LARSEN & TOUBRO LTD.
,ECCD PROJECT QUALITY PLAN
DAILY PROGRESS REPORT
DATE:FORMAT NO. QAF/DPR/20 REV NO.00
QUALITY MANAGEMENT
Name of Work : Employer : Contractor : Dur. in Days:
SITE
RMZ CENTENNIAL
PROJECT
Contract Start Date
Contract Completion
Total Rainy
LOCATION
From :
Elapsed
To :
Balance Site Conditions:
FOR THE DAY
Normal Day
ACTIVITY DESCRIPTION
Slushy
PL. NEXT DAY Cum Achieved
Dry
% COMP
UNIT TOTAL QTY.
PLANNED
ACHIEVED
EXCAVATION BACKFILLING FORMWORK PCC REINFORCEMENT WORK PROGRESS RCC BLOCKWORK BRICKWORK SSM PLASTER WATER PROOFING
MAN POWER
DESCRIPTION PLANNED ACTUAL DESCRIPTION UNIT
MATERIAL
RECEIPTS FOR DAY TILL DATE CONSUMPTION FOR DAY TILL DATE
LABOUR & MATERIAL
TOTAL
Distribution
Prepared by:
Construction manager
CONSTRAINTS