 21
days from issue of LOA. Extension of time for submission of PG beyond
21 (Twenty one) days and up to 60 days from the date of issue of LOA
may be given by the authority who is competent to sign the contract
agreement. However, a panel interest of 12% per annum shall be charged
for the delay beyond 21 (Twenty one) days, i.e. from 22nd day after the
date of issue of LOA. Further, if the 60th day happens to be a declare
holiday in the concerned office of the Railway, submission of PG can be
accepted on the next working day. In case the contractor fails to submit the
requisite PG within 60 days from the date of issue of LOA, the contract
shall be terminated and contractor shall be debarred from participating in
re-tender for a period of 12 months from the date such banning done on e-
platform ireps.

The entire work shall be completed within 9 month from the date of
issue of Letter of Acceptance. Final date of completion of the work may
be read 06.11.2023.

LEO, EPFO & OTHER REQUISITE LICENSES:: You are requested to


contact respective labour Enforcement office (C) & EPFO and arrange to
obtain Requisite labour license without delay if labour required are more
than twenty in number and submit the same to this office and also intimate
the strength of labour engaged in this work.

FORFEITURE OF EMD:: It may be noted that if you do not act indicated


in Para No.3 above and fail to undertake the contract after acceptance of
tender, the full earnest money will be forfeited.

FORMAL AGREEMENT:: Until a formal contract agreement is prepared


and executed, acceptance latter shall constitute a binding contract.

CONTACT PERSON:: You are requested to contact ADEN/THB for


further necessary action in the regard.

REBATE:: 8.25%.

All Other terms and conditions, as stipulated in the tender documents


shall be applicable.

SHAILESH KUMAR SINHA


DENII
Digitally Signed
View Signature Details

Awarded Quantities And Rates

Item Item Desc Item Item Qty Unit Escl. [Link] Bid Rate/ Bid
Sno. Code Qty Unit Rate(Rs) (%) (Rs) Unit Rate Amount
(Rs)
Schedule A1-All Items of Work provided in the ECRUSSOR -
2012 with upto date corrections as per (Schedule - A),
Annexure ''A-1" attached except item no. 033060, 045010, 3395218.99 0.00 % At Par 3395218.99
081030 & 081360 under chapter- 03, 04 & 08 only. (Item
Directory - ECR-HQ-USSOR-2010-1-Ver-2012)
01 All Items of Work View Details 30.29 3395218.99
provided in the
ECRUSSOR - 2012
with upto date
corrections as per
(Schedule - A),
Annexure ''A-1"
attached except
item no. 033060,
045010, 081030 &
081360 under
chapter- 03, 04 &
08 only.
Schedule Totals 3395218.99
Schedule A2-Items of Work provided in the USSOR - 2012
with upto date corrections as per Annexure ''A-2" attached
1069353.56 0.00 % At Par 1069353.56
for item no. 033060 under chapter-03 only. (Item Directory
- ECR-HQ-USSOR-2010-1-Ver-2012)
Items of Work
provided in the
USSOR - 2012 with
upto date
02 corrections as per View Details 28.51 1069353.56
Annexure ''A-2"
attached for item
no. 033060 under
chapter-03 only.
Schedule Totals 1069353.56
Schedule A3-Items of Work provided in the USSOR - 2012
with upto date corrections as per Annexure ''A-3" attached
for item no. 045010 , 081030 & 081360 under chapter- 04 & 4408659.41 0.00 % At Par 4408659.41
08 only. (Item Directory - ECR-HQ-USSOR-2010-1-Ver-
2012)
Items of Work
provided in the
USSOR - 2012 with
upto date
corrections as per
03 Annexure ''A-3" View Details 29.73 4408659.41
attached for item
no. 045010 ,
081030 & 081360
under chapter- 04
& 08 only.
Schedule Totals 4408659.41
Total Value 8873231.96 8873231.96
Rebate on Total Value
8.25
(%)
Net Bid Value 8141190.32

Item Breakup
A1-All Items of Work provided in the ECRUSSOR - 2012 with upto date corrections as per (Schedule
Schedule - A), Annexure ''A-1" attached except item no. 033060, 045010, 081030 & 081360 under chapter-
03, 04 & 08 only.

All Items of Work provided in the ECRUSSOR - 2012 with upto date corrections as per (Schedule -
Item - 01 A), Annexure ''A-1" attached except item no. 033060, 045010, 081030 & 081360 under chapter-
03, 04 & 08 only.

