Isolator LAR

The West Central Railway has issued a Letter of Acceptance to M/s Kanha Construction for the provision of isolators at major stations in the Kota division, with a total contract value of Rs. 2,312,307.66. The contractor is required to submit a Performance Guarantee of Rs. 115,615.38 within 21 days, and the work must be completed within 12 months. Additional compliance with labor regulations and monthly reporting on worker details is mandated as part of the contract terms.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
67 views3 pages

Isolator LAR

The West Central Railway has issued a Letter of Acceptance to M/s Kanha Construction for the provision of isolators at major stations in the Kota division, with a total contract value of Rs. 2,312,307.66. The contractor is required to submit a Performance Guarantee of Rs. 115,615.38 within 21 days, and the work must be completed within 12 months. Additional compliance with labor regulations and monthly reporting on worker details is mandated as part of the contract terms.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

9/26/23, 2:13 PM [Link]/epsn/works/tds/publishLOAWorksLetter.

do

WEST CENTRAL RLY


KOTA DIVISION-
ELECTRICAL
DRM TRD OFFICE, KOTA
JUNCTION
KOTA, 324002
Rajasthan, India

Letter No: KOTA DIVISION-ELECTRICAL / EL-TRD-50-08-2023-


Dated: 08/09/2023
24 / 10851420086432

M/s KANHA CONSTRUCTION-JAIPUR


6th floor 604 vardhman sampada
gandhi path jaipur
jaipur- 302021
Rajasthan, India

Sub: Letter Of Acceptance

Ref: 1. Tender No. EL-TRD-50-08-2023-24 closing date 11-08-2023 15:30 for


Provision of isolators at major stations to improve OHE sectioning in Kota
division.
2. Your bid ID 15565015 dated 10/08/2023 23:15

The Competent Authority has accepted your offered rates in connection with the subject
work. The total cost of the work at the accepted rates works out to Rs. 2312307.66 (Rupees
Twenty-Three Lakh Twelve Thousand Three Hundred And Seven Rupees And Sixty-Six Paise
Only)

A sum of Rs.45100 deposited as Earnest Money vide IREPS reference ID


PE961419544028 has been retained towards initial Security Money for due and faithful
fulfillment of the contract, and the balance Security Money will be recovered from the
progressive bills @ 6 % of the bill amount till it reaches 5 % of the contract value in terms of
clause 16 (1) to 16 (3) of GCC -April-2022.

You are requested to submit Performance Guarantee in the form as given in Clause 16 (4)
of GCC-April-2022 equivalent to 5 % of the contract value amounting to Rs. 115615.38
(Rupees One Lakh Fifteen Thousand Six Hundred And Fifteen Rupees And Thirty-Eight Paise
Only) within 21 days from the date of issue of Letter of Acceptance, valid up to stipulated date
of completion plus 60 days so that contract agreement can be executed. The successful bidder
shall have to submit a Performance Guarantee (PG) within 21 (Twenty one)days from the date
of issue of Letter of Acceptance (LOA) in favour of [Link]/KOTA/WCR. Extension of time
for submission of PG beyond 21(Twenty one) days and up to 60 days from the date of issue of
LOA may be given by the Authority who is competent to sign the contract agreement.
However, a penal interest of 12% per annum shall be charged for the delay beyond 21(Twenty
one) days, i.e. from 22ndday after the date of issue of LOA. Further, if the 60th day happens to
be a declared holiday in the concerned office of the Railway, submission of PG can be accepted
on the next working day. In all other cases, if the Contractor fails to submit the requisite PG
even after 60 days from the date of issue of LOA, the contract is liable to be terminated. In
case contract is terminated railway shall be entitled to forfeit Earnest Money Deposit and other
dues payable against that contract. In case a tenderer has not submitted Earnest Money Deposit
on the strength of their registration as a Startup recognized by Department of Industrial Policy
and Promotion (DIPP) under Ministry of Commerce and Industry, DIPP shall be informed to
this effect. The failed Contractor shall be debarred from participating in re-tender for that
work.

The entire work shall be completed within 12 month from the date of issue of Letter of
Acceptance.

