Pipeline Design for Oil and Gas Transport
Pipeline Design for Oil and Gas Transport
1
NATIONAL POLYTECHNIC SCHOOL
OIL PIPELINES AND MULTI-PRODUCT PIPELINES
Content
OBJECTIVES ............................................................................................................ 4
INTRODUCTION .................................................................................................... 5
CHAPTER 1 ........................................................................................................... 6
THE FOUNDATIONS FOR PIPELINE DESIGNS ............................... 6
KEY PARAMETERS FOR PIPELINE DESIGN ...................... 6
CHARACTERISTICS OF THE PIPE ............................................................ 7
PHYSICAL PROPERTIES OF THE FLUIDO ......................................................... 11
RELATIONSHIP BETWEEN THE PIPE AND THE FLUID............................................ 14
DISTANCE BETWEEN PUMPING STATIONS .............................. 16
PUMPS AND PUMP STATIONS ............................... 16
PIPELINES WITH MULTISTATIONS ................................................... 17
USE OF MAXIMUM OPERATING PRESSUREN ........................................ 17
EFFECT OF PUMPING OPERATION ON THE HYDRAULIC PROFILEO . 17
THE HYDRAULIC GRADIENT BETWEEN STATIONS ................................. 18
CHAPTER 2 ......................................................................................................... 20
DUCT CLASSIFICATION.......................................................................... 20
GAS PIPELINE.- .............................................................................................. 20
OIL PIPELINEO .20
POLYDUCT
ASPECTS TO FOLLOW FOR THE DESIGN AND SELECTION OF MATERIALS
FROM THE PIPES:............................................................................................. 21
CONSTRUCTION PROCEDURE:........................................................ 21
EQUIPMENT AND MACHINERY CERTIFICATES. ............................................ 22
LASTRADO .................................................................................................... 22
OPENING OF THE RIGHT OF WAY............................................................. 23
TRENCH EXCAVATION......................................................................... 24
LAYING OF THE PIPE WITH OVERLAP ............................................... 25
BENT AND ALIGNED................................................................................ 25
CAMP WELDINGSO ........................................................................... 26
DIELECTRIC TEST FOR THE COATING ................................. 27
LOWERED AND COVERED FROM THE DITCH............................................................... 27
2
NATIONAL POLYTECHNIC SCHOOL
Pipelines and Multiducts
TIES
HYDROSTATIC TEST .............................................................. 28
INTERIOR CLEANING ..................................................................................... 29
SIGNAGE ............................................................................................. 30
SPECIAL WORKSS .................................................................................... 30
CROSSING WITH BODIES OF WATER .............................................................. 30
DEVIL'S TRAPSS ................................................................................ 31
BIBLIOGRAPHY ..................................................................................................... 32
3
NATIONAL POLYTECHNIC SCHOOL
Pipelines and Multiproduct Pipelines
OBJECTIVES
After this section, you will be able to achieve the following objectives:
• Recognize the three physical characteristics of pipes that affect the design of
pipelines.
Identify the definition of the friction factor, f.
Recognize how the six physical properties of a liquid affect the design of
pipelines.
Identify the variables used to calculate the Reynolds Number, Re
Determine the necessary foundations for the construction of oil pipelines and multiproduct pipelines.
4
NATIONAL POLYTECHNIC SCHOOL
OIL PIPELINES AND MULTI-PRODUCT PIPELINES
INTRODUCTION
The transportation of hydrocarbons represents a fundamental axis in the world
highly competitive modern; therefore the operations scheduling of
provision, refining, storage, and transportation of petroleum products
it is an extremely complex and essential task to achieve an adequate
coordination between the links in the fuel supply chain.
From raw materials, crude or varieties of oil obtained in vast
regions of the planet, up to refined fuels with their different grades of
quality, and the products of this sophisticated value chain travel thousands of
kilometers starting from its origin until reaching its final destination.
Both oil pipelines and multiproduct pipelines represent the most reliable means,
economical and safe to transport large volumes of material over
extensive distances.
5
NATIONAL POLYTECHNIC SCHOOL
OIL PIPELINES AND MULTI-PRODUCT PIPELINES
CHAPTER 1
6
NATIONAL POLYTECHNIC SCHOOL
OIL PIPELINES AND MULTI-PRODUCT PIPELINES
The physical characteristics of the pipe affect the way a fluid behaves.
It will behave in a pipeline. Specifically, there are three parameters that must be
consider in the design:
Internal diameter of the pipe (D).
Length of the pipe (L).
Relative roughness of the internal surface of the pipe wall (e).