S No. Item No Description of Item Unit Qty Rate Amount

Earth work in excavation as per approved


drawings and dumping at embankment site
or spoil heap, within railway land, including
50m lead and 1.5m lift, the lead to be
measured from the centre of gravity of
excavation to centre of gravity of spoil
heap: the lift to be measured from natural
ground level and paid for in layers of 1.5m
each, including incidental work, as per
specifications-in

1 011011 All kinds of soils cum 710 93.54 66413.40

Extra over item 011010 for excavation in


foundations for buildings and bridges to
cover dressing to neat dimension and
2 012010 cum 155.5 10.20 1586.10
plumbing sides etc. Note : Dressing under
this item is payable for the total quantity of
excavation in foundation and not partly
3 012050 Supplying and filling sand in plinth and cum 7.5 602.73 4520.48
under floors including watering, ramming,
consolidating and dressing complete

Providing and laying in position cement


concrete of specified proportion excluding
cost of cement, centering and shuttering -
All works upto Plinth level :

[Link] (1 cement : 4 sand : 8 graded stone


4 031013 cum 15.5 2353.89 36485.30
aggregate 40mm nominal size)

Providing and laying in position M 20 Grade


concrete for reinforced concrete structural
elements but excluding cost of centering,
shuttering, reinforcement and Admixtures
in recommended proportion (as per
IS:9103) to accelerate, retard setting of
concrete, improve workability without
impairing strength and durability as per
direction of Engineer in charge

All work upto plinth level, including raft


foundation of washable aprons, HS tank,
5 041011 cum 191 3341.60 638245.60
pile cap, footings of FOB, and Platform
shelter etc.

All work in buildings above plinth level upto


6 041012 cum 40 3619.33 144773.20
floor two level.

Centering and shuttering including


strutting, propping etc. and removal of
form for :

Foundations, footings, bases of columns,


7 042011 raft foundation of washable aprons, Pile Sqm 50 138.30 6915.00
caps, Footings of FOB etc.

Walls (any thickness) including attached


8 042012 plasters, buttresses, plinth and string Sqm 550 227.40 125070.00
courses etc.

Providing, hoisting and fixing in position


upto floor two level M20 Grade precast RCC
work including setting in cement mortar
1:3 (1 cement : 3 coarse sand) and
finishing smooth with 6mm thick cement
plaster 1:3 (1 cement : 3 fine sand) on
exposed surfaces complete including cost
of centering, shuttering, finishing,
Admixtures in recommended proportion (as
per IS:9103) to accelerate, retard setting
of concrete, improve workability without
impairing strength and durability, excluding
cost of cement and steel reinforcement, as
per approved plan & direction of Engineer
incharge.

In slabs for drain covers, manhole covers,


9 043015 cum 11.6 3735.88 43336.21
flue tops etc.

Brick work with non-modular (FPS) bricks


of class designation 7.5 in foundation and
plinth in :

Cement mortar 1:6 (1 cement : 6 coarse


10 051018 cum 8.75 2880.95 25208.31
sand)

Providing hand packed dry flat brick


flooring, class designation 7.5 (FPS Bricks),
excluding pointing with joints filled with
sand over a bed of dry sand (ordinary)of
average thickness 25 mm including
ramming sub grade :

11 091032 Flat brick Sqm 1282.5 237.25 304273.13

Providing ridges or hips of width 60cm


overall width plain G.S. sheet fixed with
polymer coated J or L hooks, bolts and nuts
8mm dia. G.I. limpet and bitumen washers
complete

0.63mm thick with zinc coating not less


12 101042 Metre 120 371.51 44581.20
than 275gm/ sqm

Extra for providing and fixing wind ties of


13 103040 40x6mm flat iron section complete with Metre 180 108.96 19612.80
hooks, nuts, washers etc.