Shramik kalyan details: [Link] Contractor should upload details of their LOAs, engaged workmen
,wage payment details , PE/ESI details, bonus details etc on monthly basis on Railway Shramik
kalyan [Link][As per RB, New Delhi Letter No.
2018/CE-I/CT/4 dated 17/10/2018 and GCC Clause 55 (c)].

Shramik kalyan details: [Link] While Processing payment of any ON Account Bill or Final Bill or
release of Advances or PG/SD , contractor shall submit a certificate to the Engineer or
Engineer Representatives that I have uploaded the correct details of contract Labours engaged
in connection with this contract and payments made to them during the wage period in
Railway's Shramik Kalyan Portal at [Link] till ________
Month ____ year.

Prices and payments:-: 3: The Prices are inclusive of all taxes, Payments will be made as per
tender documents, PVC is not applicable for this case.

[Link] 1/3
9/26/23, 2:13 PM [Link]/epsn/works/tds/[Link]

Authorized Representative: 4: Work should be carried out under the supervision of


SSE/TRD/BTE,BXN,HAN,GGC,SWM,LKE,SGAC,KOTA,RMA,SGZ,VMA,BUDI,MLGH
of Kota division

Measurement : 5:: SSE/TRD/SWM shall record the detail measurement along with necessary
certificate in MB.

Scope Of work and special condition: 6: The work shall be carried out as per technical
specifications, explanatory notes and special conditions contain in the tender document

Inspection of: [Link] As mentioned in Tender documents.

Remarks 8:-: You are advised to get yourself registered immediately under the contract and
labour (Regulation & Abolition) Act 1970 with the concerned regional labour commissioner
/Assistant Labour Commissioner. Further you should intimate the date of commencement and
completion of work to the concerned regional labour commissioner. All the responsibility
regarding security and other favours will be all yours. Please inform the number of employees
to be deputed for the present work by you to this office.

Remarks 9 :-: While every care has been taken to fully incorporate the decision of the
Accepting authority regarding acceptance of your offer , The railway administration reserves
the rights to correct the inadvertent mistakes which may have occurred in communication of
the accepted rates and other terms and conditions of the accepted rates and other terms and
conditions at the time of signing the formal Contract agreement between the contractor and the
railway administration

C/T:-: Sr. DFM/KOTA/WCR , ADEE/TRD/SGZ,BTE,KOTA for kind information ,


SSE/TRD/BTE,BXN,HAN,GGC,SWM,LKE,KOTA,RMA,SGZ,VMA,BUDI,MLGH,SGAC
of kota division for monitoring progress of work

All Other terms and conditions, as stipulated in the tender documents shall be applicable.

ABHIJEET KUMAR MEENA


ADEE/TRD/KOTA
Digitally Signed
View Signature Details

Awarded Quantities And Rates


Item Item Desc Item Item Qty Unit Escl. [Link] Bid Rate/ Bid Amount (Rs)
Sno. Code Qty Unit Rate(Rs) (%) (Rs) Unit Rate
Schedule 01-Provision of isolators at major stations to improve OHE
2254810.00
sectioning in Kota division (Item Directory - Not Applicable)
Cement concrete for foundation
and plinth in normal, loose,
01 01 28 cum 6105.00 At Par 170940.00
black cotton, hard and rock y
soil-All type of soil
Supply of Galvinized steel
02 02 2 MT 105838.00 At Par 211676.00
traction mast & SPS
Erection of Galvinized steel
03 03 2 MT 11242.00 At Par 22484.00
traction mast & SPS
Supply of Bracket assembly (
04 04 5 Numbers 27296.00 At Par 136480.00
Tramway)
Erection of bracket assembly
05 05 5 Numbers 1551.00 At Par 7755.00
(Tramway)
Supply of Overhead equipment
with complete fitting including Per Track
06 06 0.5 47664.00 At Par 23832.00
briddle wire (tramway) note:- KM
Contact wire supplied by Railway
Erection of Overhead equipment
with complete fitting including Per Track
07 07 0.5 35797.00 At Par 17898.50
briddle wire (tramway) note:- KM
Contact wire supplied by Railway
Supply of section Insulator
assembly including cut in
08 08 10 Numbers 50551.00 At Par 505510.00
insulator with complete fitting
(Tram way)
Erection of section Insulator
assembly including cut in
09 09 10 Numbers 4867.00 At Par 48670.00
insulator with complete fitting
(Tram way)
Supply of SP isolator 1250 amp.
10 10 9 Numbers 51815.00 At Par 466335.00
Without earthing contact.
Erection of SP isolator 1250
11 11 9 Numbers 2636.00 At Par 23724.00
amp. Without earthing contact.
12 Supply of structure bonds 12 15 Numbers 624.00 At Par 9360.00

