MTS Discrete Manufacturing
MTS Discrete Manufacturing
Table of Contents
1 Purpose
2 Prerequisites
2.1 System Access
2.2 Roles
2.3 Master Data, Organizational Data, and Other Data
2.4 Business Conditions
2.5 Preliminary Steps
2.5.1 Manufacturing Bill of Material – Mass Change (Optional)
2.5.2 Create Production Version for Master Data used in 1ZI (Optional)
2.5.3 Create Initial Material Stock
3 Overview Table
4 Test Procedures
4.1 Anonymous Forecast and MRP
4.1.1 Create Planned Independent Requirements
4.1.2 Material Requirements Planning at Plant Level
4.1.3 Evaluate Stock/Requirements Situation
4.2 Production Order Convertion and Available-to-promise Check
4.2.1 Conversion to Production Orders for Subassembly and Final Assembly
4.2.2 Review Material Availability Status for Production Orders
4.3 Production Order Processing for Subassembly
4.3.1 Material Staging for Subassembly
4.3.2 Release Production Order for Subassembly
4.3.3 Confirm Production Operations for Subassembly
4.3.4 Post Goods Receipt for Subassembly Production Order
4.4 Production Order Processing for Final Assembly
4.4.1 Material Staging for Final Assembly
4.4.2 Release Production Order for Final Assembly
4.4.3 Check Serial Numbers
4.4.4 Pick Components for Final Assembly
4.4.5 Confirm Production Operations for Final Assembly
4.4.6 Review Production Order
4.4.7 Final Confirmation of Production Operations for Final Assembly
4.4.8 Post Goods Receipt for Final Assembly Production Order
4.4.9 Preview Goods Receipt Slip and Label (Optional)
4.5 Review Scrap Report
4.6 Review Manufacturing Object Pages
5 Appendix
5.1 Succeeding Processes
This scope item enables production planning in make-to-stock scenarios for a serial number managed finished good.
The process starts with the creation of a demand forecast for finished goods represented by Planned Independent Requirements (PIRs). Based on PIRs, Mate-
rial Requirements Planning (MRP) creates a production plan for finished goods and explodes the entire bill of material structure. As a result, semifinished
component production and raw material demand is planned. Production planners can analyze and manually change the planned order based production plan.
Raw material demand leads to purchase requisitions that trigger alternative procurement scenarios referenced in this scope item.
The production process itself is entirely covered by using the conversion of planned into production orders, order release, material staging and picking, con-
firmation of order operations, and goods receipt posting. Order-based target and actual cost is created, ensuring fully integrated material and value streams.
This document provides a detailed procedure for testing this scope item after solution activation, reflecting the predefined scope of the solution. Each
process step, report, or item is covered in its own section, providing the system interactions (test steps) in a table view. Steps that are not in scope of the
process but are needed for testing are marked accordingly. Project-specific steps must be added.
This section summarizes all the prerequisites for conducting the test in terms of systems, users, master data, organizational data, other test data and busi-
ness conditions.
Sys- Details
tem
Sys- Accessible via SAP Fiori launchpad. Your system administrator provides you with the URL to access the various
tem apps assigned to your role.
2.2 Roles
Assign the following business roles to your individual test users.
Note The following roles are provided as example roles from SAP. You can use these as templates to create your own roles.
For more information about business roles, refer to Assigning business roles to a user in the Administration Guide to Implementation of SAP S/4HANA with
SAP Best Practices.
Make-to-Stock Production - Discrete Manufacturing (BJ5_IN) PUBLIC
Purpose Error: Reference source not found 4
2.3 Master Data, Organizational Data, and Other Data
The organizational structure and master data of your company has been created in your system during activation. The organizational structure reflects the
structure of your company. The master data represents materials, customers, and vendors, for example, depending on the operational focus of your com-
pany.
Use your own master data or the following sample data to go through the test procedure.
For more information on creating master data objects, see the following Master Data Scripts (MDS)
Table 1: Master Data Script Reference
Master Description
Data ID
BNR Create Raw Material ("ROH")
BNZ - Create New Open You have completed the step described in the Create New Open MM Posting Period (BNZ) master data script. Posting Period is
MM Posting Period up to date.
1R5 - Engineering Bill of The test script 1R5 describes the controlled mass change and replacement process for one or more Engineering Bill of Material
Material - Mass Change (EBOM). This process is also valid to change a Manufacturing Bill of Material (MBOM). A MBOM created in 1ZI can be used as a
(Optional) reference to change a Manufacturing BOM.
Context
After you have implemented Handover of Engineering Bill of Material to Manufacturing (1ZI), you can use the generated Manufacturing BOM for testing the
replace material functionality for Manufacturing BOM. To display the list of all manufacturing BOMs for the specified material, make the entry BOM Usage: 1.
