Incoming Material Inspection Report

The document is an Incoming Material Inspection Report detailing the inspection and testing criteria for various construction materials and activities, including anti-termite treatment, masonry works, concrete works, and plastering. It includes sections for client information, material specifications, acceptance criteria, physical tests, and inspection requests. Additionally, it outlines the responsibilities of contractors and client representatives during the inspection process.

Uploaded by

Rizwan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
25 views7 pages

Incoming Material Inspection Report

The document is an Incoming Material Inspection Report detailing the inspection and testing criteria for various construction materials and activities, including anti-termite treatment, masonry works, concrete works, and plastering. It includes sections for client information, material specifications, acceptance criteria, physical tests, and inspection requests. Additionally, it outlines the responsibilities of contractors and client representatives during the inspection process.

Uploaded by

Rizwan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

Incoming Material Inspection Report

Client :-
Project:-
PMC :- Cushman & Wakefield
Contractor :-
Date of Receip

Name of material:

Complete Description of material with Relevent Specification :

ACCEPTANCE CRITERIAS
Clause no:
Technical spec Ref:
BOQ Ref: Item No:
Drg. Ref:
Client / Consultant / Architects Instruction Ref:
Challan / Invoice no: Quantity:
Vehicle No:
Cumulative Quantity of material recived :

Availability of MTC: MTC no Batch no ./lot

Status of External test Report (if Required ) To be Sent / Available / Not required

Manufacture Date : Expiry Date of Product (if Applicable):

Approved
Approved with comment
Rejected
Remark of Client / PMC Personal:

Physical Tests Conducted/ not conducted


Tests Detail Refrence ITP NO.
1}
2}
3}
Response of Contractor Representative

Proposed use:

Contractor QC- Engineer Client /pmc


Name: Name:
Signature Signature
Revision no:- 00
DATE:-
Document no:-

INSPECTION REQUEST
IR NO. : Date :
Location

We request for an Inspection of the following Activity prior to proceed further :


Activity PCC Footings Cloumn Slab Block work Plaster

Date of Inspection : Time :


Name & Designation of Contractors Representative with Signature :

Comments of Client/PMC Representative :

Approved Inspection done by

Not Approved

Any other comments : Sign & Name

comments :

SITE ENG Site QC C&W ENG

Name :

Designation :

Signature :

Date :
In coming check for Reinforcement STEEL
PROJECT :
Client :
Worksite :
Quantity
Rusting/
Sr. Dia. Of Received Supplies External
Challan Num Type Grade Packing Site Bend Test Loose Weight/ meter kg/m MTC
No. Steel (mm) as per Name lab Test
scale
Challan
1 2 3

Checked By : - Reviewed By :- PMC ENGINEER


Name: Name:
Designation: Designation:
Sign: Sign:
Date : Date :
INSPECTION AND TEST PLAN
PROJECT
Client
PMC

ACTIVITY: ANTI-TERMITE TRATMENT.

Inspection and Testing Controlling Verifying Frequency of [Link] Remark


[Link].
Description Specification. Document Inspec./Testing CIPL Client s
Technical External Lab
01 Approval of Chemicals and Applicator Specification Report/Approval Each Applicator p R
/BOQ/IS-6313 Letter
Incoming
Technical Materials
02 Approval of Methodology Specification Inspection Each Applicator R R
/BOQ/IS-6313 Report /External
Lab Report
03 Incoming materials Inspection MTC QAP Every lot p R

Application of Chemicals as per Technical Every Pour before


04 Check List p W
procedure Specification /BOQ Concrete

LEGEND:P:Performance H: Hold Point; W: Witness S: Surviellance Inspection; R: Review of Reports; MTC: Manufacturer's Test Certificate;
INSPECTION AND TEST PLAN
PROJECT
Client
PMC

ACTIVITY: Masonary Works.

Controlling Frequency of [Link]


[Link]. Inspection and Testing Description Verifying Document Remarks
Specification. Inspec./Testing CIPL Client
Technical
Approval of Work Procedures-(As specified At the beginning
01 Specification Approval stamp/Letter R/W R/W
in PQP) for each type
/BOQ/IS-6313
Technical
02 Source Approval Specification Test Reports Each Source R/W R/W
/BOQ/IS -8112
Incoming materials IS- ELR:Three
MTC or Incoming
3 Inspection/Cement/water/ waterproofing 8112/3025/1542/ ELR/Every lot R/W R/W monthly or as
checks per source (ELR)
compound 2645
MTC or Incoming ELR/Every 10000
04 Incoming materials Inspection/Blocks IS-1077/8112 R/W R/W
checks nos
05 Setting Out including opening Drawing Check List Every Location. R/W R/W

06 Mixing of Materials BOQ/TS Check List Every Location. R/W R/W

Laying of Bricks ,maintaing joints and


07 racking of joints, Lintels, mullians,bends, [Link], Drawings Check List Every days work R/W R/W
considering also the position of openings.