Supplying, fabricating and erecting valley


gutter having 1.00 meter width, made out
of 0.91mm thick aluminum sheets, the
joints shall be made by aluminum welding
to make water tight including supplying
manufacturing and fixing brackets made
14 109150 out of MS flats 50mm x 6mm at the Metre 240 1030.19 247245.60
spacing of 75 cm center to center. The rate
will be including supply of all materials,
labours, tools, plants, equipments,
scaffolding and staging etc. Complete work
shall be carried out as directed by engineer
in charge

Providing and fixing permanently colour


coated trapezoidal profiled sheet of depth
28-30mm at 195-205mm pitch distance
with precisely engineered 'Rib & Flute"
design. Profiled sheets shall be min. 0.5mm
TCT/0.45mm BMT high tensile zinc
aluminium alloy coated zincalume /
galvalume steel sheet (550 mpa yield
strength) having a coating of mass of 150
gsm zinc-aluminium coating AZ-150 total
on both sides as per, AS 1397:1993
15 109200 finished with 20 microns approved colour Sqm 700 713.34 499338.00
coating of Silicon Modified Polyester (SMP)
/ Super Polyester paint coat on exposed
surface over a primer coat of 5 microns and
a back coat of 5 microns on reverse side
over a 5 microns primer coat. There shall
be 2 small ribs/square flutes between
profiles for providing additional strength.
The sheet to be fixed over the purlins with
hexagonal head self drilling suitable
fasteners with neoprene / EPDM washer on
crests of the sheet

12 mm cement plaster 1:3 (1cement:


16 111090 3coarse sand) finished with a floating coat Sqm 5 81.81 409.05
of neat cement

Painting with synthetic enamel paint of


approved brand and manufacture to give
an even shade

17 121051 Two or more coats on new work Sqm 340 49.12 16700.80

Constructing soak pit 1.20x1.20x1.20m


filled with brickbats including S.W. drain
18 143280 pipe 100mm diameter and 1.20m long Each 2 1414.41 2828.82
complete as per standard design including
excavation complete

Drilling of bore well for specified depth in


all types of soil and rock mechanically with
all contractor's tools, plants, material and
labour up to 75 meters

19 171523 For 250 mm dia Metre 45 523.81 23571.45

Providing supplying, lowering and fixing in


bore G.I.B Class perforated casing pipe 6
mm thickness up to specified depth below
ground level with all contractor's tools,
plants, material and labour etc. complete

20 171533 200 mm internal pipe Metre 12.5 1532.95 19161.88

Providing supplying, lowering and fixing in


bore unperforated MS casing pipe 6 mm
thickness up to specified depth below
ground level with all contractor's tools,
plants, material and labour etc. complete

21 171543 200 mm internal pipe Metre 25 1235.18 30879.50

Providing, supplying and fixing mild steel


plug or screw cap of standard make on top
of casing pipe on completed bore as
directed by Engineer-In-Charge

22 171563 200mm dia Each 2 166.37 332.74

Cement concrete Grade M15 of coarse


aggregate 40mm nominal size, in
pavements, laid to required slope and
23 236010 cum 120 2536.71 304405.20
camber in panels as required including
consolidation finishing and tamping
complete

Total 2605893.77

A2-Items of Work provided in the USSOR - 2012 with upto date corrections as per Annexure ''A-2"
Schedule
attached for item no. 033060 under chapter-03 only.

Items of Work provided in the USSOR - 2012 with upto date corrections as per Annexure ''A-2"
Item - 02
attached for item no. 033060 under chapter-03 only.

S No. Item No Description of Item Unit Qty Rate Amount

Supply and using cement at worksite :

1 033063 PPC Tonne 130 6400.90 832117.00

Total 832117.00

A3-Items of Work provided in the USSOR - 2012 with upto date corrections as per Annexure ''A-3"
Schedule
attached for item no. 045010 , 081030 & 081360 under chapter- 04 & 08 only.

Items of Work provided in the USSOR - 2012 with upto date corrections as per Annexure ''A-3"
Item - 03
attached for item no. 045010 , 081030 & 081360 under chapter- 04 & 08 only.

S No. Item No Description of Item Unit Qty Rate Amount

Supplying Reinforcement for R.C.C. work


including straightening, cutting, bending,
placing in position and binding all complete.

1 045016 Thermo-Mechanically Treated bars Kg 26850 64.46 1730751.00

Structural steel work welded in built up


sections, trusses and framed work, girders,
stagings, racks, etc including cutting,
bending, straightening, hoisting, fixing in
position, including applying a priming coat
of approved steel primer, complete - upto
6m height above GL

2 081031 In RSJ, tees, angles and channels Kg 14400 87.27 1256688.00

3 081032 In flats, plates , round or square bars Kg 4000 84.23 336920.00

Providing and fixing M.S. round holding


4 081360 down bolts with nuts and washer plates Kg 1045 70.79 73975.55
complete

Total 3398334.55