Procedure
Context
If you want to execute this test script as a succeeding process after completing activities in test script Handover of Engineering Bill of Material to Manufactur-
ing (1ZI), and want to use the Manufacturing BOM created in 1ZI, you should create a Production Version for Master Data used in 1ZI. Otherwise, you should
skip this step.
Procedure
2 Access the app Open Manage Production Versions. The Production Version: Mass Pro-
cessing screen appears.
3 Enter Plant and Material On the Production Version: Mass Processing screen, make
the following entries and choose Enter:
Example
Plant: 1810
Material: FG126
4 Create a Production Choose the Create Production Version icon. The Maintain Production Version: Detail
Version Screen dialog box appears.
5 Enter the production In the Maintain Production Version: Detail Screen dialog box,
version details make the following entries:
Material: FG126
Production Version: Select a production version that doesn't
exist already.
Short Text for Production Version: FIN126, MTS-DI, PD,
Batch- Fifo, Serial No
6 Enter the task list de- In the Task Listt section, in the Detailed planning - Group The values in Task List Type, Group
tails field, use the value help and proceed as follows: and Group Counter are populated.
1. In the Restrict Value Range dialogue box, choose C:
Search using material.
2. Make the following entries:
• Material: FG126
• Plant: 1810
3. Choose Find.
4. Select one entry.
5. Choose the Copy (Enter) icon.
7 Enter the bill of mater- In the Bill of Material section, in the Alternative BOM field, The values in Alternative BOM and
ial details use value help and proceed as follows: BOM Usage are populated.
1. In the Alternative BOM 1 Entry dialog box, select one
entry which is created in 1ZI.
2. Choose the Copy (Enter) icon.
8 Check the Production In the Maintain Production Version: Detail Screen dialog box, The Maintain Production Version: Detail
Version choose Check. Screen dialog box appears.
9 Check and close the In the Maintain Production Version: Detail Screen dialog box, No error messages exist.
consistency check log check the following entries:
Task list exists
BOM exists
No error messages exist.
10 Save the production In the Maintain Production Version: Detail Screen dialog box, The Maintain Production Version: Detail
version details choose Save Changes and Close Screen. Screen dialog box appears.
11 Save the Production On the Production Version: Mass Processing screen, choose The system saves the production ver-
Result
Context
In a real business case, the materials are usually purchased from external suppliers in that case, process is covered by the standard purchasing or subcon-
tracting processes. For the purpose of this test, we post initial stock directly to the storage locations.
Procedure
2 Access the App Open Post Goods Movement. The Post Goods Movement screen displays.
4 Specify Mater- Make the following entries: For a detailed materials list, see the Bill of Materials structure list in the Mas-
6 Post Choose Post. Material document XXX posted and materials are available in stock.
We recommend that you check the stock for SG124 and FG126. To check, log onto the SAP Fiori launchpad as a Production Planner and open Check Material
Coverage. If there is sufficient stock, remove some stock; otherwise, no plan orders are generated later. After removing some stock, run the test again.
You can either post initial stock directly to the storage location or refer to the Procurement of Direct Materials (J45) or Scheduling Agreements in Procurement
(BMR) test scripts.
This scope item consists of several process steps provided in the table below.
Material Requirements Planning at Plant Level Production Planner Schedule MRP Runs The Application Jobs screen dis-
[page ] 16 plays.
Evaluate Stock/Requirements Situation [page ] Production Planner Monitor Material Coverage Net/ The Monitor Material Coverage
18 Individual Segments screen displays.
Conversion to Production Orders for Sub- Production Planner Check Material Coverage The Manage Material Coverage
assembly and Final Assembly [page ] 20 screen displays.
Review Material Availability Status for Production Production Supervisor – Dis- Manage Production Orders The Manage Production Orders
Orders [page ] 22 crete Manufacturing screen displays.
Material Staging for Subassembly [page ] 24 Production Operator – Dis- Stage Materials for Production The Material Staging for Planned
crete Manufacturing Orders screen displays.
Release Production Order for Subassembly Production Supervisor – Dis- Manage Production Orders The Manage Production Orders
[page ] 26 crete Manufacturing screen displays.
Confirm Production Operations for Subassembly Production Operator – Dis- Confirm Production Operation The Peform Work screen displays.
[page ] 28 crete Manufacturing
Post Goods Receipt for Subassembly Production Warehouse Clerk Post Goods Movement The Post Goods Movement screen
Order [page ] 30 displays.
Material Staging for Final Assembly [page ] 32 Production Operator – Dis- Stage Materials for Production The Material Staging for Planned
crete Manufacturing Orders screen displays.
Release Production Order for Final Assembly Production Supervisor – Dis- Manage Production Orders The Manage Production Orders
[page ] 34 crete Manufacturing screen displays.