7
NATIONAL POLYTECHNIC SCHOOL
OIL PIPELINES AND POLYDUCTS
8
NATIONAL POLYTECHNIC SCHOOL
Pipelines and Polyducts
Moody diagrams, which relate the friction factor, f, with the two
dimensionless parameters, the Reynolds number, Re, and the relative roughness of
the internal wall of the pipe, e/D. The friction factors are usually
selected from a graph similar to that shown in Figure 5.
9
NATIONAL POLYTECHNIC SCHOOL
OIL PIPES AND MULTI-PIPES
The relative roughness of the pipe's inner wall is the ratio of the
absolute roughness, e, and the internal diameter, D, of the pipe. Figure 6 illustrates the
relative roughness.
10
NATIONAL POLYTECHNIC SCHOOL
Pipelines and multiproduct pipelines
Along with the characteristics of the pipe, the physical properties of the fluid.
Transported through the pipeline affects the design of the pipeline. There are six
properties of the liquid that must be recognized:
Viscosity
Density or specific gravity
Vapor pressure
Fluency point
Compressibility and
Temperature
VISCOSITY
11
NATIONAL POLYTECHNIC SCHOOL
Oil pipelines and multi-product pipelines
Vapor Pressure
The vapor pressure is the pressure above which the liquid no longer
it evaporates at a given temperature. Vapor pressure is a criterion
especially important when handling liquids that contain
volatile components. An example of a liquid with high volatility is gas
natural liquid (the volatile components are those that evaporate)
quickly). The minimum pressure in a pipeline must be sufficiently high
to keep light crude oils in their liquid state.
Figure 8. A high vapor pressure increases the minimum allowed value in the
pipe pressure
POINT OF FLUIDITY
The fluidity point is defined as the lowest temperature at which a liquid becomes
it will turn or flow when it has cooled. Although there are raw materials that can be
pumped at temperatures below their flow points, more is required
energy to do that. Thus, the fluidity point is an important parameter for
consider not only in the design but also in the operation of a liquid in the
pipeline
12
NATIONAL POLYTECHNIC SCHOOL
PIPELINES AND POLYDUCTS
Compressibility
It is the degree to which the volume of the fluid changes with a change in pressure.
the pump increases the pressure in the pipeline causing the volume of the liquid
decrease or compress. The amount of compression is directly
related to the pressure and molecular composition of the liquid. When the
pressure decreases as the liquid flows down the pipe and
away from the bomb, the liquid returns to its original volume. A liquid
more comprehensible like LPG does not respond to pressure changes as quickly
as one less comprehensible than crude. Figure 10 illustrates how a liquid
more understandable as LPG slows the rate at which an increase of
pressure goes down in the pipeline.
Figure 10. LPG reduces its volume while the pressure increases a fluid
more comprehensible like the LPG will not respond to pressure changes as quickly
as a less comprehensible one like crude.
TEMPERATURE
13
NATIONAL POLYTECHNIC SCHOOL
Pipelines and Multi-Pipelines
Figure 11. As the temperature increases, the viscosity of the oil decreases.
flows more easily at higher temperatures and has a lower pressure drop
by friction.
The characteristics of the pipe and the fluid moving through it are
interdependent. The diameter of the pipe, the viscosity of the liquid and the
flow velocity combines to affect the flow. The type of flow is determined
through the Reynolds Number, using the formula:
∗
=
Where:
Re = Reynolds number
D = internal diameter of the pipe [ft]
flow velocity [ft/sec]
µ=viscosity [ft2/sec]
The interdependence between the pipe diameter, the viscosity of the liquid and the
flow velocity is defined by a mathematical relationship called the number
of Reynolds,(Re).
14
NATIONAL POLYTECHNIC SCHOOL
OIL PIPES AND POLY PIPES
Figure 12. The Reynolds number varies with diameter, velocity, and
viscosity
2213 * Q 13920 * Q
= =
∗ ∗
Where:
Re= Reynolds number
Q = flow rate [Bls/h] or [m3/h]
D = internal diameter of the pipe [ft]
μ=viscosity [ft2/sec]
15
NATIONAL POLYTECHNIC SCHOOL
Pipelines and Multipipes
16
NATIONAL POLYTECHNIC SCHOOL
PIPELINES AND POLYDUCTS
The pumps will be integrated into the system to maintain the desired flow rate and
allow future expansions. Since the economic aspect plays a role
important in the design and operations of the pipeline, a combination of
theoretical design and economic evaluation must be taken into account for the
different operating conditions.
With large pipelines, it is common to have more than one pumping station to
transport the liquid over a great distance and different elevations. The
pumping stations are generally located at evenly spaced intervals
as the variations in the terrain allow it. The difference in elevations between
the stations will determine more precisely the actual location of the
pumping stations as long as these height differences have a
greater impact on pump performance. The difference in elevation between the
stations can help or hinder that performance. Two should be considered.
important aspects when establishing the distance between pumping stations, the
CNPS required by the pumps and the pipeline MPO.