Curing and Final Inspection for line/


08 BOQ/TS Check List Every days work R/W R/W
level/plumb etc.
ELR once in a
09 Check for compressive Strength of Mortar TS/IS 516 Check List month/Every days R/W R/W
work
LEGEND:P:Performance H: Hold Point; W: Witness S: Surviellance Inspection; R: Review of Reports; MTC: Manufacturer's Test Certificate; ELR:External Lab report
Note- Silt content in the sand for masonry = max. 8% by volume, for external plaster & waterproofing works = max. 2% by volume
INSPECTION AND TEST PLAN

PROJECT
Client
PMC
ACTIVITY: CAST IN SITU CONCRETE WORKS

Frequency of [Link]
Inspection and Testing Controlling Verifying
[Link]. Inspec./Testi Remarks
Description Specification. Document CIPL Client
ng

MTC/External/
Technical
01 Material Testing and Approval Internal Refer ITP R/W R/W
Specification
Lab Forms

Concrete Once per each


Concrete Design Mix for each Technical
02 Design Mix Source of R/W R/W
Grade and Approval Specification
Report(S) Materials

List of Relevant Every Pour


Check for availability of GFC
03 Approved Contruction before R/W R/W
Drawings
Drawings Drawing Concrete

Relevant Every Pour


Survey & Setting out for relevant Approved
04 Construction before R/W R/W
Structure to be concreted format
Drawings Concrete

Every
Preparation and approval of Bar Technical Approved Structure
05 R/W R/W
Bending Schedules Specification format before
Concrete

Every
Base Preparation,Laying
Technical Approved Structure
06 Leveling Course [Link] R/W R/W
Specification format before
the Foundaation
Concrete

Every Pour
Reinforcement Placing,Tieing Technical Approved
07 before R/W R/W
and Inspection Specification format
Concrete

Technical
For Each type
Submission of Formwork design Specification/IS-
8 Design & drg. of shuttering R/W R/W
& drawing and approval 456 and other
work
codes

Every Pour
Technical Approved
08 Checking of Formwork before R/W R/W
Specification format
Concrete

Calibration of Batching As per


Approved
09 Plant/Gauge Boxes for Volume Approved Once in month R/W R/W
format
Batching Procedure

Check for Every Pour


Technical Approved
10 Mixing,Transporting,Placing,Com during R/W R/W
Specification format
paction of Concrete etc. Concrete

Check for Curing,Stripping time


Every
of Shuttering and identification Technical Approved
11 Structure after R/W R/W
of defects,if any etc and Specification format
Concrete
repairing the Concrete etc.

Cubes will be tested at 56 days incase


Check
Check for
for Strength of Concrete
proper curing of tha Technical Approved strength not achieved at 28 days./
12 As Per IS: 456 R/W R/W
(Cubes) for desired duration of
structure Specification format/Register External test report of cubes in every
time by covering with wet in six month.
hessian bags,sprinkling water or
LEGEND:P:Performance,
applying approved H:curing
Hold Point; W: Witness; S: Surviellance Inspection; R: Review of Reports; MTC: Manufacturer's Test Certificate;
compounds.
23
PROJECT

Client

PMC

ACTIVITY: PLASTERING WORKS

Frequency of [Link]
Inspection and Testing Controlling Verifying
[Link]. Inspec./Testin Remarks
Description Specification. Document
g CIPL Client

Technical
At the beginning for each
01 Approval of Work Procedures-(As specified in PQP) Specification /BOQ/IS- Approval stamp/Letter
type R/W R/W
6313
Technical
02 Source Approval Specification /BOQ/IS - Test Reports Each Source R/W R/W
8112
IS- MTC or Incoming
Incoming materials Inspection ELR:Three monthly or
03
(Cement/Water/waterproofing compound)
1077/8112/3025/1542/ ELR/Every lot R/W R/W as per source (ELR)
2645 checks

Hand Over of areas from B/Work to Plastering


04
including clearance from other trades.
Drawing Check List Every Location. R/W R/W

Preparation of substrate to receive plastering , level


5 packs, G.I/[Link] [Link] of bonding [Link]/BOQ Check List Every Location. R/W R/W
agent whereever applicable.

6 Cement Mortar Mixing [Link], Drawings Check List In Process R/W R/W

7 Application of 1 st/ 2 nd coat as per the item [Link] Check List Every days work R/W R/W

8 Check for cracks [Link] Check List Every days work R/W R/W

Separately for Sale &


9 Check for compressive Strength of Mortar [Link]/IS516 Check List Every days work R/W R/W Rehab

9 Curing and Final Acceptance [Link] Check List Every days work R/W R/W

LEGEND:P:Performance H: Hold Point; W: Witness S: Surviellance Inspection; R: Review of Reports; MTC: Manufacturer's Test Certificate; ELR:External third party lab
Note- Silt content in the sand for masonry = max. 8% by volume, for external plaster & waterproofing works = max. 2% by volume