Check Serial Numbers [page ] 36 Production Operator – Dis- Display Production Order The Production Order Display: Ini-
crete Manufacturing tial screen displays.
Pick Components for Final Assembly [page ] 37 Production Operator – Dis- Pick Components for Production The Picking List: Initial Screen dis-
crete Manufacturing Orders plays.
Make-to-Stock Production - Discrete Manufacturing (BJ5_IN) PUBLIC
Purpose Error: Reference source not found 13
Process Step Business Role Transaction/App Expected Results
Confirm Production Operations for Final As- Production Operator – Dis- Confirm Production Operation The Perform Work screen displays.
sembly [page ] 39 crete Manufacturing
Review Production Order [page ] 41 Production Supervisor – Dis- Manage Production Orders The Manage Production Opera-
crete Manufacturing tions screen displays.
Final Confirmation of Production Operations for Production Operator – Dis- Confirm Production Operation The Perform Work screen displays.
Final Assembly [page ] 43 crete Manufacturing
Post Goods Receipt for Final Assembly Production Warehouse Clerk Post Goods Movement The Post Goods Movement screen
Order [page ] 44 displays.
Preview Goods Receipt Slip and Label (Optional) Warehouse Clerk Material Documents Overview The Material Document screen dis-
[page ] 46 plays.
Review Scrap Report [page ] 48 Production Supervisor – Dis- Material Scrap Maximum Devi- Material scrap report displays.
crete Manufacturing ation
Review Manufacturing Object Pages [page ] 49 Any role for production listed Search function The list of search result displays.
in chapter Roles
This section describes test procedures for each process step that belongs to this scope item.
Test Administration
Business
Role(s)
Responsibil- <State the Service Provider, Customer or Joint Service Provider and Customer> Duration Enter a duration.
ity
Context
Planned independent requirements are used to perform demand management functions. A planned independent requirement contains one planned quantity
and one date, or a number of planned independent requirements schedule lines, such as one planned quantity split over time according to dates.
Note Instead of creating a single requirement, sometimes a requirements plan that includes one or more planned independent requirements can be main-
tained for mass processing. In this case, the requirements are grouped and maintained under a requirement plan number.
2 Access the Open Manage PIRs. The Manage PIRs screen displays.
App
3 Check Default On the Manage PIRs, click your If there is no entry Plant 1 IN in the Area of Responsibility screen, choose Add
Area of Re- user name and choose icon to select it and then choose OK. For other plant entries in the Area of Responsibil-
sponsibility Area of Responsibility. ity screen, choose Delete to remove the others and then choose OK.
Check only this entry is dis-
played there: Plant 1 IN
6 Select Mater- Choose the material item to dis- The Manage PIRs view displays.
ial Item play the Draft PIRs field.
8 Save PIRs Choose Save Draft (bottom The PIRs Draft is saved.
draft right).
9 Release PIRs Choose Release PIRs (bottom The PIRs are released.
right).
Test Administration
Business
Role(s)
Responsibil- <State the Service Provider, Customer or Joint Service Provider and Customer> Duration Enter a duration.
ity
Context
The aim of material requirement planning is to tailor available capacities and receipts on time to suit requirement quantities. You can use MRP or consump-
tion-based planning for this purpose. Single-item multi-level requirement planning is performed for plant 1810.
Prerequisite
The finished product for MTS (FG126) is planned at plant level. There is now a requirement for the material Finished Product MTS (FG126) in plant 1810.
Procedure
2 Access the App Open Schedule MRP Runs. The Application Jobs screen displays.
5 Schedule New Job In the New Job screen, choose Schedule (bottom right The new job was created and will display in
section). the table of Application Jobs.
6 Refresh Application Jobs To check the status of the job you created, choose Go The Application Jobs table is refreshed.
List at the top right section of the screen.
Test Administration
Business
Role(s)
Context
After the requirement planning has been performed, you want to display the stock/requirements situation for the Finished Good MTS (FG126) in the stock/re-
quirements list.
Prerequisite
Procedure
2 Access the Open Monitor Material Coverage Net/Individual Segments. The Monitor Material Coverage
App screen displays.
3 Select Ma- Mark the checkbox for the following materials, and then choose Manage Materials (bot- The Material screen and Mater-
terial tom right). ial Details screen display.
Material: FG126
Material: SG124
4 Review Select the corresponding material on theMaterial screen on the left. The detailed Stock/Require-
Stock/Re- ments List for each material
quirements displays.
List
5 Display From the list on the Material screen on your left, select the material for which you want The selected planned order
Make-to-Stock Production - Discrete Manufacturing (BJ5_IN) PUBLIC
Purpose Error: Reference source not found 19
Test Test Step Instruction Expected Result Pass /
Ste Name Fail /
p# Com-
ment
Planned Or- to check the planned order. displays on the screen.
der Material: FG126 If there is no shortage for
Material: SG124 those materials, the planned
order will not be generated.