[Link] 2/3
9/26/23, 2:13 PM [Link]/epsn/works/tds/[Link]
13 Erection of structure bonds 13 15 Numbers 261.00 At Par 3915.00
14 Supply of longitudinal bonds 14 10 Numbers 434.00 At Par 4340.00
15 Erection of longitudinal bonds 15 10 Numbers 236.00 At Par 2360.00
Supply of splice and extension of
16 16 10 Numbers 3136.00 At Par 31360.00
OHE
Erection of splice and extension
17 17 10 Numbers 1896.00 At Par 18960.00
of OHE
18 Transfer of OHE 18 10 Numbers 6335.00 At Par 63350.00
Dismantling of all OHE
fittingsi.e. wiring, cantilever,
19 19 0.5 Kilometre 24130.00 At Par 12065.00
isolator, section insulator, ATD,
etc
Dismantling of Mast/Upright by
20 20 5 Numbers 1249.00 At Par 6245.00
gas cutting
Supply of retro reflective
21 21 10 Numbers 932.00 At Par 9320.00
number plates
Erection of retro reflective
22 22 10 Numbers 49.00 At Par 490.00
number plates
23 Supply of single earth electrode 23 5 Numbers 2974.00 At Par 14870.00
24 Erection of single earth electrode 24 5 Numbers 1262.00 At Par 6310.00
Preparation and fixing of TSWR Square
25 25 50 628.00 At Par 31400.00
diagram board Foot
Preparation of TSWR diagram
26 copies and annexure booklet of 26 3 Numbers 7425.00 At Par 22275.00
yard
Supply of material for copper
27 27 6 Numbers 6720.00 At Par 40320.00
jumper
erection of material for copper
28 28 6 Numbers 554.00 At Par 3324.00
jumper
Supply of material for solid
29 29 10 Metre 1426.00 At Par 14260.00
copper busbar 18mm
Erection of material for solid
30 30 10 Metre 111.00 At Par 1110.00
copper busbar 18mm
Supply of material for solid
31 copper busbar connector bus 31 6 Numbers 3150.00 At Par 18900.00
terminal
Erection of material for solid
32 copper busbar connector bus 32 6 Numbers 47.00 At Par 282.00
terminal
Supply of material for solid
33 copper busbar connector bus 33 6 Numbers 3322.00 At Par 19932.00
splice
Erection of material for solid
34 copper busbar connector bus 34 6 Numbers 47.00 At Par 282.00
splice
Supply of material of post
35 35 10 Numbers 7027.00 At Par 70270.00
porcelain insulator
Erection of material of post
36 36 10 Numbers 487.00 At Par 4870.00
porcelain insulator
Supply of material for single
37 37 5 Numbers 27067.00 At Par 135335.00
bracket assembly (conv.)
Erection of bracket assemble
38 38 5 Numbers 2151.00 At Par 10755.00
(conv.)
Supply of material for over head
equipment with complete fittings Per Track
39 39 0.5 49387.00 At Par 24693.50
(Conv.) ( Catenary and contact KM
wire supplied by Railway)
Manual erection of material for
over head equipment with
Per Track
40 complete fittings (Conv.) ( 40 0.5 49524.00 At Par 24762.00
KM
Catenary and contact wire
supplied by Railway)
Supply of florocent stirp yellow
41 41 70 Sqm 197.00 At Par 13790.00
colour
Schedule Totals 0.00
Total Value 2254810.00 2.55 %Above 2312307.66
Rebate on Total Value
0.00
(%)
Net Bid Value 2312307.66

Item Breakup