Quality Management Plan Implementation Alignment Meeting 2

The document outlines the Quality Management Plan for the 183MW Isimba Hydropower Project in Uganda, detailing the project's scope, quality policy, objectives, and management system aligned with ISO 9001:2015. It includes roles and responsibilities, key processes for quality control in design, procurement, and construction, as well as monitoring and improvement strategies. The plan emphasizes compliance, continuous improvement, and outlines next steps for implementation and training.

Uploaded by

emmanuel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
42 views30 pages

Quality Management Plan Implementation Alignment Meeting 2

The document outlines the Quality Management Plan for the 183MW Isimba Hydropower Project in Uganda, detailing the project's scope, quality policy, objectives, and management system aligned with ISO 9001:2015. It includes roles and responsibilities, key processes for quality control in design, procurement, and construction, as well as monitoring and improvement strategies. The plan emphasizes compliance, continuous improvement, and outlines next steps for implementation and training.

Uploaded by

emmanuel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd

Quality Management Plan

Implementation Alignment
Meeting

183MW Isimba Hydropower Project, Uganda


Date: [Insert Date]
Presented by: [Your Name/Team]
Agenda

 1. Introduction & Project Overview


 2. Quality Policy & Objectives
 3. Quality Management System (QMS)
 4. Roles & Responsibilities
 5. Key Processes & Controls
 6. Monitoring & Improvement
 7. Next Steps
Project Overview

Client: Government of Uganda (Ministry of Energy)


Contractor: China International Water & Electric Corp. (CWE)
Scope:
 Civil, hydro-mechanical, electrical works
 183.2MW capacity, 1,062 GWh/year output
 Key Components: Dam, spillway, power house, switch yard
Quality Management Purpose

 Ensure compliance with ISO 9001:2015 and EPC contract.


 Achieve zero defects in procurement/construction.
 Continuous improvement via internal audits.
Quality Policy

1. Compliance with ISO 9001:2015.


2. Excellence in design, procurement, and construction.
3. Sustainable enhancement to meet contract requirements.
Quality Objectives

 Design: Deliverables on time, within budget.


 Procurement: 100% inspection acceptance rate.
 Construction: Zero defects, ITP adherence, calibrated tools.
Quality Management System (QMS)

 ISO 9001:2015 aligned.


Key Components:
 Documented procedures (QA/QC).
 Resource management (human, infrastructure).
 Risk assessment (RAMS).
QMS Schematic Diagram

Visualize Fig. 3.2-1:


 Inputs (client needs) → Processes → Outputs (completed works).
 Feedback loops for improvement.
Organizational Structure

 Project Manager: Qian Fuyun


Key Roles:
Deputy PMs (Civil/EM&HM).
QA/QC Managers.
Design & Construction Directors.
Key Personnel

Table 3.4-1 highlights:


 Mechanical Supervisor: Liu Jianwei
 Civil Supervisor: Fu Zhipan
 Electrical Supervisor: Xiao Kui
Responsibilities Overview

 Project Manager: Overall accountability.


 Construction Teams: On-site QC.
 Quality Manager: Audits, non-conformity resolution.
Design Quality Control

Stages: Basic → Construction → Completion Design.


Key Checks:
 Compliance with Employer’s Requirements.
 Peer reviews, validation tests.
Procurement Quality Control

Steps:
1.Supplier pre-qualification.
2.ITP (Inspection & Test Plan) approval.
3.Factory Acceptance Tests (FAT).
Construction QC Measures

Earth-Rock Excavation:
 Pre-splitting blasting, slope stability checks.
Concrete Works:
 Formwork, rebar, curing controls.
Inspection & Test Plan (ITP)

Phases:
 FAT (Factory) → Site Tests → Completion (CAT).
 Hold/Witness Points: Employer’s right to review.
Non-Conforming Product Control

Process:
 Identify → Record → Evaluate → Treat (rework/reject).
 Reports: NCR (Non-Conformity Reports).
Commissioning Plan

 Static Checks: HV tests, relay tests.


 Dynamic Tests: Turbine/generator load tests.
 Training: O&M manuals for Employer.
Documentation Management

 Types: Drawings, RAMS, O&M manuals.


 Control: Versioning, approvals, archiving.
Key Performance Indicators (KPIs)

 Design: On-time submission rate.


 Procurement: 100% inspection pass rate.
 Construction: Low Defect frequency.
Internal Audits

 Frequency: Annually (min. 15% and 60% completion).


 Focus: Compliance, process effectiveness.
External Audits

 Employer’s right to audit with 3 weeks’ notice.


 Audit results shared for corrective actions.
Data Analysis & Improvement

 Sources: Customer feedback, QC records, audits.


 Actions: Corrective/preventive measures.
Risk Management

 RAMS (Risk Assessment & Method Statements):


 Mandatory for all activities.
Training & Competence

 Requirements: ISO 9001 awareness, technical skills.


 Records: Maintained for audits.
Monthly Progress Reporting

Contents:
 HSE, design, procurement, construction updates.
 Risks, claims, documentation status.
Communication Matrix

Table 6.3-1:
 RACI (Responsible, Accountable, Consulted, Informed).
E.g., Design approval: PM (A), Design Team (R).
Annexes Overview

Key Annexes:
 ITP samples, meeting minutes, checklists.
 Personnel certifications (ISO 9001).
Challenges & Mitigations

 Challenge: Supplier non-compliance.


 Solution: Strict pre-qualification, FAT oversight
Next Steps

1.Finalize ITPs for upcoming activities.


2.Schedule QMS training for subcontractors.
3.Prepare for internal audit (15% completion).
Slide 30: Q&A

 ________________________________________
 Open floor for stakeholder questions.