On the Material Details screen, click the PldOrd XXXX in column MRP Element.
If you want to display more in-
Note The BOM explosion during the MRP run has generated dependent requirements for formation about the planned
the demand-driven planned components. If inventory does not cover the requirements, order, on the right bottom of
planned orders are created for in-house-produced materials and purchase requisitions this pop-up, choose Open
for externally procured materials. To continue processing externally procured materials, Planned Order.
please execute test script J45(Procurement of Direct Materials) or BMR(Scheduling
Agreements in Procurement) depends on the element created in MRP run.
Test Administration
Business
Role(s)
Responsibil- <State the Service Provider, Customer or Joint Service Provider and Customer> Duration Enter a duration.
ity
The daily MRP run creates planned orders for goods that are to be produced internally. When the planned opening date is reached, the planned orders are
converted to production orders for both semifinished goods and finished goods.
Prerequisite
The MRP run has generated planned orders for material Subassembly (SG124) and Final Assembly (FG126).
Procedure
2 Access the App Open Check Material Coverage. The Find Material screen displays.
3 Select Material Enter Material number and select Plant and Manage Material Coverage screen display.
Shortage Definition. Then click OK button.
Material:FG126
Plant:1810
Shortage Definition:: MRP Standard
4 Find Planned Or- Click the generated planned order Order Information displays
der If no planned orders were generated, there is sufficient stock
for material FG126. Try removing some stock and begin the test
from the beginning to create PIRs and run MRP.
5 Convert Planned Choose Change Orderon the PldOrddialog The production order is created.
Order to Produc- box, choose Convert to Production Order, and
tion Order confirm End Date and Quantity.
Repeat step#2 to #5 for SG124
Test Administration
Business
Role(s)
Responsibil- <State the Service Provider, Customer or Joint Service Provider and Customer> Duration Enter a duration.
ity
Prerequisite
Procedure
2 Access the Choose Home on top of the screen to open All My Apps The Manage Production Ordersscreen displays.
App list.
In the App list, choose Production Control (Discrete) -
Order Management and then
Choose Manage Production Orders.
Make-to-Stock Production - Discrete Manufacturing (BJ5_IN) PUBLIC
Purpose Error: Reference source not found 22
Test Test Step Instruction Expected Result Pass /
Ste Name Fail /
p# Com-
ment
3 Check De- On the Manage Production Orders screen, make the fol- If no entry Plant 1 1810 in the Area of Responsibility(Super-
fault Area of lowing entries: visor) screen, choose Add to select it and then choose OK .
Responsibil- To check Default Area of Responsibility (supervisor), For other plant entries in the Area of Responsibility (Super-
ity(supervi- select the user (from the top left corner): App Settings visor) screen, choose Delete to remove the others and then
osr) > Area of Responsibility Production Supervisor. Check choose OK.
only this entry is displayed:
Plant 1 1810
MTS DI – Valuated (YB1)
4 Select Pro- On the Manage Production Orders screen, enter the fol- The Manage Production Orders screen displays.
duction Or- lowing search condition as filter.
der Choose Adapt Filters to display more selection filter.
Choose More filters under Production Orders. Check the
checkbox for Material and Production Plant and choose
OK. Choose Go. Material and Production Plant fields are
then added to filter bar.
Status: Created
Material: FG126
Production Plant: 1810
Choose Go to execute.
5 Review Ma- Check the Missing Components icon on the right part of The Manage Production Orders screen displays.
terial avail- the order. The following missing parts are expected for FG126.
ability status Click the icon to display missing parts list. ● RM122
Repeat step#4 and #5 for Material SG124 ● RM120
● RM20
● SG124
Note However, it’s also possible that SG124 is not a missing
part for final assembly production order. This happens when
you have SG124 supply(released production order for SG124 or
unrestricted stock) already but it is not yet reserved by any fi-
nal assembly production orders.
The shortage of raw materials to be supplied after Material
Make-to-Stock Production - Discrete Manufacturing (BJ5_IN) PUBLIC
Purpose Error: Reference source not found 23
Test Test Step Instruction Expected Result Pass /
Ste Name Fail /
p# Com-
ment
Staging for Final Assembly step.
The shortage of semifinished goods to be supplied after Re-
lease Production Order for Parts Production step.
The following missing parts are expected for SG124, RM124.
Note The shortage to be supplied after Material Staging for
Part Production step.
Test Administration
Business
Role(s)
Responsibil- <State the Service Provider, Customer or Joint Service Provider and Customer> Duration Enter a duration.
ity
Context
Prerequisite
Procedure
2 Access the App Open Stage Materials for Production. The Material Staging for Planned Orders screen displays.
3 Enter Details Make the following entries and choose Execute. The Pull List: Storage Location Level screen displays.
Staging Types, SLoc Level: activate checkbox
Plant: 1810
Selection Horizon for Remts: date must be in the
future – after scheduled start date
Select the Production/Process Order tab.