17
NATIONAL POLYTECHNIC SCHOOL
Pipelines and multiproduct pipelines
The hydraulic gradient is the line on the total energy diagram that shows the
sum of the head height and the static head at any point in the
pipeline. The slope of the hydraulic gradient represents the rate at which the
the fluid head is lost due to friction.
Consider the simple example of a tank with a nozzle and an extension in the
base of the tank as shown in Figure 15.
The hydraulic gradient is the graphical representation of the pressure of the line between
the tank and the end of the nozzle extension (Figure 15). The total head of the
liquid, at any moment, has three components: static head, head
of speed, and lifting head.
18
NATIONAL POLYTECHNIC SCHOOL
Pipelines and Multiline Pipelines
Consider a series of three tanks arranged in a row as shown in Figure 16. The
the objective is to transfer the liquid stored in the first tank, A, to the second
tank B, and finally to the last tank, C.
A straight line is then drawn between the discharge head at a station and
the suction head at the next station for the entire length of the pipeline,
as shown in Figure 17.
The hydraulic gradient is drawn between the discharge head of the pump and the
suction head of the next downstream station.
19
NATIONAL POLYTECHNIC SCHOOL
Pipelines and Polyducts
CHAPTER 2
CLASSIFICATION OF DUCTS
GAS PIPELINE.
OIL PIPELINE
The term pipeline refers to the pipe and related facilities used for the
transport of oil, its derivatives and biobutanol over long distances. The
the exception is natural gas, which, despite being derived from petroleum, is
gas pipelines are named for their pipes because they are in a gaseous state at temperature
environment.
20
NATIONAL POLYTECHNIC SCHOOL
OLEDPIPES AND POLYDUCTS
Pipelines
It is the duct for the transport of products derived from crude oil from the
charging point to a terminal that includes the facilities and equipment
necessary for such transport.
Construction: for the specific case of transporting distilled products from
oil.
CONSTRUCTION PROCEDURE:
21
NATIONAL POLYTECHNIC SCHOOL
OIL PIPES AND MULTI-PIPES
Whoever carries out the work must deliver a quality certificate and the supervisor must
to know the construction rules and specifications as well as:
The valid calibration certificates for the equipment and machinery must be held.
that requires only calibration, and will have to be issued by a
accredited certification company.
LASTRADO
In case the duct crosses rivers, swamps, lakes, etc., it must be ballasted.
achieve with the placement of concrete ballast, with a minimum thickness of 25mm.
Connections and branches: They are made using welded 'tees' and 'crosses'.
22
NATIONAL POLYTECHNIC SCHOOL
Pipelines and multipurpose pipelines
23
NATIONAL POLYTECHNIC SCHOOL
PIPELINES AND MULTI-PRODUCT PIPELINES
The separation between ducts in the same trench must be at least 1 meter and in
different ditch must be 2m.
Ditch Excavation
A trench must be dug so that the duct is not exposed to the elements, the trench
where the pipe will be housed must have the indicated depth and width
in the Project according to its diameter.
The depth at which the duct will be buried will depend on the type of terrain.
in such a way that there is a layer of soil over the pipe from 60 cm;
minimum in rocky or desert terrain, of 1.25 m; in irrigated lands
channels and 60 cm in other types; the width will be 30 cm more than the diameter
the exterior of our pipe; the mattress should be made of a soft material, if it
find in a rocky terrain, increasing the depth of the trench by 10 cm.
24
NATIONAL POLYTECHNIC SCHOOL
OIL PIPELINES AND POLYDUCTS
The bends of the tubes must be made without altering the dimensions of the section.
the cross-section of the straight tube must be free of wrinkles, cracks, or others
evidence of mechanical damage. Bends must be made with machines
special bending machines suitable for the diameter of the tube; it is not allowed to
heating of the tubes to be bent.
Before aligning the sections, they must be inspected and cleaned if they are stitched.
longitudinal, overlapping its seam within 30° on each side of the vertical axis. The
required direction changes to adhere to the outline of the trench may
to be performed by bending the duct according to the minimum radii indicated in the
next table:
25
NATIONAL POLYTECHNIC SCHOOL
OIL PIPELINES AND MULTI-PRODUCT PIPELINES
FIELD WELDINGS
The electrodes used must be in accordance with what is described in the specification.
of welding procedure and comply with what is established. The application of the
welding should be protected from weather conditions (rain, wind,
dust, humidity, among others) that may harm it.
All field duct welds both in regular line and in construction work
specials and ties must be x-rayed at 100% with a radiation source
according to the thickness and with the simple wall inspection technique, in ducts
from 12" to 60" in diameter.
