JASA PENGAWASAN DAN EVALUASI PEKERJAAN
KONSTRUKSI EPC ISBL OSBL RDMP RU V
BALIKPAPAN
LAPORAN PELAKSANAAN KEGIATAN
Evaluasi Pekerjaan Konstruksi Proyek W1
Maret - Area-Unit (Piperack U-321
R10,R11).pptx W5 April (Tgl 26 April – 30 April ) 2025
FUNGSI CONSTRUCTION BALIKPAPAN
PT. KILANG PERTAMINA BALIKPAPAN
TAHUN 2025
FUNGSI CONSTRUCTION BALIKPAPAN
PT. KILANG PERTAMINA BALIKPAPAN
LAPORAN PELAKSANAAN KEGIATAN PENGAWASAN DAN EVALUASI Sheet 2 of 7
PEKERJAAN KONSTRUKSI PROYEK
TABLE OF CONTENT
I. MONITORING ACTIVITY .................................................................. 3
1. INTERCONNECTING PIPERACK – U321 – R11 .............................................................. 3
II. CONSTRAINT AND EVALUATION OF CONSTRUCTION WORK ... 4
2. Hydrogen manufacturing unit U-321 .......................................................................... 4
III. OTHERS ........................................................................................... 5
IV. CONSTRUCTION PROGRESS MAPPING ....................................... 6
V. DOCUMENTATION........................................................................... 7
This document is the property of PT. Kilang Pertamina Balikpapan who will safeguard its rights according to the civil and penal provisions of the Law.
FUNGSI CONSTRUCTION BALIKPAPAN
PT. KILANG PERTAMINA BALIKPAPAN
LAPORAN PELAKSANAAN KEGIATAN PENGAWASAN DAN EVALUASI Sheet 3 of 7
PEKERJAAN KONSTRUKSI PROYEK
I. MONITORING ACTIVITY
1. INTERCONNECTING PIPERACK – U321 – R11
Following are weekly construction activities in Area/Unit Hydrogen manufacturing unit U-321 :
- Piping Work INTERCONNECTING PIPERACK – U321 – R11
• Closing punchlist
• Pipe support installation
This document is the property of PT. Kilang Pertamina Balikpapan who will safeguard its rights according to the civil and penal provisions of the Law.
FUNGSI CONSTRUCTION BALIKPAPAN
PT. KILANG PERTAMINA BALIKPAPAN
LAPORAN PELAKSANAAN KEGIATAN PENGAWASAN DAN EVALUASI Sheet 4 of 7
PEKERJAAN KONSTRUKSI PROYEK
II. CONSTRAINT AND EVALUATION OF CONSTRUCTION WORK
2. Hydrogen manufacturing unit U-321
Following are weekly construction constraints and evaluation in Area/Unit Hydrogen
manufacturing unit U-321:
- Leak of manpower
This document is the property of PT. Kilang Pertamina Balikpapan who will safeguard its rights according to the civil and penal provisions of the Law.
FUNGSI CONSTRUCTION BALIKPAPAN
PT. KILANG PERTAMINA BALIKPAPAN
LAPORAN PELAKSANAAN KEGIATAN PENGAWASAN DAN EVALUASI Sheet 5 of 7
PEKERJAAN KONSTRUKSI PROYEK
III. OTHERS
1. Deliver Project Monitoring Action Report (PMAR) as follow:
- PMAR No XXXX:
2. Deliver Pengamatan Keselamatan Kerja (PEKA) as follow:
- PEKA:
This document is the property of PT. Kilang Pertamina Balikpapan who will safeguard its rights according to the civil and penal provisions of the Law.
FUNGSI CONSTRUCTION BALIKPAPAN
PT. KILANG PERTAMINA BALIKPAPAN
LAPORAN PELAKSANAAN KEGIATAN PENGAWASAN DAN EVALUASI Sheet 6 of 7
PEKERJAAN KONSTRUKSI PROYEK
IV. CONSTRUCTION PROGRESS MAPPING
Construction Progress Mapping can be found in Appendix A
This document is the property of PT. Kilang Pertamina Balikpapan who will safeguard its rights according to the civil and penal provisions of the Law.
FUNGSI CONSTRUCTION BALIKPAPAN
PT. KILANG PERTAMINA BALIKPAPAN
LAPORAN PELAKSANAAN KEGIATAN PENGAWASAN DAN EVALUASI Sheet 7 of 7
PEKERJAAN KONSTRUKSI PROYEK
V. DOCUMENTATION
Documentation can be found in Appendix B