Order: Production Order Number for Semi-
finished Goods, for example, Production
Order for SG124
.
4 Choose Replen- Select the required line items from the left-hand Note If there is sufficient stock available on the production stor-
ishment Ele- margin and choose Replenishment proposal from age location, no line items are generated. In this case, you can
ments the top of the screen. skip material staging step and proceed to the next step.
6 Enter Replen- On the bottom half of the split screen, select the
Make-to-Stock Production - Discrete Manufacturing (BJ5_IN) PUBLIC
Purpose Error: Reference source not found 25
Test Test Step Instruction Expected Result Pass /
Step Name Fail /
# Com-
ment
ishment Stor- lines and enter the replenishment storage loca-
age Location tion (181C).
8 Save Save your entries. Missing materials are transferred to the shop floor from the
designated storage area.
Note With this step, the shortage of Material RM124 for Sub-
assembly production order is supplied.
Test Administration
Business
Role(s)
Responsibil- <State the Service Provider, Customer or Joint Service Provider and Customer> Duration Enter a duration.
ity
Context
Releasing the order at header level, releases the order and all its operations. The order and the operations receive the status REL (released).
The production order created by the MRP controller is assigned a release date in accordance with the scheduling margin key.
Procedure
2 Access the App Open Manage Production Orders. The Manage Production Orders screen dis-
plays.
3 Check Default On the Manage Production Orders screen, make the following entries: If no entry Plant 1 1810 in the Area of Re-
Area of Re- Please check Default Area of Responsibility (supervisor). sponsibility(Supervisor) screen, choose add
sponsibility(su- to select it and then choose OK.
Select the user (from the top left corner).Choose App settings Choose
perviosr) For other plant entries in the Area of Re-
against Area of Responsibility Production Supervisor. Check only this
entry is displayed: sponsibility (Supervisor) screen, choose
Delete to remove the others and then
Plant 1 1810
choose OK.
MTS DI – Valuated (YB1)
4 Select Produc- On the Manage Production Orders screen, enter the following search The Manage Production Orders screen dis-
tion Order condition as filter. plays.
Choose Adapt Filters to display more selection filter. Choose More fil-
ters under Production Orders. Check the checkbox for Material and
Production Plant and choose OK. Choose Go. Material and Production
Plant fields are then added to filter bar.
Status: Created
Material: SG124
Production Plant:1810
Choose Go to execute.
5 Execute Re- On the Manage Production Orders screen, Select the searched order. The order is released.
lease Choose Release on the top right corner. Note With the release of production order
Make-to-Stock Production - Discrete Manufacturing (BJ5_IN) PUBLIC
Purpose Error: Reference source not found 27
Test Test Step Instruction Expected Result Pass /
Step Name Fail /
# Com-
ment
for parts production, the storage of mater-
ial SG124 for final assembly production or-
der is supplied.
Test Administration
Business
Role(s)
Responsibil- <State the Service Provider, Customer or Joint Service Provider and Customer> Duration Enter a duration.
ity
Context
The confirmation documents the processing status of orders, operations, sub-operations, and individual capacities. It is an instrument for controlling orders.
Here you have to confirm the operations of the production order for semifinished material SF Subassembly (SG124). When you confirm the last operation, the
system generates a goods movement document for SF Subassembly (SG124). The backflush is carried out together with the confirmation steps.
2 Access the App Open Confirm Production Order Operation The Enter Time Ticket for Production Order screen displays.
.
3 Enter Time Ticket On the Enter time ticket for production or-
for Production Or- der screen, make the following entries:
der Order: <Production Order Number you
noted down>
Operation: For example, operation 0010
Choose Enter to show related information of
the production order.
5 Choose Goods Choose the Goods movements screen. The system shows you an overview table of all materials for
Movements which the withdrawing is done automatically with the confirm-
ation of the operation.
The material RM124 is set for backflush (in material master) so
that the withdrawing is done automatically after you confirm
Test Administration
Business
Role(s)
Responsibil- <State the Service Provider, Customer or Joint Service Provider and Customer> Duration Enter a duration.
ity
Context
The purpose of this activity is to post the goods receipt for the production order.
Procedure
2 Access the App Open Post Goods Movement. The Post Goods Movement screen displays.
3 Enter Goods Re- Make the following entries: Screen name can deviate until the first two entries
ceipt Order Data On the top left frame, enter Goods Receipt and are selected with Enter.
Order.
Order: <Production order number you noted
before>
GR goods receipt: 101
Document date: default
Posting date: default
4 Enter Quantity Choose the Quantity tab and enter the quantity
you confirmed in the previous step.