The double wall inspection technique should only be performed when due to the
diameter or any obstruction makes it impossible to apply the simple wall for
obtain radiographs that meet the acceptance requirements for
non-bitter service described in API 1104 or equivalent, according to the thickness
and as indicated below:
26
NATIONAL POLYTECHNIC SCHOOL
OLEOHOUSES AND POLYPIPELINES
THICKNESS IN FONT DE
STEEL RADIATION
1 to 50 mm X-rays
19 to 80 mm Iridium 192
38 to 150 mm Cobalt 60
The thickness refers to the total thickness of the duct wall that is in contact with
the radiographic plate in single wall or double wall.
The dielectric detector will have to be run along the entire duct, this will be at
lift the pipe from its supports for the trench down, being careful
especially when passing through the points where it was supported, this
dielectric test must present, among other properties, resistance to
humidity, to the operating temperature and to the aggressive conditions of the soil.
The excavation product will have to be returned to the trench, eliminating everything.
anything that can damage the coating, so that after the
settlement, the ground surface should not have depressions and protrusions in the area
from the trench or that the pile of earth on the side interferes with any eventual traffic
It's normal in the place. Care must be taken not to damage the coating.
anticorrosive during the lowering and filling of the trench.
After filling the trench, the final surface of the right-of-way must be prepared.
27
NATIONAL POLYTECHNIC SCHOOL
OIL PIPELINES AND POLYDUCTS
by way, for the free movement of the equipment and the maintenance of the duct.
DRAWS
HYDROSTATIC TEST
Raw water or treated water at room temperature should be used, clean and free.
of suspended matter. Under no circumstances should the water temperature be
less than 289 K (16° C) and not greater than 323 K (50°C). When the temperature
if the environment is below 273 K (0° C), precautions must be taken due to
when the freezing point of water is reached. When river water is used or
lake, precautions must be taken to prevent microorganisms that
could contain, cause pollution or favor mechanisms of
microbial corrosion.
All the air inside the pipe, equipment, and components must be removed.
test, evicting it from the highest points of the circuit and increasing the
slowly press to avoid sudden increases.
28
NATIONAL POLYTECHNIC SCHOOL
OIL PIPELINES AND POLYDUCTS
Once the test is completed, the file must be integrated along with the documentation.
probationary, where the complete data of the equipment or system must appear
tested, certificates from both measuring devices, the manometric graphs and
at a minimum the following information:
INTERIOR CLEANING
The interior cleaning of the duct is carried out to displace the test water.
hydrostatics, also for periodic cleaning according to programs for
remove condensates in gas pipelines, or residues in liquid products for
increase the efficiency of transportation.
29
NATIONAL POLYTECHNIC SCHOOL
OIL PIPELINES AND MULTI-PIPELINES
SIGNAGE
SPECIAL WORKS
The contractor is responsible for not interrupting vehicle traffic or the flow.
of rivers during the construction of special works, as well as take the
necessary measures in each case.
In addition to taking into account what is established by this standard for special works,
the possibility of lining the duct internally at the crossings should be considered,
yes, due to the conditions of the fluid to be handled, this is required.
The construction of supports and anchors in surface areas must comply with
the specified in the design.
The continuity of the construction of the duct should not be interrupted when crossing.
with small channels, streams, or narrow and shallow ravines that
allow the duct, by its own resistance, to cross the obstacle without requiring
supports, and as long as there is no danger that the pipe will be reached by the
current or debris accumulates, or that the slopes of the support banks
consist of soft material that is unable to support the weight of the duct and is
subject to landslides and erosion.
30
NATIONAL POLYTECHNIC SCHOOL
OIL PIPELINES AND POLYDUCTS
DEVIL TRAPS
The 'devil' trap and its components must be installed according to the project and
test at the same pressure limits as the main duct. The duct of
the venting of gaseous hydrocarbons should be released in a wide area
such that it prevents harm to third parties and the environment.
It must be verified that the floor where the devil's trap will be placed is
without height differences greater than ±5 cm, also, that before placing the trap, the
concrete foundation has already set according to practices
recommended for concrete structures and that all have been followed
construction procedures for civil works. Records must be maintained of
all tests conducted on the devil's trap.
The pipeline, the right-of-way, the safety systems and devices, the
signage and surface installations must be considered in the
preventive maintenance tasks, defined after prior evaluation of
engineering
DEFINITION OF DEVIL
The demons are devices or artifacts that are inserted into the pipes.
hydrocarbon carriers, travel along the entire length of these driven
through the product flow; for inspection, maintenance, or cleaning of the
31
NATIONAL POLYTECHNIC SCHOOL
Pipelines and multiproduct pipelines
same pipe.
BIBLIOGRAPHY
,
32