7 Check and Post Choose Check and then choose Post. The system displays the message: Material docu-
ment 500xxxxxxx posted.
Test Administration
Business
Role(s)
Responsibil- <State the Service Provider, Customer or Joint Service Provider and Customer> Duration Enter a duration.
ity
Context
Prerequisite
2 Access the Open Stage Materials for Production. The Material Staging for Planned Orders screen
App displays.
3 Enter Details Make the following entries and choose Execute. The Pull List: Storage Location Level screen dis-
Staging Types: [Link] Activate checkbox. plays.
Plant: 1810
Selection Horizon for Remts: date must be in the future – after
scheduled start date
Select the Production/Process order tab.
Production Order: <Production Order Number for Finished
Goods, for example, Production Order for FG126>
4 Choose Re- Select the required line items from the left-hand margin and
plenishment choose Replenishment proposal from the top of the screen.
Elements
5 Choose Re- Review the staged quantity and choose Replenishment elements.
plenishment
Elements
6 Enter Replen- On the bottom half of the split screen, select the lines and enter
ishment Stor- the replenishment storage location (181C). Some materials require
age Location a Batch number to be entered. Click Batch Determination button to
decide the batch. For example:: RM122
Test Administration
Business
Role(s)
Responsibil- <State the Service Provider, Customer or Joint Service Provider and Customer> Duration Enter a duration.
ity
Context
A release at order operation level results in the order and all its operations being released. The order and the operations receive the status REL (released).
Prerequisite
The production order created by the MRP controller is assigned a release date in accordance with the scheduling margin key.
Procedure
2 Access the Open Manage Production Orders. The Manage Production Orders screen displays.
App
3 Check De- On the Manage Production Orders screen, If no entry Plant 1 1810 in the Area of Re-sponsibility(Supervisor) screen,
fault Area of make the following entries: choose add to select it and then choose OK. For other plant entries in the
Responsibil- To check Default Area of Responsibility (su- Area of Responsibility (Supervisor) screen, choose Delete to remove the
ity(super- pervisor), select the user (from the top left others and then choose OK
visor) corner): App Settings > Area of Responsib-
ility Production Supervisor . Check only this
entry is displayed:
1810
MTS DI – Valuated (YB1)
4 Select Pro- Enter the following search condition as fil- The Manage Production Orders screen displays.
duction Or- ter.
der Choose Adapt Filters to display more selec-
tion filter. choose More filters under Mater-
ial and Plant. Check the checkbox for Ma-
terial and Plant and choose Go. Choose OK.
Material and Plant fields are then added to
filter bar.
Status: Created
Material:FG126
Plant: 1810
Choose Go to execute.
5 Execute Re- Check selected order. Choose Release on The order is released.
lease the top right corner. Note If Release Order screen popups and says Non-Availability of Material,
Note If release rework production order for it means you have not made sufficient stock for FG126’s components. You
BJQ, do not execute this step. Instead, go can choose to click Release Order button on popup screen to release order
to step 6,7,8. forcely. Or you can execute preliminary steps to make intial mate-rial stock
posting and complete the production order processing for semi-finsihed
goods and come back to release this order again
7 Execute Re- Choose More > Functions > Release . The Release carried out information displays.
lease Ensure REL occurred in Status field.
Test Administration
Business
Role(s)
Responsibil- <State the Service Provider, Customer or Joint Service Provider and Customer> Duration Enter a duration.
ity
Context
The Finished Good material is managed with serial numbers. The system generates a serial number for each finished good when the production order is re-
leased.
The serial number profile is defined in the material master record and the production order is released
Procedure
2 Access the App Open the Display Production Order The Prodcution Order Dis-
play:Initial screen displays.
3 Enter the Number Make the following entries and choose Enter The Prodcution Order Dis-
Order: <Order Number> play:Header displays.
4 Navigate to Serial Choose > More > Header > Serial Number from the bottom of the screen. The Display Serial Number
Number Screen dialog box displays
5 Check the Serial In the Display Serial Number dialog box, the serial numbers generated dur-
Number ing production order releasing are listed. Make a Note of the serial numbers.
Test Administration
Responsibil- <State the Service Provider, Customer or Joint Service Provider and Customer> Duration Enter a duration.
ity
Context
The released production order is now ready for picking. Only those materials that are not in the service stock at the assembly aisle are to be picked. For pick-
ing, the warehouse manager selects the specific picking list that can be called up directly with the production order number. The warehouse manager has a
series of further selection options to allow for optimal worklist selection.
Prerequisite
Ensure that sufficient material is present on stock. To check the stock, you can use the warehouse user and the app Display Stock Overview.
Procedure
2 Access the App Open Pick Components for Production Orders The Picking List: Initial Screen displays.
3 Enter Relevant Make the following entries and choose Execute. The Order Information System: Detail
Search Criteria Profile: 000002 List of Components screen displays.
4 Picking Select the relevant reservations and choose Picking. A list of all the selected reservations is
displayed.
5 Batch Determin- Some materials are management by batch, for example: RM122, The Batch Determination MM: Select
ation Select relation line item and choose Batch Determination. Batches screen displays.
Make-to-Stock Production - Discrete Manufacturing (BJ5_IN) PUBLIC
Purpose Error: Reference source not found 38
Test Test Step Instruction Expected Result Pass / Fail /
Step Name Comment
#
6 Enter Detail Make the following entries and Choose [Link] quantity:Quant-
ity.
7 Post Choose Post to post the goods movements. The goods movements have been pos-
ted.
Test Administration
Business
Role(s)
Responsibil- <State the Service Provider, Customer or Joint Service Provider and Customer> Duration Enter a duration.
ity
Context
The confirmation documents the processing status of orders, operations, sub-operations, and individual capacities. It is an instrument for controlling orders.
This test script uses time event confirmation.
Note In practice some operations produce scrap due to operational or component defects. If you want to simulate this process, refer to scope item Rework
Processing - Work-in-Process (BJQ) and carry out steps described in the related Test Script.
Procedure
2 Access the App Open Confirm Production Order Operation The screen displays.
3 Enter Time Ticket On the Enter Time Ticket for Production Order screen, make the
following entries:
Order: The order number you noted for the material Finished
Good MTS (FG126)
Operation: 0010
Test Administration
Business
Role(s)
Responsibil- <State the Service Provider, Customer or Joint Service Provider and Customer> Duration Enter a duration.
ity
Context
After the release or confirm of finished goods orders is performed, the production supervisor could display and check the order for the Finished Good MTS
FG126.
3 Select Produc- On the Manage Production Operations screen, enter the following search condition as Selected order displays.
tion Order filter.
Click Adapt Filters to display more selection filter. Click More filters under ‘Material’ and
‘Plant’. Check the checkbox for ‘Material’ and ‘Plant’ and click Go. Click OK. Material
and Plant fields are then added to filter bar.
Material: FG126
Plant: 1810
Click Go to execute.
4 Check detailed Check detailed information for selected production operations. Detailed operations
operations Issue: status displays.
status
1. Empty if there is no issue for production order.
2. Delay or Missing Components / PRT issue or Quantity Deviation / Quality Issue in-
formation shows if relevant issue exists.
Components:
Material, total quantity and Issued / open quantity information for order components
displays
Order Schedule:
Detailed operation information with relevant work center, confirmed quantity, start and
end time displays.
Work Center Schedule:
The relevant order that covering the same work center capacity (operation is partially
confirmed) displayed.
Operations not Started:
Test Administration
Business
Role(s)
Responsibil- <State the Service Provider, Customer or Joint Service Provider and Customer> Duration Enter a duration.
ity
Context
In the usual business practices, confirmations of all assembly activities of the production order are executed before posting the goods receipt. The backflush
is carried out together with the confirmation steps.
2 Access the App Open Confirm Production Order Operation. The screen displays.
3 Enter Time Ticket On the Enter Time Ticket for Production Order screen, make the fol-
lowing entries:
Order: <Production order number> (production order number you
have created before)
Operation: <last operation number>, for example 0040.
Confirm. type: Final confirmation
5 Enter Amount to Make the following entries: The final confirmation of the last
Confirm Yield: <Quantity of prod. order less scrap>, enter the amount operation is performed.
you want to confirm
Scrap: <enter the amount you want to Scrap>please input this
quantity if you want to run scrap report"
Test Administration
Responsibil- <State the Service Provider, Customer or Joint Service Provider and Customer> Duration Enter a duration.
ity
Context
This activity posts the goods receipt for the production order.
Procedure
2 Access the Open Post Goods Movement. The Post Goods Movement screen displays.
App
4 Enter Quant- On the Where tab Choose the storage location Std. storage 1
ity 181A
If Scrap quantity is booked, on the Serial Numbers tab select exact
5 Set Item OK Select the Item OK checkbox and choose Post. The system displays the message Mater-
and Post ial document 500xxxxxxx posted.
Test Administration
Business
Role(s)
Responsibil- <State the Service Provider, Customer or Joint Service Provider and Customer> Duration Enter a duration.
ity
Context
2 Open Manage Docu- Open Material Documents Overview The Material Documents Overview is
ments Overview displayed.
3 Search for Goods Re- Make the following entries and choose the Go button. The relevant Material Document item
ceipts Material Docu- Plant: 1810 displays.
ment
Material Document: Material document number, in previous
step
4 Select Material Docu- Select the row for which you would like to see the material The Material Document screen dis-
ment for Goods Receipt documents. plays.
5 Check Goods Issue De- Check the General Information, Attachments , Item , Docu- In the General Information section, you
tails ment Flow and Process Flow . can see the Posting Date, Document
Date .
6 Select the Material Docu- In the Items section, select the row of material document The Material Document Item screen
ment Item item that you want to preview. displays.
7 Preview the Material In the Output Management section, choose Display Docu- The Goods Receipt Slip is opened in
Document Goods Receipt ment icon in the item of which Output Type is GOODS_RE- PDF format.
Slip CEIPT_PO_SLIP.
8 Preview the Material In the Output Management section, choose Display Docu- The Goods Receipt Label is opened in
Document Goods Receipt ment icon in the item of which Output Type is GOODS_RE- PDF format.
Label CEIPT_LABEL.
9 Back to Launch Pad Choose the Home button to go back to the SAP Fiori launch- The SAP Fiori launchpad is displayed.
pad.
Test Administration
Business
Role(s)
Responsibil- <State the Service Provider, Customer or Joint Service Provider and Customer> Duration Enter a duration.
ity
Context
Procedure
2 Access the Open Material Scrap Maximum Deviation. The Material Scrap screen
App displays.
Test Administration
Business
Role(s)
Responsibil- <State the Service Provider, Customer or Joint Service Provider and Customer> Duration Enter a duration.
ity
Context
In this activity, you review the different objects pages available for different roles in the area of Manufacturing.
Procedure
2 Start Search Choose the Search button in the upper right area of the An input field is displayed.
Launchpad.
3 Search Cri- Make the following entries and choose Search: The system displays a list of objects that use the selec-
teria BOM Header Material: <Material> (see the Master Data, ted material.
4 Display Ob- In the All field, choose the Down arrow button. The list of objects is limited to the object type selec-
ject Select an object and choose Search. ted. If no object is selected, a message is displayed in-
stead.
5 Tailor the Below the search line, choose a symbol (for example, fil- The results list is filtered according to your selections.
result dis- ter, display as table, sort, and so on) to filter the results
play list.
6 Repeat Repeat steps 1 to 5 for any other role in this test script The list of objects offered for search differs by the role
Steps and any other object offered in the search function. you used to log on.
Type Description
Style
Example Words or characters quoted from the screen. These include field names, screen titles, push-
buttons labels, menu names, menu paths, and menu options.
Textual cross-references to other documents.
[Link]/contactsap
Example Emphasized words or expressions.
EXAMPLE Technical names of system objects. These include report names, program names, transaction © 2018 SAP SE or an SAP affiliate company. All rights re-
codes, table names, and key concepts of a programming language when they are surrounded served.
No part of this publication may be reproduced or transmitted
by body text, for example, SELECT and INCLUDE.
in any form or for any purpose without the express permis-
sion of SAP SE or an SAP affiliate company.
Example Output on the screen. This includes file and directory names and their paths, messages,
SAP and other SAP products and services mentioned herein
names of variables and parameters, source text, and names of installation, upgrade and data- as well as their respective logos are trademarks or registered
base tools. trademarks of SAP SE (or an SAP affiliate company) in Ger-
many and other countries. Please see
Example Exact user entry. These are words or characters that you enter in the system exactly as they [Link]
#trademark for additional trademark information and notices.
appear in the documentation.
Some software products marketed by SAP SE and its distribu-
tors contain proprietary software components of other soft-
<Ex- Variable user entry. Angle brackets indicate that you replace these words and characters with
ware vendors.
ample> appropriate entries to make entries in the system. National product specifications may vary.
These materials are provided by SAP SE or an SAP affiliate
EXAMPLE Keys on the keyboard, for example, F 2 or E N T E R . company for informational purposes only, without representa-
tion or warranty of any kind, and SAP SE or its affiliated com-
panies shall not be liable for errors or omissions with respect
to the materials. The only warranties for SAP SE or SAP affili-
ate company products and
services are those that are set forth in the express warranty
statements accompanying such products and services, if any.
Nothing herein should be construed as constituting an addi-
tional warranty.
In particular, SAP SE or its affiliated companies have no obli-
gation to pursue any course of business outlined in this docu-
ment or any related presentation, or to develop or release
any functionality mentioned therein. This document, or any
related presentation, and SAP SE’s or its affiliated companies’
strategy and possible future developments, products, and/or
platform directions and functionality are all subject to change
and may be changed by SAP SE or its affiliated companies at
any time for any reason without notice. The information in
this document is not a commitment, promise, or legal obliga-
tion to deliver any material, code, or functionality. All for-
ward-looking statements are subject to various risks and un-
Make-to-Stock Production - Discrete Manufacturing (BJ5_IN) PUBLIC
certainties that could cause actual results to differ materially
Purpose Error: Reference source not found 52
from expectations. Readers are cautioned not to place undue
reliance on these forward-looking statements, which speak
only as of their dates, and they should not be relied upon in
making purchasing decisions.